Prior art keywords
electric capacity
current tester
tester body
distribution network
capacity current
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120185930.4U
Other languages
Chinese (zh)
Inventor
韩刃
邵振华
刘明辉
黄海燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XIAMEN MINGHAN ELECTRIC CO Ltd
Original Assignee
XIAMEN MINGHAN ELECTRIC CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XIAMEN MINGHAN ELECTRIC CO Ltd filed Critical XIAMEN MINGHAN ELECTRIC CO Ltd
Priority to CN202120185930.4U priority Critical patent/CN214895606U/en
Application granted granted Critical
Publication of CN214895606U publication Critical patent/CN214895606U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The utility model discloses a distribution network overhauls equipment of patrolling and examining, the power distribution network maintenance box comprises a tool box body, one side surface movable mounting of instrument box has closed case lid, be provided with electric capacity current tester body in the inner chamber of instrument box, one side fixed surface of instrument box installs the lateral part handle, the surface movable mounting that the inner chamber of instrument box is located electric capacity current tester body has installation device, installation device's surface movable mounting has the buffering extension board. A distribution network overhauls equipment of patrolling and examining belongs to and overhauls the equipment field, can install electric capacity current tester body and instrument box in a flexible way, not only make things convenient for the maintenance to dismantle behind electric capacity current tester body trouble, also conveniently change damaged instrument box, in the use, the impact that the buffering extension board can multiple buffering bottom has reduced electric capacity current tester body and has received the risk that the vibrations caused the loss in the instrument box inner bottom.

Description

Distribution network overhauls equipment of patrolling and examining
Technical Field
The utility model relates to an overhaul and patrol and examine the equipment field, in particular to distribution network overhauls equipment of patrolling and examining.
Background
The power distribution network is a power network which receives electric energy from a power transmission network or a regional power plant, distributes the electric energy to various users on site through power distribution facilities or distributes the electric energy to various users step by step according to voltage, and consists of overhead lines, cables, towers, distribution transformers, isolating switches, reactive power compensators, a plurality of accessory facilities and the like, plays a role in distributing the electric energy in the power network, and currently, a capacitance current tester is used in the process of manually overhauling and inspecting the power distribution network; however, the existing capacitance current tester is installed into a tool box for a portable general screw in the process of overhauling and patrolling, but the installation mode is single, once the capacitance current tester breaks down, the capacitor current tester is extremely complex to disassemble, and in the process of carrying the tool box, the bottom of the capacitor current tester is easy to shake, so that certain risks are brought to the capacitance current tester inside.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a distribution network overhauls equipment of patrolling and examining can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a distribution network overhauls equipment of patrolling and examining, includes the instrument box, a side movable surface mounting of instrument box has closed case lid, be provided with the electric capacity current tester body in the inner chamber of instrument box, a side fixed surface of instrument box installs the lateral part handle, the inner chamber of instrument box is located the movable surface mounting of electric capacity current tester body and has installation device, installation device's movable surface mounting has the buffering extension board, installation device includes spacing splint, direction draw runner, takes out handle, second absorption magnetic path and reset spring.
Preferably, the upper surface of the capacitance current tester body is provided with a liquid crystal display, one side of the upper surface of the capacitance current tester body, which is located on the liquid crystal display, is provided with a knob, one side of the upper surface of the capacitance current tester body, which is located on the knob, is provided with a first interface, one side of the upper surface of the capacitance current tester body, which is located on the knob, is provided with a second interface, and one side of the upper surface of the capacitance current tester body, which is located on the liquid crystal display, is provided with a key.
Preferably, a hinge is fixedly mounted on the surface of one side of the tool box body close to the edge of the upper end of the tool box body, a guide sliding groove is formed in the upper end face of the tool box body, a first adsorption magnetic block is fixedly mounted on the inner bottom wall of the guide sliding groove, and the closed box cover is rotatably connected with the tool box body through the hinge.
Preferably, a guide sliding strip is fixedly mounted on the surface of one side of the limiting clamping plate, a taking-out handle is fixedly mounted on the upper surface of the guide sliding strip, a second adsorption magnetic block is fixedly mounted on the lower surface of the guide sliding strip, and a reset spring is fixedly mounted between the limiting clamping plates.
Preferably, the lower fixed surface of buffering extension board installs the rubber support, the last fixed surface of buffering extension board installs the cushion, the one end fixed surface of buffering extension board installs the slide-bar, the surface of spacing splint is located slide-bar department and has seted up the slide opening, the embedding round hole has been seted up to the inner diapire of instrument box, the inside packing of embedding round hole has the buffer block.
Preferably, two groups of limiting clamping plates are symmetrically arranged in the inner cavity of the tool box body, two ends of the reset spring are fixedly connected with the end faces of the limiting clamping plates, the limiting clamping plates are connected with the guide sliding groove in a sliding mode through the guide sliding strips, and the limiting clamping plates are fixed in a limiting mode after being adsorbed by the second adsorption magnetic blocks and the first adsorption magnetic blocks of the guide sliding groove.
Compared with the prior art, the utility model discloses following beneficial effect has:
the utility model discloses in, through the installation device who sets up, can install electric capacity current tester body and instrument box in a flexible way, not only make things convenient for the maintenance to dismantle after electric capacity current tester body trouble, also conveniently change damaged instrument box, through the buffering extension board that sets up, in the use, the impact that the buffering extension board can multiple buffering bottom has reduced the risk that electric capacity current tester body received the vibrations and has caused the loss in the instrument box inner bottom.
Drawings
Fig. 1 is a schematic view of the overall structure of the power distribution network maintenance inspection equipment of the utility model;
fig. 2 is a schematic structural view of the mounting device of the power distribution network maintenance inspection equipment of the utility model;
FIG. 3 is a schematic structural view of a buffering support plate of the inspection equipment for power distribution network maintenance of the present invention;
fig. 4 is the utility model relates to a distribution network overhauls instrument box structure schematic diagram of equipment of patrolling and examining.
In the figure: 1. a tool box; 101. a hinge; 102. a guide chute; 103. a first adsorption magnetic block; 2. closing the box cover; 3. a capacitance current tester body; 301. a liquid crystal display screen; 302. a knob; 303. a first interface; 304. pressing a key; 305. a second interface; 4. a side handle; 5. a mounting device; 501. a limiting clamp plate; 502. a guide slider; 503. taking out the handle; 504. a second adsorption magnetic block; 505. a return spring; 6. a buffering support plate; 601. a rubber support; 602. a cushion pad; 603. embedding into the round hole; 604. a buffer block; 605. a slide shaft; 606. and (4) a slide hole.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
As shown in fig. 1-4, a distribution network overhauls equipment of patrolling and examining, including tool box 1, one side surface movable mounting of tool box 1 has closed case lid 2, be provided with electric capacity current tester body 3 in the inner chamber of tool box 1, one side fixed surface of tool box 1 installs lateral part handle 4, the surface movable mounting that the inner chamber of tool box 1 is located electric capacity current tester body 3 has installation device 5, the surface movable mounting of installation device 5 has buffering extension board 6, installation device 5 includes spacing splint 501, direction draw runner 502, take out handle 503, second adsorbs magnetic path 504 and reset spring 505.
The upper surface of electric capacity current tester body 3 is provided with liquid crystal display 301, one side that electric capacity current tester body 3's upper surface is located liquid crystal display 301 is provided with knob 302, one side that electric capacity current tester body 3's upper surface is located knob 302 is provided with first interface 303, one side that electric capacity current tester body 3's upper surface is located knob 302 is provided with second interface 305, one side that electric capacity current tester body 3's upper surface is located liquid crystal display 301 is provided with button 304.
A hinge 101 is fixedly mounted on one side surface of the tool box body 1 close to the upper end edge, a guide sliding groove 102 is formed in the upper end surface of the tool box body 1, a first adsorption magnetic block 103 is fixedly mounted on the inner bottom wall of the guide sliding groove 102, and the closed box cover 2 is rotatably connected with the tool box body 1 through the hinge 101.
In this embodiment, one side fixed surface of spacing splint 501 installs direction draw runner 502, the last fixed surface of direction draw runner 502 installs and takes out handle 503, the lower fixed surface of direction draw runner 502 installs the second and adsorbs magnetic path 504, fixed mounting has reset spring 505 between the spacing splint 501, nimble installation electric capacity current tester body 3 and instrument box 1, not only make things convenient for the maintenance of dismantling behind the electric capacity current tester body 3 trouble like this, also conveniently change damaged instrument box 1.
In this embodiment, a rubber pillar 601 is fixedly installed on the lower surface of the buffering support plate 6, a buffering cushion 602 is fixedly installed on the upper surface of the buffering support plate 6, a sliding shaft 605 is fixedly installed on the surface of one end of the buffering support plate 6, a sliding hole 606 is formed on the surface of the limiting clamp plate 501 at the sliding shaft 605, an embedding round hole 603 is formed on the inner bottom wall of the tool box body 1, a buffering block 604 is filled in the embedding round hole 603, in use, the buffering support plate 6 is embedded into the embedding round hole 603 through the rubber support 601, the bottom of the tool box body 1 can be buffered with collision force through the buffer block 604 after being shocked, and the buffer support plate 6 is provided with the buffer cushion 602 on the upper surface, so that the adverse effect of the shock on the capacitance current tester body 3 can be further reduced, the collision force at the bottom of the multiple buffer is reduced, and the risk of the bottom of the capacitance current tester body 3 in the tool box body 1 being shocked and damaged is reduced.
Two groups of limiting clamping plates 501 are symmetrically arranged in the inner cavity of the tool box body 1, two ends of a return spring 505 are fixedly connected with the end faces of the limiting clamping plates 501, the limiting clamping plates 501 are slidably connected with the guide sliding groove 102 through guide sliding strips 502, and are fixed in a limiting mode after being adsorbed by the first adsorbing magnetic blocks 103 of the guide sliding groove 102 through the second adsorbing magnetic blocks 504.
It should be noted that, the utility model relates to a distribution network overhauls equipment of patrolling and examining, before using, the spacing splint 501 slides into the inside of guide chute 102 through the guide slide bar 502, and limit fixedly after adsorbing with the first adsorption magnetic block 103 of guide chute 102 through the second adsorption magnetic block 504, pull the spacing splint 501 to both sides, make reset spring 505 stretch, in this process, the clearance between two spacing splints 501 enlarges, can imbed the electric capacity current tester body 3 into the interior region of spacing splint 501 subsequently, thus two spacing splints 501 grip the fixed electric capacity current tester body 3 from two directions simultaneously, and then install electric capacity current tester body 3 and tool box 1 flexibly, thus not only facilitate the electric capacity current tester body 3 to dismantle the maintenance after the trouble, also facilitate changing the damaged tool box 1, in the use, the buffering extension board 6 imbeds the inside of round hole 603 through the rubber pillar 601, the bottom of the tool box body 1 can be buffered with collision force through the buffer block 604 after being shocked, and the buffer support plate 6 is provided with the buffer cushion 602 on the upper surface, so that the adverse effect of the shock on the capacitance current tester body 3 can be further reduced, the collision force at the bottom of the multiple buffer is reduced, and the risk of the bottom of the capacitance current tester body 3 in the tool box body 1 being shocked and damaged is reduced.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a distribution network overhauls equipment of patrolling and examining which characterized in that: including instrument box (1), one side surface movable mounting of instrument box (1) has closed case lid (2), be provided with electric capacity current tester body (3) in the inner chamber of instrument box (1), one side fixed surface of instrument box (1) installs lateral part handle (4), the surface movable mounting that the inner chamber of instrument box (1) is located electric capacity current tester body (3) has installation device (5), the surface movable mounting of installation device (5) has buffering extension board (6), installation device (5) include spacing splint (501), direction draw runner (502), take out handle (503), second adsorb magnetic path (504) and reset spring (505).
2. The distribution network overhauls equipment of claim 1, characterized in that: the upper surface of electric capacity current tester body (3) is provided with liquid crystal display (301), one side that the upper surface of electric capacity current tester body (3) is located liquid crystal display (301) is provided with knob (302), one side that the upper surface of electric capacity current tester body (3) is located knob (302) is provided with first interface (303), one side that the upper surface of electric capacity current tester body (3) is located knob (302) is provided with second interface (305), one side that the upper surface of electric capacity current tester body (3) is located liquid crystal display (301) is provided with button (304).
3. The distribution network overhauls equipment of claim 2, characterized in that: the tool box is characterized in that a hinge (101) is fixedly mounted on one side surface of the tool box body (1) close to the upper end edge, a guide sliding groove (102) is formed in the upper end face of the tool box body (1), a first adsorption magnetic block (103) is fixedly mounted on the inner bottom wall of the guide sliding groove (102), and the closed box cover (2) is rotatably connected with the tool box body (1) through the hinge (101).
4. The distribution network overhauls equipment of claim 3, characterized in that: fixed surface installs direction draw runner (502) in one side of spacing splint (501), the last fixed surface of direction draw runner (502) installs and takes out handle (503), the lower fixed surface of direction draw runner (502) installs second and adsorbs magnetic path (504), fixed mounting has reset spring (505) between spacing splint (501).
5. The distribution network overhauls equipment of claim 4, characterized in that: the lower fixed surface of buffering extension board (6) installs rubber support (601), the last fixed surface of buffering extension board (6) installs buffering cushion (602), the one end fixed surface of buffering extension board (6) installs slide shaft (605), slide opening (606) have been seted up in slide shaft (605) department on the surface of spacing splint (501), embedding round hole (603) have been seted up to the inner bottom wall of instrument box (1), the inside packing of embedding round hole (603) has buffer block (604).
6. The distribution network overhaul inspection device of claim 5, wherein: two groups of limiting clamping plates (501) are symmetrically arranged in an inner cavity of the tool box body (1), two ends of the reset spring (505) are fixedly connected with the end faces of the limiting clamping plates (501), the limiting clamping plates (501) are connected with the guide sliding groove (102) in a sliding mode through the guide sliding strip (502), and are fixed in a limiting mode after being adsorbed with the first adsorbing magnetic block (103) of the guide sliding groove (102) through the second adsorbing magnetic block (504).
CN202120185930.4U 2021-01-22 2021-01-22 Distribution network overhauls equipment of patrolling and examining Active CN214895606U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120185930.4U CN214895606U (en) 2021-01-22 2021-01-22 Distribution network overhauls equipment of patrolling and examining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120185930.4U CN214895606U (en) 2021-01-22 2021-01-22 Distribution network overhauls equipment of patrolling and examining

Publications (1)

Publication Number Publication Date
CN214895606U true CN214895606U (en) 2021-11-26

Family

ID=78862510

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120185930.4U Active CN214895606U (en) 2021-01-22 2021-01-22 Distribution network overhauls equipment of patrolling and examining

Country Status (1)

Country Link
CN (1) CN214895606U (en)

Similar Documents

Publication Publication Date Title
CN214895606U (en) Distribution network overhauls equipment of patrolling and examining
CN212658736U (en) Portable cable sheath protector tester
CN220016632U (en) Novel portable auxiliary assembly that checks meter
CN209467017U (en) A kind of metro traction power supply device
CN209342771U (en) A kind of electric power detection device mounting bracket easy to use
CN207231702U (en) A kind of pressure vacuum gauge
CN220731682U (en) Adjustable new energy automobile battery protection device
CN210071727U (en) Power grid salt density and ash density detection device
CN219801982U (en) On-vehicle wireless clamping structure that fills
CN218534499U (en) Electric power overhauls toolbox
CN205972422U (en) Portable box of apparatus
CN219892628U (en) Power box for power engineering
CN216820325U (en) Safety device for electrical equipment
CN217011350U (en) Power plant electrical and thermal integrated control device
CN219067503U (en) Power distribution and utilization monitoring terminal with protection function
CN213424557U (en) Zither tuning device for zither training
CN213656127U (en) Fixed equipment of placing of electrical instrument
CN210922834U (en) Portable dustproof noise monitoring device
CN216812665U (en) Buffer mechanism for endurance power supply
CN214586869U (en) Test generator for software test
CN211784937U (en) Little water on-line monitoring device of density
CN219521935U (en) High-insulation and convenient-to-apply dismounting clamp
CN210269776U (en) Portable online monitoring device for dissolved gas in transformer oil
CN213482340U (en) Full-automatic transformation ratio group tester
CN220010609U (en) Waste sheet collecting box for solar cell production

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant