CN214884254U CN202121017470.0U CN202121017470U CN214884254U CN 214884254 U CN214884254 U CN 214884254U CN 202121017470 U CN202121017470 U CN 202121017470U CN 214884254 U CN214884254 U CN 214884254U
Authority
CN
China
Prior art keywords
well
sewage
lift
lifting
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121017470.0U
Other languages
Chinese (zh)
Inventor
林彩虹
赵磊
周中太
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202121017470.0U priority Critical patent/CN214884254U/en
Application granted granted Critical
Publication of CN214884254U publication Critical patent/CN214884254U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model provides a sewage lifting well for reforming construction projects, belonging to the technical field of sewage treatment; be located underground lift well both ends and be provided with inlet tube and outlet pipe respectively, lift well upper portion is provided with the access hole, and access hole department is connected with the breather pipe, and the breather pipe other end extends to and just is provided with breather pipe cover on the ground, can guarantee that the circulation of air is smooth and easy in the well, pressure stability. A short wall is arranged in the lift well, and a grid is arranged at the top of the short wall to divide the inner space of the lift well into two parts, namely a first well pool and a second well pool; partial impurity in the sewage can be precipitated in first well pond, and the floater in the sewage can be filtered to the grid, guarantees that the smooth and easy work of sewage elevator pump in the second well pond avoids blockking up, effectively improves sewage treatment efficiency, promotes the reliability of construction transformation project intermediate temporary pipeline drainage system to a great extent.

Description

A sewage lifting shaft for reforming transform construction project
Technical Field
The utility model belongs to the technical field of sewage treatment, especially, relate to a sewage lifting shaft for reforming transform construction project.
Background
In the process of urban rainwater and sewage diversion engineering, old community transformation and large project staging and batching construction, a lot of projects have had rain sewage pipelines before the construction, face the condition of construction while using, according to the on-the-spot construction excavation demand, need cut off original pipeline before the construction, carry out the pipeline trend adjustment during the construction, increase sewage hoisting device. The upper end of a pipeline system in old engineering is mostly not provided with a rainwater grate, and as rainwater pipelines are generally large, a lot of ground garbage can enter a rainwater and sewage pipeline system along with the rainwater and sewage pipeline system in heavy rain; in addition, as the transformation projects are all in historical old areas, the arrangement and maintenance of pipelines are not good, and sometimes, workers do not collect domestic garbage according to the standard, and open individual sewage well covers nearby to serve as garbage dumping openings. Under the influence of the above factors, the existing sewage lifting device is often blocked when in use, and the sewage lifting shaft is paralyzed in use, so how to reasonably modify the existing sewage lifting shaft becomes one of the problems to be solved urgently in the current modification construction project.
SUMMERY OF THE UTILITY MODEL
To exist not enough among the prior art, the utility model provides a sewage lifting well for reforming transform construction project utilizes quarter wall and grid to be divided into two with lifting well inner space, and sewage is through deposiing and grid filtration back, by outlet pipe discharge under the effect of sewage lift pump, has effectively solved the jam problem of sewage lift pump, and sewage treatment efficiency is high.
The utility model discloses a realize above-mentioned technical purpose through following technological means.
A sewage lifting well for improving construction projects is characterized in that a water inlet pipe and a water outlet pipe are respectively arranged at two ends of the lifting well which is located underground, an access hole is formed in the upper portion of the lifting well, a vent pipe is connected to the access hole, and the other end of the vent pipe extends to the ground and is provided with a vent pipe cover; a short wall is arranged in the lift well, a grid is arranged at the top of the short wall, and the short wall and the grid divide the inner space of the lift well into two parts, namely a first well pool and a second well pool; and a sewage lifting pump is arranged in the second well pool, and a water outlet of the sewage lifting pump is connected with a water outlet pipe.
Further, the volume ratio of the first well pool to the second well pool is 2: 1.
furthermore, the water inlet pipe adopts a DN300 pipeline, and the water outlet pipe and the vent pipe both adopt DN100 pipelines.
Further, the diameter of the access hole is 700 mm.
Further, the height of the breather pipe cover is 300 mm.
Further, the heights of the lift well and the short wall are set according to the parameters of the sewage lift pump.
The utility model discloses following beneficial effect has:
the utility model provides a sewage lifting shaft for reforming transform construction project through quarter wall and grid, is divided into two with lifting shaft inner space, and sewage is after first well pond deposits, and through the grid filtration, later flow in second well pond, by outlet pipe discharge under the effect of sewage lift pump, avoided impurity such as silt, floater in the sewage to block up sewage lift pump, help improving sewage treatment efficiency, can promote the reliability of construction transformation project intermediate temporary pipeline drainage system to a great extent.
Drawings
FIG. 1 is a cross-sectional view of a sewage lifting well according to the present invention;
FIG. 2 is a top view of the sewage lifting well of the present invention;
in the figure: 1-water inlet pipe; 2-water outlet pipe; 3-a breather pipe; 4-a breather pipe cover; 5-grating; 6-sewage lift pump; 7-short wall; 8, a maintenance port; 9-a first well basin; 10-second well.
Detailed Description
The invention will be further described with reference to the drawings and the following examples, but the scope of the invention is not limited thereto.
As shown in figure 1, a sewage lifting well for reforming transform construction project, including inlet tube 1, outlet pipe 2, breather pipe 3, breather pipe casing 4, grid 5, sewage elevator pump 6, quarter wall 7 and access hole 8.
As shown in fig. 1 and 2, a water inlet pipe 1 and a water outlet pipe 2 are respectively arranged at two ends of an underground lifting well, and an access hole 8 is arranged at the upper part of the lifting well; one end of the vent pipe 3 is communicated with the access hole 8, the other end of the vent pipe extends to the ground and is provided with a vent pipe cover 4, so that smooth air circulation in the well can be ensured, and the pressure is stable. A short wall 7 is arranged in the lift well, a grid 5 is arranged at the top of the short wall 7, and the short wall 7 and the grid 5 divide the inner space of the lift well into two parts, namely a first well pool 9 and a second well pool 10; inlet tube 1 and first wellhole pond 9 intercommunications, the volume ratio of first wellhole pond 9 and second wellhole pond 10 is 2: 1; first well pond can deposit the granule impurity in the sewage, and the floater in the sewage can be filtered to grid 5. A sewage lifting pump 6 with a cutter device is arranged in the second well pool 10, and the water outlet of the sewage lifting pump 6 is connected with the water outlet pipe 2; in actual construction, the overall height of the lift shaft and the short wall 7 is set according to the parameters of the sewage lift pump 6.
In this embodiment, preferably, the water inlet pipe 1 is a DN300 pipe, the water outlet pipe 2 is a DN100 pipe, and the air pipe 3 is a DN100 pipe; the diameter of the access hole 8 is 700 mm; the height of the snorkel cover 4 is 300 mm.
In practical application, sewage flows into the first well tank through the water inlet pipe 1 and is precipitated in the first well tank 9, so that the subsequent sewage lift pump 6 can work normally and cannot be blocked by silt and the like; when the water level of the first well basin 9 is higher than the height of the short wall 7, the sewage in the first well basin 9 after sedimentation flows into the second well basin 10, the sewage in the second well basin 10 is conveyed out through the water outlet pipe 2 by utilizing the sewage lifting pump 6, and in the process, the grids 5 at the top of the short wall 7 can further filter sundries such as plastic bags floating on the water surface, and the normal work of the sewage lifting pump 6 is ensured. Sewage lifting shaft can deposit, filtration treatment to various impurity in the sewage and floater for sewage elevator pump 6 can function smoothly, guarantees sewage lifting efficiency, has promoted the reliability of construction transformation in-process interim pipeline drainage system greatly.
The embodiment is a preferred embodiment of the present invention, but the present invention is not limited to the above embodiment, and any obvious improvement, replacement or modification which can be made by those skilled in the art without departing from the essence of the present invention belongs to the protection scope of the present invention.

Claims (6)

1. A sewage lifting well for improving construction projects is characterized in that a water inlet pipe (1) and a water outlet pipe (2) are respectively arranged at two ends of the lifting well positioned underground, an access hole (8) is formed in the upper portion of the lifting well, a vent pipe (3) is connected to the access hole (8), and the other end of the vent pipe (3) extends to the ground and is provided with a vent pipe cover (4); a short wall (7) is arranged in the lift well, a grid (5) is arranged at the top of the short wall (7), and the short wall (7) and the grid (5) divide the inner space of the lift well into two parts, namely a first well pool (9) and a second well pool (10); a sewage lifting pump (6) is arranged in the second well pool (10), and the water outlet of the sewage lifting pump (6) is connected with the water outlet pipe (2).
2. Sewage lift well for retrofitting construction projects according to claim 1, characterized in that the volume ratio of said first well basin (9) to said second well basin (10) is 2: 1.
3. the sewage lifting well for reforming construction projects according to claim 1, wherein the water inlet pipe (1) adopts DN300 pipeline, and the water outlet pipe (2) and the air pipe (3) adopt DN100 pipeline.
4. The sewage lift shaft for rebuilding construction projects of claim 1, wherein said access opening (8) is 700mm in diameter.
5. The sewage lift shaft for rebuilding construction projects of claim 1, wherein said snorkel shield (4) has a height of 300 mm.
6. The sewage lift shaft for retrofitting a construction project according to claim 1, characterized in that the height of the lift shaft and of the stub wall (7) is set according to the parameters of the sewage lift pump (6).
CN202121017470.0U 2021-05-13 2021-05-13 A sewage lifting shaft for reforming transform construction project Active CN214884254U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121017470.0U CN214884254U (en) 2021-05-13 2021-05-13 A sewage lifting shaft for reforming transform construction project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121017470.0U CN214884254U (en) 2021-05-13 2021-05-13 A sewage lifting shaft for reforming transform construction project

Publications (1)

Publication Number Publication Date
CN214884254U true CN214884254U (en) 2021-11-26

Family

ID=78890812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121017470.0U Active CN214884254U (en) 2021-05-13 2021-05-13 A sewage lifting shaft for reforming transform construction project

Country Status (1)

Country Link
CN (1) CN214884254U (en)

Similar Documents

Publication Publication Date Title
CN211621640U (en) Well water circulating system of foundation pit dewatering well
CN201635168U (en) Automatic upgrading device for sewage of rest room of basement
CN214089309U (en) Sponge urban road storage drainage structure
CN214884254U (en) A sewage lifting shaft for reforming transform construction project
CN206138806U (en) Waste water sedimentation pond's cleaning device
CN105536313B (en) Sewage-treatment plant and sewage lifting system
CN212127752U (en) Improved oil separation tank
CN216108848U (en) A energy-conserving integration sewage pump station for crossing a river
CN206090805U (en) No deposit formula sewage lifting pump station
CN215253321U (en) Drainage system of underpass tunnel
CN210976044U (en) Wall-mounted micro drainage pump station for sewage interception engineering
CN209620172U (en) Novel inverted siphon water pipeline mud discharging and emptying structure
CN207295964U (en) A kind of horizontal prefabricated pumping plant of integration
CN212689184U (en) Integrated assembly type deep tunnel regulation pump station pre-spiral water collecting device
CN105002980A (en) Integrated pumping station bottom self-cleaning method
CN110725394A (en) Full-automatic drainage system and drainage method beneficial to prolonging service life of water pump
CN214143603U (en) Automatic sedimentation, filtration and energy-saving water return system for leachate in refuse dump
CN216075447U (en) Low-carbon environment-friendly overflow pollution control intercepting well
CN110029723A (en) A kind of large-scale integrated pump station that there is slagging-off to collect for three barrels of parallel connections
CN218911592U (en) Initial rainwater collecting device
CN221020562U (en) Magnetic material grinding material recovery system
CN221513601U (en) Unilateral drainage V-shaped filter tank capable of preventing sand from running
CN217460843U (en) Intercepting well capable of reducing sludge blockage
CN212052825U (en) Foundation pit dewatering system
CN212914817U (en) Mining static pressure water filter equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant