CN214789780U - Temporary leakage repairing assembly for PE pipe - Google Patents

Temporary leakage repairing assembly for PE pipe Download PDF

Info

Publication number
CN214789780U
CN214789780U CN202121363902.3U CN202121363902U CN214789780U CN 214789780 U CN214789780 U CN 214789780U CN 202121363902 U CN202121363902 U CN 202121363902U CN 214789780 U CN214789780 U CN 214789780U
Authority
CN
China
Prior art keywords
wall
pipe
interim
block
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121363902.3U
Other languages
Chinese (zh)
Inventor
徐志强
陈浩生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Runsoo Pipe Industry Co ltd
Original Assignee
Jiangsu Runsoo Pipe Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Runsoo Pipe Industry Co ltd filed Critical Jiangsu Runsoo Pipe Industry Co ltd
Priority to CN202121363902.3U priority Critical patent/CN214789780U/en
Application granted granted Critical
Publication of CN214789780U publication Critical patent/CN214789780U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pipe Accessories (AREA)

Abstract

The utility model discloses an interim mending-leakage subassembly for PE pipe, including the interim mending-leakage subassembly main part of PE pipe, still be provided with interim mending-leakage subassembly coupling mechanism of PE pipe, holding ring, leak protection ring mechanism, first installation piece, second installation piece, connect with installation piece, button head slider, spacing circle piece, reset spring, fixed stereoplasm cover, soft rubber cover and fixed logical groove. A interim mending-leakage subassembly for PE pipe, connect through the setting with installation piece, round-head slider, spacing circle piece and reset spring are convenient to be connected first installation piece and second installation piece or unpack apart, on the PE pipe that leaks is installed to the convenient interim mending-leakage subassembly main part of PE pipe, the soft rubber cover in the leak protection mechanism of rethread setting reduces the gap that PE pipe and the interim mending-leakage subassembly main part of PE pipe were installed together, reduce the possibility that the infiltration appears, for the interim mending-leakage subassembly field of PE pipe has brought better use prospect.

Description

Temporary leakage repairing assembly for PE pipe
Technical Field
The utility model relates to a PE manages interim trapping assembly field, specifically is an interim trapping assembly for PE manages.
Background
The PE pipe is also called a polyethylene pipe, the PE pipe has wide application fields, wherein a water supply pipe and a gas pipe are two largest application markets, the material of the polyethylene pipe is divided into five grades of PE32, PE40, PE63, PE80 and PE100 internationally, the material for the gas pipe and the water supply pipe is mainly PE80 and PE100, China has no classification on the special material of the polyethylene pipe, so that domestic polyethylene gas pipes and water supply pipe manufacturers have difficulty in selecting raw materials, and the polyethylene pipe is not slightly hidden danger in use, therefore, the national standard bureau makes a large amount of revisions in a GB/T13663-2000 new standard, specifies different pressure strengths corresponding to different grades of the PE80 and the PE100 of the water supply pipe, removes the tensile strength performance in the old standard, increases the elongation at break (more than 350%), and emphasizes basic toughness.
When the existing temporary leakage repairing assembly for the PE pipe is installed and used, the following two problems exist:
1. the existing temporary leakage repairing assembly for the PE pipe is installed by adopting bolts and nuts, and the time required by installation is long when the temporary leakage repairing assembly is reused.
2. When the conventional temporary leakage repairing assembly for the PE pipe is used, a gap exists between the PE pipe and the temporary leakage repairing assembly for the PE pipe, and the leakage of the PE pipe easily flows out from the gap between the PE pipe and the temporary leakage repairing assembly for the PE pipe.
In view of the above disadvantages, a temporary leak repairing assembly for PE pipes is proposed to overcome the above problems.
SUMMERY OF THE UTILITY MODEL
Solves the technical problem
The utility model provides a not enough to prior art, the utility model provides a interim mending-leakage subassembly for PE pipe possesses convenient ann and tears and reduce advantages such as oozing that PE pipe leaked as far as, can effectively solve the problem in the background art.
Technical scheme
In order to achieve the above purpose, the utility model adopts the following technical scheme: the utility model provides an interim mending-leakage subassembly for PE pipe, includes the interim mending-leakage subassembly main part of PE pipe, the upper and lower end surface integrated into one piece holding ring of the interim mending-leakage subassembly main part of PE pipe, two sets of interim mending-leakage subassembly coupling mechanisms of PE pipe of the interim mending-leakage subassembly main part of outer wall fixed connection of PE pipe, every group the interim mending-leakage subassembly coupling mechanism of a set of PE pipe of outer wall fixed connection of holding ring, the interim mending-leakage subassembly main part of PE pipe can be dismantled with the inner wall of holding ring and be connected leak protection mechanism.
Preferably, a set of temporary leakage repairing assembly connecting mechanism for the PE pipe comprises a first mounting block, a second mounting block, a mounting block for connection, a round-head sliding block, a limiting round block and a return spring.
Preferably, first installation piece is located the one end surface of second installation piece, it is located the inner wall of first installation piece and second installation piece to connect with the installation piece, the button head slider is provided with two sets ofly, and all is located the upper end internal surface of connecting with the installation piece, spacing circle piece is provided with two sets ofly, and is located the lower extreme surface of two sets of button head sliders respectively, reset spring is provided with two sets ofly, and is located the lower extreme surface of two sets of spacing circles piece respectively.
Preferably, a movable groove is arranged between the first mounting block and the mounting block for connection, the inner wall of the first mounting block is movably connected with the outer wall of the mounting block for connection through the movable groove, a movable groove is arranged between the second mounting block and the mounting block for connection, the inner wall of the second mounting block is movably connected with the outer wall of the mounting block for connection through the movable groove, a movable groove is arranged between the mounting block for connection and the round-head sliding block, the inner surface of the upper end of the mounting block for connection is movably connected with the outer wall of the round-head sliding block through the movable groove, a movable groove is arranged between the mounting block for connection and the limiting round block, the inner wall of the mounting block for connection is movably connected with the outer wall of the limiting round block through the movable groove, the round-head sliding block and the limiting round block are integrally formed, and the reset spring is located in a movable groove between the mounting block for connection and the limiting round block.
Preferably, the leakage-proof mechanism comprises a fixed hard sleeve, a soft rubber sleeve and a fixed through groove, the fixed hard sleeve is located on the outer wall of the soft rubber sleeve, the fixed through groove is provided with sixteen groups, eight groups the fixed through groove is located around the upper end and the lower end of the outer wall of the fixed hard sleeve, the other eight groups of the fixed through groove is located around the upper end and the lower end of the outer wall of the soft rubber sleeve, and the fixed through grooves on the fixed hard sleeve and the soft rubber sleeve correspond to each other.
Preferably, waterproof glue is arranged between the fixed hard sleeve and the soft rubber sleeve, the inner wall of the fixed hard sleeve is fixedly connected with the outer wall of the soft rubber sleeve through the waterproof glue, and the fixed through grooves are formed in the periphery of the upper end and the lower end of the outer wall of the fixed hard sleeve and the outer wall of the soft rubber sleeve.
Compared with the prior art, the utility model discloses following beneficial effect has:
the utility model discloses in, connect with installation piece, round head slider, spacing boss and reset spring through setting up and conveniently be connected first installation piece and second installation piece or unpack apart, conveniently with PE pipe mend leakage subassembly main part temporarily install the PE pipe that leaks on, the soft rubber cover in the leak protection mechanism of rethread setting reduces PE pipe and the PE pipe and mends leakage subassembly main part temporarily and install the gap together, reduces the possibility that the infiltration appears.
Drawings
Fig. 1 is the utility model relates to an overall structure schematic diagram of interim trapping assembly for PE pipe.
Fig. 2 is the utility model relates to a PE manages interim trapping assembly coupling mechanism's structural schematic in interim trapping assembly for PE manages.
Fig. 3 is the utility model relates to a show picture of first installation piece and second installation piece in interim mending-leakage subassembly for PE pipe.
Fig. 4 is the utility model relates to a connect in interim trapping assembly of PE pipe with the show picture of installation piece and button head slider.
Fig. 5 is a schematic diagram of an enlarged view of a portion a of fig. 4 according to the present invention.
Fig. 6 is a schematic structural view of a leakage-proof mechanism in a temporary leakage-repairing assembly for a PE pipe.
Fig. 7 is an exploded view of the leakage preventing mechanism in the temporary leakage repairing assembly for PE pipe of the present invention.
In the figure: 1. the PE pipe temporary leakage repairing assembly main body; 2. the temporary leakage repairing assembly connecting mechanism of the PE pipe; 3. a positioning ring; 4. a leakage prevention mechanism; 201. a first mounting block; 202. a second mounting block; 203. a mounting block for connection; 204. a round-head slider; 205. a limiting round block; 206. a return spring; 401. fixing a hard sleeve; 402. a soft rubber sleeve; 403. and fixing the through groove.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Detailed description of the preferred embodiment
The present embodiment is an embodiment of a temporary leak repair assembly for PE pipe.
As shown in fig. 1-7, an interim mending-leakage subassembly for PE pipe, including interim mending-leakage subassembly main part 1 of PE pipe, the interim mending-leakage subassembly main part 1's of PE pipe upper and lower end surface integrated into one piece holding ring 3, the interim mending-leakage subassembly main part 1's of PE pipe outer wall fixed connection two sets of interim mending-leakage subassembly coupling mechanisms 2 of PE pipe, the interim mending-leakage subassembly coupling mechanisms 2 of a set of PE pipe of the outer wall fixed connection of every group holding ring 3, the interim mending-leakage subassembly main part 1 of PE pipe can be dismantled with the inner wall of holding ring 3 and be connected leak protection mechanism 4.
The group of temporary leakage repairing assembly connecting mechanisms 2 for the PE pipes comprise a first mounting block 201, a second mounting block 202, a mounting block 203 for connection, a round-head sliding block 204, a limiting round block 205 and a return spring 206; the first mounting block 201 is located on the outer surface of one end of the second mounting block 202, the mounting blocks 203 for connection are located on the inner walls of the first mounting block 201 and the second mounting block 202, two groups of round-head sliders 204 are arranged and located on the inner surface of the upper end of the mounting blocks 203 for connection, two groups of limiting round blocks 205 are arranged and located on the outer surfaces of the lower ends of the two groups of round-head sliders 204 respectively, two groups of reset springs 206 are arranged and located on the outer surfaces of the lower ends of the two groups of limiting round blocks 205 respectively; a movable groove is arranged between the first mounting block 201 and the mounting block 203 for connection, the inner wall of the first mounting block 201 is movably connected with the outer wall of the mounting block 203 for connection through the movable groove, a movable groove is arranged between the second mounting block 202 and the mounting block 203 for connection, the inner wall of the second mounting block 202 is movably connected with the outer wall of the mounting block 203 for connection through the movable groove, a movable groove is arranged between the mounting block 203 for connection and the round-head slider 204, the inner surface of the upper end of the mounting block 203 for connection is movably connected with the outer wall of the round-head slider 204 through the movable groove, a movable groove is arranged between the mounting block 203 for connection and the limiting round block 205, the inner wall of the mounting block 203 for connection is movably connected with the outer wall of the limiting round block 205 through the movable groove, the round-head slider 204 and the limiting round block 205 are integrally formed, and a return spring 206 is positioned in the movable groove between the mounting block 203 for connection and the limiting round block 205; the leakage-proof mechanism 4 comprises a fixed hard sleeve 401, a soft rubber sleeve 402 and fixed through grooves 403, the fixed hard sleeve 401 is positioned on the outer wall of the soft rubber sleeve 402, sixteen groups of fixed through grooves 403 are arranged, eight groups of fixed through grooves 403 are positioned on the periphery of the upper end and the lower end of the outer wall of the fixed hard sleeve 401, the other eight groups of fixed through grooves 403 are positioned on the periphery of the upper end and the lower end of the outer wall of the soft rubber sleeve 402, and the fixed hard sleeve 401 and the fixed through grooves 403 on the soft rubber sleeve 402 correspond to each other; waterproof glue is arranged between the fixed hard sleeve 401 and the soft rubber sleeve 402, the inner wall of the fixed hard sleeve 401 is fixedly connected with the outer wall of the soft rubber sleeve 402 through the waterproof glue, and the fixed through groove 403 is formed in the periphery of the upper end and the lower end of the outer wall of the fixed hard sleeve 401 and the outer wall of the soft rubber sleeve 402.
It should be noted that, the present invention is a temporary leakage repairing assembly for PE pipe, which first presses a set of round-head sliders 204 on a mounting block 203 for connection, presses the round-head sliders 204 into the mounting block 203 for connection, and then puts this portion into the first mounting block 201 through the groove, so that the round-head sliders 204 reach between the first mounting block 201 and the second mounting block 202, and during this period, the round-head sliders 204 will be ejected by a return spring 206 because of the circular groove on the first mounting block 201, a limiting circular block 205 is provided to prevent the round-head sliders 204 from being ejected out of the temporary leakage repairing assembly connecting mechanism 2 for PE pipe, and then the ejected round-head sliders 204 are pressed into the mounting block 203 for connection, and then continue to push forward until reaching between the first mounting block 201 and the second mounting block 202, and then other mounting blocks 203 for connection are mounted into the first mounting block 201 in the same way, then, four sets of second mounting blocks 202 and four sets of first mounting blocks 201 provided with mounting blocks 203 for connection are mounted at the edges of the PE pipe temporary leakage repairing assembly main body 1 and the positioning ring 3, then two sets of round head sliders 204 on one set of mounting blocks 203 for connection are all pressed into the mounting blocks 203 for connection, then the mounting blocks 203 for connection are slid in through the grooves of the second mounting blocks 202, then the first mounting blocks 201 and the second mounting blocks 202 are put together, the mounting blocks 203 for connection are continuously pushed in, the two sets of round head sliders 204 are popped up due to the round grooves on the first mounting blocks 201 and the second mounting blocks 202, the first mounting blocks 201 and the second mounting blocks 202 are connected together, then the other three sets of first mounting blocks 201 and the second mounting blocks 202 are connected together, the PE pipe temporary leakage repairing assembly main body 1 is closed, and the soft rubber sleeve 402 is tightly attached to and acts on the PE pipe, the diameter of the soft rubber cover 402 that sets up after the circle is less than the diameter of PE pipe, can avoid PE pipe and the interim gap that produces between the subassembly main part 1 of mending leakage of PE pipe too big, lead to the infiltration, the fixed stereoplasm cover 401 of setting is stereoplasm deformable material, support for soft rubber cover 402 provides, avoid soft rubber cover 402 to cross softly, lead to unable lug and the fixed logical groove 403 that pass through on the holding ring 3 to install the inner wall at the interim subassembly main part 1 of mending leakage of PE pipe and lead to leak protection mechanism 4 unable performance.
Detailed description of the invention
The embodiment is an embodiment of a PE pipe temporary leak-stopping assembly connecting mechanism used on a temporary leak-stopping assembly for a PE pipe.
As shown in fig. 1-5, a PE pipe temporary leakage-stopping assembly connecting mechanism 2 for use in a temporary leakage-stopping assembly of a PE pipe, a set of PE pipe temporary leakage-stopping assembly connecting mechanism 2 includes a first mounting block 201, a second mounting block 202, a connecting mounting block 203, a round-head slider 204, two sets of limiting round blocks 205 and a return spring 206, the first mounting block 201 is located on an outer surface of one end of the second mounting block 202, the connecting mounting block 203 is located on an inner wall of the first mounting block 201 and the second mounting block 202, the round-head slider 204 is provided with two sets, and is located on an inner surface of an upper end of the connecting mounting block 203, the two sets of limiting round blocks 205 are provided, and are located on outer surfaces of lower ends of the two sets of round-head sliders 204, the return spring 206 is provided with two sets, and is located on outer surfaces of lower ends of the two sets of limiting round blocks 205, a movable groove is provided between the first mounting block 201 and the connecting mounting block 203, the inner wall of the first mounting block 201 is movably connected with the outer wall of the mounting block 203 for connection through a movable groove, the movable groove is arranged between the second mounting block 202 and the mounting block 203 for connection, the inner wall of the second mounting block 202 is movably connected with the outer wall of the mounting block 203 for connection through a movable groove, the movable groove is arranged between the mounting block 203 for connection and the round-head slider 204, the inner surface of the upper end of the mounting block 203 for connection is movably connected with the outer wall of the round-head slider 204 through a movable groove, the movable groove is arranged between the mounting block 203 for connection and the limiting round block 205, the inner wall of the mounting block 203 for connection is movably connected with the outer wall of the limiting round block 205 through a movable groove, the round-head slider 204 and the limiting round block 205 are integrally formed, and the reset spring 206 is positioned in the movable groove between the mounting block 203 for connection and the limiting round block 205.
Detailed description of the preferred embodiment
The present embodiment is an embodiment of a leak protection mechanism for use on a temporary leak repair assembly for PE tubing.
As shown in fig. 1 and 6 to 7, a leakage preventing mechanism 4 for a temporary leakage repairing assembly of a PE pipe, the leakage preventing mechanism 4 includes a fixed hard sleeve 401, a soft rubber sleeve 402 and fixed through grooves 403, the fixed hard sleeve 401 is located on the outer wall of the soft rubber sleeve 402, the fixed through grooves 403 are provided with sixteen groups, eight groups of fixed through grooves 403 are located around the upper end and the lower end of the outer wall of the fixed hard sleeve 401, the other eight groups of fixed through grooves 403 are located around the upper end and the lower end of the outer wall of the soft rubber sleeve 402, the fixed hard sleeve 401 corresponds to the fixed through grooves 403 on the soft rubber sleeve 402, waterproof glue is provided between the fixed hard sleeve 401 and the soft rubber sleeve 402, the inner wall of the fixed hard sleeve 401 is fixedly connected with the outer wall of the soft rubber sleeve 402 through the waterproof glue, and the fixed through grooves 403 are provided around the upper end and the lower end of the outer walls of the fixed hard sleeve 401 and the soft rubber sleeve 402.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a interim mending-leakage subassembly for PE pipe, includes interim mending-leakage subassembly main part (1) of PE pipe, its characterized in that: PE manages upper and lower end surface integrated into one piece holding ring (3) of interim trapping assembly main part (1), two sets of PE of the outer wall fixed connection of interim trapping assembly main part (1) manage interim trapping assembly coupling mechanism (2), every group the interim trapping assembly coupling mechanism (2) of a set of PE of the outer wall fixed connection of holding ring (3), the interim trapping assembly main part of PE pipe (1) can be dismantled with the inner wall of holding ring (3) and be connected leak protection mechanism (4).
2. A temporary leak repair assembly for PE tubing as claimed in claim 1 wherein: a group of temporary leakage repairing assembly connecting mechanism (2) for the PE pipe comprises a first mounting block (201), a second mounting block (202), a mounting block (203) for connection, a round-head sliding block (204), a limiting round block (205) and a return spring (206).
3. A temporary leak repair assembly for PE pipe according to claim 2, wherein: first installation piece (201) is located the one end surface of second installation piece (202), the inner wall that is located first installation piece (201) and second installation piece (202) is installed with installation piece (203) to the connection, button head slider (204) are provided with two sets ofly, and all are located the upper end internal surface of connecting with installation piece (203), spacing circle piece (205) are provided with two sets ofly, and are located the lower extreme surface of two sets of button head sliders (204) respectively, reset spring (206) are provided with two sets ofly, and are located the lower extreme surface of two sets of spacing circle pieces (205) respectively.
4. A temporary leak repair assembly for PE tubing as claimed in claim 3 wherein: a movable groove is arranged between the first installation block (201) and the connection installation block (203), the inner wall of the first installation block (201) is movably connected with the outer wall of the connection installation block (203) through the movable groove, a movable groove is arranged between the second installation block (202) and the connection installation block (203), the inner wall of the second installation block (202) is movably connected with the outer wall of the connection installation block (203) through the movable groove, a movable groove is arranged between the connection installation block (203) and the round-head slider (204), the inner surface of the upper end of the connection installation block (203) is movably connected with the outer wall of the round-head slider (204) through the movable groove, a movable groove is arranged between the connection installation block (203) and the limit round block (205), the inner wall of the connection installation block (203) is movably connected with the outer wall of the limit round block (205) through the movable groove, the round-head sliding block (204) and the limiting round block (205) are integrally formed, and the return spring (206) is located in a movable groove between the connecting mounting block (203) and the limiting round block (205).
5. A temporary leak repair assembly for PE tubing as claimed in claim 1 wherein: leak protection mechanism (4) are including fixed stereoplasm cover (401), soft rubber cover (402) and fixed logical groove (403), fixed stereoplasm cover (401) is located the outer wall of soft rubber cover (402), fixed logical groove (403) are provided with sixteen groups, eight groups fixed logical groove (403) are located around the lower extreme on fixed stereoplasm cover (401) outer wall, and eight groups in addition fixed logical groove (403) are located around the lower extreme on soft rubber cover (402) outer wall, and fixed stereoplasm cover (401) and the fixed logical groove (403) on soft rubber cover (402) correspond to each other.
6. A temporary leak repair assembly for PE pipe according to claim 5, wherein: waterproof glue is arranged between the fixed hard sleeve (401) and the soft rubber sleeve (402), the inner wall of the fixed hard sleeve (401) is fixedly connected with the outer wall of the soft rubber sleeve (402) through the waterproof glue, and the fixed through groove (403) is formed in the periphery of the upper end and the lower end of the outer wall of the fixed hard sleeve (401) and the outer wall of the soft rubber sleeve (402).
CN202121363902.3U 2021-06-19 2021-06-19 Temporary leakage repairing assembly for PE pipe Active CN214789780U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121363902.3U CN214789780U (en) 2021-06-19 2021-06-19 Temporary leakage repairing assembly for PE pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121363902.3U CN214789780U (en) 2021-06-19 2021-06-19 Temporary leakage repairing assembly for PE pipe

Publications (1)

Publication Number Publication Date
CN214789780U true CN214789780U (en) 2021-11-19

Family

ID=78713563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121363902.3U Active CN214789780U (en) 2021-06-19 2021-06-19 Temporary leakage repairing assembly for PE pipe

Country Status (1)

Country Link
CN (1) CN214789780U (en)

Similar Documents

Publication Publication Date Title
CN214789780U (en) Temporary leakage repairing assembly for PE pipe
CN207621568U (en) Three-way joint for water pipe repairs component
CN203614944U (en) Compression thread bonding type pipe connecting piece
CN201028218Y (en) Pipe fitting joint
CN215928692U (en) Cutting ferrule formula copper pipe fitting
CN202992501U (en) Connecting piece of plastic flared tube
CN216200860U (en) Check valve convenient to dismantle
CN211550824U (en) Stainless steel pipeline connecting piece for building fire fighting
CN202360965U (en) Pipeline connection device
CN219655527U (en) Corrosion-resistant oil suction hose
CN2381258Y (en) Sealed lining for telescopic pipe of dust cleaner
CN209696065U (en) A kind of adapter of catheter
CN208629909U (en) A kind of steel pipe is compound to use liner fixture
CN201827456U (en) Self-locking type one-way water outlet valve of bucket type hand-operated hydraulic giant
CN206449345U (en) A kind of construction drainage expansion joint structure
CN212016907U (en) Water inlet joint of pipeline water dispenser
CN201062692Y (en) Internal thread pressing type pipe fitting connecting piece
CN211259996U (en) Embedded screw-fixed rubber soft joint
CN221097808U (en) Clamp type rubber joint
CN217714064U (en) Water hose with connector
CN213393978U (en) Spraying switching device in coal mining machine
CN208295368U (en) A kind of pipe fitting with blocking function
CN215568921U (en) Lining structure for trenchless repairing of pipeline
CN210950252U (en) Throttle socket joint formula HDPE winding reinforcing pipe
CN219082513U (en) Thin-wall pipeline connecting piece for house

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A temporary leak repair component for PE pipe

Effective date of registration: 20220915

Granted publication date: 20211119

Pledgee: Bank of Jiangsu Co.,Ltd. Suining Sub branch

Pledgor: JIANGSU RUNSOO PIPE INDUSTRY CO.,LTD.

Registration number: Y2022320000548