Prior art keywords
chamber
outer baffle
conservancy diversion
water conservancy
curb
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120403991.3U
Other languages
Chinese (zh)
Inventor
夏秋菊
黄明
秦俊杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Hengchang Construction Co ltd
Original Assignee
Zhejiang Hengchang Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Hengchang Construction Co ltd filed Critical Zhejiang Hengchang Construction Co ltd
Priority to CN202120403991.3U priority Critical patent/CN214737088U/en
Application granted granted Critical
Publication of CN214737088U publication Critical patent/CN214737088U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model relates to a road paving structure relates to road paving's field, including permeable brick, backup pad and curb, the curb on be equipped with the drainage chamber, the permeable brick setting in the backup pad, the backup pad on be equipped with the water conservancy diversion hole, the water conservancy diversion hole upwards run through the backup pad, the permeable brick cover at the water conservancy diversion hole, the backup pad on still be equipped with the water conservancy diversion chamber, the water conservancy diversion chamber with the water conservancy diversion hole be linked together, the one end in water conservancy diversion chamber with the drainage chamber be linked together. This application has the effect that reduces the probability that the brick that permeates water rocked easily under using for a long time.

Description

Road paving structure
Technical Field
The application relates to the field of road pavement, in particular to a road pavement structure.
Background
At present urban road is mostly waterproof pavement, and waterproof road surface relies on the curb that sets up on the roadside to carry out the drainage, and consequently the rainwater is got rid of and flood discharge ability very limited through the road surface table, and when meetting heavy rainfall weather, ponding on a large scale will appear on the road surface.
Chinese patent CN208649830U discloses a firm type town road structure of mating formation that permeates water, including the brick that permeates water, the brick that permeates water is kept away from one side of curbstone and is provided with the curb, the curb is kept away from one side of the brick that permeates water and is provided with the carriageway, the inlet for stom water has been seted up to the surface one side of carriageway, the below of inlet for stom water is provided with the rainwater collecting vat, the bottom of the brick that permeates water is provided with the metalling, the below of metalling is provided with thick sand bed, the below on thick sand bed is provided with strutting arrangement, strutting arrangement includes the waterproof board, the top of waterproof board is provided with a plurality of backup pads, be provided with the support column between the bottom surface of backup pad and the top of waterproof board, strutting arrangement's below transversely is provided with the pipe of permeating water.
In view of the above-mentioned related technologies, the inventor believes that there is a defect that the gravel layer and the coarse sand layer are displaced after long-term use, and then the water permeable brick is easy to shake.
SUMMERY OF THE UTILITY MODEL
In order to reduce under the long-time use, the probability that the brick that permeates water rocked easily, this application provides a road pavement structure.
The application provides a road pavement structure adopts following technical scheme:
the utility model provides a road paving structure, includes brick, backup pad and the curb of permeating water, the curb on be equipped with the drainage chamber, the brick setting of permeating water in the backup pad, the backup pad on be equipped with the water conservancy diversion hole, the water conservancy diversion hole upwards run through the backup pad, the brick that permeates water cover in the water conservancy diversion hole, the backup pad on still be equipped with the water conservancy diversion chamber, the water conservancy diversion chamber with the water conservancy diversion hole be linked together, the one end in water conservancy diversion chamber with the drainage chamber be linked together.
Through adopting above-mentioned technical scheme, when using, because the brick setting of permeating water is in the backup pad, under the condition of long-time use, the probability that the backup pad takes place the displacement is lower, consequently make and to keep the good support effect to the brick that permeates water, consequently under long-time use, can reduce the probability that the brick that permeates water rocked easily, simultaneously, the rainwater can flow into to the water conservancy diversion intracavity from the water conservancy diversion hole after through the brick that permeates water to from water conservancy diversion intracavity flow to the drainage intracavity, consequently make the drainage effect of road better.
Preferably, the kerbstone on still be equipped with the water inlet, the water inlet with the drainage chamber be linked together, water inlet department be equipped with the sideboard, the sideboard on be equipped with the intake antrum, the intake antrum run through the sideboard make drainage chamber and external world be linked together.
Through adopting above-mentioned technical scheme, in the use, partial ponding can enter into to the inlet port through the intake chamber to from the water inlet entering drainage intracavity, consequently further strengthened the drainage effect, the existence of sideboard also can block debris simultaneously, effectively reduces the probability that debris entered into to the drainage intracavity.
Preferably, the barrier comprises an outer barrier and an inner barrier, and the outer barrier is slidably connected with the kerb.
Through adopting above-mentioned technical scheme, in use, when ponding is more, slide outer baffle for outer baffle and interior baffle coincide completely, consequently can make the intake chamber not receive and block, and then strengthen the drainage effect, when rainfall is not big, when ponding is less, slide outer baffle, make outer baffle and interior baffle partial coincidence, and then can shelter from the intake chamber on the interior baffle, thereby play and reduce the probability that debris got into to the drainage intracavity from the intake chamber.
Preferably, the interior baffle with curb fixed connection, the curb on still be equipped with the gliding spout of outer baffle of confession, the curb on still be equipped with the hidden chamber that is used for outer baffle to stretch into, the spout stretch into to hiding the intracavity.
Through adopting above-mentioned technical scheme, when using, outer baffle is not protruding in the curb, consequently in use, can reduce outer baffle because with external object collision and the probability of damaging.
Preferably, outer baffle on still be equipped with the suggestion chamber, the suggestion intracavity be equipped with the light-emitting unit, the suggestion chamber towards the direction of keeping away from interior baffle on run through outer baffle, the suggestion chamber on still be equipped with the light-passing board, the sealed suggestion chamber of light-passing board.
Through adopting above-mentioned technical scheme, in the use, because the existence of luminescence unit, consequently when ponding is more, the position of outer baffle of assurance that patrol personnel can be comparatively easy through light position to be convenient for patrol personnel and adjust the position of outer baffle.
Preferably, the outer baffle is further provided with a pulling block, the pulling block is located at one end, far away from the hidden cavity, of the outer baffle, and the prompting cavity is also located at one end, far away from the hidden cavity, of the outer baffle.
Through adopting above-mentioned technical scheme, in the use, pulling the piece and the suggestion chamber is located the patrol personnel of also being convenient for of same end and can find the piece that pulls fast for be more convenient for adjust the position of outer baffle.
Preferably, the outer baffle on still be equipped with the intake antrum, the intake antrum with the suggestion chamber each other not communicate, intake antrum and external world be linked together, the luminescence unit include lamp pearl, power and first wire and second wire, the one end of first wire and the positive pole electricity of power are connected, the one end and the lamp pearl electricity of second wire are connected, the negative pole electricity of lamp pearl and power is connected, the other end of first wire and second wire all is located the intake intracavity and each other not connected.
Through adopting above-mentioned technical scheme, when ponding is more, ponding can enter into the water cavity, and when first wire and second wire were located the one end of intaking the intracavity and all were located the ponding, the circuit switched on, and the lamp pearl is luminous to reach the effect of suggestion.
Preferably, the outer baffle on still be equipped with the holding tank, the pulling piece be located the holding tank and with outer baffle looks articulated, the pulling piece with hold the articulated department of groove mutually and be located the one end that the pulling piece is far away from ground.
Through adopting above-mentioned technical scheme, in use, when need not to adjust outer baffle position, the pulling piece is located the holding tank, consequently can reduce the occupation space of pulling the piece, and because the pulling piece is located the one end that the pulling piece is far away from ground with holding tank looks articulated department, consequently under the effect of gravity, the pulling piece is in the holding tank and is difficult for following and hold the inslot and shift out.
In summary, the present application includes at least one of the following beneficial technical effects:
the permeable brick is not easy to shake after being used for a long time;
when ponding is more, the existence of luminescence unit is more convenient for the inspection personnel to confirm the position of outer baffle.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present application.
Fig. 2 is a schematic cross-sectional structure diagram of an embodiment of the present application.
Fig. 3 is a schematic cross-sectional structure diagram of a curb according to an embodiment of the present application.
Fig. 4 is a schematic structural diagram of an outer baffle plate according to an embodiment of the application.
Description of reference numerals: 1. water permeable bricks; 2. a support plate; 21. a flow guide hole; 22. a flow guide cavity; 3. a curb; 31. a water inlet; 32. an auxiliary port; 33. a drainage cavity; 34. a chute; 35. a hidden cavity; 4. a sideboard; 41. a water inlet groove; 42. an outer baffle; 421. an outer plate; 422. an inner plate; 43. an inner baffle; 51. a prompt cavity; 511. a light-transmitting plate; 52. a water inlet cavity; 61. accommodating grooves; 62. and pulling the block.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses road pavement structure. Referring to fig. 1 and 2, the road curb comprises a curb 3, a support plate 2 and a water permeable brick 1 laid on the support plate 2, wherein a diversion hole 21 and a diversion cavity 22 are formed in the support plate 2, the diversion hole 21 is communicated with the diversion cavity 22, the diversion hole 21 upwards penetrates through the support plate 2 in the vertical direction, and the water permeable brick 1 covers the diversion hole 21.
Referring to fig. 2 and 3, the kerbstone 3 is arranged on one side of the road surface formed by the supporting plate 2 and the water permeable bricks 1, the kerbstone 3 is provided with a water drainage cavity 33, the kerbstone 3 is also provided with a water inlet 31 and an auxiliary port 32, and the water inlet 31 and the auxiliary port 32 are both communicated with the water drainage cavity 33. The diversion chamber 22 and the drainage chamber 33 are communicated through the auxiliary port 32.
Referring to fig. 2 and 3, water inlet 31 department is equipped with sideboard 4, be equipped with intake antrum 41 on sideboard 4, intake antrum 41 runs through sideboard 4 and makes drainage chamber 33 and external intercommunication, sideboard 4 includes outer baffle 42 and interior baffle 43, baffle 43 keeps away from the one side of drainage chamber 33 including outer baffle 42 sets up, interior baffle 43 and curb 3 fixed connection, curb 3 is last to have seted up spout 34 and hidden chamber 35, hidden chamber 35 sets up and is linked together in one side of water inlet 31 and with water inlet 31, spout 34 is seted up on the up end of water inlet 31 and lower terminal surface and is stretched into hidden chamber 35. The upper end of the outer baffle 42 is positioned in the chute 34 on the upper end face of the water inlet 31, and the lower end of the outer baffle 42 is positioned in the chute 34 on the lower end face of the water inlet 31, so as to realize the sliding connection between the outer baffle 42 and the kerb 3.
Referring to fig. 4, an accommodating groove 61 is further formed in one end of the outer baffle 42, which is far away from the hidden cavity 35, a pulling block 62 is hinged in the accommodating groove 61, and the hinged position of the pulling block 62 and the accommodating groove 61 is located at one end of the pulling block 62, which is far away from the ground.
When the rainwater falls on the permeable brick 1 in rainy weather, the rainwater seeps from the permeable brick 1 to the support plate 2, enters the diversion cavity 22 from the diversion hole 21, and finally enters the drainage cavity 33 in the kerbstone 3 through the diversion cavity 22. Part of the accumulated rainwater enters the drain chamber 33 from the inlet channel 41 at the inlet 31. Therefore, the water-collecting device can perform a good draining effect on the accumulated water. Meanwhile, the contact ratio between the outer baffle 42 and the inner baffle 43 can be adjusted through the pulling block 62 according to actual conditions, so that the purpose of adjusting the size of the water inlet tank 41 is achieved. That is, when the water inlet groove 41 on the outer baffle 42 and the water inlet groove 41 on the inner baffle 43 are not completely overlapped, the opening of the water inlet groove 41 is small, and the probability that external impurities enter the drainage cavity 33 can be effectively reduced.
Referring to fig. 2 and 4, the outer baffle 42 is further provided with a water inlet cavity 52 and a prompting cavity 51, the water inlet cavity 52 and the prompting cavity 51 are located at one end of the outer baffle 42 far away from the hidden cavity 35, and the prompting cavity 51 and the water inlet cavity 52 are not communicated with each other. Outer baffle 42 includes fixed connection's planking 421 and inner panel 422, and planking 421 are located the one side that water drainage chamber 33 was kept away from to inner panel 422, and planking 421 can be the plastics material, and inner panel 422 is the concrete material that permeates water, and suggestion chamber 51 sets up on planking 421, and intake antrum 52 sets up on inner panel 422. The suggestion chamber 51 runs through planking 421 in the direction of keeping away from interior baffle 43, still through glue fixedly connected with light-passing board 511 in the suggestion chamber 51, and light-passing board 511 is transparent acrylic board in this embodiment, and light-passing board 511 seals suggestion chamber 51. Be equipped with the luminescence unit in the suggestion chamber 51, the luminescence unit includes lamp pearl, power and first wire and second wire, and in this embodiment, the lamp pearl is LED lamp pearl, and the power is button cell. The lamp pearl is connected with the negative pole electricity of power, and the anodal one end electricity of first wire of power is connected, and the other end of first wire stretches into intake antrum 52, and the one end and the lamp pearl point of second wire are connected, and the other end of second wire stretches into and is connected to intake antrum 52 and not be located intake antrum 52 with first wire one end and be connected.
Great when rainfall, when curb 3 was submerged by ponding, ponding can enter into intake antrum 52 this moment for first wire and second wire switch on, and then make the circuit intercommunication, the lamp pearl is luminous. Thereby facilitating the position of the outer barrier 42 to be confirmed by the inspector.
The implementation principle of the road pavement structure of the embodiment of the application is as follows: when meetting rainfall weather, the rainwater can be followed brick 1 that permeates water and oozed to backup pad 2 department to flow to water conservancy diversion chamber 22 in from water conservancy diversion hole 21, and flow to water drainage chamber 33 in by water conservancy diversion chamber 22, when curb 3 is submerged simultaneously, ponding can enter into intake antrum 52 in, and then makes first wire and second wire switch on, and the lamp pearl is luminous, and then is convenient for patrol personnel and confirms the position of outer baffle 42.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a road pavement structure which characterized in that: including brick (1), backup pad (2) and curb (3) of permeating water, curb (3) on be equipped with drainage chamber (33), brick (1) of permeating water set up in backup pad (2), backup pad (2) on be equipped with water conservancy diversion hole (21), water conservancy diversion hole (21) upwards run through backup pad (2), brick (1) of permeating water cover in water conservancy diversion hole (21), backup pad (2) on still be equipped with water conservancy diversion chamber (22), water conservancy diversion chamber (22) with water conservancy diversion hole (21) be linked together, the one end in water conservancy diversion chamber (22) with drainage chamber (33) be linked together.
2. A road pavement structure as claimed in claim 1, wherein: curb (3) on still be equipped with water inlet (31), water inlet (31) with drainage chamber (33) be linked together, water inlet (31) department be equipped with sideboard (4), sideboard (4) on be equipped with intake chamber (41), intake chamber (41) run through sideboard (4) make drainage chamber (33) and external world be linked together.
3. A road pavement structure as claimed in claim 2, wherein: the baffle plate (4) comprises an outer baffle plate (42) and an inner baffle plate (43), and the outer baffle plate (42) is connected with the curb stone (3) in a sliding mode.
4. A road pavement structure as claimed in claim 3, wherein: interior baffle (43) with curb (3) fixed connection, curb (3) on still be equipped with and supply outer baffle (42) gliding spout (34), curb (3) on still be equipped with and be used for outer baffle (42) to stretch into hide chamber (35), spout (34) stretch into to hiding in chamber (35).
5. A road pavement structure as claimed in claim 4, wherein: outer baffle (42) on still be equipped with suggestion chamber (51), suggestion chamber (51) in be equipped with the luminescence unit, suggestion chamber (51) run through outer baffle (42) towards the direction of keeping away from inner baffle (43), suggestion chamber (51) on still be equipped with light-passing board (511), sealed suggestion chamber (51) of light-passing board (511).
6. A road pavement structure as claimed in claim 5, wherein: the outer baffle (42) on still be equipped with pulling piece (62), pulling piece (62) be located outer baffle (42) and keep away from the one end that hides chamber (35), suggestion chamber (51) also be located outer baffle (42) and keep away from the one end that hides chamber (35).
7. A road pavement structure as claimed in claim 5, wherein: outer baffle (42) on still be equipped with intake antrum (52), intake antrum (52) with suggestion chamber (51) each other not communicate, intake antrum (52) and external world be linked together, luminescence unit include lamp pearl, power and first wire and second wire, the one end of first wire and the positive pole electric connection of power, the one end and the lamp pearl electricity of second wire are connected, the negative pole electricity of lamp pearl and power is connected, the other end of first wire and second wire all is located intake antrum (52) and each other not connected.
8. A road pavement structure as claimed in claim 6, wherein: outer baffle (42) on still be equipped with holding tank (61), pulling piece (62) be located holding tank (61) and articulated mutually with outer baffle (42), pulling piece (62) and holding tank (61) articulated mutually locate to be located the one end that pulls piece (62) and keep away from ground.
CN202120403991.3U 2021-02-23 2021-02-23 Road paving structure Active CN214737088U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120403991.3U CN214737088U (en) 2021-02-23 2021-02-23 Road paving structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120403991.3U CN214737088U (en) 2021-02-23 2021-02-23 Road paving structure

Publications (1)

Publication Number Publication Date
CN214737088U true CN214737088U (en) 2021-11-16

Family

ID=78589573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120403991.3U Active CN214737088U (en) 2021-02-23 2021-02-23 Road paving structure

Country Status (1)

Country Link
CN (1) CN214737088U (en)

Similar Documents

Publication Publication Date Title
CN205171636U (en) Urban road rainwater collection utilization system
CN210002201U (en) Permeable pavement green belt drainage curb rain and sewage separation regulation and storage system
CN106638917B (en) Split type rainwater recycling, storing and adjusting system and construction method thereof
CN109338839B (en) Urban seepage storage system for recycling construction waste
CN214737088U (en) Road paving structure
CN213013738U (en) Sponge city water storage device
CN211898832U (en) Urban road drainage and water storage structure
CN217811979U (en) But green building of rainwater utilization
CN207861912U (en) A kind of filtration underground sand bed for sponge city
CN214497045U (en) Novel aerated concrete brick-containing recycled aggregate concrete permeable brick
CN205839924U (en) A kind of first rain separate tank of band automatic open close gate
CN210066404U (en) A central separation area curb for highway
CN210341533U (en) Multi-functional colored art spills black terrace
CN221345168U (en) Pavement structure of plaza
CN217629234U (en) Concrete road permeates water
CN217203452U (en) Sponge city drainage structures
CN218404904U (en) Town road rainwater back-seeping structure
CN209652684U (en) A kind of road drainage system
CN216239407U (en) Landscape type rainwater garden adopting ribbon to guide roof drainage
CN215405395U (en) Prevent sintering permeable pavement of ponding
CN221501623U (en) Sponge city oozes row structure and sponge city water circulation system
CN217203436U (en) Permeable pavement structure for city
CN213539069U (en) Well lid for town road
CN217460151U (en) Green energy-conserving municipal water-permeable pavement in sponge city
CN211713565U (en) Drainage tank rack for road paving

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant