CN214695583U - Long-distance pile feeding device for hammering tubular pile - Google Patents

Long-distance pile feeding device for hammering tubular pile Download PDF

Info

Publication number
CN214695583U
CN214695583U CN202121112941.6U CN202121112941U CN214695583U CN 214695583 U CN214695583 U CN 214695583U CN 202121112941 U CN202121112941 U CN 202121112941U CN 214695583 U CN214695583 U CN 214695583U
Authority
CN
China
Prior art keywords
pile
hammering
limiting
tubular pile
stop gear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121112941.6U
Other languages
Chinese (zh)
Inventor
冷亚夫
匡辉煌
樊友赣
冷淋涌
姚兴龙
丁金谱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiushui County Investment Real Estate Development Co ltd
Original Assignee
Xiushui County Investment Real Estate Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiushui County Investment Real Estate Development Co ltd filed Critical Xiushui County Investment Real Estate Development Co ltd
Priority to CN202121112941.6U priority Critical patent/CN214695583U/en
Application granted granted Critical
Publication of CN214695583U publication Critical patent/CN214695583U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model belongs to the technical field of hammering tubular pile foundation construction technique and specifically relates to a hammer tubular pile long distance pile feeder, including pile feeder mechanism, stop gear, hammering head, protruding falcon and precast tubular pile, wherein: on pile feeding mechanism's upper end fixed connection to stop gear, pile feeding mechanism's bottom fixed connection to protruding falcon, the hammering head plug-in connection to stop gear on, the precast tubular pile inserts and establishes to protruding falcon on, protruding falcon cooperatees with the inner wall of precast tubular pile. The utility model discloses a pile feeding mechanism passes through stop gear and connects the hammering head, and stop gear guarantees that pile feeding mechanism and hammering head laminating closely and axis and plane position do not squint when the hammering is under construction, and the protruding falcon of pile feeding device sub-unit connection, protruding falcon and the laminating of precast tubular pile inner wall are inseparable, ensure not squint in hammering in-process lower part butt joint, have greatly improved the straightness that hangs down of hammering precast tubular pile long distance pile feeding and the rate of accuracy of plane position, guarantee construction quality and safety.

Description

Long-distance pile feeding device for hammering tubular pile
Technical Field
The utility model relates to a hammering tubular pile basis construction technical field especially relates to a long distance pile feeding device of hammering tubular pile.
Background
In the construction of the prefabricated tubular pile foundation of the basement of the building construction, in order to ensure the construction period and avoid secondary foundation treatment of pile foundation operation, the long-distance pile feeding condition before basement excavation often exists, the perpendicularity and the plane position of the pile feeding within the range of 3 meters can be ensured by the conventional pile feeding device, the perpendicularity and the plane position of the long-distance pile feeding exceeding 3 meters are difficult to ensure, the pile quality and the loaded bias voltage of a bearing platform are directly influenced or not due to improper control of the perpendicularity and the plane position, the conventional long-distance pile feeding difficulty is large, the control of the perpendicularity and the plane position is poor, and the implementation effect is poor.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that the lower part of the hammering process is butted and deviated, the verticality of the long-distance pile feeding of the hammering precast tubular pile and the accuracy of the plane position are lower, and providing the long-distance pile feeding device of the hammering tubular pile.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the design is a long distance pile feeding device of hammering tubular pile, including pile feeding mechanism, stop gear, hammering head, protruding falcon and precast tubular pile, wherein:
the upper end fixed connection of pile feeding mechanism is in on the stop gear, the bottom fixed connection of pile feeding mechanism is in on the protruding falcon, the hammering head peg graft to on the stop gear, precast tubular pile insert establish to on the protruding falcon, protruding falcon with the inner wall of precast tubular pile cooperatees.
Preferably, the limiting mechanism comprises a limiting seat and a limiting groove, the limiting seat is fixedly connected to the pile feeding mechanism, the limiting groove is formed in the limiting seat, and the limiting groove is matched with the hammering head.
Preferably, the pile feeding mechanism, the limiting mechanism and the convex falcon are of an integral structure.
Preferably, the hammering head comprises a hammer head body and a limiting block, the hammer head body is matched with the limiting mechanism, and the limiting block is fixedly connected to the hammer head body and used for limiting.
Preferably, the bottom end of the hammer head body is fixedly connected with a positioning block, a groove is formed in the limiting mechanism, and the groove is matched with the positioning block.
The utility model provides a pair of hammer tubular pile long distance pile follower device, beneficial effect lies in:
the pile feeding device is characterized in that the limiting mechanism is connected with the hammering head, the limiting mechanism ensures that the pile feeding mechanism is tightly attached to the hammering head and the axis and the plane position are not deviated during hammering construction, the lower part of the pile feeding device is connected with the convex falcon, the convex falcon is tightly attached to the inner wall of the precast tubular pile, the lower part is ensured to be not deviated during hammering, the perpendicularity of the long-distance pile feeding of the hammered precast tubular pile and the accuracy of the plane position are greatly improved, and construction quality and safety are ensured.
Drawings
Fig. 1 is a schematic structural view of a long-distance pile feeding device for hammering a tubular pile, which is provided by the utility model;
fig. 2 is a schematic view of a cross-sectional structure of a long-distance pile feeding device for hammering a tubular pile, which is provided by the utility model;
fig. 3 is the utility model provides a stop gear's among tubular pile long distance pile feeder is hit to hammer structural schematic.
In the figure: pile feeding mechanism 1, stop gear 2, hammering head 3, protruding falcon 4, precast tubular pile 5, spacing seat 21, spacing groove 22, tup body 31, spacing 32, recess 6, locating piece 7.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Example 1
Referring to fig. 1-3, a long-distance pile feeding device for hammering tubular piles comprises a pile feeding mechanism 1, a limiting mechanism 2, a hammering head 3, a convex tenon 4 and a precast tubular pile 5, wherein:
on pile feeding mechanism 1's upper end fixed connection to stop gear 2, on pile feeding mechanism 1's bottom fixed connection to protruding falcon 4, protruding falcon 4 is used for cooperateing with precast tubular pile 5, and hammering head 3 pegs graft to stop gear 2 on, and hammering head 3 is used for hammering pile feeding mechanism 1, and precast tubular pile 5 inserts and establishes to protruding falcon 4 on, protruding falcon 4 cooperatees with precast tubular pile 5's inner wall, and pile feeding mechanism 1, stop gear 2 and protruding falcon 4 structure as an organic whole.
The working process is as follows: pile feeding mechanism 1 passes through stop gear and connects hammering head 3, and stop gear guarantees that pile feeding mechanism 1 and hammering head 3 laminating are inseparable and axis and plane position do not squint when hammering construction time limit, and pile feeding device sub-unit connection protruding falcon 4, protruding falcon 4 and 5 inner walls of precast tubular pile laminating are inseparable, guarantee not squint in hammering in-process lower part butt joint, have greatly improved the straightness that hangs down and the rate of accuracy of plane position of 5 long distance pile feeders of hammering precast tubular pile, guarantee construction quality and safety.
Example 2
Referring to fig. 1-3, as another preferred embodiment of the present invention, the difference from embodiment 1 is that the limiting mechanism 2 includes a limiting seat 21 and a limiting groove 22, the limiting seat 21 is fixedly connected to the pile feeding mechanism 1, the limiting groove 22 is formed on the limiting seat 21, the limiting groove 22 is matched with the hammering head 3, and the limiting groove 22 limits the hammering head 3, so that the pile feeding mechanism 1 is tightly attached to the hammering head 3 and the axis and the plane position do not deviate.
Example 3
Referring to fig. 1-3, as another preferred embodiment of the present invention, the difference from embodiment 1 is that the hammering head 3 includes a hammer head body 31 and a limiting block 32, the hammer head body 31 is matched with the limiting mechanism 2, and the hammer head body 31 is fixedly connected to the limiting block 32 for limiting.
Example 4
Referring to fig. 1-3, as another preferred embodiment of the present invention, the difference from embodiment 3 lies in that a positioning block 7 is fixedly connected to the bottom end of the hammer head body 31, a groove 6 is formed in the limiting mechanism 2, and the groove 6 is matched with the positioning block 7, so that the pile feeding mechanism 1 does not deviate from the axis and the plane position of the hammering head 3 when the hammer head body 31 hammers.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (5)

1. The utility model provides a hammer tubular pile long distance pile feeding device which characterized in that, includes pile feeding mechanism (1), stop gear (2), hammering head (3), tenon (4) and precast tubular pile (5), wherein:
the upper end fixed connection of pile feeding mechanism (1) is in on stop gear (2), the bottom fixed connection of pile feeding mechanism (1) is in on protruding falcon (4), hammering head (3) peg graft extremely on stop gear (2), precast tubular pile (5) are inserted and are established extremely on protruding falcon (4), protruding falcon (4) with the inner wall of precast tubular pile (5) cooperatees.
2. The long-distance pile feeding device for the hammered tubular piles according to claim 1, wherein the limiting mechanism (2) comprises a limiting seat (21) and a limiting groove (22), the limiting seat (21) is fixedly connected to the pile feeding mechanism (1), the limiting groove (22) is formed in the limiting seat (21), and the limiting groove (22) is matched with the hammering head (3).
3. The long-distance pile feeding device for the hammer pipe piles according to claim 1, wherein the pile feeding mechanism (1), the limiting mechanism (2) and the falcon (4) are of an integral structure.
4. The long-distance pile feeding device for the hammered pipe pile according to claim 1, wherein the hammering head (3) comprises a hammerhead body (31) and a limiting block (32), the hammerhead body (31) is matched with the limiting mechanism (2), and the limiting block (32) is fixedly connected to the hammerhead body (31) for limiting.
5. The long-distance pile feeding device for the hammering tubular pile as claimed in claim 4, wherein a positioning block (7) is fixedly connected to the bottom end of the hammer head body (31), a groove (6) is formed in the limiting mechanism (2), and the groove (6) is matched with the positioning block (7).
CN202121112941.6U 2021-05-24 2021-05-24 Long-distance pile feeding device for hammering tubular pile Expired - Fee Related CN214695583U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121112941.6U CN214695583U (en) 2021-05-24 2021-05-24 Long-distance pile feeding device for hammering tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121112941.6U CN214695583U (en) 2021-05-24 2021-05-24 Long-distance pile feeding device for hammering tubular pile

Publications (1)

Publication Number Publication Date
CN214695583U true CN214695583U (en) 2021-11-12

Family

ID=78553557

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121112941.6U Expired - Fee Related CN214695583U (en) 2021-05-24 2021-05-24 Long-distance pile feeding device for hammering tubular pile

Country Status (1)

Country Link
CN (1) CN214695583U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115369876A (en) * 2022-07-15 2022-11-22 安徽昌健建筑劳务有限公司 Bridge implanted tubular pile positioning device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115369876A (en) * 2022-07-15 2022-11-22 安徽昌健建筑劳务有限公司 Bridge implanted tubular pile positioning device and method
CN115369876B (en) * 2022-07-15 2023-08-18 安徽昌健建筑劳务有限公司 Bridge implanted pipe pile positioning device and method

Similar Documents

Publication Publication Date Title
CN214695583U (en) Long-distance pile feeding device for hammering tubular pile
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN108797571A (en) A kind of novel stiff composite pile efficient construction method
CN100376752C (en) Method for construction of underground continuous steel jacket box
CN107013046B (en) A kind of antidote of big section steel pipe concrete combination column
CN211547723U (en) Anti-tilting device for constructional engineering
CN214783831U (en) Steel-pipe pile foundation reinforced structure
CN106522224A (en) Deep water area prestressed concrete U-shaped plate pile guide frame pile sinking process
CN215487993U (en) Steel cylinder with hoop for horizontal spiral drilling jacking machine pipe jacking
CN212561503U (en) Prestressed pipe pile
CN112921942B (en) Vertical ship lift capable of being constructed on water and construction method thereof
CN214006270U (en) Novel combination tool for adjusting position of prefabricated shear wall sleeve joint bar of prefabricated building
CN210712905U (en) Novel bionic tree root foundation
CN212052733U (en) Combined pile for building foundation engineering
CN211171920U (en) Plastic steel sheet pile
CN209066610U (en) A kind of filling wall drawknot positioning tool
CN208650049U (en) A kind of cement mixing pile instant-plugging steel pipe and cement mixing pile
CN105544551A (en) Super-long cast-in-place pile construction method for rapidly downwards putting steel reinforcement cage
CN218931541U (en) Main chord member connecting structure of standard section of tower crane
CN208563345U (en) A kind of top plate supporting structure using building enclosure preformed groove
CN218148294U (en) High-pressure grouting type steel pipe pile
CN218562387U (en) Pile foundation engineering foundation reinforcing apparatus
CN221052569U (en) Wear-resistant pile tip
CN217710686U (en) Double static pressure belt steel core prestressed concrete pipe pile
CN211257013U (en) Side slope support pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211112

CF01 Termination of patent right due to non-payment of annual fee