CN214690075U - Waterborne ship drilling platform for engineering investigation - Google Patents

Waterborne ship drilling platform for engineering investigation Download PDF

Info

Publication number
CN214690075U
CN214690075U CN202120937248.6U CN202120937248U CN214690075U CN 214690075 U CN214690075 U CN 214690075U CN 202120937248 U CN202120937248 U CN 202120937248U CN 214690075 U CN214690075 U CN 214690075U
Authority
CN
China
Prior art keywords
anchor
drilling
drilling platform
water
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120937248.6U
Other languages
Chinese (zh)
Inventor
席大成
李晓龙
王沈力
王淼
刘辰麟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu CSCEC Municipal Engineering Investigation and Design Institute Co Ltd
Original Assignee
Gansu CSCEC Municipal Engineering Investigation and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu CSCEC Municipal Engineering Investigation and Design Institute Co Ltd filed Critical Gansu CSCEC Municipal Engineering Investigation and Design Institute Co Ltd
Priority to CN202120937248.6U priority Critical patent/CN214690075U/en
Application granted granted Critical
Publication of CN214690075U publication Critical patent/CN214690075U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a water ship drilling platform for engineering investigation, which structurally comprises an iron barge, wherein five anchors are arranged on the iron barge, the anchor is a front main anchor, the anchor is two front anchors and the anchor is two rear anchors, a crawler-type drilling machine is arranged above the iron barge, a sleeve clamp plate is fixed at a position 10cm below an orifice of an outer sleeve, an inner sleeve is placed on a hull of the iron barge through the sleeve clamp plate from the lower part of the orifice of the ship during drilling, and the lower part of the sleeve is deep into river bottom water; the construction of the drilling platform in the technical scheme saves materials, is simple, quick, safe and efficient, saves manpower, material resources and financial resources, reduces the lease cost and the production cost of drilling ships, and is particularly suitable for water drilling in reservoir areas, lakes and inland river basins; is a technical innovation of one-time expansibility in the prior art, and has good popularization and use values.

Description

Waterborne ship drilling platform for engineering investigation
Technical Field
The utility model relates to a drilling engineering operation technical field specifically is a marine drilling platform on water for engineering reconnaissance.
Background
In engineering investigation, water drilling is carried out on an inland river, two ships with the same tonnage are generally selected and connected in parallel to form a whole, and then boards and the like are laid on the ship surface to form a water engineering drilling platform; a floating pontoon is generally adopted to build a drilling platform on water with quiet water surface and slow water flow, such as lakes, ponds, reservoir areas and the like. The drilling platform has the advantages of large construction workload, high manual strength, large safety risk, long platform construction period and high cost, and directly influences the production efficiency of engineering investigation.
The existing engineering investigation overwater drilling platform is generally built, and is high in labor consumption and safety risk.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the main technical problem who solves how to provide an engineering investigation is with boats and ships drilling platform on water, and this technical scheme drilling platform's buildding has saved used material, accomplishes simply swiftly, and is safe high-efficient, has saved manpower and materials financial resources, reduces drilling boats and ships lease expense and manufacturing cost, the drilling on water of specially adapted reservoir area, lake, inland river basin.
In order to solve the technical problem, the utility model discloses a technical scheme is:
a water ship drilling platform for engineering investigation is characterized by structurally comprising an iron barge, a crawler-type drilling machine, an outer movable sleeve, an inner sleeve and an anchorage device; wherein, five anchors are arranged on the iron barge (1), the front main anchor (2) is one, the front side anchor (3) is two, the rear side anchor (4) is two, the crawler-type drilling machine (5) is arranged above the iron barge (1), a sleeve clamp plate is fixed at the position of 10cm below the pipe orifice of the outer live casing pipe (6), an inner casing pipe (7) is placed on the hull of the iron barge (1) through the sleeve clamp plate from the position below the ship orifice (8) during drilling, the lower part of the casing pipe extends into the water of the river bottom (9), and the inner casing pipe (7) extends into the hard soil layer of the river bottom from the inner part of the outer live casing pipe (6).
Preferably, in order to match the selected weight of the drilling ship, the weight of drilling machine equipment and the like and ensure that the drilling ship is fixed on the water surface, the weight of the front main anchor (2) is 100-200 kg, the weight of the front side anchor (3) and the rear side anchor (4) is 50-100 kg, and the anchor type is a four-claw anchor.
Preferably, the crawler-type drilling machine (5) is provided with four hydraulic support legs, the hydraulic support legs are lowered from the periphery of the drilling machine and fixed, and the safety protective guard (10) with the height of about 1.0m is installed around the ship body.
Preferably, the five anchor winches are fixed on the hull of the iron barge (1) through bottom bolts and can be detached after exploration operation is finished.
Preferably, the iron barge 1 has a width of 5.0 to 6.0m or more and a length of 12 to 15.0 m.
Preferably, the crawler-type drilling machine (5) is about 2.3m in width and about 3.5m in length.
Preferably, the size of the outer live sleeve (6) is 3.0-4.0 m.
Preferably, the size of the inner sleeve is 5.0-10.0m, and the inner sleeve is increased or decreased according to the water depth and the thickness of the loose soil layer at the river bottom and is ensured to be deeper into the hard soil layer by more than 3 m.
The drilling platform of the utility model has the advantages of quick construction, less material consumption, simple method, short time consumption, high working efficiency and labor, material and financial resources saving; the installation mode of the drilling machine is flexible, the drilling machine is directly hoisted through a crane, the modified drilling machine is provided with hydraulic support legs, the self-stabilization is facilitated, and the drilling machine does not need to be fixed in other modes; the drilling platform has high safety and stability, the outer live casing of the drill hole is arranged on the central axis in the ship cabin, during exploration operation, the inner casing of the drill hole is put into an underwater stratum through the casing in the cabin for drilling, and then is fixed through anchor ropes around the ship, the overall stability of the ship platform is good during drilling, and the operation is safe and reliable; the drilling efficiency is high, the vertical direction adapts to the fluctuation change of water level by adjusting the height of the outer movable sleeve, the horizontal direction is fixed and basically has no displacement, and the vertical shaft and the orifice of the drilling machine are always on the vertical line, thereby being beneficial to smooth drilling; is a technical innovation of one-time expansibility in the prior art, and has good popularization and use values.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained without inventive work, wherein:
fig. 1 is a schematic top view of the present invention;
fig. 2 is a schematic view of the structure of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below, and it should be apparent that the described embodiments are only some embodiments of the present invention, but not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
Referring to the drawings, in one embodiment of the present invention, a water vessel drilling platform for engineering investigation is characterized in that the structure includes an iron barge, a crawler-type drilling machine, an outer sleeve, an inner sleeve and an anchorage; the crawler-type drilling machine 5 is arranged above the iron barge 1, a sleeve clamp plate is fixed at a position 10cm below a pipe orifice of the outer live sleeve 6, an inner sleeve 7 is placed on a ship body of the iron barge 1 through the sleeve clamp plate from below a ship orifice 8 during drilling, and the lower part of the sleeve goes deep into the water at the river bottom 9.
In the specific implementation process, in order to match the weight of the drilling ship, the weight of drilling machine equipment and the like selected and ensure that the drilling ship is fixed on the water surface, the weight of the front main anchor 2 is 100-200 kg, the weight of the front anchor 3 and the weight of the rear anchor 4 are 50-100 kg, and the anchor type is a four-claw anchor.
In the specific implementation process, the crawler-type drilling machine 5 is provided with four hydraulic support legs, the hydraulic support legs are put down from the periphery of the drilling machine and fixed, and the safety protective guard 10 with the height of about 1.0m is installed around the ship body.
In the specific implementation process, the five anchor winches are fixed on the hull of the iron barge 1 through bottom bolts, and can be detached after exploration operation is finished.
The width of the iron barge 1 is more than 5.0-6.0m, and the length is 12-15.0m, because the width of the crawler-type drilling machine (5) adopted by the method is about 2.3m, the length is about 3.5m, the length of the front working surface of the drilling machine is about 5.0m during normal tripping operation, the length of the rear working surface of the drilling machine is about 1m, and a drilling platform is refitted by selecting a ship with the width of more than 5.0-6.0m and the length of 12-15.0m, so that enough drilling working surface is ensured, and a certain safety protection distance is provided. The iron barge 1 is too small in size, so that the safety operation condition is not facilitated; the size is too big, the tonnage is heavy, and the cost is also not economical and practical, in addition because the drilling boats and ships of choosing for use are unpowered, and the size is too big, the tonnage is heavy, is unfavorable for migrating on water. The selected iron barge 1 can be towed by a general small traffic ship.
The hole opening on the ship is 150-170mm, because the technology is particularly suitable for drilling within 100 meters of hole depth, the final hole diameter is not less than 91mm in general engineering exploration, particularly on-water geological drilling, so that the diameter of the hole is determined to be larger than 91mm, the diameter of the hole is 130mm according to a drilling technical method, the diameter of a matched geological casing is 127mm, the drilling casing is an inner casing adopted by the method, the inner casing needs to go deep into a hard soil layer at the bottom of a river through an outer live casing according to the method, the size of the inner casing is 5.0-10.0m, and the depth of the inner casing is increased or decreased according to the water depth and the thickness of the loose soil layer at the bottom of the river, so that the inner casing can go deep into the hard soil layer by more than 3 m. The outer sleeve is selected to have a diameter of 146 mm. The size of the outer movable sleeve is 3.0-4.0m, which is mainly determined by the maximum water level expansion condition and the deep depth condition of the inner sleeve under the normal condition, the length is favorable for the inner sleeve to be upwards deep into 1.0m-2.0m, which can ensure that the drilling ship vertically displaces after the water level is expanded but not separate from the inner sleeve and the outer sleeve, and the inner sleeve and the outer sleeve are deep into each other and are favorable for ensuring the stability of the drilling ship body and not generating horizontal displacement, thereby creating favorable conditions for smooth drilling. The drilling hull hole 150mm-170mm can ensure the outer sleeve to be fixed, so that the vertical shaft of the drilling machine, the hull hole, the inner and outer sleeves and the underwater hole are on the same vertical line, and smooth drilling is facilitated.
The outer live sleeve is provided with a 0.3-0.5m short sleeve, because the water level fluctuation is not a fixed value, and the outer live sleeve can be immediately connected to use when needed as a stored power tool.
The above only is the embodiment of the present invention, not limiting the patent scope of the present invention, all of which utilize the equivalent structure or equivalent flow transformation made by the content of the specification of the present invention, or directly or indirectly applied to other related technical fields, all included in the same way in the patent protection scope of the present invention.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (9)

1. The utility model provides an engineering investigation is with boats and ships drilling platform on water, a serial communication port, the structure includes that iron barge (1) is gone up the installation and is provided with five ground tackle, be preceding main anchor (2) one respectively, preceding limit anchor (3) are two, back limit anchor (4) are two, crawler-type rig (5) installation sets up in iron barge (1) top, the fixed sleeve pipe splint of the 10cm department below the outer sleeve pipe (6) mouth of pipe, interior sleeve pipe (7) are followed boats and ships drill way (8) below during the probing, place on iron barge (1) hull through the sleeve pipe splint, the sleeve pipe below is deep into river bottom (9) aquatic.
2. A water craft drilling platform for engineering investigation according to claim 1, characterised in that the front main anchor (2) weighs 100-200 kg, the front side anchor (3) and the rear side anchor (4) weigh 50-100 kg and the anchor type is a four-claw anchor.
3. A water craft drilling platform for engineering investigation according to claim 1, characterized in that the crawler-type drilling machine (5) is provided with four hydraulic support legs, the hydraulic support legs are lowered from the periphery of the drilling machine and fixed, and a safety guard rail (10) with a height of about 1.0m is installed around the hull.
4. The water vessel rig for engineering investigation of claim 1, wherein five anchor winches are bolted to the hull of the iron barge (1) at the bottom and removed after the exploration is completed.
5. The water vessel rig for engineering investigation of claim 1, wherein the iron barge (1) has a width of 5.0-6.0m or more and a length of 12-15.0 m.
6. An engineering exploration water vessel drilling platform according to claim 1, wherein the crawler-type drilling rig (5) is about 2.3m wide and about 3.5m long.
7. An engineering exploration water vessel drilling platform according to claim 1, wherein the outer casing (6) has a size of 3.0-4.0 m.
8. A water craft drilling platform for engineering investigations according to claim 1, characterised in that the outer casing (6) is equipped with 0.3-0.5m short casing.
9. An engineering exploration water vessel drilling platform according to claim 1, characterized in that the size of the inner casing (7) is 5.0-10.0 m.
CN202120937248.6U 2021-04-30 2021-04-30 Waterborne ship drilling platform for engineering investigation Expired - Fee Related CN214690075U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120937248.6U CN214690075U (en) 2021-04-30 2021-04-30 Waterborne ship drilling platform for engineering investigation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120937248.6U CN214690075U (en) 2021-04-30 2021-04-30 Waterborne ship drilling platform for engineering investigation

Publications (1)

Publication Number Publication Date
CN214690075U true CN214690075U (en) 2021-11-12

Family

ID=78535474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120937248.6U Expired - Fee Related CN214690075U (en) 2021-04-30 2021-04-30 Waterborne ship drilling platform for engineering investigation

Country Status (1)

Country Link
CN (1) CN214690075U (en)

Similar Documents

Publication Publication Date Title
CN111661273B (en) Installation and construction method of deep and open sea semi-submersible fan
CN102839666B (en) Bottom-supported floating pile-driving platform
US20080247827A1 (en) Work-over rig assembly and methods thereof
CN203345167U (en) Movable jack-up artificial island
CN101837929B (en) Operation method for lifting fan for barge in shoal area
CN102116017B (en) Foam platform for drilling on waterways
CN103981846A (en) Pile positioning semi-submersible offshore dredging engineering ship
CN102312438A (en) Piling construction equipment for large steel pipe piles of seaborn intertidal zone wind power station
CN202023182U (en) Waterborne drilling foam platform
CN110185057B (en) Tool and construction method for lifting and erecting steel pipe piles of offshore wind power single pile foundation
CN101786496B (en) Deep-water directional drilling and steel-cable back-dragging device
CN103119222A (en) Surface-breaking re-usable submergeable template for installing one or more submerged columns/piles
CN214690075U (en) Waterborne ship drilling platform for engineering investigation
CN210827529U (en) Single-pile reinforced foundation of offshore wind power anti-icing structure
CN107458541A (en) A kind of built-in alignment system applied to engineering ship
CN211368838U (en) Underwater milling groove guiding and positioning device suitable for deepwater embedded foundation
CN113914783A (en) Dual-purpose engineering investigation water drilling platform and use method thereof
CN213062078U (en) Offshore wind power integral installation device utilizing mat and buoyancy tank
CN104058071B (en) A kind of semi-submersible dredget
CN215436813U (en) High holding power anchor with V-shaped structure
CN2604377Y (en) Seabeach self-navigating steel bottom base floating well site
CN217754045U (en) Water drilling platform
CN214776446U (en) Tension leg type shallow sea rock-soil exploration mobile platform
CN217637347U (en) Ocean current observation device applied to navigation mark
CN203174612U (en) Underwater construction device for large objects

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee