CN214656433U CN202120491739.2U CN202120491739U CN214656433U CN 214656433 U CN214656433 U CN 214656433U CN 202120491739 U CN202120491739 U CN 202120491739U CN 214656433 U CN214656433 U CN 214656433U
Authority
CN
China
Prior art keywords
steel sheet
scaffold
steel
connect
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120491739.2U
Other languages
Chinese (zh)
Inventor
翁国锹
陈建宁
颜苓
焦世明
杨瀛
朱桂权
邓晓辉
布振华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Third Municipal Engineering Co Ltd
Original Assignee
Guangzhou Third Municipal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Third Municipal Engineering Co Ltd filed Critical Guangzhou Third Municipal Engineering Co Ltd
Priority to CN202120491739.2U priority Critical patent/CN214656433U/en
Application granted granted Critical
Publication of CN214656433U publication Critical patent/CN214656433U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a connect buckle formula scaffold frame is set up by scaffold module successive layer more than two and is constituteed, scaffold module includes horizontal pole, montant, goes up to connect the steel sheet, connects the steel sheet down, connect buckle, cat ladder and steel sheet, and is a plurality of horizontal pole and a plurality of the montant passes through connect buckle connects and constitutes the steelframe main part, go up to connect the steel sheet weld in the top of montant, connect the steel sheet down and weld in the bottom of montant, go up to connect the steel sheet with first through-hole has all been seted up on the steel sheet down, the horizontal pole top is provided with the steel sheet is adjacent be provided with between the steel sheet the cat ladder. Through being a plurality of module with the scaffold split for operating personnel can ground assemble scaffold module, and utilize the connection steel sheet to splice into the scaffold with a plurality of scaffold modules, made things convenient for the installation and the dismantlement of scaffold, improved the efficiency of construction.

Description

Connecting buckle type scaffold
Technical Field
The utility model relates to a construction technical field, more specifically relates to a connect buckle formula scaffold.
Background
The bridge pier is an important structure for connecting an upper structure and a lower foundation, and the construction period and the construction quality of the bridge pier have great influence on the whole bridge project. The conventional fastener type scaffold is generally adopted for erection in pier column construction, the construction method is used for erecting rod pieces from bottom to top, a large amount of workers are needed for operation, the construction efficiency is low, certain danger is realized, meanwhile, the scaffold needs to be moved secondarily in the construction process, the scaffold needs to be re-assembled and disassembled and turned over, and the consumed time is long.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defects of the prior art, the utility model aims to solve the technical problem that a connection buckle formula scaffold is put forward is provided, through being a plurality of module with the scaffold split for scaffold module is assembled to operating personnel can ground, and utilizes the connection steel sheet to splice into the scaffold with a plurality of scaffold module, has made things convenient for the installation and the dismantlement of scaffold, has both guaranteed construction safety, has practiced thrift construction cost again, has improved the efficiency of construction.
To achieve the purpose, the utility model adopts the following technical proposal: the utility model provides a connect buckle formula scaffold frame, sets up by scaffold module successive layer more than two and constitutes, scaffold module includes horizontal pole, montant, goes up to connect the steel sheet, connects steel sheet, connect buckle, cat ladder and steel sheet down, and is a plurality of horizontal pole and a plurality of the montant passes through connect buckle connects and constitutes the steelframe main part, it welds in to go up to connect the steel sheet in the top of montant, connect the steel sheet weld down in the bottom of montant, go up to connect the steel sheet with all seted up first through-hole down on the connection steel sheet, the screw rod passes one in proper order scaffold module connect the steel sheet down first through-hole, adjacent below scaffold module go up the second connect the through-hole on the connection steel sheet, the horizontal pole top is provided with the steel sheet is adjacent be provided with between the steel sheet the cat ladder.
The utility model discloses in the technical scheme of preferred, steelframe main part side is provided with the safety net.
The utility model discloses in the technical scheme of preferred, steelframe main part side all is provided with the bridging.
The utility model discloses in the technical scheme of preferred, the top edge of steelframe main part is provided with the hoist and mount buckle, be connected with wire rope between the hoist and mount buckle.
The utility model discloses in the technical scheme of preferred, the montant top still is provided with supplementary connecting device, supplementary connecting device is including installation piece and fixed block, the installation piece comprises two first connecting portions, first connecting portion top has set firmly the connecting piece, first semicircular groove has been seted up to first connecting portion side, two first mounting hole is constituteed in the concatenation of first semicircular groove, the fixed block comprises two second connecting portions, second connecting portion bottom has set firmly the connecting piece, second connecting portion top is seted up flutedly, two recess concatenation forms the mounting groove, the second semicircular groove has been seted up to second connecting portion side, two the second mounting block hole is constituteed in the concatenation of second semicircular groove.
The utility model discloses among the technical scheme of preferred, the connecting piece includes circular arc board and gusset plate, two the gusset plate weld respectively in the both ends of circular arc board, the second through-hole has been seted up on the gusset plate.
The utility model has the advantages that:
the utility model aims to solve the technical problem that a connect buckle formula scaffold frame is put forward through being a plurality of module with the scaffold frame split for scaffold frame module can be assembled on ground to operating personnel, and utilize and connect the steel sheet and splice into the scaffold frame with a plurality of scaffold frame module, made things convenient for the installation and the dismantlement of scaffold frame, both guaranteed construction safety, practiced thrift construction cost again, improved the efficiency of construction.
Drawings
Fig. 1 is a schematic structural view of a connecting buckle type scaffold according to an embodiment of the present invention;
FIG. 2 is a perspective view of the auxiliary connecting device;
fig. 3 is a cross-sectional view of an auxiliary connecting device for connecting the snap-fastener type scaffolds according to an embodiment of the present invention;
fig. 4 is an enlarged schematic view at a in fig. 1.
In the figure:
1-transverse rod, 2-vertical rod, 301-upper connecting steel sheet, 302-lower connecting steel sheet, 4-connecting buckle, 5-ladder stand, 6-steel plate, 7-first through hole, 8-screw, 9-fastening nut, 11-safety net, 12-shear support, 13-hoisting buckle, 14-steel wire rope, 15-auxiliary connecting device, 16-mounting block, 17-fixing block, 18-connecting piece, 19-first connecting part, 20-second connecting part, 21-mounting groove, 211-groove, 22-first mounting hole, 221-first semicircular groove, 23-second mounting hole, 231-second semicircular groove, 24-circular arc plate, 25-reinforcing plate and 26-second through hole.
Detailed Description
The technical solution of the present invention is further explained by the following embodiments with reference to the accompanying drawings.
As shown in fig. 1, in the embodiment, a connection buckle type scaffold is provided, which is formed by erecting more than two scaffold modules layer by layer, each scaffold module comprises a cross rod 1, a vertical rod 2, an upper connection steel sheet 301, a lower connection steel sheet 302, a connection buckle 4, a ladder 5 and a steel plate 6, wherein a plurality of cross rods 1 and a plurality of vertical rods 2 are connected through the connection buckle 4 to form a steel frame main body, the upper connection steel sheet 301 is welded at the top end of the vertical rod 2, the lower connection steel sheet 301 is welded at the bottom end of the vertical rod 2, a plurality of first through holes 7 are respectively formed in the upper connection steel sheet 301 and the lower connection steel sheet 302, a screw 8 sequentially passes through the first through hole 7 on the lower connection steel sheet 302 of one scaffold module and the first through hole 7 on the upper connection steel sheet 301 of the scaffold module below and is adjacent, and the screw rod 7 is in threaded connection with the fastening nut 9, the steel plates 6 are arranged above the cross rod 1, and the crawling ladder 5 is arranged between the adjacent steel plates 6. Through splitting the scaffold into a plurality of modules, the scaffold modules can be assembled on the ground by an operator, and the scaffold modules are spliced into the scaffold by utilizing the connecting steel sheets, so that the scaffold is convenient to install and disassemble, the construction safety is ensured, the construction cost is saved, and the construction efficiency is improved
In order to prevent constructor from falling the scaffold in the work progress, improve the security of construction, further, steelframe main part side is provided with safety net 11.
In order to meet the strength requirement of the scaffold module, further, the lateral sides of the steel frame body are provided with the cross braces 12. The shear braces 12 are used for sharing the pressure on the vertical rods 2 and the cross rods 1, and the strength of the scaffold is further enhanced.
In order to facilitate the hoisting construction of the scaffold module, further, the top edge of the steel frame main body is provided with hoisting buckles 13, and steel wire ropes 14 are connected between the hoisting buckles 13. During construction, the lifting hook of the crane hooks the steel wire rope 14, the scaffold module is pulled to a set position, and the effect of erecting the scaffold layer by layer is achieved.
In order to realize the quick alignment of the scaffold modules and improve the installation speed, further, as shown in fig. 2-4, the top end of the vertical rod 2 is further provided with an auxiliary connecting device, the auxiliary connecting device comprises an installation block 16 and a fixed block 17, the installation block 16 is composed of two first connecting portions 19, a connecting member 18 is fixedly arranged at the top of each first connecting portion 19, a first semicircular groove 221 is formed in the side surface of each first connecting portion 19, the two first semicircular grooves 221 are spliced to form a first installation hole 22, the fixed block 17 is composed of two second connecting portions 20, the bottom of each second connecting portion 20 is fixedly provided with the connecting member 18, a groove 211 is formed in the top of each second connecting portion 20, the two grooves 211 are spliced to form an installation groove 21, a second semicircular groove 231 is formed in the side surface of each second connecting portion 20, and the two second semicircular grooves 231 are spliced to form a second installation hole 23. Through installing installation piece 16 in the bottom of montant 2 to install fixed block 17 in the top of montant 2, when scaffold module butt joint with the scaffold module of adjacent below, the installation piece 16 of scaffold module of adjacent top falls into in the mounting groove 21 of the fixed block 17 of scaffold module of adjacent below, has increased the butt joint area at connection position through this kind of mode, has improved the speed and the degree of accuracy of butt joint process.
In order to facilitate the installation of the installation block 16 and the fixing block 17 on the vertical rod 2, the connecting member 18 is further in an omega shape, the connecting member 18 includes an arc plate 24 and two reinforcing plates 25, the two reinforcing plates 25 are respectively welded to two ends of the arc plate 24, and the reinforcing plate 25 is provided with a second through hole 26.
While the invention has been described with reference to a preferred embodiment, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the spirit and scope of the invention. The present invention is not to be limited by the specific embodiments disclosed herein, and other embodiments that fall within the scope of the claims of the present application are intended to be within the scope of the present invention.

Claims (6)

1. The utility model provides a connect buckle formula scaffold, sets up by more than two scaffold module successive layer and constitutes its characterized in that: the scaffold module comprises a cross rod (1), a vertical rod (2), an upper connecting steel sheet (301), a lower connecting steel sheet (302), a connecting buckle (4), a ladder stand (5) and a steel plate (6), wherein the cross rod (1) and the vertical rods (2) are connected through the connecting buckle (4) to form a steel frame main body, the upper connecting steel sheet (301) is welded at the top end of the vertical rod (2), the lower connecting steel sheet (302) is welded at the bottom end of the vertical rod (2), first through holes (7) are formed in the upper connecting steel sheet (301) and the lower connecting steel sheet (302), a screw rod (8) sequentially penetrates through the first through holes (7) in the lower connecting steel sheet (302) of the scaffold module and the first through holes (7) in the upper connecting steel sheet (301) of the scaffold module below the adjacent position, the steel plate (6) is arranged above the cross rod (1), the crawling ladder (5) is arranged between the adjacent steel plates (6).
2. A connecting-clip-on scaffold according to claim 1, characterized in that: and a safety net (11) is arranged on the side surface of the steel frame main body.
3. A connecting-clip-on scaffold according to claim 1, characterized in that: the lateral surfaces of the steel frame main body are provided with scissor supports (12).
4. A connecting-clip-on scaffold according to claim 1, characterized in that: the steel frame is characterized in that hoisting buckles (13) are arranged on the top edges of the steel frame main body, and steel wire ropes (14) are connected between the hoisting buckles (13).
5. A connecting-clip-on scaffold according to claim 1, characterized in that: the top end of the vertical rod (2) is also provided with an auxiliary connecting device which comprises an installation block (16) and a fixed block (17), the mounting block (16) consists of two first connecting parts (19), a connecting piece (18) is fixedly arranged at the top of each first connecting part (19), a first semicircular groove (221) is formed in the side face of the first connecting part (19), the two first semicircular grooves (221) are spliced to form a first mounting hole (22), the fixed block (17) is composed of two second connecting parts (20), the connecting piece (18) is fixedly arranged at the bottom of each second connecting part (20), the top of the second connecting part (20) is provided with a groove (211), the two grooves (211) are spliced to form a mounting groove (21), and a second semicircular groove (231) is formed in the side surface of the second connecting part (20), and the two second semicircular grooves (231) are spliced to form a second mounting block hole (23).
6. A connecting-clip-on scaffold according to claim 5, characterized in that: the connecting piece (18) includes circular arc board (24) and gusset plate (25), two gusset plate (25) weld respectively in the both ends of circular arc board (24), second through-hole (26) have been seted up on gusset plate (25).
CN202120491739.2U 2021-03-08 2021-03-08 Connecting buckle type scaffold Active CN214656433U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120491739.2U CN214656433U (en) 2021-03-08 2021-03-08 Connecting buckle type scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120491739.2U CN214656433U (en) 2021-03-08 2021-03-08 Connecting buckle type scaffold

Publications (1)

Publication Number Publication Date
CN214656433U true CN214656433U (en) 2021-11-09

Family

ID=78451876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120491739.2U Active CN214656433U (en) 2021-03-08 2021-03-08 Connecting buckle type scaffold

Country Status (1)

Country Link
CN (1) CN214656433U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116892288A (en) * 2023-09-11 2023-10-17 山西盛帅建筑工程有限公司 Attached lifting scaffold lifting mechanism

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116892288A (en) * 2023-09-11 2023-10-17 山西盛帅建筑工程有限公司 Attached lifting scaffold lifting mechanism
CN116892288B (en) * 2023-09-11 2023-11-17 山西盛帅建筑工程有限公司 Attached lifting scaffold lifting mechanism

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN210658011U (en) Steel truss arch bridge installation system
CN111677299A (en) Lifting device and method for steel bar truss floor support plate
CN214656433U (en) Connecting buckle type scaffold
CN206646835U (en) It is a kind of from hoisting type steel structure slipping measure support
CN112502475B (en) Supporting bearing capacity conversion device and using method thereof
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN112502473B (en) Supporting bearing capacity conversion device and method for dismantling large steel framework by using same
CN213484787U (en) Photovoltaic power generation board mounting and supporting structure with suspended steel beam foundation
CN211974467U (en) Supporting device
CN112627045A (en) Hang basket template scissors cat ladder
CN107700363B (en) Bridge tower rack with lifting system and construction method
CN209179519U (en) Hang the truss splicing steel construction moulding bed of auxiliary installation in a kind of gymnasium top
CN209686924U (en) A kind of large volume arc concrete steel lattice supporting framework
CN108316119B (en) Steel construction overpass convenient to installation
CN207131062U (en) A kind of job platform
CN218177641U (en) Connection structure and support frame
CN111704058A (en) Hoisting device
CN211256673U (en) Steel truss installation attached construction platform
CN219792145U (en) Hanging bracket device for hoisting prefabricated T-beam
CN218931529U (en) Lifting device for column top steel beam
CN220246693U (en) Adjustable active transverse strut device of single-tower cable-stayed bridge
CN110005210A (en) The mounting device and its construction method of steel truss
CN214885842U (en) Support frame capable of being adjusted in lifting mode
CN220451464U (en) Steel bar truss floor carrier plate positioning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant