CN214656312U - Assembled pier steel construction - Google Patents

Assembled pier steel construction Download PDF

Info

Publication number
CN214656312U
CN214656312U CN202120546095.2U CN202120546095U CN214656312U CN 214656312 U CN214656312 U CN 214656312U CN 202120546095 U CN202120546095 U CN 202120546095U CN 214656312 U CN214656312 U CN 214656312U
Authority
CN
China
Prior art keywords
connecting plate
panel
butt joint
positioning
pier steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120546095.2U
Other languages
Chinese (zh)
Inventor
詹祖磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichang Danfeng Machinery Manufacturing Co ltd
Original Assignee
Yichang Danfeng Machinery Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yichang Danfeng Machinery Manufacturing Co ltd filed Critical Yichang Danfeng Machinery Manufacturing Co ltd
Priority to CN202120546095.2U priority Critical patent/CN214656312U/en
Application granted granted Critical
Publication of CN214656312U publication Critical patent/CN214656312U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a pier steel construction technical field discloses an assembled pier steel construction, which comprises a pane, the transversal half-circular arc that personally submits of panel, the upper and lower both ends level of panel is provided with the first connecting plate that is half-circular arc, first connecting plate with the panel is coaxial, the vertical second connecting plate that is provided with in both sides of panel, the second connecting plate is long cubic, the both ends of first connecting plate are connected with the both ends of second connecting plate respectively, first connecting plate with a plurality of connecting holes have all been seted up on the second connecting plate, still be provided with on the first connecting plate and be used for assisting the positioning mechanism of first connecting plate butt joint. The utility model is simple in operation convenient, reduced butt joint time, promoted work efficiency.

Description

Assembled pier steel construction
Technical Field
The utility model relates to a pier steel construction technical field, in particular to assembled pier steel construction.
Background
At present, bridge piers are sub-buildings which support bridge span structures and transmit constant loads and vehicle live loads to foundations, bridge abutments are arranged between two lakes of a bridge, the bridge piers are arranged between the two bridge abutments and are used for supporting the bridge span structures, and the bridge abutments are connected with embankments and are used for preventing the embankments from sliding out of fields besides the bridge span structures. The existing assembled pier steel structure is a cylindrical steel structure formed by butting two arc-shaped panels, then a plurality of cylindrical steel structures are butted up and down to form an arrangement, in the process of up-down butting, because the steel structure is overall heavier, a crane is usually adopted to hoist the steel structure, and then connecting holes of the upper steel structure and the lower steel structure are connected and welded after being aligned, so that the whole butting process is very complicated.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an assembled pier steel construction aims at solving among the prior art loaded down with trivial details problem of butt joint process about the pier steel construction.
The above technical purpose of the present invention can be achieved by the following technical solutions:
the utility model provides an assembled pier steel construction, includes the panel, the transversal semicircle arc that personally submits of panel, the upper and lower both ends level of panel is provided with the first connecting plate that is semicircle arc, first connecting plate with the panel is coaxial, the vertical second connecting plate that is provided with in both sides of panel, the second connecting plate is long cubic, the both ends of first connecting plate are connected with the both ends of second connecting plate respectively, first connecting plate with a plurality of connecting holes have all been seted up on the second connecting plate, still be provided with on the first connecting plate and be used for assisting the positioning mechanism of first connecting plate butt joint.
Through the technical scheme, when carrying out pier steel structure assembly, align two panel about then twist the bolt and weld again, form a cylindric steel construction, with cylindric steel construction opening back up, hang another cylindric steel construction again and put above, align the location with first connecting plate through positioning mechanism, then twist the bolt and weld again, whole butt joint process just can be accomplished very fast like this, and easy operation is convenient, has reduced the butt joint time, has promoted work efficiency.
The utility model discloses a further set up to: the positioning mechanism comprises positioning pieces arranged at the end parts of the first connecting plates, the positioning pieces are positioned at the top of one of the first connecting plates, the other one of the first connecting plates is provided with a first positioning groove, one end, close to the first positioning groove, of the second connecting plate is provided with a second positioning groove, a positioning cavity is formed between the first positioning groove and the second positioning groove, and the positioning cavity is matched with the positioning pieces.
Through above-mentioned technical scheme, two semi-circular pier steel construction are connected and are accomplished the back, and the one end that will have the setting element is placed up, then uses the crane to hoist another cylinder steel construction that splices, then slowly transfers, carries out after the position fine setting, and the setting element is arranged in the location chamber, and the butt joint has just been accomplished, and the connecting hole also aligns automatically, and only need next twist the bolt then weld can, easy operation is convenient, has reduced the butt joint time, has promoted work efficiency.
The utility model discloses a further set up to: the positioning piece is in a quarter-sphere shape.
Through above-mentioned technical scheme, two semicircular pier steel construction are connected and are accomplished the back, and two spherical setting elements of fourth form a hemispherical structure, and when carrying out butt joint from top to bottom, even the position is misaligned, because two setting elements constitute the hemisphere, its arc border also can slide along the border of constant head tank, then slide into the location chamber, let the butt joint operation simple and convenient more.
The utility model discloses a further set up to: the number of the positioning pieces is two, and the two positioning pieces are respectively positioned at two ends of the first connecting plate.
Through above-mentioned technical scheme, the setting element at both ends is placed in the location chamber after, and the butt joint is accomplished, can not take place to rotate again, can carry out next process, stable in structure, easy operation.
The utility model discloses a further set up to: one of the two second connecting plates is also provided with a butt joint block, the other second connecting plate is provided with a butt joint groove matched with the butt joint block, and the butt joint block and the butt joint groove are both positioned on one surface of the second connecting plate, which deviates from the panel.
Through above-mentioned technical scheme, when butt joint about with two semi-circular pier steel construction, only need aim at the butt joint mouth on the other one with the butt joint board on the second connecting plate, can accomplish the preliminary butt joint of left and right directions, then twist the bolt again and can accomplish the connection, easy operation is convenient, has promoted work efficiency.
The utility model discloses a further set up to: the butt-joint block is hemispherical.
Through above-mentioned technical scheme, when carrying out the left and right sides butt joint, even the position is not aimed at, because the butt joint piece is the hemisphere, the butt joint piece can slide along the border in butt joint groove, then slides in butt joint groove, lets the butt joint operation simple and convenient more.
The utility model discloses a further set up to: the butt-joint blocks are sequentially provided with a plurality of butt-joint blocks from top to bottom.
Through above-mentioned technical scheme, adopt polylith butt joint board to control the butt joint location simultaneously, the location is more accurate, and efficiency is higher.
The utility model discloses a further set up to: one end of the second connecting plate is provided with a correction barrel, the center of the correction barrel is hollow, the other end of the second connecting plate is provided with a correction plate, and the correction plate is provided with correction holes.
Through above-mentioned technical scheme, when counterpointing about going on, even the very first time is not aimed at, the staff can pass the hole of correcting on the board of correcting of top steel construction with reinforcing bar one end, then wear among the correction section of thick bamboo of below steel construction, carry out the position with the reinforcing bar and correct, wait that positioning mechanism can take out the reinforcing bar after accomplishing the butt joint, carry out operation on next step again, simple structure convenient operation lets the staff carry out the steel construction about more convenient when counterpointing.
The utility model discloses a further set up to: be provided with the first strengthening rib of a plurality of circular arcs on the outer wall of panel, first strengthening rib with the panel is coaxial, it is provided with a plurality of second strengthening ribs still to go back the axial on the outer wall of panel, the both ends of first strengthening rib with the second connecting plate is connected, the both ends of second strengthening rib with first connecting plate is connected, the panel with between the first connecting plate the panel with all be provided with a plurality of reinforcing plates between the second connecting plate.
Through above-mentioned technical scheme, first strengthening rib, second strengthening rib and reinforcing plate can let the structure more stable, promote the mechanical properties of steel construction, use more reliably.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a schematic structural diagram of an embodiment of an assembled pier steel structure of the present invention;
fig. 2 is a schematic structural diagram of an embodiment of an assembled pier steel structure of the present invention;
FIG. 3 is an enlarged view of portion A of FIG. 2;
fig. 4 is the structure schematic diagram of the assembled pier steel structure after the embodiment of the present invention is spliced.
In the figure, 1, panel; 2. a first connecting plate; 3. a second connecting plate; 4. connecting holes; 5. a positioning member; 6. a first positioning groove; 7. a second positioning groove; 8. a positioning cavity; 9. a butt joint block; 10. a butt joint groove; 11. a correction barrel; 12. straightening a plate; 13. straightening holes; 14. a first reinforcing rib; 15. a second reinforcing rib; 16. a reinforcing plate.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings and specific embodiments. It is obvious that the described embodiments are only some of the embodiments of the present invention, and not all of them. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
The utility model provides a pair of assembled pier steel construction, as shown in fig. 1 to fig. 4, including panel 1, panel 1's transversal semicircular arc of personally submitting, panel 1's upper and lower both ends level is provided with the first connecting plate 2 that is semicircular arc, first connecting plate 2 with panel 1 is coaxial, the vertical second connecting plate 3 that is provided with in both sides of panel 1, second connecting plate 3 is the rectangular bodily form, first connecting plate 2's both ends are connected with the both ends of second connecting plate 3 respectively, first connecting plate 2 with a plurality of connecting holes 4 have all been seted up on the second connecting plate 3, still be provided with on first connecting plate 2 and be used for assisting the positioning mechanism of 2 butt joints of first connecting plate. Positioning mechanism including set up in setting element 5 of first connecting plate 2's tip, setting element 5 is the quarter sphere, setting element 5 has two, two setting element 5 is located respectively first connecting plate 2's both ends, another one first constant head tank 6 has been seted up to first connecting plate 2's bottom, second connecting plate 3 is close to second constant head tank 7 has been seted up to the one end of first constant head tank 6, first constant head tank 6 with form location chamber 8 between the second constant head tank 7, location chamber 8 with setting element 5 cooperatees.
Two one of them of second connecting plate 3 still is provided with butt joint piece 9, butt joint piece 9 is the hemisphere, butt joint piece 9 from the top down has set gradually a plurality ofly, another one seted up on the second connecting plate 3 with butt joint piece 9 matched with butt joint groove 10, butt joint piece 9 with butt joint groove 10 all is located second connecting plate 3 deviates from the one side of panel 1.
One end of the second connecting plate 3 is provided with a correction barrel 11, the center of the correction barrel 11 is hollow, the other end of the second connecting plate 3 is provided with a correction plate 12, and the correction plate 12 is provided with a correction hole 13.
Be provided with a plurality of convex first strengthening ribs 14 on the outer wall of panel 1, first strengthening rib 14 with panel 1 is coaxial, it is provided with a plurality of second strengthening ribs 15 still to go back the axial on the outer wall of panel 1, the both ends of first strengthening rib 14 with second connecting plate 3 is connected, the both ends of second strengthening rib 15 with first connecting plate 2 is connected, panel 1 with between first connecting plate 2 panel 1 with all be provided with a plurality of reinforcing plates 16 between the second connecting plate 3.
Through the technical scheme, when carrying out pier steel structure assembly, align about two panels 1 and then twist the bolt and weld again, form a cylindric steel construction, two spherical setting element 5 of fourth form a hemispherical structure, with cylindric steel construction opening up, hang another cylindric steel construction and put above, when carrying out the butt joint from top to bottom, even the position is misaligned, because two setting element 5 constitute the hemisphere, the border slip of constant head tank also can be followed to its arc border, then slide into location chamber 8, the connecting hole is also automatic alignment like this, then twist the bolt and weld again, whole butt joint process just can be accomplished very fast like this, and easy operation is convenient, the butt joint time has been reduced, and the work efficiency is improved.
When butt joint about with two semi-circular pier steel construction, only need aim at the interface on the other one with the butt joint board on the second connecting plate 3, can accomplish the preliminary butt joint of left right direction, because butt joint piece 9 is the hemisphere, butt joint piece 9 can slide along the border of butt joint groove 10, then slide into butt joint groove 10, twist the bolt again after the butt joint is accomplished and can accomplish the connection, easy operation is convenient, has promoted work efficiency.
When counterpointing about going on, even the very first time is not aimed at, the staff can pass the correction hole 13 on the correction board 12 of top steel construction with reinforcing bar one end, then wear among the correction section of thick bamboo 11 of below steel construction, carry out the position with the reinforcing bar and correct, wait that positioning mechanism can take out the reinforcing bar after accomplishing the butt joint, carry out operation on next step again, simple structure convenient operation makes the staff carry out the steel construction about more convenient when counterpointing.
The first reinforcing rib 14, the second reinforcing rib 15 and the reinforcing plate 16 can enable the structure to be more stable, improve the mechanical property of a steel structure and enable the steel structure to be more reliable in use.
It should be noted that, in the present specification, the embodiments are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments may be referred to each other.
The above description is only for the preferred embodiment of the present invention and is not intended to limit the scope of the present invention, and any modification and modification made by those skilled in the art according to the above disclosure are all within the scope of the claims.

Claims (9)

1. The utility model provides an assembled pier steel construction which characterized in that: the novel multifunctional electric heating plate comprises a panel, the transversal semicircle arc that personally submits of panel, the upper and lower both ends level of panel is provided with the first connecting plate that is semicircle arc, first connecting plate with the panel is coaxial, the vertical second connecting plate that is provided with in both sides of panel, the second connecting plate is the rectangular bodily form, the both ends of first connecting plate are connected with the both ends of second connecting plate respectively, first connecting plate with a plurality of connecting holes have all been seted up on the second connecting plate, still be provided with on the first connecting plate and be used for assisting the positioning mechanism of first connecting plate butt joint.
2. An assembled pier steel structure according to claim 1, wherein: the positioning mechanism comprises positioning pieces arranged at the end parts of the first connecting plates, the positioning pieces are positioned at the top of one of the first connecting plates, the other one of the first connecting plates is provided with a first positioning groove, one end, close to the first positioning groove, of the second connecting plate is provided with a second positioning groove, a positioning cavity is formed between the first positioning groove and the second positioning groove, and the positioning cavity is matched with the positioning pieces.
3. An assembled pier steel structure according to claim 2, wherein: the positioning piece is in a quarter-sphere shape.
4. An assembled pier steel structure according to claim 3, wherein: the number of the positioning pieces is two, and the two positioning pieces are respectively positioned at two ends of the first connecting plate.
5. An assembled pier steel structure according to claim 1, wherein: one of the two second connecting plates is also provided with a butt joint block, the other second connecting plate is provided with a butt joint groove matched with the butt joint block, and the butt joint block and the butt joint groove are both positioned on one surface of the second connecting plate, which deviates from the panel.
6. An assembled pier steel structure according to claim 5, wherein: the butt-joint block is hemispherical.
7. An assembled pier steel structure according to claim 6, wherein: the butt-joint blocks are sequentially provided with a plurality of butt-joint blocks from top to bottom.
8. An assembled pier steel structure according to claim 1, wherein: one end of the second connecting plate is provided with a correction barrel, the center of the correction barrel is hollow, the other end of the second connecting plate is provided with a correction plate, and the correction plate is provided with correction holes.
9. An assembled pier steel structure according to claim 1, wherein: be provided with the first strengthening rib of a plurality of circular arcs on the outer wall of panel, first strengthening rib with the panel is coaxial, it is provided with a plurality of second strengthening ribs still to go back the axial on the outer wall of panel, the both ends of first strengthening rib with the second connecting plate is connected, the both ends of second strengthening rib with first connecting plate is connected, the panel with between the first connecting plate the panel with all be provided with a plurality of reinforcing plates between the second connecting plate.
CN202120546095.2U 2021-03-16 2021-03-16 Assembled pier steel construction Active CN214656312U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120546095.2U CN214656312U (en) 2021-03-16 2021-03-16 Assembled pier steel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120546095.2U CN214656312U (en) 2021-03-16 2021-03-16 Assembled pier steel construction

Publications (1)

Publication Number Publication Date
CN214656312U true CN214656312U (en) 2021-11-09

Family

ID=78453749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120546095.2U Active CN214656312U (en) 2021-03-16 2021-03-16 Assembled pier steel construction

Country Status (1)

Country Link
CN (1) CN214656312U (en)

Similar Documents

Publication Publication Date Title
CN201080609Y (en) Prestressed concrete pipe pile connecting component
CN214656312U (en) Assembled pier steel construction
CN214940058U (en) Variable-diameter prestressed high-strength concrete pipe pile structure
CN211114384U (en) Convenient kitchen concrete prefabricated part
CN116374808A (en) Hoop assembly for hoisting pipeline and hoisting method
CN216587365U (en) Steel reinforcement cage connection structure
CN210562135U (en) Reinforced concrete square pile
CN113602983A (en) Fixing structure of tower crane standard knot
CN204504600U (en) For assistance platform and the bracing or strutting arrangement thereof of the welding of jack up drilling platform spud leg
CN208328908U (en) A kind of piecing devices for prefabricated pile connection
CN208733642U (en) A kind of box-type pattern foundation pit supporting structure frame
CN211973057U (en) Arch rib segment structure and arch bridge
CN211369068U (en) Steel structure connecting structure
CN215316545U (en) Supporting device
CN215854763U (en) Fixing structure of tower crane standard knot
CN215293863U (en) Base device is assembled to steel bifurcated pipe
CN215482911U (en) Novel high-strength connecting structure of concrete pipe pile
CN214784129U (en) Prefabricated assembled mortar jar places basis
CN216516768U (en) Scaffold for industrial and civil buildings
CN215165485U (en) Pile cap capable of saving manpower and improving strength
CN212670826U (en) Assembled beam column of butt joint steadiness
CN220225222U (en) Multi-pile-position offshore construction platform
CN210851367U (en) Building engineering pipeline butt joint auxiliary device
CN219862781U (en) Novel concrete square pile
CN210916967U (en) Cantilever beam segment device and steel box girder

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant