CN214574608U - Steel structure concrete building house - Google Patents

Steel structure concrete building house Download PDF

Info

Publication number
CN214574608U
CN214574608U CN202120327578.3U CN202120327578U CN214574608U CN 214574608 U CN214574608 U CN 214574608U CN 202120327578 U CN202120327578 U CN 202120327578U CN 214574608 U CN214574608 U CN 214574608U
Authority
CN
China
Prior art keywords
groove
draw
pole
horizontal pole
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202120327578.3U
Other languages
Chinese (zh)
Inventor
谢华
罗永才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Yizhi Construction Engineering Co ltd
Original Assignee
Sichuan Yizhi Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Yizhi Construction Engineering Co ltd filed Critical Sichuan Yizhi Construction Engineering Co ltd
Priority to CN202120327578.3U priority Critical patent/CN214574608U/en
Application granted granted Critical
Publication of CN214574608U publication Critical patent/CN214574608U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The application relates to a steel structure concrete building house, including many with the stand, many set firmly subaerial and become rectangle evenly distributed with the stand is vertical. The top of any two adjacent upright posts is connected with a mounting main beam, and a plurality of mounting main beams construct a rectangular net structure. The embedded mounting bracket that is equipped with of arbitrary rectangle square that the installation girder constitutes is provided with many with the reinforcing bar pole on the mounting bracket, and it is crisscross structure of constitution grid structure violently indulges with the reinforcing bar pole for many. The mounting main body is mounted between two adjacent upright posts through the fixing block and the fixing groove, and the multiple mounting main beams construct a rectangular net structure. The assembled mounting frame and the steel bar rod are sequentially embedded in any rectangular grid formed by the mounting main beam through the mounting block and the mounting groove, the whole house frame is constructed, then concrete is poured on the whole frame, and the process of constructing the house frame is more convenient.

Description

Steel structure concrete building house
Technical Field
The application relates to the field of house construction, in particular to a steel structure concrete building house.
Background
When a house is built, a house frame is generally constructed by adopting a steel structure, and then concrete is poured, so that the building structure is stable, and the safety of the building is improved.
The patent with the publication number of CN212224200U discloses a precast beam column steel structure node and precast concrete house unit, including precast concrete roof beam and precast concrete column, the handing-over department of precast concrete column and precast concrete roof beam is provided with hollow square casing, all be provided with through-hole and a plurality of connecting hole on each lateral wall of square casing, the tip of precast concrete column and precast concrete roof beam all is provided with reserves exposes the reinforcing bar, reserve and expose reinforcing bar and connecting hole one-to-one, the tip of reserving to expose the reinforcing bar passes the connecting hole that corresponds and arranges in the square casing or arranges in the outside of square casing, the end connection who reserves to expose the reinforcing bar has lock nut, square casing, precast concrete column and precast concrete roof beam link to each other through concreting.
With respect to the related art among the above, there are the following drawbacks: when the house frame is constructed, the steel bars need to penetrate through the connecting holes and then be fixed, and the operation process is complicated.
SUMMERY OF THE UTILITY MODEL
In order to make it more convenient to construct the house frame, this application provides a steel construction concrete building house.
The application provides a pair of steel structure concrete building house adopts following technical scheme:
the utility model provides a steel structure concrete building house, includes a plurality of stands, and a plurality of places are adjacent be provided with between the stand with stand vertically installation girder, can dismantle on the installation girder and be provided with the mounting bracket, can dismantle on the mounting bracket and be provided with a plurality of reinforcing bar poles.
Through adopting above-mentioned technical scheme, when constructing whole steel framework frame, install the reinforcing bar pole and form the mounting bracket structure on the mounting bracket, then will install the girder and install between the stand, then will assemble mounting bracket direct mount between the installation girder, then just can pour overall structure, make the process of constructing house frame convenient and fast more.
Preferably, the top of stand has seted up the fixed slot, the tip of installation girder sets firmly the fixed block and is used for with the fixed slot joint.
Through adopting above-mentioned technical scheme, when installing the girder, inlay the fixed block that establishes at installation girder both ends in the mounting groove to connect the installation girder between two stands, make the process of founding the installation girder more convenient.
Preferably, be provided with on the mounting bracket and be used for the connecting portion of being connected with the installation girder, including a plurality of installation pieces, it is a plurality of installation piece evenly distributed is on the mounting bracket, offer the mounting groove that is used for supplying the installation piece joint on the installation girder.
Through adopting above-mentioned technical scheme, when installing the mounting bracket on the installation girder, with the installation piece embedding on the mounting bracket installation in the mounting groove on the girder, can fix the mounting bracket between the installation girder, form steel framework frame, make the process of construction more convenient.
Preferably, the mounting bracket includes horizontal pole and vertical pole, horizontal pole and vertical pole connect gradually into the rectangle, can dismantle the connection between horizontal pole and the vertical pole, the spread groove has been seted up at the both ends of horizontal pole, the setting is opened along horizontal pole thickness direction's both sides to the spread groove, the both ends of vertical pole set firmly be used for with the connecting block of spread groove joint, set up the second screw hole that supplies clamping screw threaded connection on the connecting block.
Through adopting above-mentioned technical scheme, during the equipment mounting bracket, connect gradually horizontal pole and vertical pole, insert the mounting groove with the connecting block in, then it is fixed with the installation piece through the fixed portion, can accomplish the equipment of mounting bracket, make whole process more convenient.
Preferably, the fixing part comprises a fixing screw, a first threaded hole communicated with the connecting groove is formed in the cross rod, the fixing screw is connected in the first threaded hole in a threaded mode, and a second threaded hole for the fixing screw to be connected in a threaded mode is formed in the connecting block.
Through adopting above-mentioned technical scheme, insert the connecting block back in the spread groove, through clamping screw in proper order with first screw hole and second screw hole threaded connection, can be fixed the fixed block, effectively improved the stability of whole device.
Preferably, the vertical side wall of the connecting groove is perpendicular to the length direction of the cross bar, and the connecting block is attached to the vertical side wall of the connecting groove.
Through adopting above-mentioned technical scheme, insert the connecting block back in the spread groove, with the inner wall butt of connecting block and spread groove to make horizontal pole and vertical pole keep mutually perpendicular, improved the stability of whole structure.
Preferably, a plurality of first draw-in grooves have been seted up at the top of horizontal pole along the even interval of self length direction, a plurality of second draw-in grooves have been seted up at the top of vertical pole along the even interval of self length direction, the degree of depth of first draw-in groove is greater than the degree of depth of second draw-in groove, the reinforcing bar joint constitutes spatial grid structure between the relative first draw-in groove on the horizontal pole of both sides and between the relative second draw-in groove on the horizontal pole of both sides.
Through adopting above-mentioned technical scheme, when constructing the mounting bracket, construct horizontal pole and vertical pole into rectangular frame, then inlay in proper order with reinforcing bar pole both ends and establish in the first draw-in groove of both sides, inlay in proper order with reinforcing bar pole again and establish in the second draw-in groove of both sides, because the degree of depth of first draw-in groove is greater than the degree of depth of second draw-in groove, make reinforcing bar pole amalgamation become spatial grid structure, make installation convenient and fast more.
Preferably, the third draw-in groove has been seted up along vertical direction in the bottom of horizontal pole and vertical pole, set up the fourth draw-in groove that communicates with the third draw-in groove along the direction of perpendicular to third draw-in groove on the lateral wall of third draw-in groove, the fifth draw-in groove has been seted up downwards along vertical direction in the fourth draw-in groove bottom on the horizontal pole, the sixth draw-in groove has been seted up downwards along vertical direction in the fourth draw-in groove bottom on the vertical pole, the degree of depth of fifth draw-in groove is greater than the degree of depth of sixth draw-in groove, the reinforcing bar joint constitutes spatial grid structure between the relative fifth draw-in groove on the horizontal pole of both sides and between the relative sixth draw-in groove on the horizontal pole of both sides.
Through adopting above-mentioned technical scheme, when the construction mounting bracket, remove third draw-in groove and fourth draw-in groove on the horizontal pole of both sides along the both ends of reinforcing bar pole in proper order, then in the embedding fifth draw-in groove, remove third draw-in groove and fourth draw-in groove on the longitudinal rod along the both ends of reinforcing bar pole in proper order again, then in the embedding sixth draw-in groove, because the degree of depth of fifth draw-in groove is greater than the degree of depth of sixth draw-in groove, make reinforcing bar pole overlap constitution spatial grid structure, it is more convenient to make the assembling process, and make whole mounting bracket become double-deck spatial grid structure, the stability of the building floor that forms after effectively having improved pouring.
In summary, the present application includes at least one of the following beneficial technical effects:
when the whole structure is constructed, the mounting main beam is clamped between the two adjacent stand columns, and the mounting frame is clamped on the mounting main beam, so that the construction of the steel structure of the whole house can be completed, and the construction process is more convenient and quicker;
when the mounting frame is assembled, the transverse rod and the longitudinal rod are sequentially clamped through the connecting block on the transverse rod and the connecting groove on the longitudinal rod, and the condensing block is fixed through the fixing part, so that the mounting frame is assembled more conveniently and quickly;
when the grid structure of the mounting frame is assembled, the steel bar rods are sequentially clamped in the corresponding clamping grooves, so that the assembling process is more convenient.
Drawings
Fig. 1 is a schematic overall structure diagram of an embodiment of the present application.
Fig. 2 is a schematic diagram of an explosive structure according to an embodiment of the present application.
Fig. 3 is a partially enlarged schematic view of a portion a in fig. 1.
Fig. 4 is an exploded view of the mounting frame portion in the embodiment of the present application.
Fig. 5 is a schematic diagram of an exploded structure of a cross bar and a longitudinal bar in an embodiment of the present application.
Fig. 6 is a partially enlarged schematic view of a portion B in fig. 5.
Description of reference numerals: 1. a column; 11. fixing grooves; 2. mounting a main beam; 21. a fixed block; 22. mounting grooves; 3. a mounting frame; 31. a cross bar; 311. connecting grooves; 312. a first card slot; 32. a longitudinal bar; 321. connecting blocks; 322. a second card slot; 33. mounting blocks; 34. a third card slot; 341. a fourth card slot; 343. a fifth card slot; 342. a sixth card slot; 35. a fixed part; 351. a first threaded hole; 352. a second threaded hole; 353. fixing the screw rod; 4. a reinforcing bar.
Detailed Description
The present application is described in further detail below with reference to figures 1-6.
The embodiment of the application discloses steel structure concrete building house. Referring to fig. 1 and 2, a steel structure concrete building house includes many with stand 1, and many are vertical to set firmly subaerial and become rectangle evenly distributed with stand 1. The top of any two adjacent upright posts 1 is connected with a mounting main beam 2, and a plurality of mounting main beams 2 construct a rectangular net structure. The embedded mounting bracket 3 that is equipped with of arbitrary rectangle square that installation girder 2 constitutes is provided with many on the mounting bracket 3 with reinforcing bar pole 4, and it is crisscross structure of constitution grid structure violently indulges with reinforcing bar pole 4 more.
Referring to fig. 2 and 3, four fixing grooves 11 are formed in the top of the upright post 1, the four fixing grooves 11 are respectively communicated with the vertical side wall on one side, and the depth of each fixing groove 11 is equal to the thickness of the installation main beam 2. The both ends of installation girder 2 all have welded fixed block 21 for inlay and establish in fixed slot 11, when founding the netted crossbeam structure of rectangle, with the fixed block 21 at installation girder 2 both ends inlay respectively establish on two adjacent stands 1 each other be close to one side in the fixed slot 11 can, make the process of founding more convenient.
Referring to fig. 2 and 3, a plurality of mounting grooves 22 are formed in the top wall of the mounting main beam 2, the mounting grooves 22 are evenly distributed in two rows along the length direction of the mounting main beam 2, and the side walls of the mounting grooves 22 are communicated with the vertical side walls of the mounting main beam 2 close to the mounting main beam.
Referring to fig. 4 and 5, the mounting frame 3 includes two cross bars 31 and two longitudinal bars 32, and the cross bars 31 and the longitudinal bars 32 are sequentially connected end to form a rectangular frame. The vertical side walls of the outer sides of the transverse rod 31 and the longitudinal rod 32 are welded with a plurality of mounting blocks 33 which are used for being clamped with the mounting grooves 22. When in installation, the installation block 33 is embedded in the installation groove 22, so that the installation frame 3 can be installed on the installation main beam 2, and the framework process is more convenient.
Referring to fig. 4 and 5, the connecting grooves 311 are respectively formed at two ends of the cross bar 31, two sides of the cross bar are opened along the thickness direction of the cross bar in the horizontal direction by the connecting grooves 311, the vertical side walls of the connecting grooves 311 are perpendicular to the length direction of the cross bar 31, the connecting blocks 321 are respectively welded at two ends of the longitudinal bar 32, and the connecting blocks 321 are used for being embedded in the connecting grooves 311 and abutted against the side walls of the connecting grooves 311, so that the cross bar 31 is perpendicular to the longitudinal bar 32 after being connected.
Referring to fig. 4 and 5, the cross bar 31 is provided with a fixing portion 35 for fixing the connecting block 321, including a fixing screw 353. The corresponding position with the mounting groove 22 on the roof of horizontal pole 31, offered the first screw hole 351 with the mounting groove 22 intercommunication along the direction of perpendicular to roof, offered second screw hole 352 along the direction of perpendicular to roof on the installation piece 33, first screw hole 351 and second screw hole 352 coaxial line after installation piece 33 inlays to be established in mounting groove 22, and set screw 353 is used for threaded connection in proper order in first screw hole 351 and the second screw hole 352.
Referring to fig. 4 and 6, a plurality of first locking grooves 312 are formed at the top of the cross bar 31, and the first locking grooves 312 on the cross bars 31 at two sides and the side walls of the two cross bars 31 close to each other are opened; a plurality of second draw-in grooves 322 have been seted up at the top of vertical pole 32, the setting is opened with the lateral wall that two vertical poles 32 are close to each other to second draw-in groove 322 on the vertical pole 32 of both sides, the degree of depth of first draw-in groove 312 is greater than the degree of depth of second draw-in groove 322, the degree of depth difference is reinforcing bar pole 4's diameter, with reinforcing bar pole 4 joint in proper order in corresponding first draw-in groove 312, then in with reinforcing bar pole 4 joint in proper order in corresponding second draw-in groove 322, make reinforcing bar pole 4 constitution rectangle lattice construction on horizontal pole 31 and the vertical pole 32.
Referring to fig. 4 and 6, a plurality of third clamping grooves 34 are vertically and upwardly formed in the bottoms of the cross bar 31 and the vertical bar 32, the third clamping grooves 34 are uniformly arranged along the length direction of the cross bar 31 or the vertical bar 32 at intervals, a fourth clamping groove 341 is formed in a side wall of the third clamping groove 34 perpendicular to the length direction of the cross bar 31 or the vertical bar 32 where the third clamping groove is located, and the length direction of the fourth clamping groove 341 is perpendicular to the length direction of the third clamping groove 34. A fifth clamping groove 343 is formed in the position, corresponding to the first clamping groove 312, at the bottom of the fourth clamping groove 341 on the cross bar 31 and in the vertical direction, a sixth clamping groove 342 is formed in the position, corresponding to the second clamping groove 322, at the bottom of the fourth clamping groove 341 on the longitudinal bar 32 and in the vertical direction, the depth of the fifth clamping groove 343 is larger than that of the sixth clamping groove 342, and the depth difference is the diameter of the steel bar 4. The two ends of the reinforcing steel bar 4 are sequentially moved along the third clamping grooves 34 and the fourth clamping grooves 341 on the cross bars 31 on the two sides, and then are embedded into the fifth clamping grooves 343, and then the two ends of the reinforcing steel bar 4 are sequentially moved along the third clamping grooves 34 and the fourth clamping grooves 341 on the longitudinal bars 32, and then are embedded into the sixth clamping grooves 342, so that a second-layer rectangular grid structure is constructed.
The implementation principle of the steel structure concrete building house of the embodiment of the application is as follows: the transverse rods 31 and the longitudinal rods 32 are sequentially connected through the fixing parts 35 to be assembled into a rectangular net structure, and then the reinforcing steel bars 4 are sequentially embedded into the corresponding clamping grooves to be assembled into a two-layer grid structure. With many become the rectangle distribution with stand 1 to vertically set firmly subaerial, will install girder 2 and install between two adjacent stands 1 through fixed block 21 and fixed slot 11, many construct rectangle network structure with installation girder 2. With the mounting bracket 3 of assembling together with reinforcing bar 4, inlay in proper order through installation piece 33 and mounting groove 22 and establish in arbitrary rectangle square that installation girder 2 constitutes, accomplish whole house frame's construction, then with whole frame on concreting can, make the process of constructing house frame more convenient.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a steel construction concrete building house which characterized in that: including a plurality of stands (1), a plurality of places are adjacent be provided with between stand (1) with stand (1) vertically installation girder (2), can dismantle on installation girder (2) and be provided with mounting bracket (3), can dismantle on mounting bracket (3) and be provided with a plurality of reinforcing bar poles (4).
2. The steel structural concrete building house of claim 1, wherein: fixed slot (11) have been seted up at the top of stand (1), the tip of installation girder (2) has set firmly fixed block (21) and is used for with fixed slot (11) joint.
3. The steel structural concrete building house of claim 1, wherein: be provided with on mounting bracket (3) and be used for the connecting portion of being connected with installation girder (2), including a plurality of installation piece (33), it is a plurality of installation piece (33) evenly distributed is on mounting bracket (3), offer mounting groove (22) that are used for supplying installation piece (33) joint on installation girder (2).
4. The steel structural concrete building house of claim 1, wherein: mounting bracket (3) include horizontal pole (31) and vertical pole (32), horizontal pole (31) and vertical pole (32) connect gradually into the rectangle, can dismantle the connection between horizontal pole (31) and vertical pole (32), spread groove (311) have been seted up at the both ends of horizontal pole (31), the setting is opened along the both sides of horizontal pole (31) thickness direction in spread groove (311), the both ends of vertical pole (32) set firmly connecting block (321) that are used for with spread groove (311) joint, be provided with fixed part (35) that are used for fixed connection block (321) on horizontal pole (31).
5. The steel structural concrete building house of claim 4, wherein: the fixing portion (35) comprises a fixing screw rod (353), a first threaded hole (351) communicated with the connecting groove (311) is formed in the cross rod (31), the fixing screw rod (353) is connected in the first threaded hole (351) in a threaded mode, and a second threaded hole (352) for the fixing screw rod (353) to be connected in a threaded mode is formed in the connecting block (321).
6. The steel structural concrete building house of claim 5, wherein: the vertical side wall of connecting groove (311) is perpendicular with the length direction of horizontal pole (31), connecting block (321) and the vertical side wall laminating of connecting groove (311).
7. The steel structural concrete building house of claim 4, wherein: a plurality of first draw-in grooves (312) have been seted up at the top of horizontal pole (31) along the even interval of self length direction, a plurality of second draw-in grooves (322) have been seted up at the top of vertical pole (32) along the even interval of self length direction, the degree of depth of first draw-in groove (312) is greater than the degree of depth of second draw-in groove (322), between relative first draw-in groove (312) and on horizontal pole (31) of both sides relative second draw-in groove (322) on horizontal pole (31) of both sides steel bar pole (4) joint constitute spatial grid structure.
8. The steel structural concrete building house of claim 7, wherein: third draw-in groove (34) have been seted up along vertical direction to the bottom of horizontal pole (31) and vertical pole (32), along the direction of perpendicular to third draw-in groove (34) on the lateral wall of third draw-in groove (34) set up fourth draw-in groove (341) that communicate with third draw-in groove (34), fifth draw-in groove (343) have been seted up downwards along vertical direction to fourth draw-in groove (341) bottom on horizontal pole (31), sixth draw-in groove (342) have been seted up downwards along vertical direction to fourth draw-in groove (341) bottom on vertical pole (32), the degree of depth of fifth draw-in groove (343) is greater than the degree of depth of sixth draw-in groove (342), reinforcing bar pole (4) joint constitutes spatial grid structure between relative fifth draw-in groove (343) on both sides horizontal pole (31) and between relative sixth draw-in groove (342) on both sides horizontal pole (31).
CN202120327578.3U 2021-02-04 2021-02-04 Steel structure concrete building house Withdrawn - After Issue CN214574608U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120327578.3U CN214574608U (en) 2021-02-04 2021-02-04 Steel structure concrete building house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120327578.3U CN214574608U (en) 2021-02-04 2021-02-04 Steel structure concrete building house

Publications (1)

Publication Number Publication Date
CN214574608U true CN214574608U (en) 2021-11-02

Family

ID=78350190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120327578.3U Withdrawn - After Issue CN214574608U (en) 2021-02-04 2021-02-04 Steel structure concrete building house

Country Status (1)

Country Link
CN (1) CN214574608U (en)

Similar Documents

Publication Publication Date Title
CN218912324U (en) Reinforcing steel bar framework binding auxiliary frame
CN112360009A (en) Wall and floor connecting node and method for prefabricated building
CN210164045U (en) Assembly joint of primary and secondary beams
CN214574608U (en) Steel structure concrete building house
CN208152558U (en) Aluminum dipping form at a kind of precast prestressed frame joint
CN209653365U (en) Tool-type wall-connecting piece
CN114150765B (en) Frame beam column connecting node structure and construction method thereof
CN215670918U (en) Operation frame for high slope lattice beam
CN210976584U (en) Combined type supporting template for constructional engineering
CN213741599U (en) Large-span factory building steel frame
CN221031884U (en) Prefabricated assembly rail guard
CN221461435U (en) Quick connecting structure
CN114278019B (en) Assembled roof frame and preparation process and construction method thereof
CN214034237U (en) Light assembled prefabricated plate
CN217631272U (en) Assembled formwork support integrated system
CN212358689U (en) Shear wall structure for building
CN217840300U (en) Support-free fabricated concrete structure connecting node unit
CN215167221U (en) Prefabricated building conversion node reserves wall body joint bar positioner
CN211447348U (en) High shock resistance shear force wall
CN216516100U (en) Assembled beam column frame construction
CN217652364U (en) Device is pour to bulky concrete wall sectional type
CN217975751U (en) Enclose fender basis with equipment that sprays
CN219196705U (en) Steel tube bundle outsourcing concrete formwork reinforcing apparatus
CN214575580U (en) Aluminum alloy scaffold with truss
CN113718941B (en) Assembled balcony structure of prefabricated building and implementation method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20211102

Effective date of abandoning: 20240528

AV01 Patent right actively abandoned

Granted publication date: 20211102

Effective date of abandoning: 20240528