CN214532068U - Heavy beam support frame - Google Patents

Heavy beam support frame Download PDF

Info

Publication number
CN214532068U
CN214532068U CN202120385525.7U CN202120385525U CN214532068U CN 214532068 U CN214532068 U CN 214532068U CN 202120385525 U CN202120385525 U CN 202120385525U CN 214532068 U CN214532068 U CN 214532068U
Authority
CN
China
Prior art keywords
supporting
connecting seat
pole
threaded rod
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120385525.7U
Other languages
Chinese (zh)
Inventor
邢立化
张凯
郝海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Tosun Technology Development Co ltd
Original Assignee
Beijing Tosun Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Tosun Technology Development Co ltd filed Critical Beijing Tosun Technology Development Co ltd
Priority to CN202120385525.7U priority Critical patent/CN214532068U/en
Application granted granted Critical
Publication of CN214532068U publication Critical patent/CN214532068U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a heavy roof beam support frame, belong to room roof beam maintenance equipment's field, it includes a plurality of support upright pole groups, every supports the upright pole group and all is provided with many support uprights, the grafting chamber has been seted up along self length direction to the one end that supports the upright pole, the other end that supports the upright pole sets firmly along self length direction with grafting chamber grafting complex peg graft pole, the length direction along the support rods group is provided with a plurality of reinforcement assembly at the interval between supporting the upright pole group, the top that supports the upright pole group is provided with the supporting component who is used for supporting the room roof beam, the bottom that supports the upright pole group is provided with the base, be provided with coupling assembling between base and support upright pole group, be equipped with in the base and be used for driving the pneumatic cylinder that coupling assembling removed along vertical direction. This application has the effect that reaches simple, high-efficient completion support frame and build.

Description

Heavy beam support frame
Technical Field
The utility model belongs to the technical field of room roof beam maintenance of equipment and specifically relates to a heavy roof beam support frame is related to.
Background
The roof beam is used for supporting the firm ledger (also having reinforced concrete to make now) of house top structure, and among the modern architecture, the roof beam of flat-topped building mostly is steel wood roof beam, steel roof beam, reinforced concrete roof beam, and each roof beam mutually perpendicular or parallel is the main load-carrying members of building.
When the staff is in some buildings that lack the support room roof beam of maintenance, the staff often need adopt a large amount of steel sheets to build fixedly, lead to the groove and adopt the bolt, bind or welded mode, constitute the support frame that plays interim supporting role for the room roof beam to avoid taking place the phenomenon of collapsing when the maintenance room roof beam, after finishing maintaining the room roof beam, demolish the support frame that the steel sheet was built again.
Aiming at the related technologies, the inventor thinks that the mode of building the supporting frame structure by adopting the steel plate wastes time and labor and has the defect of increasing the workload of workers.
SUMMERY OF THE UTILITY MODEL
In order to reach the effect that simple, high-efficient completion support frame was built, this application provides a heavy roof beam support frame.
The application provides a heavy roof beam support frame adopts following technical scheme:
the utility model provides a heavy roof beam support frame, including a plurality of support pole groups, every supports pole group and all is provided with many support poles, the grafting chamber has been seted up along self length direction to the one end of supporting the pole setting, the other end of supporting the pole setting has set firmly along self length direction with grafting chamber grafting complex peg graft pole, the length direction along the pole group is being supported the interval and is being provided with a plurality of reinforcement subassemblies between the pole group, the top of supporting the pole group is provided with the supporting component who is used for supporting the room roof beam, the bottom of supporting the pole group is provided with the base, be provided with coupling assembling between base and support pole group, be equipped with in the base and be used for driving the pneumatic cylinder that coupling assembling removed along vertical direction.
Through adopting above-mentioned technical scheme, the staff earlier constitutes through the grafting cooperation between peg graft pole and the grafting chamber between supporting the pole setting and supports the pole setting group, fix the reinforcement subassembly between supporting the pole setting group again, then will support the top installation supporting component of pole setting group, the bottom that will support the pole setting group again is passed through coupling assembling and is connected with the base, will support the pole setting and set up along vertical direction, put into to the base inside the pneumatic cylinder, the staff is through raising the pneumatic cylinder, make the pneumatic cylinder pass through coupling assembling and drive the upward movement of support pole setting subassembly, support the pole setting and driving the bottom of supporting component butt at the room beam again, make this support frame play the effect of interim support for the room beam. In conclusion, the effect of simply and efficiently completing the construction of the support frame is achieved through the structure.
Optionally, along the length direction of supporting the pole setting interval has set firmly a plurality of plum blossom snap rings on the circumference lateral wall of supporting the pole setting, and the plum blossom snap ring is seted up and is run through the joint hole of self, consolidates the subassembly and includes the horizontal pole and set up the plug connector at the horizontal pole both ends, and the plug connector is close to the position of horizontal pole tip and has set firmly the plugboard, and the plugboard is pegged graft with the horizontal pole and is cooperated, the bottom and the joint hole grafting cooperation of plug connector.
Through adopting above-mentioned technical scheme, pass through the plugboard with the plug connector and peg graft and fix at the both ends of horizontal pole, insert the plug connector bottom to the joint downthehole again, and the plug connector deviates from one side of horizontal pole and the circumference lateral wall butt that supports the pole setting to make the horizontal pole play the additional strengthening between to supporting the pole setting, improved the stress intensity of this support frame, also improved the stability of supporting between the pole setting simultaneously.
Optionally, first inserting groove has been seted up at the both ends of horizontal pole, and the second inserting groove has been seted up to the plug connector, and first inserting groove and second inserting groove communicate each other, and it has oblique champs to peg graft in first inserting groove and second inserting groove, and oblique champs bottom inserts to the joint downthehole, and one side and the plum blossom snap ring butt of oblique champs, the opposite side and the plug connector butt of oblique champs.
Through adopting above-mentioned technical scheme, the horizontal pole is installed between two support pole settings after, inserts oblique champs from the top of first inserting groove and second inserting groove again and inserts to it is downthehole to make the bottom insert to the card, thereby has strengthened the fixed effect of horizontal pole between the support pole setting, has improved stability, makes the horizontal pole provide good additional strengthening for supporting between the pole setting.
Optionally, one side of the plug connector close to the supporting vertical rod is arc-shaped.
Through adopting above-mentioned technical scheme, improved the laminating effect between plug connector and the support pole setting, make the plug connector and support the fastening more of laminating between the pole setting.
Optionally, the supporting component includes connecting seat and last threaded rod, goes up the threaded rod along vertical direction run through the connecting seat and with last connecting seat sliding connection, the top of going up the threaded rod has set firmly the backup pad, goes up threaded rod threaded connection and has last nut, goes up the upper surface butt of nut and last connecting seat, the bottom of going up the connecting seat sets firmly the last connecting rod with the grafting pole grafting complex.
By adopting the technical scheme, a worker can hold the supporting plate to pull upwards to enable the upper threaded rod to extend out of the upper connecting seat, then the upper nut is rotated to enable the upper nut to move downwards, and therefore the position of the supporting plate is lifted; the upper nut is rotated upwards to enable the upper threaded rod to be retracted into the upper connecting seat, so that the position of the supporting plate is lowered. The height of the supporting plate is adjusted through the structure, and meanwhile, the stability of the supporting plate is improved through the abutting relation between the upper nut and the upper connecting seat, so that the supporting plate is not easy to fall down in the supporting process of the supporting frame; through the grafting cooperation between last connecting rod and the support pole setting, realized going up the installation between connecting seat and the support pole setting and fixed.
Optionally, coupling assembling includes lower threaded rod and lower connecting seat, the bottom fixed connection of lower threaded rod top and lower connecting seat, lower threaded rod along vertical run through the base and with base sliding connection, lower threaded rod threaded connection has the lower nut, the upper surface butt of lower nut and lower base, the last fixed surface of lower connecting seat has the lower connecting rod with grafting chamber grafting complex.
Through adopting above-mentioned technical scheme, after the threaded rod rebound to suitable height under the pneumatic cylinder drives, the nut rotates downwards, makes the upper surface butt of lower nut and base to for providing the guarantee between threaded rod and the base down, make the phenomenon that the threaded rod is difficult for appearing the whereabouts down, through connecting rod and the grafting cooperation of supporting between the pole setting from top to bottom, realized down the connecting seat and supported the installation between the pole setting fixed.
Optionally, through holes are formed in the side wall of the lower connecting rod, the side wall of the upper connecting rod and the side wall of the supporting vertical rod close to the two ends, and positioning pins are inserted in the through holes.
Through adopting above-mentioned technical scheme, with this support frame equipment back that finishes, insert the locating pin to the through-hole in to all provide good stability for between lower connecting rod and the support pole setting, between support pole setting and the support pole setting, go up the connecting rod and support between the pole setting through the locating pin, make this carriage be difficult for taking place the phenomenon that drops in the support process.
Optionally, an elastic snap ring is fixedly arranged at one end of the positioning pin and is clamped on the circumferential side wall of the supporting vertical rod or the upper connecting rod.
Through adopting above-mentioned technical scheme, make the locating pin be difficult for falling out in the through-hole through the snap ring, further improved the device's stability.
Drawings
FIG. 1 is a schematic structural view of a heavy beam support frame of the present application;
FIG. 2 is a partial schematic structural view of a support assembly and connection assembly connection structure;
FIG. 3 is a schematic structural view of a supporting upright structure;
FIG. 4 is a schematic view of a portion of a reinforcement member;
FIG. 5 is a schematic, disassembled view of a reinforcement member;
fig. 6 is a schematic structural view showing a structure of a positioning pin and a snap ring.
Description of reference numerals: 1. a set of support rods; 11. supporting the upright stanchion; 111. an insertion cavity; 112. a plug rod; 2. a reinforcement assembly; 21. a cross bar; 211. a first insertion groove; 22. a plug-in unit; 221. a plugboard; 222. a second insertion groove; 223. oblique elps; 3. a quincuncial snap ring; 31. a clamping hole; 4. a support assembly; 41. an upper connecting seat; 411. an upper connecting rod; 42. an upper threaded rod; 421. a support plate; 43. screwing a nut; 5. a connecting assembly; 51. a lower connecting seat; 511. a lower connecting rod; 52. a lower threaded rod; 53. a lower nut; 6. a base; 61. a placement chamber; 7. a hydraulic cylinder; 8. positioning pins; 81. an elastic snap ring.
Detailed Description
The present application is described in further detail below with reference to the attached drawings.
The embodiment of the application discloses heavy roof beam support frame.
Referring to fig. 1 and 2, a heavy roof beam support frame includes four bracing piece group 1, four bracing piece group 1 all set up along vertical direction, four bracing piece group are around setting up, it plays stiffening assembly 2 of reinforcing effect to be provided with the multiunit along the even interval of horizontal direction between two adjacent bracing piece group 1, be provided with the supporting component 4 that is used for the room roof beam to play supporting role at the top of bracing piece group 1, the bottom of bracing piece group 1 is provided with base 6, be provided with coupling assembling 5 between base 6 and the bracing piece group 1, base 6 has been seted up and has been placed chamber 61, place and place pneumatic cylinder 7 in the chamber 61. When the staff need carry out interim support to the room roof beam, assemble this support frame earlier, install earlier reinforcement assembly 2 between the bracing piece group 1, install bracing piece 4 at the top of bracing piece group 1 again, then install coupling assembling 5 in the bottom of bracing piece group 1, install base 6 in the one side that coupling assembling 5 deviates from bracing piece group 1 again, after finishing the installation with vertical the placing of this support frame, place chamber 61 with pneumatic cylinder 7, driving coupling assembling 5 rebound through pneumatic cylinder 7, coupling assembling 5 is driving bracing piece group 1 rebound again, bracing piece group 1 is driving 4 butts of bracing piece in the below of room roof beam again. To sum up, the support frame simply and efficiently completes the construction work, so that the working efficiency of the house beam maintenance work is improved.
Referring to fig. 1 and 3, every bracing piece group 1 all includes many supports pole setting 11, grafting chamber 111 has been seted up along self length direction in the inside of supporting pole setting 11 one end, the other end of supporting pole setting 11 sets firmly with grafting chamber 111 grafting complex grafting pole 112, grafting pole 112 with support pole setting 11 structure as an organic whole, be provided with a plurality of plum blossom snap ring 3 along the even interval of length direction of supporting pole setting 11, support pole setting 11 from the inside of plum blossom snap ring 3 pass and with plum blossom snap ring 3 welded fastening, plum blossom snap ring 3 and reinforcement component 2 one-to-one. When assembling the support rod group 1, the end of the support vertical rod 11 with the insertion rod 112 is inserted into the adjacent support vertical rod 11 to drive the inside of the insertion cavity 111, so as to complete the assembling of the support rod group 1, and then the reinforcing component 2 is fixed with the quincuncial clamping ring 3 on the adjacent support rod group 1, thereby playing a role of reinforcing the support rod group 1.
Referring to fig. 4 and 5, reinforcement subassembly 2 includes horizontal pole 21 and plug connector 22, plug connector 22 in every reinforcement subassembly 2 all is provided with two, two plug connectors 22 are located the both sides of horizontal pole 21 respectively, one side that every plug connector 22 is close to horizontal pole 21 all sets firmly two with 21 tip grafting complex plugboard 221 of horizontal pole, one side that plugboard 221 deviates from each other and the inner wall butt of horizontal pole 21, the first inserting groove 211 that runs through self is seted up along vertical direction at the both ends of horizontal pole 21, second inserting groove 222 has been seted up along vertical direction in one side that is close to horizontal pole 21 to plug connector 22, first inserting groove 211 and second inserting groove 222 communicate each other. Plum blossom snap ring 3 is seted up and is run through self joint hole 31, and joint hole 31 constitutes for the multistage arc, and in this embodiment, four, even interval distribution between four snap rings have all been seted up to joint hole 31 on every plum blossom snap ring 3. The bottom of plug connector 22 inserts to joint hole 31 in, makes plug connector 22 and the cooperation of pegging graft of plum blossom snap ring 3, is provided with oblique champs 223 at the both ends of horizontal pole 21, and one side that plug connector 22 is close to horizontal pole 21 is the inclined plane, and plug connector 22 deviates from horizontal pole 21 one side and is the arcwall face. The inclined champs 223 are obliquely inserted into the first inserting groove 211 and the second inserting groove 222 along the inclined surface of the inserting piece 22, one side of the bottom of the inclined champs 223 is abutted against the inner wall of the plum blossom clamp ring 3 at the clamping hole 31, and the other side of the inclined champs 223 is abutted against the inserting piece 22. When the staff need fix reinforcement component 2 between two adjacent support pole settings 11, insert the inside of horizontal pole 21 with the fixed plate earlier, make plug connector 22 install the both sides at horizontal pole 21, insert to joint hole 31 from last extremely down with the bottom of plug connector 22 again, thereby make horizontal pole 21 horizontally fix between two support pole settings 11, then insert oblique champs 223 to first inserting groove 211 and second inserting groove 222 in, and make oblique champs 223's bottom insert to joint hole 31 in, thereby it is fixed with the installation of supporting between the pole setting 11 to accomplish reinforcement component 2, make reinforcement component 2 for supporting provide good reinforcement effect between the pole setting 11.
Referring to fig. 2, the support assembly 4 includes an upper connection seat 41, an upper threaded rod 42, and an upper nut 43. An upper connecting rod 411 is fixedly arranged at each of four corners of the bottom of the upper connecting seat 41, the inside of the upper connecting rod 411 is of a hollow structure, and the insertion rod 112 of the supporting upright rod 11 positioned at the topmost part is inserted into the inside of the upper connecting rod 411, so that the upper connecting seat 41 and the supporting upright rod 11 are inserted and fixed; the upper threaded rod 42 penetrates through the upper connecting seat 41 along the vertical direction and is in sliding connection with the upper connecting seat 41, and the upper nut 43 is in threaded connection with the upper threaded rod 42 and is located above the upper connecting seat 41. The top of the upper threaded rod 42 is fixedly connected with the support plate 421.
Referring to fig. 2, the connection assembly 5 includes a lower connection block 51, a lower threaded rod 52, and a lower nut 53. A lower connecting rod 511 is fixedly arranged at each of four corners of the top of the lower connecting seat 51, and the lower connecting rod 511 is inserted into the inserting cavity 111 of the bottommost supporting upright rod 11, so that the lower connecting seat 51 and the supporting upright rod 11 are inserted and fixed; the top of lower threaded rod 52 and the bottom fixed connection of lower connecting seat 51, lower nut 53 and lower threaded rod 52 threaded connection just are located between lower connecting seat 51 and the base 6, lower threaded rod 52 along vertical direction run through base 6 and with base 6 sliding connection, the butt of the bottom of lower threaded rod 52 and pneumatic cylinder 7.
When the staff uses this support frame to carry out interim support to the room roof beam, earlier with backup pad 421 driving threaded rod 42 rebound, after backup pad 421 adjustment to suitable height, rotate again and go up nut 43 and make upper nut 43 lapse to with the upper surface butt of last connecting seat 41, make the high fixed of backup pad 421, thereby realized the effect to backup pad 421 altitude mixture control. Then the staff is driving lower threaded rod 52 rebound through pneumatic cylinder 7 again, makes lower threaded rod 52 drive the bracing piece group 1 rebound through lower connecting seat 51, bracing piece group 1 is driving backup pad 421 rebound through last connecting seat 41 again, until backup pad 421 and room roof beam butt, then rotates lower nut 53 again, makes lower nut 53 rebound and the upper surface butt of base 6, provides the safety guarantee for this support frame, makes the difficult automatic phenomenon of taking place the whereabouts of this support frame. Thereby realizing the support of the device to the house beam.
Referring to fig. 2 and 6, through holes are formed in the side walls of the upper connecting rod 411 and the lower connecting rod 511, through holes are also formed in the side walls of the supporting upright 11 near the two ends, and the through holes are aligned when the insertion rod 112 is inserted into the upper connecting rod 411; when the insertion rod 112 is inserted into the insertion cavity 111, the through holes between the support upright rods 11 are aligned; the through holes are aligned when the lower connection rod 511 is inserted into the plugging chamber 111. The locating pin 8 is inserted in the through hole, one end of the locating pin 8 is fixedly provided with the elastic clamping ring 81, and the elastic clamping ring 81 is clamped and fixed with the circumferential side wall of the supporting upright rod 11 or the upper connecting rod 411. After finishing the equipment of this support frame, insert locating pin 8 to the through-hole in, make simultaneously circlip 81 joint on last connecting rod 411 or the circumference lateral wall that supports pole setting 11 to for connecting rod 511 and supporting between the pole setting 11 down, support pole setting 11 and support between the pole setting 11, go up connecting rod 411 and support between the pole setting 11 and all provide good stability through locating pin 8, circlip 81 makes locating pin 8 be difficult for dropping from the through-hole.
The implementation principle of the heavy beam support frame of the embodiment of the application is as follows: connect earlier and constitute bracing piece group 1 through the mode of pegging graft between the pole setting 11, then install additional between bracing piece group 1 and consolidate subassembly 2, pass through coupling assembling 5 and base 6 with the bottom of bracing piece group 1 again and be connected bracing piece group 1's top and supporting component 4, and carry out altitude mixture control to supporting component 4, then insert locating pin 8 in to the through-hole, put into the inside of base 6 with pneumatic cylinder 7 at last, make this support frame rise through pneumatic cylinder 7, until the bottom butt of backup pad 421 and room beam, thereby realized the effect of supporting the room beam temporarily. In conclusion, the effect of simply and efficiently completing the construction of the supporting frame is achieved through the structure, and therefore the working efficiency of house beam repairing is improved.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a heavy roof beam support frame which characterized in that: including a plurality of bracing piece group (1), every bracing piece group (1) all is provided with many and supports pole setting (11), grafting chamber (111) have been seted up along self length direction to the one end that supports pole setting (11), the other end that supports pole setting (11) has set firmly along self length direction with grafting chamber (111) grafting complex grafting pole (112), length direction along bracing piece group (1) is provided with a plurality of reinforcement subassembly (2) at the interval between bracing piece group (1), the top of bracing piece group (1) is provided with supporting component (4) that are used for supporting the room roof beam, the bottom of bracing piece group (1) is provided with base (6), be provided with coupling assembling (5) between base (6) and bracing piece group (1), be equipped with in base (6) and be used for driving pneumatic cylinder (7) that coupling assembling (5) removed along vertical direction.
2. A heavy beam support frame according to claim 1, wherein: along the length direction of supporting pole setting (11) sets firmly a plurality of plum blossom snap rings (3) at the interval on the circumference lateral wall of supporting pole setting (11), plum blossom snap ring (3) are seted up and are run through joint hole (31) of self, consolidate subassembly (2) and include horizontal pole (21) and set up plug connector (22) at horizontal pole (21) both ends, plug connector (22) are close to the position of horizontal pole (21) tip and have set firmly plugboard (221), plugboard (221) and horizontal pole (21) cooperation of pegging graft, the cooperation of pegging graft with joint hole (31) in the bottom of plug connector (22).
3. A heavy beam support according to claim 2, wherein: first inserting groove (211) have been seted up at the both ends of horizontal pole (21), second inserting groove (222) have been seted up in plug connector (22), first inserting groove (211) and second inserting groove (222) communicate each other, it has oblique champs (223) to peg graft in first inserting groove (211) and second inserting groove (222), insert to joint hole (31) bottom champs (223), one side and plum blossom snap ring (3) butt of champs (223), the opposite side and plug connector (22) butt of champs (223).
4. A heavy beam support according to claim 2, wherein: one side of the plug connector (22) close to the supporting upright rod (11) is arc-shaped.
5. A heavy beam support according to claim 2, wherein: support assembly (4) are including last connecting seat (41) and last threaded rod (42), go up threaded rod (42) along vertical direction run through go up connecting seat (41) and with last connecting seat (41) sliding connection, the top of going up threaded rod (42) has set firmly backup pad (421), go up threaded rod (42) threaded connection has last nut (43), go up the upper surface butt of nut (43) and last connecting seat (41), the bottom of going up connecting seat (41) sets firmly and goes up connecting rod (411) with grafting pole (112) grafting complex.
6. A heavy beam support frame according to claim 5, wherein: coupling assembling (5) include lower threaded rod (52) and lower connecting seat (51), lower threaded rod (52) top and the bottom fixed connection of lower connecting seat (51), lower threaded rod (52) along vertical base (6) and with base (6) sliding connection run through, lower threaded rod (52) threaded connection has lower nut (53), lower nut (53) and the upper surface butt of base (6) down, the upper surface of lower connecting seat (51) is fixed with lower connecting rod (511) with grafting chamber (111) grafting complex.
7. The heavy beam support bracket of claim 6, wherein: the lateral wall of lower connecting rod (511), the lateral wall of upper connecting rod (411) and support pole setting (11) are close to the lateral wall at both ends and all seted up the through-hole, and it has locating pin (8) to peg graft in the through-hole.
8. A heavy beam support frame according to claim 7, wherein: one end of the positioning pin (8) is fixedly provided with an elastic clamping ring (81), and the elastic clamping ring (81) is connected to the circumferential side wall of the supporting vertical rod (11) or the upper connecting rod (411) in a clamping mode.
CN202120385525.7U 2021-02-20 2021-02-20 Heavy beam support frame Active CN214532068U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120385525.7U CN214532068U (en) 2021-02-20 2021-02-20 Heavy beam support frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120385525.7U CN214532068U (en) 2021-02-20 2021-02-20 Heavy beam support frame

Publications (1)

Publication Number Publication Date
CN214532068U true CN214532068U (en) 2021-10-29

Family

ID=78235578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120385525.7U Active CN214532068U (en) 2021-02-20 2021-02-20 Heavy beam support frame

Country Status (1)

Country Link
CN (1) CN214532068U (en)

Similar Documents

Publication Publication Date Title
CN214941054U (en) Board house structure for house construction project
CN214195730U (en) Combined workshop steel structure
CN109339425B (en) Supporting platform for building construction and installation method thereof
CN214532068U (en) Heavy beam support frame
CN115182631B (en) Steel structure plant capable of being quickly built and mounting process thereof
CN212956992U (en) Cage structural unit of fabricated building and fabricated cage structural building
CN216690258U (en) Plug-in type scaffold
CN211396542U (en) Cantilever scaffold puts up back support system
CN214614609U (en) Prefabricated assembly type foundation's assembled building
CN113323447A (en) Temporary supporting device for steel structure hoisting construction
CN211114703U (en) House building electromechanical engineering is with portable maintenance frame
CN211597685U (en) Scaffold convenient to assemble and disassemble for green building
CN215483535U (en) Integrated assembly type steel structure building
CN217460891U (en) Assembled steel girt beam connection structure
CN214786112U (en) Rack track support bed-jig that slides
CN216239601U (en) Scaffold for building construction
CN210342725U (en) Steel construction stand assembly structure
CN219508827U (en) Easy-to-disassemble movable house
CN220645154U (en) Socket type disc buckle type shaping tripod outer protection frame
CN213710396U (en) Positioning die for installing positioning support piece
CN220167426U (en) High-safety building construction frame
CN219711114U (en) Mud purifying tank rack
CN218462604U (en) Indoor side wall drilling equipment for building engineering
CN215671235U (en) High-strength assembly type steel structure support
CN218346953U (en) Temporary supporting structure of cantilever beam

Legal Events