Prior art keywords
guide rail
construction
pile driver
movable block
guardrail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120446995.XU
Other languages
Chinese (zh)
Inventor
沈俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zhonggang Ecological Engineering Co ltd
Original Assignee
Anhui Zhonggang Ecological Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Zhonggang Ecological Engineering Co ltd filed Critical Anhui Zhonggang Ecological Engineering Co ltd
Priority to CN202120446995.XU priority Critical patent/CN214530655U/en
Application granted granted Critical
Publication of CN214530655U publication Critical patent/CN214530655U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a fill out stone road bed guardrail pile driver auxiliary device for stand construction relates to guardrail stand construction technical field, including first guide rail, the top of first guide rail is seted up flutedly, and the top swing joint of recess has the movable block, the bottom swing joint of first guide rail has first slider, and the bottom of first slider is connected with the second guide rail, the outside swing joint of second guide rail has the second slider. The utility model discloses in, be provided with the second guide rail, the third guide rail, first slider and spacing ring, fix first guide rail and third guide rail in the middle of the region that two adjacent places need be under construction, according to two adjacent regional distances, outwards stimulate the handle, and then can drive second guide rail and fourth guide rail back of the body removal mutually, finally can adjust the spacing ring in the second guide rail outside and the spacing ring in the fourth guide rail outside distance between, this is done can be assisted the construction to two adjacent places simultaneously, the efficiency of construction is higher.

Description

Fill out construction of stone road bed guardrail stand and use pile driver auxiliary device
Technical Field
The utility model relates to a guardrail stand construction technical field especially relates to a fill out construction of stone road bed guardrail stand and use pile driver auxiliary device.
Background
Along with the development of science and technology and the progress of times, the use of a pile driver is more extensive, the pile driver comprises a pile hammer, a pile frame, accessory equipment and the like, the pile hammer is attached between two parallel vertical guide rods at the front part of the pile frame, the pile hammer is lifted by a lifting hook, the lifting hook is loosened to enable the pile hammer to fall freely, and the pile is driven into the ground by the gravity of the lifting hook, so that the pile driver auxiliary device for the construction of the stone-filled roadbed guardrail stand column is provided.
The utility model discloses a building pile driver is with auxiliary positioning device disclosed in chinese utility model patent application publication specification CN201921533081.6, this building pile driver is with auxiliary positioning device, though can realize with pile driver with auxiliary positioning device through setting up unable adjustment base, fix subaerial presetting the pile driver, then support horizontal base through vertical threaded connection's in the both sides screw thread ear supporting screw, support the level that high regulation changed the horizontal base that sets up in the unable adjustment base top through supporting screw, guarantee the horizontality that pile driver is with auxiliary positioning device supports spacing stake, improve the precision of pile driver, however, this building pile driver is with auxiliary positioning device, it can not carry out supplementary construction to adjacent two simultaneously to have, the efficiency of construction is lower, along with the deepening of stake, auxiliary device's righting effect is weakened.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the technical problem who solves overcomes current defect, provides a fill out stone road bed guardrail pile driver auxiliary device for stand construction, the utility model discloses simple structure, convenient to use need not to prepare the spraying head of different bores, can make the spraying liquid even at the surface distribution of PCB board, can effectively solve the problem in the background art.
In order to solve the technical problem, the utility model provides a following technical scheme:
a pile driver auxiliary device for construction of a stone-filled roadbed guardrail stand column comprises a first guide rail, wherein the top of the first guide rail is provided with a groove, a movable block is movably connected above the groove, the bottom of the first guide rail is movably connected with a first slide block, the bottom of the first slide block is connected with a second guide rail, the outer part of the second guide rail is movably connected with a second slide block, the outer side of the second slide block is welded with a connecting frame, the inner part of the connecting frame is movably connected with a bearing, the outer part of the bearing is welded with a connecting rod, the tail end of the connecting rod is connected with a limit ring, the inner side of the limit ring is connected with a second spring, the limit ring is connected with a buffer plate through the second spring, the left side of the second guide rail is movably connected with a fourth guide rail, a first spring is connected between the second guide rail and the fourth guide rail, and the middle part of the outer side of the second guide rail is provided with a handle, the bottom of second guide rail is connected with the third slider, and the bottom of third slider is provided with the third guide rail, the hinge is installed at the top of movable block, and the movable block has the stop hook through hinged joint, the outside both sides welding of movable block has the nut, and the inside swing joint of nut has locking screw, the pulley has been installed to the bottom of movable block.
Furthermore, a moving structure is formed between the movable block and the first guide rail through a pulley, and the thickness of the pulley is smaller than the width of the groove.
Furthermore, a rotating structure is formed between the limiting ring and the second sliding block through a bearing and a connecting rod, and the second sliding block is in sliding connection with the second guide rail.
Furthermore, a moving structure is formed between the second guide rail and the third guide rail through a third slider, and an elastic structure is formed between the second guide rail and the fourth guide rail through a first spring.
Furthermore, an elastic structure is formed between the buffer plate and the limiting ring through a second spring, and two groups of buffer plates are symmetrically distributed around the center of the limiting ring.
Furthermore, a rotating structure is formed between the blocking hook and the movable block through a hinge, and the diameter of the circle where the blocking hook is located is larger than the width of the first guide rail.
The utility model discloses a technological effect and advantage:
1. the utility model discloses in, be provided with the second guide rail, the third guide rail, first slider and spacing ring, fix first guide rail and third guide rail in the middle of the region that two adjacent places need be under construction, according to two adjacent regional distances, outwards stimulate the handle, and then can drive second guide rail and fourth guide rail back of the body removal mutually, finally can adjust the spacing ring in the second guide rail outside and the spacing ring in the fourth guide rail outside distance between, this is done can be assisted the construction to two adjacent places simultaneously, the efficiency of construction is higher.
2. The utility model discloses in, be provided with second guide rail, fourth guide rail, second slider and spacing ring, after the stake got into the soil inside, the second slider of lapse moved down, the second slider passes through the connecting rod and drives the spacing ring lapse, and then can ensure the stake when lapse, can be in the state of rightting always, and this lifts and to ensure that auxiliary device's righting effect can not be weakened along with the deepening of stake.
3. The utility model discloses in, be provided with spacing ring, connecting rod, second spring and buffer board, rotate the spacing ring round the bearing, and then can adjust the angle of spacing ring, can fix the stake of different position angles, and buffer board and second spring can cushion the guard action to the stake, ensure that the stake can not take place too big crooked.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
Fig. 1 is a schematic diagram of the overall three-dimensional structure of the present invention;
FIG. 2 is a schematic view of the internal structure of the stop collar of the present invention;
fig. 3 is a schematic structural view of the middle movable block of the present invention.
Reference numbers in the figures: 1. a first guide rail; 2. a first slider; 3. a groove; 4. a movable block; 5. a limiting ring; 6. a second guide rail; 7. a handle; 8. a third slider; 9. a third guide rail; 10. a first spring; 11. a bearing; 12. a connecting rod; 13. a connecting frame; 14. a second slider; 15. a second spring; 16. a buffer plate; 17. a blocking hook; 18. locking the screw; 19. a nut; 20. a pulley; 21. a hinge; 22. and a fourth guide rail.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it will be understood that they are presented herein only to illustrate and explain the present invention, and not to limit the present invention.
As shown in fig. 1-3, an auxiliary device of a pile driver for constructing a pillar of a rockfill roadbed guardrail comprises a first guide rail 1, a first slide block 2, a groove 3, a movable block 4, a limiting ring 5, a second guide rail 6, a handle 7, a third slide block 8, a third guide rail 9, a first spring 10, a bearing 11, a connecting rod 12, a connecting frame 13, a second slide block 14, a second spring 15, a buffer plate 16, a blocking hook 17, a locking screw 18, a nut 19, a pulley 20, a hinge 21 and a fourth guide rail 22, wherein the groove 3 is formed at the top of the first guide rail 1, the movable block 4 is movably connected above the groove 3, the first slide block 2 is movably connected at the bottom of the first guide rail 1, the second guide rail 6 is connected at the bottom thereof, the second slide block 14 is movably connected at the outside of the second guide rail 6, the connecting frame 13 is welded at the outside of the second slide block 14, the bearing 11 is movably connected inside the connecting frame 13, and the outside welding of bearing 11 has connecting rod 12, the end-to-end connection of connecting rod 12 has spacing ring 5, and the inboard of spacing ring 5 is connected with second spring 15, spacing ring 5 is connected with buffer board 16 through second spring 15, the left side swing joint of second guide rail 6 has fourth guide rail 22, and be connected with first spring 10 between second guide rail 6 and the fourth guide rail 22, handle 7 has been installed at the outside middle part of second guide rail 6, the bottom of second guide rail 6 is connected with third slider 8, and the bottom of third slider 8 is provided with third guide rail 9, hinge 21 is installed at the top of movable block 4, and movable block 4 is connected with through hinge 21 and blocks hook 17, the outside both sides welding of movable block 4 has nut 19, and the inside swing joint of nut 19 has locking screw 18, pulley 20 has been installed to the bottom of movable block 4.
As shown in fig. 1 and 3, a moving structure is formed between the movable block 4 and the first guide rail 1 through a pulley 20, and the thickness of the pulley 20 is smaller than the width of the groove 3, the moving structure ensures that the pulley 20 can drive the movable block 4 to move left and right on the first guide rail 1, and the thickness of the pulley 20 is smaller than the width of the groove 3, so that the pulley 20 can move freely inside the groove 3.
As shown in fig. 1, the stop collar 5 and the second slide 14 of this embodiment form a rotating structure through a bearing 11 and a connecting rod 12, and the second slide 14 and the second guide rail 6 are connected in a sliding manner, the rotating structure ensures that the stop collar 5 can rotate around the bearing 11, so as to adjust the angle of the stop collar 5, and can fix stakes at different positions and angles, the sliding connection ensures that the second slide 14 can freely move up and down outside the second guide rail 6, so as to straighten the stakes according to the length of the stakes, the second guide rail 6 and the third guide rail 9 form a moving structure through a third slide 8, the second guide rail 6 and the fourth guide rail 22 form an elastic structure through a first spring 10, the moving structure ensures that the second guide rail 6 can move left and right under the driving of the third slide 8, so as to adjust the distance between the second guide rail 6 and the fourth guide rail 22, can adjust according to the distance between the guardrail stand, and then can be under construction simultaneously to adjacent two stands, help improving the efficiency of construction, the elastic construction guarantees to block the hook 17 and removes the restriction back to second guide rail 6 and fourth guide rail 22, and second guide rail 6 and fourth guide rail 22 can get back to the normal position under the effect of first spring 10 elasticity.
As shown in fig. 2, constitute elastic force structure through second spring 15 between buffer board 16 of this embodiment and the spacing ring 5, and buffer board 16 has two sets ofly about the central symmetric distribution of spacing ring 5, and elastic force structure ensures that buffer board 16 and second spring 15 can cushion the guard action to the stake, ensures that the stake can not take place too big skew, and buffer board 16 has two sets ofly about the central symmetric distribution of spacing ring 5, can follow two directions and right the stake, and it is better to right the effect.
As shown in fig. 3, a rotation structure is formed between the blocking hook 17 and the movable block 4 through a hinge 21, and the diameter of the circle where the blocking hook 17 is located is greater than the width of the first guide rail 1, the rotation structure ensures that the blocking hook 17 can rotate around the hinge 21, the diameter of the circle where the blocking hook 17 is located is greater than the width of the first guide rail 1, the blocking hook 17 is ensured to be capable of sheathing the first guide rail 1, and further the second guide rail 6 and the fourth guide rail 22 can be blocked, and the second guide rail 6 and the fourth guide rail 22 are ensured not to be folded under the elastic force of the first spring 10 in the using process.
For the convenience of understanding the technical solution of the present invention, the following detailed description is made on the working principle or the operation mode of the present invention in the practical process.
The utility model discloses the theory of operation: when the device is used, the first guide rail 1 and the third guide rail 9 are fixed between two adjacent areas needing to be constructed, the handle 7 is pulled outwards according to the distance between the two adjacent areas, the second guide rail 6 and the fourth guide rail 22 can be driven to move back to back, finally the distance between the limiting ring 5 on the outer side of the second guide rail 6 and the limiting ring 5 on the outer side of the fourth guide rail 22 can be adjusted, the movable block 4 is moved to a designated area, the movable block 4 is fixed through the locking screw 18 and the nut 19, the blocking hook 17 is rotated around the hinge 21, the blocking hook 17 can sleeve the first guide rail 1, the second guide rail 6 and the fourth guide rail 22 can be blocked, the second guide rail 6 and the fourth guide rail 22 are ensured not to be folded under the action of the elastic force of the first spring 10 in the use process, the limiting ring 5 is aligned right above the area needing to be constructed, and a wood pile is placed in the limiting ring 5, hammer of pile driver hammering timber downwards, because the buffering of second spring 15 and buffer board 16, can ensure that the timber can not take place serious slope at the decline in-process, get into inside the soil back when the timber, the second slider 14 moves down, second slider 14 passes through connecting rod 12 and drives spacing ring 5 and move down, and then can ensure the timber when moving down, can be in the state of rightting always, rotate spacing ring 5 round bearing 11, and then can adjust the angle of spacing ring 5, can fix the timber of different position angles.
The above is the preferred embodiment of the present invention, and the technical personnel in the field of the present invention can also change and modify the above embodiment, therefore, the present invention is not limited to the above specific embodiment, and any obvious improvement, replacement or modification made by the technical personnel in the field on the basis of the present invention all belong to the protection scope of the present invention.

Claims (6)

1. The utility model provides a fill out construction of stone road bed guardrail stand and use pile driver auxiliary device, includes first guide rail (1), its characterized in that: the top of the first guide rail (1) is provided with a groove (3), a movable block (4) is movably connected above the groove (3), the bottom of the first guide rail (1) is movably connected with a first sliding block (2), the bottom of the first sliding block (2) is connected with a second guide rail (6), the outer part of the second guide rail (6) is movably connected with a second sliding block (14), the outer side of the second sliding block (14) is welded with a connecting frame (13), the inner part of the connecting frame (13) is movably connected with a bearing (11), the outer part of the bearing (11) is welded with a connecting rod (12), the tail end of the connecting rod (12) is connected with a limit ring (5), the inner side of the limit ring (5) is connected with a second spring (15), the limit ring (5) is connected with a buffer plate (16) through the second spring (15), the left side of the second guide rail (6) is movably connected with a fourth guide rail (22), and be connected with first spring (10) between second guide rail (6) and fourth guide rail (22), handle (7) have been installed at the outside middle part of second guide rail (6), the bottom of second guide rail (6) is connected with third slider (8), and the bottom of third slider (8) is provided with third guide rail (9), hinge (21) are installed at the top of movable block (4), and movable block (4) are connected with through hinge (21) and block hook (17), the outside both sides welding of movable block (4) has nut (19), and the inside swing joint of nut (19) has locking screw (18), pulley (20) have been installed to the bottom of movable block (4).
2. The pile driver assisting device for the construction of the pillar of the rockfill subgrade guardrail as claimed in claim 1, wherein: a moving structure is formed between the movable block (4) and the first guide rail (1) through a pulley (20), and the thickness of the pulley (20) is smaller than the width of the groove (3).
3. The pile driver assisting device for the construction of the pillar of the rockfill subgrade guardrail as claimed in claim 1, wherein: the limiting ring (5) and the second sliding block (14) form a rotating structure through a bearing (11) and a connecting rod (12), and the second sliding block (14) is in sliding connection with the second guide rail (6).
4. The pile driver assisting device for the construction of the pillar of the rockfill subgrade guardrail as claimed in claim 1, wherein: a moving structure is formed between the second guide rail (6) and the third guide rail (9) through a third sliding block (8), and an elastic structure is formed between the second guide rail (6) and the fourth guide rail (22) through a first spring (10).
5. The pile driver assisting device for the construction of the pillar of the rockfill subgrade guardrail as claimed in claim 1, wherein: an elastic structure is formed between the buffer plate (16) and the limiting ring (5) through a second spring (15), and two groups of buffer plates (16) are symmetrically distributed around the center of the limiting ring (5).
6. The pile driver assisting device for the construction of the pillar of the rockfill subgrade guardrail as claimed in claim 1, wherein: the blocking hook (17) and the movable block (4) form a rotating structure through a hinge (21), and the diameter of the circle where the blocking hook (17) is located is larger than the width of the first guide rail (1).
CN202120446995.XU 2021-03-02 2021-03-02 Fill out construction of stone road bed guardrail stand and use pile driver auxiliary device Expired - Fee Related CN214530655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120446995.XU CN214530655U (en) 2021-03-02 2021-03-02 Fill out construction of stone road bed guardrail stand and use pile driver auxiliary device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120446995.XU CN214530655U (en) 2021-03-02 2021-03-02 Fill out construction of stone road bed guardrail stand and use pile driver auxiliary device

Publications (1)

Publication Number Publication Date
CN214530655U true CN214530655U (en) 2021-10-29

Family

ID=78259544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120446995.XU Expired - Fee Related CN214530655U (en) 2021-03-02 2021-03-02 Fill out construction of stone road bed guardrail stand and use pile driver auxiliary device

Country Status (1)

Country Link
CN (1) CN214530655U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113996045A (en) * 2021-11-18 2022-02-01 南京林业大学 Device and method for installation, construction and treatment of facilities in community exercise field

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113996045A (en) * 2021-11-18 2022-02-01 南京林业大学 Device and method for installation, construction and treatment of facilities in community exercise field

Similar Documents

Publication Publication Date Title
CN214530655U (en) Fill out construction of stone road bed guardrail stand and use pile driver auxiliary device
CN111608166A (en) Highway is back of culvert backfill tamping plant for bridge
CN112302693A (en) Subway tunnel antidetonation support column
CN215055070U (en) Highway electromechanical construction safety device
CN109610431B (en) Rammer for straight road section of low-grade highway
CN110617013A (en) Fixing support capable of adjusting direction of rock drill and rock drill assembly
CN217923623U (en) Inner supporting structure of foundation pit
CN215562590U (en) Constructional engineering pile device
CN214577062U (en) Adjustable tunnel supporting device
CN211115804U (en) Fixing support capable of adjusting direction of rock drill and rock drill assembly
CN208717696U (en) A kind of railroad track confining bed concrete screed
CN216043735U (en) Combined tunnel engineering excavation construction rack
CN216766966U (en) Civil engineering is with stake strutting arrangement of being convenient for adjust size
CN214110305U (en) Positioning device for main steel tower segment of cable-stayed bridge
CN212743874U (en) Crawler drill and supporting leg moving device thereof
CN214835105U (en) Movable mechanical protection shed
CN215870517U (en) Mountain region high-voltage cable overlap joint crossing structure
CN220248128U (en) Supporting mechanism based on tunnel construction
CN107761583A (en) A kind of adjustable box culvert internal model branch tears system open
CN221031879U (en) Foundation pit safety protection device
CN216588040U (en) Rail device that public area fitment of subway used
CN219909868U (en) Adjustable scaffold for water conservancy construction
WO2013149488A1 (en) Plate insertion working apparatus for plate inserting machine
CN219431855U (en) Combined jumbolter
CN219366055U (en) Multi-working-condition combined tunnel construction operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211029

CF01 Termination of patent right due to non-payment of annual fee