CN214498016U - Green energy-saving building curtain wall - Google Patents

Green energy-saving building curtain wall Download PDF

Info

Publication number
CN214498016U
CN214498016U CN202120203793.2U CN202120203793U CN214498016U CN 214498016 U CN214498016 U CN 214498016U CN 202120203793 U CN202120203793 U CN 202120203793U CN 214498016 U CN214498016 U CN 214498016U
Authority
CN
China
Prior art keywords
cross
support
green energy
caulking groove
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120203793.2U
Other languages
Chinese (zh)
Inventor
詹仲恭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhuhui Curtain Wall Co ltd
Original Assignee
Zhejiang Zhuhui Curtain Wall Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zhuhui Curtain Wall Co ltd filed Critical Zhejiang Zhuhui Curtain Wall Co ltd
Priority to CN202120203793.2U priority Critical patent/CN214498016U/en
Application granted granted Critical
Publication of CN214498016U publication Critical patent/CN214498016U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a green energy-conserving building curtain, including the basic unit wall body and be fixed in the fossil fragments support on the basic unit wall body, be provided with the cross support on the fossil fragments support, detachably installs the curtain board on the cross support, has seted up the cross caulking groove on the cross support, sets up the cross abaculus that is used for embedding the inside of cross caulking groove on the curtain board back, and the cross abaculus adopts rubber materials to make, is provided with a plurality of lock pieces on the cross support, the lock piece include threaded connection in the cross caulking groove the screw rod and with screw rod integrated into one piece's inserted bar. The utility model has the advantages that: the utility model discloses joint strength is high, and structural stability is good, and when needs are dismantled, only need upwards revolve twist the screw rod and make the inserted bar extract in proper order from spacing through-hole, spacing jack can to can remove spacing to the cross abaculus, conveniently pull down the curtain board from the cross support, whole dismouting operation is comparatively convenient simple, and construction cost is lower.

Description

Green energy-saving building curtain wall
Technical Field
The utility model relates to a green building technical field specifically is a green energy-saving building curtain.
Background
With the continuous aggravation of the competition of the building curtain wall industry, the co-purchasing integration and capital operation among large building curtain wall enterprises become more and more frequent, and domestic excellent building curtain wall production enterprises pay more and more attention to the research on the industry market, in particular to the deep research on the trend change of the enterprise development environment and the customer demand. The building curtain wall is the outer wall enclosure of the building, does not bear the weight, hangs up like a curtain, so is also called as the hanging wall, is the light wall with decorative effect that modern large-scale and high-rise building commonly used. It is generally composed of a system of panels and supporting structures, which can have a certain displacement capacity or a certain deformation capacity with respect to the main structure.
At present, current building curtain wall comprises curtain wall board (glass, metal sheet, slabstone, ceramic plate etc.) and hou mian bearing structure (aluminium crossbeam stand, steel construction, glass rib etc.) usually, when installing curtain wall board on bearing structure, adopts sticky mode to realize usually, though can guarantee better installation fastness, nevertheless comparatively inconvenient during the dismouting, and construction cost is higher.
SUMMERY OF THE UTILITY MODEL
The utility model discloses an aim at just being in the green energy-conserving building curtain that provides in order to solve foretell problem, the dismouting is comparatively convenient, and construction cost is lower.
The utility model discloses a following technical scheme realizes above-mentioned purpose, a green energy-conserving building curtain, include the basic unit's wall body and be fixed in the fossil fragments support on the basic unit's wall body, be provided with the cross support on the fossil fragments support, detachably installs the curtain board on the cross support, the cross caulking groove has been seted up on the cross support, set up the cross abaculus that is used for embedding cross caulking groove inside on the curtain board back, the cross abaculus adopts rubber materials to make, be provided with a plurality of locking pieces on the cross support, the locking piece include threaded connection at the cross caulking groove the screw rod and with screw rod integrated into one piece's inserted bar, set up a plurality of spacing jacks that are used for the inserted bar to pass on the cross abaculus, set up the spacing through-hole that is used for the inserted bar to wear out on the lateral wall of cross support.
By adopting the technical scheme, the cross-shaped bracket is arranged on the keel bracket, the cross-shaped caulking groove is formed on the cross-shaped bracket, and the cross-shaped caulking block is arranged on the back surface of the curtain wall board, when the curtain wall board is installed on the cross-shaped bracket, the cross-shaped caulking block can be firstly embedded into the cross-shaped caulking groove to realize pre-positioning installation, because the plurality of locking pieces are arranged on the cross-shaped bracket, the screw rods can be screwed inwards to enable the inserted rods to penetrate through the limiting insertion holes and penetrate out from the limiting through holes, so that the cross-shaped caulking block can be limited in the cross-shaped caulking groove, the curtain wall board can be firmly installed on the cross-shaped bracket through the combined action of the plurality of locking pieces, the connection strength is high, the structural stability is good, and when the curtain wall board needs to be disassembled, the inserted rods can be sequentially pulled out from the limiting through holes and the limiting insertion holes only by screwing the screw rods upwards, so that the limitation to the cross-shaped caulking block can be removed, the curtain wall plate is conveniently detached from the cross-shaped support, the whole detaching operation is convenient and simple, and the construction cost is low.
As a further setting of the utility model, it all is provided with the thread bush to correspond spacing through-hole position on the lateral wall of cross support, the one end that the screw rod was kept away from to the inserted bar is provided with the thread head that matches with the thread bush.
Through adopting above-mentioned technical scheme, because it all is provided with the thread bush to correspond spacing through-hole position on the lateral wall of cross support, and the one end of keeping away from the screw rod at the inserted bar is provided with the thread head that matches with the thread bush, then when the inserted bar runs through spacing jack and wears out by spacing through-hole, can drive the thread head and run through spacing jack and wear out by spacing through-hole, then can be inside the thread head screw in thread bush of wearing out, through the threaded connection between thread bush and the thread head, can make the locking piece spacing more firm to the cross abaculus, thereby the fastness of curtain wall board installation has been promoted.
As a further setting of the utility model, the aperture of spacing jack is less than the diameter of jack.
Through adopting above-mentioned technical scheme, because the aperture of spacing jack is less than the diameter of inserted bar, then when the inserted bar inserted spacing jack, spacing jack received the pressure effect and can outwards expand, makes things convenient for the inserted bar to insert smoothly, and after the inserted bar inserts completely, spacing jack breaks away from the pressure constraint and can contracts and stick to tightly with the inserted bar to make the connection between inserted bar and the cross abaculus more closely firm.
As a further setting of the utility model, be provided with a plurality of location plugs on the interior diapire of cross caulking groove, a plurality of location jacks that are used for location plug male have been seted up in the one side that the cross abaculus deviates from the curtain board.
Through adopting above-mentioned technical scheme, owing to be provided with a plurality of location plugs on the interior diapire of cross caulking groove, and seted up a plurality of location jacks in the one side that the cross abaculus deviates from the curtain board, then with the inside back of cross abaculus embedding cross caulking groove, can insert the location jack inside with the location plug simultaneously, then spacing through location jack to location plug can prevent that the cross abaculus from droing from the cross caulking groove is inside, has guaranteed prepositioned fastness before the curtain board installation.
As a further setting of the utility model, the location plug including fix on the interior diapire of cross caulking groove the cutting and with cutting integrated into one piece's spacing lug, the location jack is including being used for cutting male slot and being used for the spacing draw-in groove of spacing lug embedding.
Through adopting above-mentioned technical scheme, because the location plug is including cutting and spacing lug, the location jack is including slot and spacing draw-in groove, then when the location plug inserts the location jack inside, spacing lug can insert the slot in proper order, inside spacing draw-in groove and the embedding spacing draw-in groove, make the cutting insert the slot inside thereupon, it is spacing to the block of spacing lug through spacing draw-in groove, can prevent that spacing lug from deviating from easily, thereby realize the lock of dismantling between location plug and the location jack, the operation is comparatively convenient simple.
As a further setting of the utility model, the longitudinal section of spacing lug and spacing draw-in groove is the arc.
Through adopting above-mentioned technical scheme, because the longitudinal section of spacing lug and spacing draw-in groove is the arc, then comparatively light smooth and easy when spacing lug inserts slot, spacing draw-in groove in proper order and imbeds spacing draw-in groove inside, hinder lessly.
As a further setting of the utility model, the screw rod top all is provided with grips the knob.
By adopting the technical scheme, the holding knobs are arranged at the tops of the screws, so that the screwing operation of the screws can be realized by holding and rotating the holding knobs, the holding knobs provide force application points for the operation of screwing the screws, and the operation of screwing the screws is easier and more labor-saving.
As a further arrangement of the utility model, the keel bracket and the cross bracket are made of galvanized steel.
By adopting the technical scheme, because the keel support and the cross support are both made of galvanized steel, the strength and hardness are higher, and the keel support and the cross support are not easy to rust, so that the bearing capacity and the anti-deformation capacity of the keel support and the cross support are effectively ensured, and the keel support and the cross support have longer service lives.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses when installing the curtain board on the cross support, can earlier realize the prepositioning installation with cross abaculus embedding cross caulking groove is inside, owing to be provided with a plurality of lock pieces on the cross support, then can inwards revolve wrong screw rod and make the inserted bar run through spacing jack and wear out by spacing through-hole, thereby can inject the cross abaculus inside the cross caulking groove, then through a plurality of lock piece combined action, can realize the firm installation of curtain board on the cross support, joint strength is high, structural stability is good, and when needs are dismantled, only need upwards revolve wrong screw rod and make the inserted bar follow spacing through-hole in proper order, extract in the spacing jack can, thereby can relieve spacing to the cross abaculus, the convenience is pulled down the curtain board from the cross support, whole dismouting operation is comparatively convenient simple, construction cost is lower.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a partial cross-sectional view of the present invention;
FIG. 3 is an enlarged schematic view of the structure at A in FIG. 2;
fig. 4 is a schematic structural view of the middle keel bracket and the cross bracket of the present invention;
FIG. 5 is a schematic structural view of the curtain wall plate and the cross-shaped insert of the present invention;
fig. 6 is a schematic structural view of the locking member of the present invention.
Reference numerals: 1. a base layer wall body; 2. a keel support; 3. a cross-shaped bracket; 4. a curtain wall plate; 5. a cross caulking groove; 6. a cross-shaped insert block; 7. a locking member; 71. a screw; 72. inserting a rod; 73. a screw head; 8. limiting the jacks; 9. a limiting through hole; 10. a threaded sleeve; 11. positioning the plug; 111. cutting; 112. a limiting bump; 12. positioning the jack; 121. a slot; 122. a limiting clamping groove; 13. and (4) holding the knob.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, a green energy-saving building curtain wall comprises a base wall 1 and a keel support 2 fixed on the base wall 1, wherein the keel support 2 is provided with a cross support 3, the keel support 2 and the cross support 3 are both made of galvanized steel, a curtain wall plate 4 is detachably mounted on the cross support 3, the cross support 3 is provided with a cross caulking groove 5, a cross insert 6 for being embedded into the cross caulking groove 5 is arranged on the back surface of the curtain wall plate 4, the cross insert 6 is made of rubber material, a plurality of positioning plugs 11 are arranged on the inner bottom wall of the cross caulking groove 5, a plurality of positioning insertion holes 12 for inserting the positioning plugs 11 are arranged on the surface of the cross insert 6 departing from the curtain wall plate 4, the positioning plugs 11 comprise insertion strips 111 fixed on the inner bottom wall of the cross caulking groove 5 and limiting convex blocks 112 integrally formed with the insertion strips 111, the positioning insertion hole 12 comprises a slot 121 used for inserting the insert 111 and a limiting clamping groove 122 used for embedding the limiting lug 112, the longitudinal sections of the limiting lug 112 and the limiting clamping groove 122 are arc-shaped, a plurality of locking pieces 7 are arranged on the cross support 3, each locking piece 7 comprises a screw 71 and an insertion rod 72, the screw 71 and the insertion rod 72 are connected into the cross insertion groove 5 in a threaded mode, the insertion rods 71 are integrally formed, the top of each screw 71 is provided with a holding knob 13, a plurality of limiting insertion holes 8 used for allowing the insertion rods 72 to pass through are formed in the cross insertion block 6, the hole diameter of each limiting insertion hole 8 is smaller than the diameter of each insertion rod 72, a limiting through hole 9 used for allowing the insertion rod 72 to penetrate out is formed in the outer side wall of the cross support 3, a threaded sleeve 10 is arranged on the outer side wall of the cross support 3 corresponding to the position of each limiting through hole 9, and a threaded head 73 matched with the threaded sleeve 10 is arranged at one end, far away from the screw 71, of each insertion rod 72.
Because the cross-shaped support 3 is arranged on the keel support 2, the cross-shaped caulking grooves 5 are arranged on the cross-shaped support 3, and the cross-shaped embedding blocks 6 are arranged on the back surface of the curtain wall board 4, when the curtain wall board 4 is installed on the cross-shaped support 3, the cross-shaped embedding blocks 6 can be firstly embedded into the cross-shaped caulking grooves 5 to realize pre-positioning installation, because a plurality of locking pieces 7 are arranged on the cross-shaped support 3, the screw rods 71 can be screwed inwards to enable the inserting rods 72 to penetrate through the limiting insertion holes 8 and penetrate out from the limiting through holes 9, so that the cross-shaped embedding blocks 6 can be limited in the cross-shaped caulking grooves 5, the curtain wall board 4 can be firmly installed on the cross-shaped support 3 under the combined action of the locking pieces 7, the connection strength is high, the structural stability is good, and when the curtain wall board needs to be disassembled, the inserting rods 72 can be sequentially extracted from the limiting through holes 9 and the limiting insertion holes 8 only by screwing the screw rods 71 upwards, thereby can remove spacing to cross abaculus 6, conveniently pull down curtain board 4 from cross support 3, whole dismouting operation is comparatively convenient simple, and construction cost is lower.
Because the position corresponding to the limit through hole 9 on the outer side wall of the cross support 3 is provided with the thread bush 10, and the end far away from the screw rod 71 at the inserted rod 72 is provided with the thread head 73 matched with the thread bush 10, when the inserted rod 72 runs through the limit jack 8 and is worn out by the limit through hole 9, the thread head 73 can be driven to run through the limit jack 8 and be worn out by the limit through hole 9, the thread head 73 which is worn out can be screwed into the thread bush 10, through the threaded connection between the thread bush 10 and the thread head 73, the limit of the locking piece 7 to the cross insert 6 can be firmer, and therefore the firmness of installation of the curtain wall board 4 is improved.
Because the aperture of spacing jack 8 is less than the diameter of inserted bar 72, then when inserted bar 72 inserted spacing jack 8, spacing jack 8 received the pressure effect and can outwards expand, makes things convenient for inserted bar 72 to insert smoothly, and after inserted bar 72 inserted completely, spacing jack 8 got rid of the pressure constraint and can contract and closely paste with inserted bar 72 to make the connection between inserted bar 72 and the cross abaculus 6 inseparabler firm.
Because the plurality of positioning plugs 11 are arranged on the inner bottom wall of the cross caulking groove 5 and the plurality of positioning jacks 12 are arranged on the surface of the cross slug 6, which is far away from the curtain wall board 4, the positioning plugs 11 can be simultaneously inserted into the positioning jacks 12 after the cross slug 6 is embedded into the cross caulking groove 5, the positioning plugs 11 are limited by the positioning jacks 12, the cross slug 6 can be prevented from falling off from the inside of the cross caulking groove 5, the pre-positioning firmness before the installation of the curtain wall board 4 is ensured, and because the positioning plugs 11 comprise the inserting strips 111 and the limiting lugs 112, the positioning jacks 12 comprise the inserting grooves 121 and the limiting clamping grooves 122, when the positioning plugs 11 are inserted into the positioning jacks 12, the limiting lugs 112 can be sequentially inserted into the inserting grooves 121 and the limiting clamping grooves 122 and are embedded into the limiting clamping grooves 122, so that the inserting strips 111 are inserted into the inserting grooves 121 and are clamped and limited by the limiting clamping grooves 122, can prevent that spacing lug 112 from deviating from easily to realize the lock of dismantling between location plug 11 and the location jack 12, the operation is comparatively convenient simple, because the longitudinal section of spacing lug 112 and spacing draw-in groove 122 is the arc, then comparatively easily smooth and easy when spacing lug 112 inserts slot 121, spacing draw-in groove 122 in proper order and imbeds spacing draw-in groove 122 inside, hinders lessly.
Since the holding knobs 13 are arranged on the tops of the screws 71, the screw 71 can be screwed by holding and rotating the holding knobs 13, and the holding knobs 13 provide force applying points for the operation of screwing the screws 71, so that the operation of screwing the screws 71 is easier and more labor-saving.
Because the keel bracket 2 and the cross bracket 3 are both made of galvanized steel, the strength and the hardness are higher, and the keel bracket 2 and the cross bracket 3 are not easy to rust, thereby effectively ensuring the bearing capacity and the anti-deformation capacity of the keel bracket 2 and the cross bracket 3, and ensuring that the keel bracket 2 and the cross bracket 3 have longer service lives.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (8)

1. The utility model provides a green energy-conserving building curtain, includes basic unit's wall body (1) and is fixed in fossil fragments support (2) on basic unit's wall body (1), its characterized in that: be provided with cross support (3) on fossil fragments support (2), detachably installs curtain board (4) on cross support (3), cross caulking groove (5) have been seted up on cross support (3), set up on curtain board (4) the back and be used for embedding inside cross abaculus (6) of cross caulking groove (5), cross abaculus (6) adopt rubber materials to make, be provided with a plurality of locking pieces (7) on cross support (3), locking piece (7) including threaded connection screw rod (71) in cross caulking groove (5) and with screw rod (71) integrated into one piece's inserted bar (72), set up a plurality of spacing jacks (8) that are used for inserted bar (72) to pass on cross abaculus (6), set up spacing through-hole (9) that are used for inserted bar (72) to wear out on the lateral wall of cross support (3).
2. The green energy-saving building curtain wall as claimed in claim 1, wherein: the outer side wall of the cross support (3) is provided with a threaded sleeve (10) corresponding to the position of the limiting through hole (9), and one end, away from the screw rod (71), of the inserted rod (72) is provided with a threaded head (73) matched with the threaded sleeve (10).
3. The green energy-saving building curtain wall as claimed in claim 1, wherein: the aperture of the limiting insertion hole (8) is smaller than the diameter of the insertion rod (72).
4. The green energy-saving building curtain wall as claimed in claim 1, wherein: be provided with a plurality of location plug (11) on the interior diapire of cross caulking groove (5), a plurality of location jack (12) that are used for location plug (11) male have been seted up on the one side that deviates from curtain board (4) in cross abaculus (6).
5. The green energy-saving building curtain wall as claimed in claim 4, wherein: the positioning plug (11) comprises a plug strip (111) fixed on the inner bottom wall of the cross caulking groove (5) and a limiting convex block (112) integrally formed with the plug strip (111), and the positioning insertion hole (12) comprises a slot (121) used for inserting the plug strip (111) and a limiting clamping groove (122) used for embedding the limiting convex block (112).
6. The green energy-saving building curtain wall as claimed in claim 5, wherein: the longitudinal sections of the limiting convex blocks (112) and the limiting clamping grooves (122) are arc-shaped.
7. The green energy-saving building curtain wall as claimed in claim 1, wherein: the top of each screw rod (71) is provided with a holding knob (13).
8. The green energy-saving building curtain wall as claimed in claim 1, wherein: the keel support (2) and the cross-shaped support (3) are both made of galvanized steel.
CN202120203793.2U 2021-01-25 2021-01-25 Green energy-saving building curtain wall Active CN214498016U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120203793.2U CN214498016U (en) 2021-01-25 2021-01-25 Green energy-saving building curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120203793.2U CN214498016U (en) 2021-01-25 2021-01-25 Green energy-saving building curtain wall

Publications (1)

Publication Number Publication Date
CN214498016U true CN214498016U (en) 2021-10-26

Family

ID=78216724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120203793.2U Active CN214498016U (en) 2021-01-25 2021-01-25 Green energy-saving building curtain wall

Country Status (1)

Country Link
CN (1) CN214498016U (en)

Similar Documents

Publication Publication Date Title
CN210530047U (en) Ultra-thin stone material aluminium honeycomb composite sheet
CN212248815U (en) Quick connection structure is used in installation of building curtain
CN214498016U (en) Green energy-saving building curtain wall
CN108708493B (en) Integral hanging type grating
CN111236476A (en) Edge member of steel reinforced concrete shear wall and construction method
CN214617330U (en) Furniture installation fixing seat
CN214531392U (en) Building decoration curtain wall
CN213297056U (en) Scaffold for mounting wall plates
CN114319771B (en) Copper relief point hanging structure for waterscape wall surface
CN211421533U (en) Building curtain wall mounting structure convenient to adjust
CN212478205U (en) Brick decoration curtain wall installation component
CN213626734U (en) Leveling device convenient to mount and dismount for building construction
CN214272763U (en) Energy-saving dry-hanging structure for outer wall stone
CN210002609U (en) decorative wall structure for building decoration
CN217610475U (en) Novel curtain suspension clamp
CN220550734U (en) Building curtain mount
CN217079404U (en) Convenient to detach's jointing equipment is used in reinforcing bar installation
CN215701638U (en) Side marking tool convenient to operate
CN217352956U (en) Floor preformed hole hangs mould shutoff instrument
CN216552596U (en) Novel building curtain wall
CN214884793U (en) Keel hanging piece with anti-falling structure for architectural decoration
CN220421527U (en) Motor slot wedge for compressor and motor
CN213626201U (en) Assembled installing support of curtain construction
CN218845099U (en) Metal seal convenient to installation is fixed
CN213805884U (en) Strengthening rib structure for building engineering construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant