CN214456324U - Material conveying and lifting equipment for bridge construction of bridge engineering - Google Patents
Material conveying and lifting equipment for bridge construction of bridge engineering Download PDFInfo
- Publication number
- CN214456324U CN214456324U CN202120181376.2U CN202120181376U CN214456324U CN 214456324 U CN214456324 U CN 214456324U CN 202120181376 U CN202120181376 U CN 202120181376U CN 214456324 U CN214456324 U CN 214456324U
- Authority
- CN
- China
- Prior art keywords
- portal frame
- bridge
- intelligence
- bridge construction
- material conveying
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 37
- 239000000463 material Substances 0.000 title claims abstract description 23
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 11
- 239000010959 steel Substances 0.000 claims abstract description 11
- 238000004804 winding Methods 0.000 claims description 9
- 230000005540 biological transmission Effects 0.000 claims description 6
- 238000003466 welding Methods 0.000 claims description 6
- 239000004035 construction material Substances 0.000 claims description 4
- 238000009434 installation Methods 0.000 abstract 1
- 230000005389 magnetism Effects 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 230000032258 transport Effects 0.000 description 2
- FGRBYDKOBBBPOI-UHFFFAOYSA-N 10,10-dioxo-2-[4-(N-phenylanilino)phenyl]thioxanthen-9-one Chemical compound O=C1c2ccccc2S(=O)(=O)c2ccc(cc12)-c1ccc(cc1)N(c1ccccc1)c1ccccc1 FGRBYDKOBBBPOI-UHFFFAOYSA-N 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 210000001503 joint Anatomy 0.000 description 1
- 238000012806 monitoring device Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
Images
Abstract
The utility model discloses a material conveying and lifting device for bridge construction in bridge engineering, belonging to the technical field of construction machinery, comprising a bridge body, a first portal frame and a second portal frame, one side of the bridge body is provided with the first portal frame in a spanning mode, the other side of the bridge body is provided with the second portal frame in a spanning mode, guide wheels are rotatably connected inside the first portal frame and the second portal frame, steel wire ropes are slidably connected on the guide wheels, one end of the steel wire rope is hinged with a furling component, the utility model arranges a movable portal frame I and a portal frame II on two sides of the bridge body, the first portal frame and the second portal frame are provided with a vertical hoisting structure and a transverse moving structure, so that the function of flexibly hoisting materials at the bridge construction position by the hoisting device is met, and the occupied position is smaller, the movement is convenient, and the problem of inconvenient installation and use of the traditional large-scale hoisting equipment is solved.
Description
Technical Field
The utility model relates to a bridge construction equipment especially relates to a material transports jacking equipment for bridge construction of bridge engineering, belongs to construction machinery technical field.
Background
The bridge construction refers to a process of building a bridge according to design contents, mainly refers to contents of bridge construction technology, construction organization, construction management, construction quality and the like, and bridge construction machines are engineering machines used for bridge construction, most of the bridge construction machines are general, a few of the bridge construction machines are developed into special machines in adaptation to bridge construction characteristics, and the others are between the bridge construction machines, namely vibration pile drivers, also called vibration pile sinking machines.
Most of lifting devices of existing bridge construction equipment are cranes with large sizes, and need to be matched with multiple sets of equipment for use, so that the lifting devices occupy the construction site and are not beneficial to flexible operation of the construction site.
Disclosure of Invention
The utility model mainly aims at providing a lifting means is transported to bridge construction material of bridge engineering.
The purpose of the utility model can be achieved by adopting the following technical scheme:
the utility model provides a lifting means is transported to bridge construction material of bridge engineering, includes pontic, portal frame one and portal frame two, span on one side of the pontic has portal frame one, span on the other side of the pontic has portal frame two, portal frame one with two inside equal rotations of portal frame are connected with the guide pulley, sliding connection has wire rope on the guide pulley, wire rope one end articulates there is the roll-up subassembly.
Preferably, the furling assembly comprises a winding drum and a winding motor, the other end of the steel wire rope is tied with a first lifting hook, and a first intelligent buckle is installed at the bottom of the first lifting hook in a matched mode.
Preferably, inside sliding connection has the bolt is detained to first intelligence, bolt one end welding has electric putter, first lifting hook is just right the jack has been seted up on a lateral wall of bolt.
Preferably, the top is detained to first intelligence is fixed with the magnetism post through the draw-in groove, the welding of bottom end middle part has the magnetism cap in the first lifting hook, the magnetism cap with the magnetism post is through magnetic force anastomotic connection.
Preferably, the bottom is detained to first intelligence has the thing frame of carrying through the bolt fastening, it is located to carry thing frame top first intelligence is detained both sides and is detained through the bolt fastening has the second intelligence, the second intelligence detain with the structure that first intelligence was detained is the same, the second intelligence is detained and is had two sets ofly.
Preferably, a first portal frame and a second portal frame are fixed with traversing motors through bolts, and kinetic energy output ends of the traversing motors are connected with transmission bars through keys.
Preferably, sliding connection has the electric hoist on the transmission bar, the electric hoist bottom is connected with the jib through the couple, jib bottom both sides have the second lifting hook through the bolt fastening, the second lifting hook with the structure of first lifting hook is the same.
Preferably, the moving bases are installed at the bottoms of the first portal frame and the second portal frame.
The utility model has the advantages of:
the utility model provides a pair of material transports jacking equipment for bridge construction of bridge engineering, through set up mobilizable portal frame one and portal frame two in the pontic both sides, set up perpendicular lift structure and lateral shifting structure on portal frame one and portal frame two, satisfy the function of lifting the device at the nimble handling material of bridge construction position, occupy the position less moreover, it is convenient to remove, has solved traditional large-scale lifting equipment fixing and awkward problem.
Drawings
Fig. 1 is a schematic structural view of a preferred embodiment of a material conveying and lifting device for bridge construction in bridge construction according to the present invention;
fig. 2 is a schematic diagram showing the position relationship of the first intelligent buckle, the second intelligent buckle, the first hook and the material carrying frame in the preferred embodiment of the material transporting and lifting device for bridge construction of bridge engineering according to the present invention;
fig. 3 is a right side view of a boom in a preferred embodiment of a material handling and lifting apparatus for bridge construction in a bridge construction according to the present invention;
fig. 4 is a schematic view of the internal structure of the first hook and the first intelligent buckle in the preferred embodiment of the material for bridge construction transportation lifting device in bridge engineering according to the present invention.
In the figure: 1-a first portal frame, 2-a second portal frame, 3-a moving wheel, 4-a furling assembly, 5-a steel wire rope, 6-a guide wheel, 7-a carrying frame, 8-a first intelligent buckle, 9-a bolt, 10-a magnetic column, 11-a second intelligent buckle, 13-a first lifting hook, 14-a magnetic cap, 15-an electric push rod, 16-a hanging rod, 17-a transverse moving motor, 18-a transmission rod, 19-an electric hoist, 20-a wireless electric cabinet, 21-a bridge body and 22-a second lifting hook.
Detailed Description
In order to make the technical solutions of the present invention clearer and clearer for those skilled in the art, the present invention will be described in further detail with reference to the following embodiments and the accompanying drawings, but the embodiments of the present invention are not limited thereto.
As shown in fig. 1-4, the lifting device for transporting materials for bridge construction of bridge engineering provided by this embodiment includes a bridge body 21, a first portal frame 1 and a second portal frame 2, the first portal frame 1 spans on one side of the bridge body 21, the second portal frame 2 spans on the other side of the bridge body 21, guide wheels 6 are rotatably connected inside the first portal frame 1 and the second portal frame 2, steel wire ropes 5 are slidably connected to the guide wheels 6, a furling assembly 4 is hinged to one end of each steel wire rope 5, the furling assembly 4 is used as a conventional lifting device, and materials are vertically lifted along one side walls of the first portal frame 1 and the second portal frame 2 through the steel wire ropes 5.
The winding assembly 4 comprises a winding drum and a winding motor, the other end of the steel wire rope 5 is tied with a first lifting hook 13, and a first intelligent buckle 8 is installed at the bottom of the first lifting hook 13 in a matched mode.
8 inside sliding connection have bolt 9 are detained to first intelligence, and the welding of 9 one ends of bolt has electric putter 15, and first lifting hook 13 is just having seted up the jack on 9 lateral walls of bolt, and bolt 9 is pushed the jack by electric putter 15 control in, realizes that first lifting hook 13 and first intelligence are detained being connected of 8.
8 tops are detained to first intelligence is fixed with magnetic pillar 10 through the draw-in groove, and the welding of bottom end middle part has magnetic cap 14 in first lifting hook 13, and magnetic cap 14 passes through magnetic force with magnetic pillar 10 and coincide to be connected, and magnetic pillar 10 is inhaled in magnetic cap 14 by the effect of magnetic force, and then can make first lifting hook 13 detain 8 with first intelligence and can accurate butt joint, prevents that bolt 9 and jack can not dock successfully.
8 bottoms are detained to first intelligence and are had thing frame 7 through the bolt fastening, carry thing frame 7 top to be located first intelligence and detain 8 both sides and have second intelligence to detain 11 through the bolt fastening, and second intelligence is detained 11 and is detained 8 the same with first intelligence structure, and second intelligence is detained 11 and has two sets ofly.
And the transverse moving motor 17 is fixed on one side wall of the outer parts of the first portal frame 1 and the second portal frame 2 through bolts, and the kinetic energy output end of the transverse moving motor 17 is connected with a transmission lever 18 through a key.
The transmission bar 18 is connected with an electric hoist 19 in a sliding mode, the bottom of the electric hoist 19 is connected with a hanging rod 16 through a hook, two sides of the bottom of the hanging rod 16 are fixedly provided with a second lifting hook 22 through bolts, the second lifting hook 22 is identical to the first lifting hook 13 in structure, and the electric hoist 19 is used for descending the carrying frame 7 on the surface of the bridge body 21.
And the bottoms of the first portal frame 1 and the second portal frame 2 are respectively provided with a movable base 3.
As shown in fig. 1 to 4, the working process of the lifting device for transporting bridge construction material in bridge engineering provided by this embodiment is as follows:
step 1: this device uses outside wireless control handle to operate, wireless control handle and the equipment work on the wireless control box 20 cooperation controlling means, carry thing frame 7 and load the material after, first lifting hook 13 has artifical card to go into on first intelligence is detained 8, magnetic column 10 inhales in the magnetic cap 14, the jack corresponds bolt 9 this moment, electric putter 15 pushes away bolt 9 in the jack, accomplish first lifting hook 13 and the equipment that 8 was detained to first intelligence, then can be through roll-up subassembly 4, guide pulley 6 and wire rope 5's effect will carry thing frame 7 and promote portal frame 1 and the suitable position department in top of portal frame two 2.
Step 2: carry thing frame 7 and promote to highest position department after, electric hoist 19 carries jib 16 to move to carrying thing frame 7 top, according to the video monitoring device on the electric hoist 19, the user detains 11 docks with the second intelligence with the second lifting hook 22 of jib 16 bottom, and magnetic column 10 is gone into in magnetic cap 14 because the effect of suction is automatic, and jack and bolt 9 are accurate to it this moment, and electric putter 15 is in pushing into the jack with bolt 9, accomplishes the equipment that 11 was detained with the second intelligence to second lifting hook 22.
And step 3: at this moment, the first lifting hook 13 and the first intelligent buckle 8 can be disconnected, the transverse moving motor 17 moves the electric hoist 19 and the carried object carrying frame 7 to a proper position on the surface of the bridge body 21 through the lead screw, the object carrying frame 7 is placed under the electric hoist 19, and meanwhile, the first portal frame 1 and the second portal frame 2 can be moved along the bridge body 21 through the moving base 3 to finish lifting of materials at different positions.
The above description is only a further embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, and any person skilled in the art can replace or change the technical solution and the concept of the present invention within the scope of the present invention.
Claims (8)
1. The utility model provides a lifting means is transported to bridge construction material of bridge engineering, includes pontic (21), portal frame one (1) and portal frame two (2), its characterized in that: one side of the bridge body (21) stretches across the first portal frame (1), the other side of the bridge body (21) stretches across the second portal frame (2), the first portal frame (1) and the second portal frame (2) are internally and uniformly connected with guide wheels (6) in a rotating mode, steel wire ropes (5) are connected onto the guide wheels (6) in a sliding mode, and one end of each steel wire rope (5) is hinged to a winding assembly (4).
2. The material conveying and lifting device for bridge construction of bridge engineering according to claim 1, characterized in that: the winding assembly (4) comprises a winding drum and a winding motor, the other end of the steel wire rope (5) is tied up with a first lifting hook (13), and a first intelligent buckle (8) is installed at the bottom of the first lifting hook (13) in a matched mode.
3. The material conveying and lifting device for bridge construction of bridge engineering according to claim 2, characterized in that: first intelligence is detained (8) inside sliding connection and is had bolt (9), bolt (9) one end welding has electric putter (15), first lifting hook (13) are just right the jack has been seted up on a lateral wall of bolt (9).
4. The material conveying and lifting device for bridge construction of bridge engineering according to claim 3, characterized in that: first intelligence is detained (8) top and is fixed with magnetic column (10) through the draw-in groove, bottom end middle part welding has magnetic cap (14) in first lifting hook (13), magnetic cap (14) with magnetic column (10) coincide through magnetic force and are connected.
5. The material conveying and lifting device for bridge construction of bridge engineering according to claim 4, wherein: first intelligence is detained (8) bottom and is had thing frame (7) of carrying through the bolt fastening, it is located to carry thing frame (7) top first intelligence is detained (8) both sides and is had second intelligence to detain (11) through the bolt fastening, second intelligence detain (11) with the structure that first intelligence was detained (8) is the same, second intelligence is detained (11) and is had two sets ofly.
6. The material conveying and lifting device for bridge construction of bridge engineering according to claim 5, wherein: and the transverse moving motor (17) is fixed on one side wall outside the first portal frame (1) and the second portal frame (2) through bolts, and the kinetic energy output end of the transverse moving motor (17) is connected with a transmission lever (18) through a key.
7. The material conveying and lifting device for bridge construction of bridge engineering according to claim 6, wherein: sliding connection has electric hoist (19) on driving lever (18), electric hoist (19) bottom is connected with jib (16) through the couple, jib (16) bottom both sides have second lifting hook (22) through the bolt fastening, second lifting hook (22) with the structure of first lifting hook (13) is the same.
8. The material conveying and lifting device for bridge construction of bridge engineering according to claim 7, characterized in that: and moving bases (3) are respectively installed at the bottoms of the first portal frame (1) and the second portal frame (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120181376.2U CN214456324U (en) | 2021-01-22 | 2021-01-22 | Material conveying and lifting equipment for bridge construction of bridge engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120181376.2U CN214456324U (en) | 2021-01-22 | 2021-01-22 | Material conveying and lifting equipment for bridge construction of bridge engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214456324U true CN214456324U (en) | 2021-10-22 |
Family
ID=78113281
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120181376.2U Expired - Fee Related CN214456324U (en) | 2021-01-22 | 2021-01-22 | Material conveying and lifting equipment for bridge construction of bridge engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214456324U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116117115A (en) * | 2023-02-03 | 2023-05-16 | 辽宁义圣科技集团有限公司 | Casting riser pouring process based on electromagnetic induction heating technology |
-
2021
- 2021-01-22 CN CN202120181376.2U patent/CN214456324U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116117115A (en) * | 2023-02-03 | 2023-05-16 | 辽宁义圣科技集团有限公司 | Casting riser pouring process based on electromagnetic induction heating technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107235411A (en) | One kind is based on bridge precast beam suspender | |
CN214456324U (en) | Material conveying and lifting equipment for bridge construction of bridge engineering | |
CN201288040Y (en) | Multifunctional swing machine | |
CN205151658U (en) | Practice thrift spatial mode hoisting equipment | |
CN211644394U (en) | Installation device of ditch cable duct cover plate | |
CN203946809U (en) | Light-type boom crane | |
CN206783157U (en) | Overhead explosion-proof crane with rolling screen door cut-off workshop | |
CN206417796U (en) | A kind of construction material conveying device | |
CN212982288U (en) | Tower crane lifting device | |
CN213231283U (en) | Lifting hook for lifting building template | |
CN210558934U (en) | Crane trolley and crane system | |
CN212101637U (en) | Trolley and end beam hoisting device based on crane assembly assembling production line | |
CN218371181U (en) | Four-point-crane moving lifting sling | |
CN206915602U (en) | Electrodynamic movable portal frame | |
CN220502464U (en) | Movable hoisting device | |
CN214935474U (en) | Hoisting device for air conditioner production | |
CN214653083U (en) | Automatic hoisting machine for mining | |
CN111217256A (en) | Novel building installation hoist and mount device | |
CN215797969U (en) | Sediment soil vertical conveying device for pipe jacking construction | |
CN220300216U (en) | Lifting device for transportation | |
CN215101528U (en) | Overhead hoist of dry-type transformer | |
CN217838166U (en) | Template overhead hoist is used in hydraulic engineering construction | |
CN217972338U (en) | Article handling transfer device is used in room construction | |
CN212609244U (en) | Lifting equipment for industrial engineering conveying | |
CN212953984U (en) | Article overhead hoist is used in room construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211022 |
|
CF01 | Termination of patent right due to non-payment of annual fee |