CN214326438U CN202022424050.6U CN202022424050U CN214326438U CN 214326438 U CN214326438 U CN 214326438U CN 202022424050 U CN202022424050 U CN 202022424050U CN 214326438 U CN214326438 U CN 214326438U
Authority
CN
China
Prior art keywords
natural gas
gas pipeline
pipeline
chassis
transmission frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022424050.6U
Other languages
Chinese (zh)
Inventor
杨艳荣
陈东
谢普森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongchuan Thanksgiving Energy Technology Development Co ltd
Original Assignee
Tongchuan Thanksgiving Energy Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongchuan Thanksgiving Energy Technology Development Co ltd filed Critical Tongchuan Thanksgiving Energy Technology Development Co ltd
Priority to CN202022424050.6U priority Critical patent/CN214326438U/en
Application granted granted Critical
Publication of CN214326438U publication Critical patent/CN214326438U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

A natural gas line construction is with pressing from both sides getting settling device includes: the outer wall of the base plate is provided with a pump body and a transmission mechanism, and the transmission mechanism is used for driving the base plate to move on the surface of the natural gas pipeline; the movable ring rod is sleeved on the surface of the natural gas pipeline and welded with the top end of the chassis, and a plurality of movable roller sets are arranged on the inner wall of the movable ring rod; the ring frame is sleeved on the surface of the natural gas pipeline and is connected with the movable ring rod through a plurality of connecting rods; the natural gas pipeline clamping device has the technical key points that the clamping devices are arranged on the two sides of the natural gas pipeline, so that the two ends of the pipeline can be propped open and positioned, the natural gas pipeline is fixed, and the natural gas pipeline is convenient to move and place; through design telescopic cylinder and transmission frame group, can carry out the expansion use with whole transmission frame group, turn into vertical ascending power with horizontal power for each fagging and the laminating of pipeline inner wall make the integrated device can deal with the pipeline of different specifications, have improved the use flexibility of device.

Description

Natural gas line construction is got with pressing from both sides and is settled device
Technical Field
The utility model belongs to the pipeline processing field specifically is a natural gas line construction is got with pressing from both sides and is settled device.
Background
A pipeline is a device for transporting a gas, liquid or fluid with solid particles, connected by pipes, pipe couplings, valves, etc. The pipeline is widely applied to multiple industries and fields due to the unique characteristics of the pipeline.
In the process of utilizing the pipeline to carry out the construction, need use dedicated clamp to get the device usually, the folder through twice semicircle ring gets the pipeline and gets, then settles it again, the following technical problem can appear when using in current device however: firstly, when positioning and clamping pipe bodies with different pipe diameters, certain gaps may be generated between the pipe bodies and the inner wall of the pipe body, so that smooth clamping operation is affected; secondly, the overall device has lower use flexibility.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art's defect, a natural gas line construction is got with clamp and is settled device is provided.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a natural gas line construction is with pressing from both sides getting settling device includes:
the outer wall of the base plate is provided with a pump body and a transmission mechanism, and the transmission mechanism is used for driving the base plate to move on the surface of the natural gas pipeline;
the movable ring rod is sleeved on the surface of the natural gas pipeline and welded with the top end of the chassis, and a plurality of movable roller sets are arranged on the inner wall of the movable ring rod; and
the ring frame is sleeved on the surface of the natural gas pipeline and connected with the movable ring rod through a plurality of connecting rods, a plurality of nozzles are uniformly arranged on the inner wall of the ring frame, and the nozzles are communicated with an outer pipe body arranged on the outer wall of the ring frame.
Preferably, the pump body is communicated with the outer pipe body through a hose, and paint for spraying is filled in the outer pipe body.
Preferably, the inner wall of the ring frame is provided with a soft ring pipe, the soft ring pipe is communicated with the inner cavity of the outer pipe body, and one end of the nozzle is spirally arranged in the ring frame and communicated with the soft ring pipe.
Preferably, drive mechanism contains motor shaft, post, the wheel body and the drive belt with the laminating of natural gas line surface, the motor shaft is installed in the chassis, and the drive belt is used for the transmission to connect the axis of motor shaft and wheel body avris, the one end of post is connected through setting up torsion spring with the chassis, and the other end can suit the centraxonial surface of wheel body avris.
Preferably, the outer surface of the wheel body is in the shape of an inwards concave arc, and a rubber pad is sleeved on the surface of the wheel body.
Preferably, the movable roller group comprises a connecting piece, two groups of rotating rods and two groups of rollers, the connecting piece is welded with the inner wall of the movable ring rod, one end of each rotating rod is connected with the corresponding roller, and the other end of each rotating rod is connected with the connecting piece through a torsion spring.
Compared with the prior art, the utility model provides a natural gas line construction is got with clamp and is settled device has following beneficial effect:
firstly, the clamping devices are arranged on the two sides of the natural gas pipeline, so that the two ends of the pipeline can be propped open and positioned, the natural gas pipeline is fixed, and the natural gas pipeline is convenient to move and place;
secondly, by designing the telescopic cylinder and the transmission frame group, the whole transmission frame group can be used in an expanded mode, and transverse force is converted into longitudinal force, so that each supporting plate is attached to the inner wall of the pipeline, the whole device can deal with pipelines with different specifications, and the use flexibility of the device is improved;
thirdly, the chassis and the movable seat are combined for the movable seat moves in the limiting groove on the chassis, so that each supporting plate is guaranteed to move linearly at the corresponding position, and the normal use of the whole device is guaranteed.
Drawings
Fig. 1 is an overall structure front view of the present invention;
fig. 2 is a side view of the middle chassis structure of the present invention;
fig. 3 is an enlarged view of a partial structure a of fig. 2 according to the present invention.
Reference numerals: 1. a chassis; 2. a telescopic cylinder; 3. a card holder; 4. a trough body; 5. a piston rod; 6. a movable seat; 7. a chute; 8. a transmission frame set; 81. a first frame body; 82. a second frame body; 9. a supporting plate; 10. A limiting groove.
Detailed Description
The following description further illustrates a specific embodiment of the clamping and placing device for natural gas pipeline construction according to the present invention with reference to fig. 1. The utility model relates to a natural gas line construction is with pressing from both sides getting settling device is not limited to the description of following embodiment.
This embodiment provides a natural gas line construction is with pressing from both sides specific structure of getting settling device, as shown in fig. 1-3, a natural gas line construction is with pressing from both sides getting settling device includes:
a telescopic cylinder 2 is arranged on one side of a chassis 1, and a clamping seat 3 is welded on the other side of the chassis; and
the transmission frame group 8 comprises a first frame body 81 and a second frame body 82 which are connected in a crossed mode, the piston rod 5 matched with the telescopic cylinder 2 can drive the transmission frame group 8 to move in an extending mode, one end of the transmission frame group 8 is connected with the movable seat 6, and a supporting plate 9 is welded on the surface of the movable seat 6.
The device is got to the aforesaid design clamp through in natural gas line both sides, can strut the location with the both ends of pipeline to the realization is handled the fixed of natural gas line, and the convenience is removed and is placed it.
As shown in fig. 1, four sets of limiting grooves 10 are formed in the surface of the chassis 1, the four sets of limiting grooves 10 are distributed in a cross shape on the same plane, and the movable seat 6 is slidably assembled in the corresponding limiting groove 10.
As shown in fig. 2, the clamping seat 3 is a cylindrical structure, and a groove 4 is formed in the clamping seat 3, and the groove 4 is used for filling the transmission frame group 8 in a contracted state;
as shown in fig. 1, the first frame body 81 and the second frame body 82 have the same specification, the first frame body 81 includes three groups of interconnected steel plates, the steel plate located in the middle is fixedly connected with the piston rod 5, and the steel plates located on both sides are connected with the steel plate of the second frame body 82 through a rotating shaft.
Above-mentioned through design telescopic cylinder and transmission frame group, can carry out the expansion use with whole transmission frame group, turn into vertical ascending power with horizontal power for each fagging is laminated with the pipeline inner wall, makes the integrated device can deal with the pipeline of different specifications, has improved the use flexibility of device
As shown in fig. 3, the sliding groove 7 is formed in the surface of the movable seat 6, and the shaft blocks located at one end of the two steel plates in the second frame body 82 can be slidably assembled in the sliding groove 7;
in the use process, the shaft block at one end of the second frame body 82 can slide in the sliding groove 7.
As shown in fig. 3, a supporting plate 9 is welded on one side of the movable seat 6, and the cross section of the supporting plate 9 is arc-shaped and can be attached to the inner wall of the natural gas pipeline.
The chassis 1 and the movable seat 6 are combined for use, so that the limiting groove 10 of the movable seat 6 on the chassis 1 moves, each supporting plate 9 is guaranteed to move linearly at the corresponding position, and normal use of the whole device is guaranteed.
The foregoing is a more detailed description of the present invention, taken in conjunction with the specific preferred embodiments thereof, and it is not intended that the invention be limited to the specific embodiments shown and described. To the utility model belongs to the technical field of ordinary technical personnel, do not deviate from the utility model discloses under the prerequisite of design, can also make a plurality of simple deductions or replacement, all should regard as belonging to the utility model discloses a protection scope.

Claims (6)

1. The utility model provides a natural gas line construction is with pressing from both sides getting settling device which characterized in that includes:
the device comprises a chassis (1), wherein one side of the chassis is provided with a telescopic cylinder (2), and the other side of the chassis is welded with a clamping seat (3); and
transmission frame group (8), its support body (81) and No. two support bodies (82) that contain the cross-type and connect, the supporting piston rod (5) of telescopic cylinder (2) can drive transmission frame group (8) and extend the activity, and the one end of transmission frame group (8) is connected with sliding seat (6) to there is fagging (9) at the skin weld of sliding seat (6).
2. The gripping and placing device for natural gas pipeline construction as claimed in claim 1, wherein: four groups of limiting grooves (10) are formed in the surface of the chassis (1), the four groups of limiting grooves (10) are distributed in a cross shape on the same plane, and the movable seat (6) is assembled into the corresponding limiting grooves (10) in a sliding mode.
3. The gripping and placing device for natural gas pipeline construction as claimed in claim 1, wherein: the clamping seat (3) is of a cylindrical structure, a groove body (4) is formed in the clamping seat (3), and the groove body (4) is used for filling the transmission frame group (8) in a contraction state.
4. The gripping and placing device for natural gas pipeline construction as claimed in claim 1, wherein: the specification of a support body (81) is the same with No. two support bodies (82), No. one support body (81) contains three group interconnect's steel sheet, and the steel sheet that is located the middle part is connected through the pivot with piston rod (5) fixed connection, the steel sheet that is located both sides and the steel sheet of No. two support bodies (82).
5. The gripping and placing device for natural gas pipeline construction as claimed in claim 4, wherein: a sliding groove (7) is formed in the surface of the movable seat (6), and a shaft block positioned at one end of each of the two steel plates in the second frame body (82) can be assembled in the sliding groove (7) in a sliding mode.
6. The gripping and placing device for natural gas pipeline construction as claimed in claim 1, wherein: one side welding of sliding seat (6) has fagging (9), and the cross-section of fagging (9) is the arc to can laminate with natural gas line's inner wall.
CN202022424050.6U 2020-10-28 2020-10-28 Natural gas line construction is got with pressing from both sides and is settled device Active CN214326438U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022424050.6U CN214326438U (en) 2020-10-28 2020-10-28 Natural gas line construction is got with pressing from both sides and is settled device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022424050.6U CN214326438U (en) 2020-10-28 2020-10-28 Natural gas line construction is got with pressing from both sides and is settled device

Publications (1)

Publication Number Publication Date
CN214326438U true CN214326438U (en) 2021-10-01

Family

ID=77893698

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022424050.6U Active CN214326438U (en) 2020-10-28 2020-10-28 Natural gas line construction is got with pressing from both sides and is settled device

Country Status (1)

Country Link
CN (1) CN214326438U (en)

Similar Documents

Publication Publication Date Title
CN109399187A (en) Portable tubular product centre gripping distributor
CN102974970B (en) Fixture for welding car axle housing, air bag bottom plate and upper traction bar base
CN214326438U (en) Natural gas line construction is got with pressing from both sides and is settled device
CN112145833A (en) Sealed anti-corrosion steel structure butt joint piece for pipeline splicing
CN114013526A (en) Annular telescopic pipe clamping claw
CN112303332A (en) Pipe work apparatus and method for pipe gallery
CN210533691U (en) Pipeline pressure-bearing equipment detection equipment
CN207309299U (en) A kind of tubular workpiece butt welding tool fixture
CN112756344A (en) Cleaning device for hydraulic oil cylinder
CN105904467B (en) A kind of self-centering docking robot of pipe
CN212377442U (en) Pipe installation aligning device with high-finish inner wall
CN112110125B (en) Secondary limiting rapid transfer equipment for processing anti-pinch steel structure prefabricated part
CN208945486U (en) A kind of steel reinforcement cage processing welder
CN108749890B (en) Multipurpose cart for machining
CN113790309A (en) Support device with wide application range for municipal pipeline laying and use method thereof
CN114393361A (en) Be applied to group of water conservancy water and electricity penstock field welding process to platform truck
CN113547314A (en) Crimping machine
CN2447598Y (en) Multiple oil tank combined main-jacking device
CN209757214U (en) Ball pushing vehicle for conveying pipe cleaner of oil-gas pipeline engineering
CN214393038U (en) Frock clamp is used in filter processing
CN219336068U (en) Valve body drilling device
CN117090997B (en) Pipeline connection correction inspection robot
CN216446462U (en) Quick-dismantling integrated supporting table for building engineering management
CN117537212A (en) Install compressive equipment on pipeline
CN219925948U (en) Be used for sewage treatment pipeline coupling assembling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant