Temporary support device for mounting steel structure stand column Download PDFInfo
- Publication number
- CN214302938U CN214302938U CN202023194930.5U CN202023194930U CN214302938U CN 214302938 U CN214302938 U CN 214302938U CN 202023194930 U CN202023194930 U CN 202023194930U CN 214302938 U CN214302938 U CN 214302938U
- Authority
- CN
- China
- Prior art keywords
- steel structure
- support device
- platform
- support
- temporary support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Revetment (AREA)
Abstract
The utility model relates to the technical field of building construction, in particular to a temporary support device for mounting a steel structure upright post, which comprises at least a pair of support bodies; the bracket body comprises a fixed support and a platform support which are vertically connected together, the upper part of the fixed support is fixedly provided with a hanging piece which is matched and connected with the fastener, the bracket body is hung on the steel structure upright post through the hanging piece, and each bracket body is connected with different steel structure upright posts; all be connected with the connecting rod between the platform support of every pair of support body in order to form the platform frame, this platform frame upper berth is equipped with the steel sheet net, and this platform frame outside is provided with the guardrail bar. Adopt this interim support device to carry out steel structure stand installation construction, easy operation is applicable to the steel structure stand installation construction in large tracts of land and the less region in space, can effectually ensure steel structure stand's welding construction safety, has improved the efficiency of construction.
Description
Technical Field
The utility model relates to a construction technical field especially relates to a steel construction column mouting's interim support device.
Background
According to the steel structure installation construction technology in the building industry, aiming at the high-altitude installation construction of a steel structure, the adopted construction supports are mostly tools such as a scaffold platform, a lifter, a hanging basket and the like, but the tools have relatively high cost, and aiming at the steel structure construction with limited space, the tools such as the lifter, the hanging basket and the like are inconvenient to construct, so that the construction efficiency is seriously influenced; these are undesirable to those skilled in the art.
SUMMERY OF THE UTILITY MODEL
In order to solve the existing problems, the utility model discloses a temporary support device for mounting a steel structure upright post, wherein the temporary support device comprises at least one pair of support bodies;
the steel structure upright post is provided with a fastener;
the bracket bodies comprise fixed supports and platform supports which are vertically connected together, hanging pieces which are matched and connected with the fasteners are fixedly arranged at the upper parts of the fixed supports, the bracket bodies are hung on the steel structure upright posts through the hanging pieces, and each bracket body is connected with different steel structure upright posts;
every all be connected with the connecting rod between every the platform of support body supports in order to form the platform frame, the platform frame upper berth is equipped with the steel sheet net, just the platform frame outside is provided with the guardrail bar.
Preferably, a baffle is arranged at the bottom end of the fixed support, and the width of the baffle is the same as that of the hanging piece.
Preferably, the bracket body is a right triangle.
Preferably, the bracket body is an isosceles right triangle.
Preferably, the fastener comprises a U-shaped groove body and fixing plates positioned on two sides of an opening of the U-shaped groove body.
Preferably, the guard rail comprises rail columns, and rungs are connected between the adjacent rail columns.
Above-mentioned utility model has following advantage or beneficial effect:
adopt this interim support device to carry out steel structure stand installation construction, easy operation is applicable to the steel structure stand installation construction in large tracts of land and the less region in space, can effectually ensure steel structure stand's welding construction safety, has improved the efficiency of construction.
Drawings
The invention and its features, aspects and advantages will become more apparent from a reading of the following detailed description of non-limiting embodiments with reference to the attached drawings. The drawings, in which like reference numerals refer to like parts throughout the several views and which are not necessarily to scale, emphasis instead being placed upon illustrating the principles of the invention.
Fig. 1 is a schematic structural view of a fastener according to an embodiment of the present invention;
fig. 2 is a schematic structural view of a bracket body according to an embodiment of the present invention;
fig. 3 is a top view of the temporary support device for mounting the steel structure upright column in the embodiment of the present invention;
fig. 4 is a side view of the temporary support device for mounting the steel structure column in the embodiment of the present invention.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and specific examples, which should not be construed as limiting the invention.
As shown in fig. 1-4, the utility model discloses a temporary support device for mounting a steel structure upright, specifically, a fastener 1 is arranged on the steel structure upright (specifically, one fastener 1 is welded on the upper end of each section of steel structure upright); the temporary stand device includes at least a pair of stand bodies 2; the bracket body 2 comprises a fixed support 22 and a platform support 21 which are vertically connected together, the upper part of the fixed support 22 is fixedly provided with a hanging piece 24 which is matched and connected with the fastener 1, the bracket body 2 is hung on an installed steel structure upright post through the hanging piece 24, and each bracket body 2 is connected with different steel structure upright posts; all be connected with the connecting rod between every platform support 21 to support body 2 in order to form the platform frame, this platform frame upper berth is equipped with steel sheet net 3, and the platform frame outside is provided with guard rail 4 in order to protect constructor's safety.
In a preferred embodiment of the present invention, the bracket body 2 is a right triangle; specifically, the support body 2 is an isosceles right triangle with a waist length of 600mm, and each side is welded and fixed. The two right-angle sides are used as a fixed support 22 and a platform support 21, the fixed support 22 and the platform support 21 and an inclined support 23 connecting the fixed support 22 and the platform support 21 are all manufactured by L50 x 50 x 5, the upper part of the fixed support 22 (the position of an upper opening of the fixed support 22) is manufactured into a hanging piece 24 by adopting a steel plate with 50 x 5, the lower part of the fixed support 22 (the position of a lower opening of the fixed support 22) is manufactured into a baffle 25 by adopting a steel plate with 50 x 5, the hanging piece 24 and the baffle 25 are welded and fixed with the fixed support 22, and the width of the baffle 25 is the same as that of the hanging piece 24 so as to prevent the platform support 21 from inclining.
In a preferred embodiment of the present invention, the fastening member 1 includes a U-shaped groove 11 and a fixing plate 12 located on both sides of the opening of the U-shaped groove 11, specifically, the fastening member 1 is made of a steel plate with a width of 50mm and a thickness of 5mm, the length of the U-shaped groove 11 is 180mm, and the length of the fixing ends on both sides is 60mm respectively.
In a preferred embodiment of the present invention, every two of the above-mentioned support bodies 2 are used in cooperation (used in pairs), and 2L 50 × 50 × 5 connections are adopted between the supports to form a platform frame, and the steel plate net 3 is laid on the connecting rods.
In a preferred embodiment of the present invention, the protection balustrade 4 comprises balustrade posts 41, and a crosspiece 42 is connected between the adjacent balustrade posts 41. Specifically, this prevent guardrail 4 and adopt L50 50 the preparation of 5 to form, should prevent guardrail 4 height 1200mm, this railing post 41 adopts 30mm square pipe preparation, and horizontal interval 1000mm sets up, and the bottom sets up the wide baffle 25 of 120mm, is connected with crosspiece 42 between the adjacent railing post 41, and crosspiece 42 is by square pipe preparation, and is provided with three upper, middle and lower crosspieces 42 between the railing post 41.
The utility model provides an interim support device of steel construction column mouting accomplishes the back at steel construction column mouting, only needs to hang the support body on the fastener, then carries out the platform and connects and steel sheet net, protection railing equipment, and it is all more convenient to install and dismantle.
Those skilled in the art will appreciate that variations may be implemented by those skilled in the art in combination with the prior art and the above-described embodiments, and will not be described herein in detail. Such variations do not affect the essence of the present invention, and are not described herein.
The above description is directed to the preferred embodiment of the present invention. It is to be understood that the invention is not limited to the particular embodiments described above, and that devices and structures not described in detail are understood to be implemented in a manner common in the art; without departing from the scope of the invention, it is intended that the present invention shall not be limited to the above-described embodiments, but that the present invention shall include all the modifications and variations of the embodiments. Therefore, any simple modification, equivalent change and modification made to the above embodiments by the technical entity of the present invention all still fall within the protection scope of the technical solution of the present invention, where the technical entity does not depart from the content of the technical solution of the present invention.
Claims (6)
1. A temporary support device for mounting a steel structure upright column is characterized by comprising at least one pair of support bodies;
the steel structure upright post is provided with a fastener;
the bracket bodies comprise fixed supports and platform supports which are vertically connected together, hanging pieces which are matched and connected with the fasteners are fixedly arranged at the upper parts of the fixed supports, the bracket bodies are hung on the steel structure upright posts through the hanging pieces, and each bracket body is connected with different steel structure upright posts;
every all be connected with the connecting rod between every the platform of support body supports in order to form the platform frame, the platform frame upper berth is equipped with the steel sheet net, just the platform frame outside is provided with the guardrail bar.
2. A temporary support device for mounting a steel structure upright according to claim 1, wherein a baffle is provided at the bottom end of the fixed support, and the width of the baffle is the same as that of the hanging member.
3. A temporary support device for the installation of steel structural uprights according to claim 1, wherein the support body is right-angled triangular.
4. A temporary support device for the installation of steel structural columns according to claim 3, wherein the support body is an isosceles right triangle.
5. A temporary support device for the installation of steel structural uprights according to claim 1, wherein the fasteners comprise U-shaped channels and fixing plates located on both sides of the openings of the U-shaped channels.
6. A temporary support device for installing steel structural columns according to claim 1, wherein the protective railings comprise railing columns, and rungs are connected between adjacent railing columns.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202023194930.5U CN214302938U (en) | 2020-12-25 | 2020-12-25 | Temporary support device for mounting steel structure stand column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202023194930.5U CN214302938U (en) | 2020-12-25 | 2020-12-25 | Temporary support device for mounting steel structure stand column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214302938U true CN214302938U (en) | 2021-09-28 |
Family
ID=77862335
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202023194930.5U Active CN214302938U (en) | 2020-12-25 | 2020-12-25 | Temporary support device for mounting steel structure stand column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214302938U (en) |
-
2020
- 2020-12-25 CN CN202023194930.5U patent/CN214302938U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN214302938U (en) | Temporary support device for mounting steel structure stand column | |
CN212773388U (en) | Novel all-steel lifting scaffold | |
CN112267661A (en) | Climbing frame convenient to adjust for construction industry | |
CN217897363U (en) | Building construction safety device | |
CN217975496U (en) | Construction elevator well protective structure is built to building room | |
CN214659376U (en) | Novel guardrail bar is prevented at elevator shaft entrance to a cave | |
CN212295608U (en) | System for stabilizing climbing scaffold | |
RU2009135481A (en) | CONSTRUCTION SCAFFOLDES IN WHICH RANKS HAVE RACK SECTIONS | |
CN215858956U (en) | Scaffold frame that security performance is high | |
CN207436477U (en) | For the sleigh of installation photovoltaic component | |
CN217652295U (en) | Steel movable cantilever operation platform | |
CN203783106U (en) | Hanging assembling moving platform | |
CN215291259U (en) | Prevent building scaffold that part dropped | |
CN217518117U (en) | Novel unsettled cage platform | |
CN219909888U (en) | Tower crane attaches wall operation platform | |
CN217949707U (en) | I-steel beam hanging basket connecting system | |
CN220621173U (en) | Face limit protection device of assembled building | |
CN103628694B (en) | A kind of suspended formwork protective net apparatus | |
CN213555003U (en) | Safety belt hanging support | |
CN215594861U (en) | Closed protection device for cantilever scaffold bottom plate | |
CN213774374U (en) | Support for installing reinforcing steel bars | |
CN215564254U (en) | Scaffold frame that construction was used | |
CN215168396U (en) | Safety channel | |
CN214220563U (en) | Steel construction roof boarding installation hanging flower basket device | |
CN214653222U (en) | Anti-climbing device for tower crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |