CN214272936U - Special material conveying opening grooving iron box for building aluminum mold - Google Patents

Special material conveying opening grooving iron box for building aluminum mold Download PDF

Info

Publication number
CN214272936U
CN214272936U CN202023200861.4U CN202023200861U CN214272936U CN 214272936 U CN214272936 U CN 214272936U CN 202023200861 U CN202023200861 U CN 202023200861U CN 214272936 U CN214272936 U CN 214272936U
Authority
CN
China
Prior art keywords
hopper
reinforcing bar
transmission
lateral wall
material conveying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023200861.4U
Other languages
Chinese (zh)
Inventor
姜淦清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhaoqing Chuangfu New Materials Technology Co ltd
Original Assignee
Zhaoqing Chuangfu New Material Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhaoqing Chuangfu New Material Technology Co ltd filed Critical Zhaoqing Chuangfu New Material Technology Co ltd
Priority to CN202023200861.4U priority Critical patent/CN214272936U/en
Application granted granted Critical
Publication of CN214272936U publication Critical patent/CN214272936U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a special material mouth fluting iron box that passes of building aluminium mould relates to the building templates field, including first transmission hopper, the inner wall of first transmission hopper is provided with a plurality of pipe of strengthening on, the bottom of first transmission hopper is provided with second transmission hopper, and the inner wall of second transmission hopper is provided with a plurality of pipe of strengthening down, a plurality of horizontal reinforcing bar cross-under grooves have been seted up to the long lateral wall of second transmission hopper, and the short lateral wall of second transmission hopper has seted up a plurality of vertical reinforcing bar cross-under grooves. The utility model discloses when carrying out concrete placement to aluminium mould biography material entrance to a cave department, first conveying hopper forms cascaded biography material mouth with the second biography hopper, go up and strengthen the pipe and make the holistic intensity increase of device with strengthening the pipe down, device lateral wall has seted up a plurality of horizontal reinforcing bars cross-under groove and vertical reinforcing bar cross-under groove simultaneously, need not cut off the reinforcing bar, the reinforcing bar directly passes from the notch, make things convenient for the workman dismouting simultaneously, entrance to a cave safety protection has played very big effect again, need not the secondary bar planting, a lot of costs have been saved.

Description

Special material conveying opening grooving iron box for building aluminum mold
Technical Field
The utility model relates to a building templates field specifically is a special biography material mouth fluting iron box of building aluminium mould.
Background
The aluminum alloy template is a building template made of aluminum alloy and is also called an aluminum template, the aluminum alloy template is manufactured and designed according to modulus, the aluminum template is manufactured by extruding special equipment, universal accessories consisting of aluminum panels and side frames can be combined and spliced into integral die frames with different sizes and complex external dimensions, and the assembled and industrialized system aluminum template solves the defects of the traditional template and greatly improves the construction efficiency.
When putting up aluminum alloy template system, leave the biography material hole that supplies the template to transport in the template, make things convenient for the template to pass through the manual work up the transmission, need not to occupy perpendicular transportation equipment, pass the biography material device that material mouthful position installation supplied aluminum mould board to pass the material usefulness, tradition passes material mouthful iron box complex operation, will cut off the reinforcing bar, follow-up secondary bar planting, and be unfavorable for the entrance to a cave protection, have very big potential safety hazard.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: in order to solve the problem that the common material conveying opening iron box has certain potential safety hazards, the special material conveying opening slotted iron box for the building aluminum mold is provided.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a special material mouth fluting iron box that passes of building aluminium mould, includes first transmission hopper, the inner wall of first transmission hopper is provided with a plurality of enhancement pipes that go up, the bottom of first transmission hopper is provided with second transmission hopper, and the inner wall of second transmission hopper is provided with a plurality of enhancement pipes down, a plurality of transverse reinforcement cross-under grooves have been seted up to the long lateral wall of second transmission hopper, and the short lateral wall of second transmission hopper has seted up a plurality of vertical reinforcement cross-under grooves.
Preferably, the top of the inner side wall of the first material conveying hopper is provided with a handle, and the handle is formed by welding round pipes with the radius of 16 mm.
Preferably, the radius of strengthening the pipe all is 30mm with strengthening the pipe down on going up, and strengthen the pipe all through welding setting in the inner wall of first biography hopper and second biography hopper with strengthening the pipe down on going up.
Preferably, the height of first transfer hopper top to second transfer hopper bottom is 178mm, and first transfer hopper height and second transfer hopper height are 128mm and 50mm respectively, the contained angle of first transfer hopper lateral wall and second transfer hopper lateral wall extension line all is 25, and bottom length of first transfer hopper bottom length and second transfer hopper is 872mm and 790mm respectively.
Preferably, the width in horizontal reinforcing bar cross-under groove and vertical reinforcing bar cross-under groove is 15mm, and horizontal reinforcing bar cross-under groove and vertical reinforcing bar cross-under groove all equidistance set up in the second passes the hopper lateral wall.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses when carrying out concrete placement to aluminium mould biography material entrance to a cave department, first conveying hopper forms cascaded biography material mouth with the second biography hopper, go up and strengthen the pipe and make the holistic intensity increase of device with strengthening the pipe down, device lateral wall has seted up a plurality of horizontal reinforcing bars cross-under groove and vertical reinforcing bar cross-under groove simultaneously, need not cut off the reinforcing bar, the reinforcing bar directly passes from the notch, make things convenient for the workman dismouting simultaneously, entrance to a cave safety protection has played very big effect again, need not the secondary bar planting, a lot of costs have been saved.
Drawings
Fig. 1 is a top view of the present invention;
FIG. 2 is a sectional top view of the present invention;
fig. 3 is a front view of the present invention;
fig. 4 is a side view of the present invention;
FIG. 5 is a side cross-sectional view of the present invention;
fig. 6 is a front sectional view of the present invention.
In the figure: 1. a first transfer hopper; 2. a second material conveying hopper; 3. an upper reinforcing circular tube; 4. a lower reinforcing circular tube; 5. a handle; 6. the transverse steel bar penetrates through the groove; 7. the vertical steel bar is connected with the groove in a penetrating way.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "connected" and "disposed" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art. The following describes an embodiment of the present invention according to its overall structure.
Referring to fig. 1-6, a slotted iron box for a material transfer port special for a building aluminum mold comprises a first material transfer hopper 1, wherein a plurality of upper reinforcing circular tubes 3 are arranged on the inner wall of the first material transfer hopper 1, a second material transfer hopper 2 is arranged at the bottom of the first material transfer hopper 1, a plurality of lower reinforcing circular tubes 4 are arranged on the inner wall of the second material transfer hopper 2, a plurality of transverse steel bar penetrating grooves 6 are formed on the long side wall of the second material transfer hopper 2, a plurality of vertical steel bar penetrating grooves 7 are formed on the short side wall of the second material transfer hopper 2, when concrete is poured at a material transfer port of the aluminum mold, the first material transfer hopper 1 and the second material transfer hopper 2 form a stepped material transfer port, the upper reinforcing circular tubes 3 and the lower reinforcing circular tubes 4 increase the strength of the whole device, and the side walls of the device are provided with a plurality of transverse steel bar penetrating grooves 6 and vertical steel bar penetrating grooves 7, steel bars do not need to be cut off, and directly pass through the port, meanwhile, the device is convenient for workers to disassemble and assemble, the safety protection of the opening plays a great role, secondary bar planting is not needed, and a lot of cost is saved.
Please refer to fig. 1 and fig. 2, a handle 5 is disposed on the top of the inner sidewall of the first material transferring hopper 1, and the handle 5 is formed by welding circular pipes with a radius of 16mm, and the handle 5 is disposed to facilitate pulling out the whole device after concrete pouring.
Please refer to fig. 1 and fig. 2, the radii of the upper circular reinforcing pipe 3 and the lower circular reinforcing pipe 4 are both 30mm, and the upper circular reinforcing pipe 3 and the lower circular reinforcing pipe 4 are both welded to the inner walls of the first material transferring hopper 1 and the second material transferring hopper 2, and the strength of the whole device is effectively enhanced by the upper circular reinforcing pipe 3 and the lower circular reinforcing pipe 4.
Please refer to fig. 1 and fig. 2 heavily, the height from the top of the first material transferring hopper 1 to the bottom of the second material transferring hopper 2 is 178mm, and the height of the first material transferring hopper 1 and the height of the second material transferring hopper 2 are 128mm and 50mm respectively, the included angle between the extension lines of the side wall of the first material transferring hopper 1 and the side wall of the second material transferring hopper 2 is 25 °, and the length of the bottom of the first material transferring hopper 1 and the length of the bottom of the second material transferring hopper 2 are 872mm and 790mm respectively, and the material transferring ports are stepped through the arranged first material transferring hopper 1 and the second material transferring hopper 2, thereby facilitating the material transferring.
Please refer to fig. 2 and fig. 3, the width of the transverse steel bar threading slot 6 and the vertical steel bar threading slot 7 is 15mm, the transverse steel bar threading slot 6 and the vertical steel bar threading slot 7 are both equidistantly arranged on the side wall of the second material conveying hopper 2, and the steel bar can directly pass through the notch by the arranged transverse steel bar threading slot 6 and the vertical steel bar threading slot 7.
The working principle is as follows: when passing material entrance to the aluminium mould and mouthful carrying out concrete placement, first conveying hopper 1 passes hopper 2 with the second and forms cascaded biography material mouth, on strengthen pipe 3 and strengthen pipe 4 and make the holistic intensity increase of device down, device's lateral wall has been seted up a plurality of horizontal reinforcing bars and has been worn groove 6 and vertical reinforcing bar and wear groove 7 simultaneously, need not cut off the reinforcing bar, the reinforcing bar directly passes from the notch, make things convenient for workman's dismouting simultaneously, entrance to a cave safety protection has played very big effect again, need not the secondary bar planting, a lot of costs have been saved, use and accomplish the back and pull out the device wholly through handle 5, seal with the concrete.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (5)

1. The utility model provides a special biography material mouth fluting iron box of building aluminium mould, includes first transfer hopper (1), its characterized in that: the inner wall of first transmission hopper (1) is provided with a plurality of pipe (3) of strengthening of going up, the bottom of first transmission hopper (1) is provided with second transmission hopper (2), and the inner wall of second transmission hopper (2) is provided with a plurality of pipe (4) of strengthening down, a plurality of transverse reinforcement cross-under grooves (6) have been seted up to the long lateral wall of second transmission hopper (2), and a plurality of vertical reinforcement cross-under grooves (7) have been seted up to the short lateral wall of second transmission hopper (2).
2. The special material conveying opening slotted iron box for the building aluminum mold as claimed in claim 1, characterized in that: the top of the inner side wall of the first conveying hopper (1) is provided with a handle (5), and the handle (5) is formed by welding round pipes with the radius of 16 mm.
3. The special material conveying opening slotted iron box for the building aluminum mold as claimed in claim 1, characterized in that: the radius of the upper reinforcing circular tube (3) and the lower reinforcing circular tube (4) is 30mm, and the upper reinforcing circular tube (3) and the lower reinforcing circular tube (4) are arranged on the inner walls of the first material conveying hopper (1) and the second material conveying hopper (2) through welding.
4. The special material conveying opening slotted iron box for the building aluminum mold as claimed in claim 1, characterized in that: first transfer hopper (1) top is 178mm to the height of second transfer hopper (2) bottom, and first transfer hopper (1) height highly is 128mm and 50mm respectively with second transfer hopper (2), the contained angle that first transfer hopper (1) lateral wall and second transfer hopper (2) lateral wall extension line all is 25, and first transfer hopper (1) bottom length and second transfer hopper (2) bottom length be 872mm and 790mm respectively.
5. The special material conveying opening slotted iron box for the building aluminum mold as claimed in claim 1, characterized in that: the width of horizontal reinforcing bar cross-under groove (6) and vertical reinforcing bar cross-under groove (7) is 15mm, and horizontal reinforcing bar cross-under groove (6) and vertical reinforcing bar cross-under groove (7) are all seted up at second biography hopper (2) lateral wall equidistance.
CN202023200861.4U 2020-12-25 2020-12-25 Special material conveying opening grooving iron box for building aluminum mold Active CN214272936U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023200861.4U CN214272936U (en) 2020-12-25 2020-12-25 Special material conveying opening grooving iron box for building aluminum mold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023200861.4U CN214272936U (en) 2020-12-25 2020-12-25 Special material conveying opening grooving iron box for building aluminum mold

Publications (1)

Publication Number Publication Date
CN214272936U true CN214272936U (en) 2021-09-24

Family

ID=77783340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023200861.4U Active CN214272936U (en) 2020-12-25 2020-12-25 Special material conveying opening grooving iron box for building aluminum mold

Country Status (1)

Country Link
CN (1) CN214272936U (en)

Similar Documents

Publication Publication Date Title
CN214272936U (en) Special material conveying opening grooving iron box for building aluminum mold
CN105525750A (en) Construction method of door lintel and aluminum alloy door lintel formwork
CN203755533U (en) Integrated combined wallboard
CN210888038U (en) Replaceable assembled template
CN211691486U (en) Novel telescopic connecting piece for steel back ribs
CN209384631U (en) A kind of aluminium alloy extrusions matching component
CN214498399U (en) Special wire-releasing iron box for building aluminum mold
CN212583266U (en) Aluminum profile for aluminum material transmission box
CN204754207U (en) Aluminium alloy door lintel template
CN210947733U (en) Splicing reservation device for square opening of civil and electrical wiring duct of building
CN218375230U (en) Preformed hole forming combined side die
CN219058350U (en) Instrument convenient to vertical transport aluminum alloy template
CN220167507U (en) Back edge section bar with I-shaped cross section
CN214658783U (en) Detachable bathroom falls board and hangs mould device
CN213391202U (en) Aluminum alloy template wall body reinforced structure
CN212271592U (en) Positioning device for installing arc-shaped wall formwork
CN205894630U (en) Bear scaffold frame of reinforce
CN212984211U (en) Connecting beam head
CN219241353U (en) Novel aluminum template pull sheet system
CN209244268U (en) A kind of novel back cord angle connector
CN208668963U (en) A kind of novel back cord connector
CN214062326U (en) Standard general type side seal aluminum mould board for building
CN211286652U (en) Novel external corner connecting piece
CN212743368U (en) Constructional column moulded die plate structure
CN220247393U (en) Novel sleeve structure for connecting formed steel reinforcement frameworks

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 526200 No. 11, Huiyuan Avenue, Longfu Town, Sihui City, Zhaoqing City, Guangdong Province

Patentee after: Zhaoqing Chuangfu New Materials Technology Co.,Ltd.

Address before: 526200 customs supervision office building, No.11 Huiyuan Avenue, longfu Town, Sihui City, Zhaoqing City, Guangdong Province is only used as office space

Patentee before: Zhaoqing Chuangfu New Material Technology Co.,Ltd.

CP03 Change of name, title or address