CN214272166U - Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting - Google Patents

Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting Download PDF

Info

Publication number
CN214272166U
CN214272166U CN202120085257.7U CN202120085257U CN214272166U CN 214272166 U CN214272166 U CN 214272166U CN 202120085257 U CN202120085257 U CN 202120085257U CN 214272166 U CN214272166 U CN 214272166U
Authority
CN
China
Prior art keywords
pipe
sediment thickness
post
detecting
foundation pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120085257.7U
Other languages
Chinese (zh)
Inventor
张剑
吕建仁
匡静
李应文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Academy Of Building Sciences Group Co ltd
Original Assignee
Gansu Academy Of Building Science Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Academy Of Building Science Co ltd filed Critical Gansu Academy Of Building Science Co ltd
Priority to CN202120085257.7U priority Critical patent/CN214272166U/en
Application granted granted Critical
Publication of CN214272166U publication Critical patent/CN214272166U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model belongs to the technical field of the engineering construction, a device for detecting deep long foundation pile sediment thickness of major diameter and back slip casting reinforcement is disclosed, detect the major diameter with solving prior art, the problem that exists during the sediment thickness of overlength concrete bored concrete pile, the device is including installing the double-deck pipe of loosing core in pile body steel reinforcement cage, and pile body steel reinforcement cage and double-deck pipe of loosing core are all installed in the drilling, the top and the pile body steel reinforcement cage parallel and level of double-deck pipe of loosing core, the bottom of double-deck pipe of loosing core is not less than 0.5 meters apart from the bottom of drilling, the double-deck pipe of loosing core includes outer PVC pipe and installs the intraductal recoverable hollow steel pipe of outer PVC with one heart, and the bottom of outer PVC pipe is sealed, concrete layer has all been pour between the outer wall of outer PVC pipe and the inner wall of drilling. The utility model discloses a pipe of loosing core, the detection and the control of effective supplementary stake end sediment thickness, the recoverable back reuse of the recoverable hollow steel pipe of pipe is loosed core to the multiple layer is favorable to controlling engineering investment cost, increases material cyclic utilization rate.

Description

Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting
Technical Field
The utility model relates to an engineering and construction technical field, concretely relates to bore device that core detected sediment thickness and back slip casting reinforcement.
Background
With the development and demand of economic construction, the current building (structure) is continuously developed towards the direction of height, size and difficulty, which puts higher requirements on the foundation engineering of the building (structure) and generates more and more large-diameter deep and long pile foundations. For a long time, the detection of the engineering pile sediment thickness is a difficult problem which puzzles the engineering world, especially for the sediment thickness of a large-diameter and ultra-long concrete cast-in-place pile, although the pile end pouring quality can be detected to a certain extent by the sound wave transmission method, the sound wave transmission method needs to embed a sound detection pipe in the sediment and ensures that the sediment is penetrated, the human factor is large during construction, and the accuracy of 100% cannot be ensured. The prior art cannot solve the technical problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that exists when prior art detects the sediment thickness of major diameter, overlength cast-in-place concrete pile, provide a device that is used for detecting the deep long foundation pile sediment thickness of major diameter and back slip casting reinforcement.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a device for detecting deep long foundation pile sediment thickness of major diameter and back slip casting reinforcement, loose core the pipe including installing the multiple layer in pile body steel reinforcement cage, and pile body steel reinforcement cage and multiple layer are loosed core the pipe and are all installed in the drilling, the top and the pile body steel reinforcement cage parallel and level of pipe are loosed core to the multiple layer, the multiple layer is loosed core the pipe and is included outer PVC pipe and install the intraductal recoverable hollow steel pipe of outer PVC with one heart, and the bottom of outer PVC pipe seals, concrete layer has all been pour between the outer wall of outer PVC pipe and the inner wall of drilling.
Furthermore, the outer layer PVC pipe is formed by connecting a plurality of sections of PVC pipes through buckles.
Furthermore, the recyclable hollow steel pipe is formed by connecting a plurality of sections of steel pipes through threads.
Further, the inner wall of the outer layer PVC pipe is filled with a lubricating agent layer.
Further, the pile body reinforcement cage comprises a spiral hoop and a plurality of main reinforcements welded in the spiral hoop.
Further, the thickness of the outer layer PVC pipe is not less than 4 mm.
Further, the thickness of the recyclable hollow steel pipe is not less than 4 mm.
Furthermore, the outer wall of the outer PVC pipe is provided with throat hoops at intervals, and the throat hoops and the spiral hoops are fastened through reinforcing steel bars.
Further, the distance between the bottom of the multilayer core-pulling guide pipe and the bottom of the drill hole is not less than 0.5 m.
Compared with the prior art, the utility model, following beneficial effect has:
the utility model discloses a device whole device for detecting deep long foundation pile sediment thickness of major diameter and back slip casting reinforcement is pre-buried simultaneously with pile body steel reinforcement cage, takes recoverable hollow steel pipe out after pile body concrete placement, forms the diameter and far exceeds the pipe of loosing core that bores the core and detect used drill bit diameter, and the pipe is inside for empty, has reduced greatly along this pipe when boring and get pile end concrete core appearance and has bored the core distance, energy-conserving material saving, raise the efficiency. Meanwhile, the pile body is quickly reinforced as a post-grouting reinforcement channel under the condition that pile end sediment needs to be treated or reinforcement is needed, the purpose of quickly detecting and reinforcing the quality of the pile body is achieved by the aid of the same device, the accuracy and convenience of detection and reinforcement construction are improved, the advantages of ensuring engineering quality and saving materials and construction period are achieved, and the method has good economic and environmental benefits and high engineering popularization and application values. The utility model discloses a pipe of loosing core, the detection and the control of effective supplementary stake end sediment thickness when guaranteeing foundation pile bearing capacity, further realize the purpose that the control building subsides. The recyclable hollow steel pipe of the double-layer core-pulling guide pipe can be recycled, so that the engineering investment cost can be controlled, and the material recycling rate can be increased.
Drawings
Fig. 1 is a schematic view of the present invention.
Fig. 2 is a schematic view of the multi-layer core-pulling catheter of the present invention.
Fig. 3 is a cross-sectional view of a-a of fig. 1 according to the present invention.
The reference numerals have the following meanings: 1. a multi-layer core-pulling conduit; 2. an outer layer of PVC pipe; 3. the hollow steel pipe can be recycled; 4. a main rib; 5. a spiral hoop; 6. a concrete layer; 7. drilling; 8. a hose clamp.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and the following detailed description.
As shown in fig. 1-3, a device for detecting the sediment thickness of a large-diameter deep and long foundation pile and reinforcing by post-grouting comprises a multi-layer core-pulling guide pipe 1 installed in a pile body steel reinforcement cage, wherein the pile body steel reinforcement cage and the multi-layer core-pulling guide pipe 1 are both installed in a drill hole 7, and the pile body steel reinforcement cage comprises a spiral hoop 5 and a plurality of main ribs 4 welded in the spiral hoop 5. The top of the double-layer core-pulling guide pipe 1 is flush with a pile body reinforcement cage, the distance between the bottom of the double-layer core-pulling guide pipe 1 and the bottom of the drill hole 7 is not less than 0.5m, the double-layer core-pulling guide pipe 1 comprises an outer-layer PVC pipe 2 and a recyclable hollow steel pipe 3 concentrically installed in the outer-layer PVC pipe 2, the thickness of the recyclable hollow steel pipe 3 is not less than 4mm, and the recyclable hollow steel pipe 3 is formed by connecting a plurality of sections of steel pipes through threads. The outer wall of outer layer PVC pipe 2 is gone up the interval and is set up larynx hoop 8, and larynx hoop 8 passes through the reinforcing bar fastening with spiral hoop 5.
The bottom of outer PVC pipe 2 is sealed, and concrete layer 6 has all been pour between the outer wall of outer PVC pipe 2 and the inner wall of drilling 7. Outer layer PVC pipe 2 is formed by the buckle connection of multisection PVC pipe, and outer layer PVC pipe 2's thickness is not less than 4mm, and the inner wall of outer layer PVC pipe 2 is filled and is scribbled lubricated reagent layer.
The method comprises the following specific steps:
the outside of the double-layer core-pulling conduit, namely the outer PVC pipe 2, is provided with throat hoops every 2m, and binding steel bars are connected with the inner wall of the spiral reinforcing rib of the steel reinforcement cage under the throat hoops, so that the verticality of the conduit body is ensured in the connection process, the upper opening of the finished conduit is flush with the upper opening of the steel reinforcement cage of the pile body, and the lower opening is closed and is not less than 0.5m away from the bottom of the pile.
After foundation pile pore-forming, hoist and put aforementioned steel reinforcement cage of installing double-deck guide tube of loosing core 1, transfer the process and need at the uniform velocity slowly, avoid the steel reinforcement cage to produce the lateral oscillations and cause the pore wall to collapse. If the steel reinforcement cage is completed by adopting a process of hoisting and welding, the double-layer core-pulling guide pipe 1 is also hoisted and connected with the steel reinforcement cage synchronously and sectionally, and the verticality of the steel reinforcement cage and the guide pipe needs to be ensured in the connection process respectively.
And (4) pouring concrete into the foundation pile after hoisting is finished, wherein the concrete guide pipe is not contacted with the composite core-pulling guide pipe 1 in the pouring process, and no concrete is required in the composite core-pulling guide pipe 1 after pouring is finished.
After the foundation pile concrete is finally condensed, the outer layer PVC pipe 2 of the double-layer core-pulling catheter 1 is kept as a core-pulling channel, and the recyclable hollow steel pipe 3 is connected by a thread external thread lifting tool matched with a thread of the recyclable hollow steel pipe and then is hoisted and pulled out in sections for recycling for secondary use.
The core sample with the length not less than 2.0m from the pile end section to the position below the bearing layer is drilled through the core-pulling channel, the drill bit extends into the core-pulling guide pipe to the pile bottom, the core sample at the pile end section is drilled from the lower opening of the guide pipe to detect the sediment thickness and the concrete pouring quality, and due to the guiding effect of the core-pulling guide pipe, the core sample needing to be drilled is short in length and accurate in position, so that the phenomenon of deviation of long-distance core drilling is avoided, the core drilling efficiency is improved, and the core drilling material, time and cost are saved.
And if the core sample shows that the thickness of the sediment at the pile end and the quality of the concrete are qualified, the core drilling hole and the core pulling channel are plugged by the poured cement paste.
If the core sample shows that the thickness of the sediment at the pile end is too large or the concrete pouring quality is poor, the guide pipe and the drilled core hole are used as a post-grouting guide pipe, and a high-pressure grouting pipe is arranged to perform post-grouting reinforcement on the pile end. The concrete method is that low-pressure grouting M35 cement mortar with the pressure of 0.2-0.5 MPa is adopted until the grouting is full, secondary pressure grouting is carried out after the low-pressure grouting is finished for 24 hours, the grouting material is pure cement slurry, the water cement ratio is 0.5-0.6, the grouting pressure is 1.0 MPa, and the channel is sealed and filled by clean slurry after the grouting reinforcement is finished.

Claims (9)

1. The utility model provides a device for detecting heavy diameter deep and long foundation pile sediment thickness and back slip casting reinforcement, characterized by: including installing double-deck pipe (1) of loosing core in pile body steel reinforcement cage, and pile body steel reinforcement cage and double-deck pipe (1) of loosing core are all installed in drilling (7), the top and the pile body steel reinforcement cage parallel and level of double-deck pipe (1) of loosing core, double-deck pipe (1) of loosing core includes outer PVC pipe (2) and installs recoverable hollow steel pipe (3) in outer PVC pipe (2) with one heart, and the bottom of outer PVC pipe (2) seals, concrete layer (6) have all been pour between the outer wall of outer PVC pipe (2) and the inner wall of drilling (7).
2. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 1, which is characterized in that: the outer layer PVC pipe (2) is formed by connecting a plurality of sections of PVC pipes through buckles.
3. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 2, wherein the device comprises: the recyclable hollow steel pipe (3) is formed by connecting a plurality of sections of steel pipes through threads.
4. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 1 or 3, which is characterized in that: and the inner wall of the outer layer PVC pipe (2) is filled with a lubricating reagent layer.
5. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 1 or 3, which is characterized in that: the pile body reinforcement cage comprises a spiral hoop (5) and a plurality of main reinforcements (4) welded in the spiral hoop (5).
6. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 1, which is characterized in that: the thickness of the outer layer PVC pipe (2) is not less than 4 mm.
7. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 1, which is characterized in that: the thickness of the recyclable hollow steel pipe (3) is not less than 4 mm.
8. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 5, wherein the device comprises: the outer wall of the outer PVC pipe (2) is provided with throat hoops (8) at intervals, and the throat hoops (8) and the spiral hoops (5) are fastened through reinforcing steel bars.
9. The device for detecting the sediment thickness and post-grouting reinforcement of the large-diameter deep and long foundation pile according to claim 1, which is characterized in that: the distance between the bottom of the multilayer core-pulling guide pipe (1) and the bottom of the drill hole (7) is not less than 0.5 m.
CN202120085257.7U 2021-01-13 2021-01-13 Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting Active CN214272166U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120085257.7U CN214272166U (en) 2021-01-13 2021-01-13 Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120085257.7U CN214272166U (en) 2021-01-13 2021-01-13 Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting

Publications (1)

Publication Number Publication Date
CN214272166U true CN214272166U (en) 2021-09-24

Family

ID=77791981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120085257.7U Active CN214272166U (en) 2021-01-13 2021-01-13 Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting

Country Status (1)

Country Link
CN (1) CN214272166U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931239A (en) * 2021-10-29 2022-01-14 山东省交通规划设计院集团有限公司 Device and method for detecting quality of pile body of bridge squeezing and expanding supporting disc pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931239A (en) * 2021-10-29 2022-01-14 山东省交通规划设计院集团有限公司 Device and method for detecting quality of pile body of bridge squeezing and expanding supporting disc pile
CN113931239B (en) * 2021-10-29 2023-08-25 山东省交通规划设计院集团有限公司 Device and method for detecting pile disc quality of bridge extrusion-expansion support disc

Similar Documents

Publication Publication Date Title
CN100575618C (en) Construction method of opening locked steel tube pilecofferdam
CN109083183A (en) Collapsible loess super long large diameter pile foundation churning driven expires hole mud wet process pore-forming technique
CN106761474A (en) A kind of the full-sleeve engineering method steel sleeve and its construction method of the soil that can actively muck haulage
CN214272166U (en) Device for detecting sediment thickness of large-diameter deep and long foundation pile and reinforcing through post-grouting
CN111364444A (en) Shallow-buried rock stratum section diaphragm wall grooving construction method
CN110777775A (en) Foundation pit structure and construction method thereof
CN113481973A (en) Construction method of steel pipe pile of subway station
CN102041806A (en) Construction method for inserting steel column in bored pile
CN109083181A (en) Collapsible loess super long large diameter pile foundation churning driven half bore mud wet process pore-forming technique
CN112301995A (en) Prefabricated composite reinforcement structure serving as precipitation grouting channel and construction method
CN1102188C (en) Construction method and equipment for continuous underground wall
CN111749231A (en) Double-sleeve double-drive full-rotation pile forming device and pile forming process
CN110820728A (en) Cast-in-situ bored pile construction method for penetrating underground deep-buried waste pipeline
CN201296932Y (en) Segmentation prefabricating sunken outer wall and guide wall thereof
CN116084393A (en) Construction method of bored pile
CN206581314U (en) Screw head muscle body posttension pile foundation
CN111733803B (en) Dry operation one-column one-pile steel pipe composite pile concrete subsection construction method
CN113931179A (en) Anchor cable pore-forming and grouting construction method
CN212688926U (en) Resistance to plucking device suitable for precast tubular pile
CN114277786A (en) High-strength concrete bearing body, pressure type anti-floating pile and construction method
CN209722952U (en) Pile foundation provisions for grouting
CN113026801A (en) Construction method for reinforcing steel pipe pile of construction elevator foundation
CN213805307U (en) Prefabricated composite reinforcement body structure used as precipitation grouting channel
CN217267482U (en) Simple and easy drilling bored concrete pile post-grouting device based on flexible slip casting pipe
CN216379675U (en) Core-pulling guide tube for foundation pile core drilling detection

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 730070 no.516, Beibinhe West Road, Anning District, Lanzhou City, Gansu Province

Patentee after: Gansu Academy of Building Sciences (Group) Co.,Ltd.

Address before: 730070 no.516, Beibinhe West Road, Anning District, Lanzhou City, Gansu Province

Patentee before: Gansu Academy of Building Science Co.,Ltd.