CN214246330U - Basement vertical component reinforcing bar construction structures - Google Patents
Basement vertical component reinforcing bar construction structures Download PDFInfo
- Publication number
- CN214246330U CN214246330U CN202022351665.0U CN202022351665U CN214246330U CN 214246330 U CN214246330 U CN 214246330U CN 202022351665 U CN202022351665 U CN 202022351665U CN 214246330 U CN214246330 U CN 214246330U
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- vertical
- steel bar
- bar
- basement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Foundations (AREA)
Abstract
The utility model relates to a vertical component steel bar construction structures of basement, including concrete slab, roof beam and the vertical reinforcing bar of structure, concrete slab is connected with the roof beam, and the vertical reinforcing bar of structure is connected with concrete slab, and the vertical reinforcing bar of structure is provided with a plurality of, a plurality of be connected with interim fixed steel bar on the vertical reinforcing bar of structure, the vertical reinforcing bar of structure is provided with the mounting with the junction of interim fixed steel bar. The utility model discloses the main objective adopts reinforcing bar cross clamp can make the junction temporary fixation of the vertical reinforcing bar of structure and temporary fixation reinforcing bar, guarantees workman construction safety nature, and convenient to use has shortened the engineering time, improves the efficiency of construction, improves the vertical component reinforcing bar construction shaping quality of basement.
Description
Technical Field
The utility model relates to a basement vertical member reinforcing bar construction quality control technical research technical field specifically is a basement vertical member reinforcing bar construction structures.
Background
Because construction process's characteristics, during basement vertical component steel bar construction, the conventional way is that the back is welded to the vertical reinforcing bar of structure, binds with the stirrup, and its structure is very insecure, and some connect it through electroslag pressure welding, but, after long-time the back, the condition of freely scattering appears in it easily, causes constructor injured's condition easily, and factor of safety is lower, is difficult to satisfy staff's demand.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a vertical component steel bar construction structures of basement adopts reinforcing bar cross clamp can make the junction temporary fixation of the vertical reinforcing bar of structure and temporary fixation reinforcing bar, guarantees workman construction safety nature, and convenient to use has shortened the engineering time, improves the efficiency of construction, improves the vertical component steel bar construction shaping quality of basement.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a basement vertical component steel bar construction structure, includes concrete slab, roof beam and the vertical reinforcing bar of structure, and concrete slab is connected with the roof beam, and the vertical reinforcing bar of structure is connected with concrete slab, and the vertical reinforcing bar of structure is provided with a plurality of, a plurality of be connected with the interim fixed steel bar on the vertical reinforcing bar of structure, the vertical reinforcing bar of structure is provided with the mounting with the junction of interim fixed steel bar.
Preferably, the fixing piece is a steel bar cross-shaped hoop.
Preferably, the reinforcing bar cross clamp is provided with a plurality of, and installs respectively the junction of the vertical reinforcing bar of structure and interim fixed steel bar.
Preferably, the inside hollow groove that is provided with of reinforcing bar cross clamp, the vertical reinforcing bar of structure and temporary fixation reinforcing bar joint are in hollow groove.
Preferably, the diameter of the hollow groove is larger than the diameter of the structural vertical steel bar and the diameter of the temporary fixing steel bar.
Preferably, a plurality of the structural vertical steel bars are connected together through electroslag pressure welding.
(III) advantageous effects
Compared with the prior art, the utility model provides a vertical component reinforcing bar construction structures of basement possesses following beneficial effect:
the utility model provides a basement vertical component reinforcing bar construction structures, the main objective adopts reinforcing bar cross clamp can make the junction temporary fixation of structure vertical steel bar and temporary fixation reinforcing bar, guarantees workman construction safety nature, and convenient to use has shortened the engineering time, improves the efficiency of construction, improves basement vertical component reinforcing bar construction shaping quality.
Drawings
Fig. 1 is a front view of a reinforcing steel bar construction structure of a vertical component of a basement;
figure 2 is the utility model relates to a structural schematic of reinforcing bar cross clamp among basement vertical component reinforcing bar construction structures.
In the figure: 1. structural vertical steel bars; 2. temporarily fixing the steel bars; 3. a concrete slab; 4. a beam; 5. a steel bar cross hoop; 6. a hollow groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example (b):
please refer to fig. 1-2, which is a reinforced bar construction structure of a vertical component of a basement, and includes a concrete slab 3, a beam 4 and a structural vertical reinforced bar 1, wherein the concrete slab 3 is connected to the beam 4, the structural vertical reinforced bar 1 is connected to the concrete slab 3, the structural vertical reinforced bar 1 is provided with a plurality of reinforced bars, the structural vertical reinforced bars 1 are connected to temporary fixed reinforced bars 2, and a fixing member is arranged at a connection position of the structural vertical reinforced bars 1 and the temporary fixed reinforced bars 2.
In this embodiment, the fixing member is a reinforcement cross clip 5. Thereby allowing for better use of the fastener.
In this embodiment, reinforcing bar cross clamp 5 is provided with a plurality of, and installs respectively the junction of structure vertical reinforcement 1 and interim fixed steel bar 2. Further improve the fastness of structure vertical reinforcement and interim fixed steel bar connection.
In this embodiment, inside hollow groove 6 that is provided with of reinforcing bar cross clamp 5, the vertical reinforcing bar of structure 1 and reach the joint of temporary fixation reinforcing bar 2 in hollow groove 6. Can effectively block the junction of structure vertical reinforcement 1 and interim fixed steel bar 2 through hollow groove 6.
In this embodiment, the diameter of the hollow groove 6 is larger than the diameter of the structural vertical steel bar 1 and the temporary fixing steel bar 2. Can effectively block the junction of structure vertical reinforcement 1 and interim fixed steel bar 2, convenient to use, durable avoids structure vertical reinforcement 1 to freely scatter because of the overlength and causes the phenomenon emergence of constructor injury.
In this embodiment, several of the structural vertical steel bars 1 are connected together by electroslag pressure welding. Further improving the firmness.
The construction technology comprises the following steps:
the method comprises the following steps: welding the vertical component steel bars 1 by electroslag pressure welding, arranging temporary fixing steel bars 2 at intervals along the outer sides of the vertical component steel bars 1, and firmly fixing the connecting parts of the structural vertical steel bars 1 and the temporary fixing steel bars 2 by using a steel bar cross clamp 5 to form integral rigidity and avoid displacement;
step two: then use reinforcing bar cross clamp 5 firmly to fix the connection position of structure vertical reinforcement 1 and interim fixed steel bar 2, form the bulk rigidity, avoid shifting, the inside hollow groove 6 diameter of reinforcing bar cross clamp 5 slightly is greater than the diameter of vertical member reinforcing bar 1, can effectively block the junction of structure vertical reinforcement 1 and interim fixed steel bar 2, convenient to use, durable avoids structure vertical reinforcement 1 to freely scatter because the overlength and cause the phenomenon of constructor injury to take place.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a basement vertical component steel bar construction structure, includes concrete slab, roof beam and the vertical reinforcing bar of structure, and concrete slab is connected with the roof beam, and the vertical reinforcing bar of structure is connected with concrete slab, and the vertical reinforcing bar of structure is provided with a plurality of, its characterized in that, a plurality of be connected with interim fixed steel bar on the vertical reinforcing bar of structure, the vertical reinforcing bar of structure is provided with the mounting with the junction of interim fixed steel bar.
2. The basement vertical member steel bar construction structure of claim 1, characterized in that: the fixing piece is a steel bar cross hoop.
3. The basement vertical member steel bar construction structure of claim 2, characterized in that: the reinforcing bar cross clamp is provided with a plurality of, and installs respectively the junction of the vertical reinforcing bar of structure and interim fixed steel bar.
4. The basement vertical member steel bar construction structure of claim 3, characterized in that: the inside hollow groove that is provided with of reinforcing bar cross clamp, the vertical reinforcing bar of structure and temporary fixation reinforcing bar joint are in hollow groove.
5. The basement vertical member steel bar construction structure of claim 4, characterized in that: the diameter of the hollow groove is larger than the diameter of the structural vertical reinforcing steel bar and the diameter of the temporary fixing reinforcing steel bar.
6. The basement vertical member steel bar construction structure of claim 1, characterized in that: and a plurality of the structural vertical steel bars are connected together through electroslag pressure welding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022351665.0U CN214246330U (en) | 2020-10-21 | 2020-10-21 | Basement vertical component reinforcing bar construction structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022351665.0U CN214246330U (en) | 2020-10-21 | 2020-10-21 | Basement vertical component reinforcing bar construction structures |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214246330U true CN214246330U (en) | 2021-09-21 |
Family
ID=77729818
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022351665.0U Active CN214246330U (en) | 2020-10-21 | 2020-10-21 | Basement vertical component reinforcing bar construction structures |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214246330U (en) |
-
2020
- 2020-10-21 CN CN202022351665.0U patent/CN214246330U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103603494B (en) | A kind of ultra-thin steel truss sloping core construction method and formwork structure | |
CN214246330U (en) | Basement vertical component reinforcing bar construction structures | |
CN113585550A (en) | Concrete wall with restrained shear-resistant ribs and hook connecting nodes and construction method | |
CN207794090U (en) | Inner supporting device for pattern foundation pit supporting structure | |
CN214696793U (en) | Climb and shelve superelevation and spring layer extension and adhere to support | |
CN218990617U (en) | Assembled superimposed sheet for building engineering | |
CN204753819U (en) | Take tree -like supporting grid structure of secondary branching of prestressing force | |
CN204850044U (en) | Prefabricated post and composite beam combination department node structure | |
CN208073013U (en) | A kind of anti-offset positioning supporting frame of prestressing force bellows positioning | |
CN211735808U (en) | Girder and crossbeam connection structure of H shaped steel concrete | |
CN210713765U (en) | Wall connecting piece for special-shaped curtain wall building scaffold | |
CN110439155B (en) | Point type curtain wall structure of diamond section daylighting roof | |
CN212671009U (en) | Steel bar connecting piece truss and application pouring structure thereof | |
CN110424580B (en) | Process for manufacturing shear wall by using mould-disassembly-free maintenance system | |
CN112593657A (en) | Manufacturing method of large-span light beam | |
CN209538483U (en) | The mounting structure of energy-saving curtain wall | |
CN202124934U (en) | Connecting device for reinforced concrete beam and shear wall | |
CN106193456A (en) | A kind of high-layer shear force wall reinforcing steel bar Exact Location Method and truss strength fixing device | |
CN203684722U (en) | Strengthening tool for steel columns of independent columns | |
CN110878591A (en) | Girder and crossbeam connection structure of H shaped steel concrete | |
CN212897596U (en) | Novel back ridge connecting assembly and template assembly thereof | |
CN218346407U (en) | Flexural steel member reinforced structure | |
CN211572254U (en) | Easily-disassembled stirrup | |
CN208415923U (en) | A kind of frame column support shuttering and support construction | |