High pier stud concrete curing means of bridge Download PDF

Info

Publication number
CN214219400U
CN214219400U CN202022963870.2U CN202022963870U CN214219400U CN 214219400 U CN214219400 U CN 214219400U CN 202022963870 U CN202022963870 U CN 202022963870U CN 214219400 U CN214219400 U CN 214219400U
Authority
CN
China
Prior art keywords
water
high pier
storage barrel
pier stud
water pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022963870.2U
Other languages
Chinese (zh)
Inventor
贺建宏
殷玉彬
汪家雄
郝各贵
苗永军
张泽文
薛云观
戴少波
胥皓文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction and Investment Holding Group Co Ltd
Original Assignee
Yunnan Construction and Investment Holding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Construction and Investment Holding Group Co Ltd filed Critical Yunnan Construction and Investment Holding Group Co Ltd
Priority to CN202022963870.2U priority Critical patent/CN214219400U/en
Application granted granted Critical
Publication of CN214219400U publication Critical patent/CN214219400U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a high pier stud concrete curing means of bridge, includes: the water storage and storage device comprises a bracket, a water storage and storage barrel, a water pipe, a valve, a water injector and a supporting plate; the support consists of four upright posts, two cross rods and a support plate; the four upright posts are vertically fixed on two sides of the middle high pier stud concrete, the two cross rods are horizontally fixed on the upright posts, and the support plate is fixed on the two cross rods; the water storage barrel is fixedly arranged on the support plate of the bracket; the water injector is arranged at the top of the water storage barrel; the valve is arranged between the water injector and the water storage barrel; two water pipes are arranged and are respectively arranged at two sides of the water storage barrel; one end of the water pipe is communicated with the water storage barrel through a water pipe joint, and the other end of the water pipe is closed; the bottom of the water pipe is provided with a water spray hole at the position corresponding to the concrete of each high pier stud; the backup pad is vertical to be set up between two adjacent high pier stud concretes. The utility model can automatically carry out maintenance operation, saves labor and improves working efficiency; the utility model discloses still can have enough to meet the need the use.

Description

High pier stud concrete curing means of bridge
Technical Field
The utility model belongs to the technical field of bridge engineering concrete maintenance, concretely relates to high pier stud concrete curing means of bridge.
Background
In the prior art, a manual watering and curing method is mostly adopted for concrete piers of road and bridge engineering. Because concrete piers are all higher, manual watering and maintenance consume a large amount of water resources and correspondingly higher labor cost. The problems of improper and untimely maintenance and unavoidable floor drain can occur when manual watering is adopted, and the manual operation efficiency is low. If the concrete pier stud is not maintained timely, after the surface of the concrete is dehydrated, the hydration reaction of the cement is stopped, and the surface is dried and shrunk; under the effect of shrinkage stress, the concrete structure can produce the crack, influences the safety and the normal use of structure, can reduce the quality and the life of pier.
Disclosure of Invention
Based on the not enough of above-mentioned prior art, the utility model provides a high pier stud concrete curing means of bridge for solve the water waste that artifical watering curing concrete pier stud appears and the high problem of cost of labor.
The utility model discloses a following technical scheme realizes:
the utility model provides a high pier stud concrete curing means of bridge, includes: the water storage and storage device comprises a bracket, a water storage and storage barrel, a water pipe, a valve, a water injector and a first supporting plate; wherein the content of the first and second substances,
the support consists of four upright posts, two cross rods and a second support plate; the four upright posts are vertically fixed on two sides of the middle high pier stud concrete, the two cross rods are horizontally fixed on the upright posts, and the second support plate is fixed on the two cross rods;
the water storage barrel is fixedly arranged on a second support plate of the bracket; the water injector is arranged above the water storage barrel and is communicated with a tap water pipe; the valve is arranged between the water injector and the water storage barrel;
the two water pipes are respectively arranged on two sides of the water storage barrel; one end of the water pipe is communicated with the water storage barrel through a water pipe joint, and the other end of the water pipe is closed; the bottom of the water pipe is provided with a water spray hole at the position corresponding to the concrete of each high pier stud;
a backup pad is vertical to be set up between two adjacent high pier stud concretes for support the water pipe.
Preferably, a semicircular groove is formed in the top of the first support plate.
Preferably, the distance between the water pipe joint and the bottom of the water storage barrel is greater than 2 cm.
Preferably, the water pipe is horizontally placed on the first support plate or is placed on the first support plate at an inclination angle not greater than 5 °.
Preferably, a reinforcing rib is additionally arranged between the upright post and the cross bar or between the two cross bars.
Preferably, the bottom of the water pipe is provided with at least one water-sprinkling hole corresponding to the position of each high pier column concrete.
Has the advantages that: the utility model can automatically carry out maintenance operation, saves manpower, improves working efficiency, avoids the problems of improper and untimely manual maintenance, and saves water resources; the utility model discloses still can have enough to meet the need the use, reduce construction cost.
Drawings
FIG. 1 is a schematic view of the present invention;
fig. 2 is a top view of the bracket of the present invention;
fig. 3 is a schematic view of the support plate of the present invention.
Detailed Description
Embodiments of the present invention will now be described with reference to the accompanying drawings. It will be appreciated by those skilled in the art that the following examples are illustrative of the invention only and should not be taken as limiting the scope of the invention. In the embodiments, specific techniques, connection relationships, or conditions are not specified, and are performed according to the techniques, connection relationships, or conditions described in the literature in the art or according to the product specification, and are not described herein again. The materials, instruments or equipment are not indicated by manufacturers, and all the materials, instruments or equipment are conventional products which can be obtained by purchasing.
The structure of the present invention will be described with reference to the accompanying drawings.
Combine fig. 1-fig. 3 to show, the utility model discloses a high pier stud concrete curing means of bridge, include: the water storage and storage device comprises a bracket 1, a water storage barrel 2, a water pipe 3, a valve 4, a water injector 5 and a first supporting plate 6; wherein the content of the first and second substances,
the support 1 consists of four upright posts 11, two cross rods 12 and a second support plate 13; the four upright posts 11 are vertically fixed on two sides of the middle high pier stud concrete 8, the two cross rods 12 are horizontally fixed on the upright posts 11, and the second support plate 13 is fixed on the two cross rods 12; reinforcing ribs 14 are additionally arranged between the upright post 11 and the cross bars 12 or between the two cross bars 12;
the water storage barrel 2 is fixedly arranged on a second support plate 13 of the bracket 1; the water injector 5 is arranged above the water storage barrel 2 and is communicated with a tap water pipe; the valve 4 is arranged between the water injector 5 and the water storage barrel 2;
two water pipes 3 are arranged and are respectively arranged at two sides of the water storage barrel 2; one end of the water pipe 3 is communicated with the water storage barrel 2 through a water pipe joint 7, and the other end is closed; the distance between the water pipe joint 7 and the bottom of the water storage barrel 2 is more than 2 cm; the bottom of the water pipe 3 is provided with water dispersion holes 31 at the positions corresponding to each high pier stud concrete, and the number of the water dispersion holes 31 at the positions corresponding to each high pier stud concrete is at least one;
the first supporting plate 6 is vertically arranged between two adjacent high pier stud concretes and used for supporting the water pipe 3; a semicircular groove 61 is formed in the top of the first supporting plate 6 and used for placing the water pipe 3 and further supporting and fixing the water pipe 3.
Further, water pipe 3 level is placed in backup pad 6, as shown in fig. 1, or is placed in backup pad 6 with inclination that is not more than 5 °.
The utility model arranges the water storage barrel above the middle pier column (or the highest pier column) of a row of piers, and connects water pipes at the two sides of the water storage barrel, the two water pipes pass through each pier column at the two sides below the water storage barrel in sequence, and the water distribution holes are arranged at the positions corresponding to the pier columns of the two water pipes; because the water storage barrel is positioned at a higher position, water can flow to two sides along the water pipe under the action of gravity, and the water can flow to the pier column below the water storage barrel when passing through the water dispersion holes, thereby achieving the purpose of pier water dispersion maintenance.
The utility model can effectively maintain the moisture on the surface of the concrete in an automatic water dispersion maintenance mode, avoid the water loss condition on the surface of the concrete and prolong the service life of the pier; the whole water dispersing process is automatically carried out, so that the manpower and water resources are saved, and the working efficiency is also improved; the utility model discloses with low costs, efficient, safe and reliable is applicable to various pier concrete curing. The utility model discloses can also used repeatedly, reduce construction cost.
The above disclosure is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the scope of the invention, therefore, the invention is not limited thereto.

Claims (6)

1. The utility model provides a high pier stud concrete curing means of bridge which characterized in that includes: the water storage and storage device comprises a bracket (1), a water storage and storage barrel (2), a water pipe (3), a valve (4), a water injector (5) and a first supporting plate (6); wherein the content of the first and second substances,
the support (1) consists of four upright posts (11), two cross rods (12) and a second support plate (13); four upright posts (11) are vertically fixed on two sides of the middle high pier stud concrete (8), two cross rods (12) are horizontally fixed on the upright posts (11), and a second support plate (13) is fixed on the two cross rods (12);
the water storage barrel (2) is fixedly arranged on a second support plate (13) of the bracket (1); the water injector (5) is arranged above the water storage barrel (2) and is communicated with a tap water pipe; the valve (4) is arranged between the water injector (5) and the water storage barrel (2);
two water pipes (3) are arranged and are respectively arranged at two sides of the water storage barrel (2); one end of the water pipe (3) is communicated with the water storage barrel (2) through a water pipe joint (7), and the other end is closed; the bottom of the water pipe (3) is provided with a water spray hole (31) at the position corresponding to each high pier column concrete;
a backup pad (6) vertical setting is between two adjacent high pier stud concretes for support water pipe (3).
2. The high pier stud concrete curing means of bridge of claim 1, characterized in that: the top of the first support plate (6) is provided with a semicircular groove (61).
3. The high pier stud concrete curing means of bridge of claim 1, characterized in that: the distance between the water pipe joint (7) and the bottom of the water storage barrel (2) is more than 2 cm.
4. The high pier stud concrete curing means of bridge of claim 1, characterized in that: the water pipe (3) is horizontally arranged on the first supporting plate (6) or is arranged on the first supporting plate (6) at an inclination angle not larger than 5 degrees.
5. The high pier stud concrete curing means of bridge of claim 1, characterized in that: reinforcing ribs (14) are additionally arranged between the upright posts (11) and the cross bars (12) or between the two cross bars (12).
6. The high pier stud concrete curing means of bridge of claim 1, characterized in that: at least one water spray hole (31) is arranged at the bottom of the water pipe (3) and at the position corresponding to the concrete of each high pier column.
CN202022963870.2U 2020-12-08 2020-12-08 High pier stud concrete curing means of bridge Active CN214219400U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022963870.2U CN214219400U (en) 2020-12-08 2020-12-08 High pier stud concrete curing means of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022963870.2U CN214219400U (en) 2020-12-08 2020-12-08 High pier stud concrete curing means of bridge

Publications (1)

Publication Number Publication Date
CN214219400U true CN214219400U (en) 2021-09-17

Family

ID=77701658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022963870.2U Active CN214219400U (en) 2020-12-08 2020-12-08 High pier stud concrete curing means of bridge

Country Status (1)

Country Link
CN (1) CN214219400U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113653350A (en) * 2021-09-18 2021-11-16 国网山东省电力公司建设公司 Concrete pier post watering curing means

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113653350A (en) * 2021-09-18 2021-11-16 国网山东省电力公司建设公司 Concrete pier post watering curing means
CN113653350B (en) * 2021-09-18 2023-03-10 国网山东省电力公司建设公司 Concrete pier post watering curing means

Similar Documents

Publication Publication Date Title
CN201567532U (en) Novel supporting structure of lid beam of bridge
CN211517947U (en) Bridge case roof beam is prefabricated with shaped steel pedestal
CN214219400U (en) High pier stud concrete curing means of bridge
CN110965474A (en) Construction method of cable tower cross beam
CN205691411U (en) A kind of railway concrete simply supported beam static test reaction frame
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN206428588U (en) A kind of road bridge construction prestressed anchor
CN210066504U (en) Large-span cantilever truss type bent cap support system
CN206800200U (en) A kind of pier stud capping beam template support meanss
CN214938931U (en) High-strength compression-resistant concrete pavement structure of wharf storage yard
CN112962427A (en) Off-standard span cast-in-place beam support across valley and construction method
CN112127282B (en) Main pier steel structure of super bridge
CN105064159B (en) A kind of concrete road of Fast Installation
CN211228129U (en) Prefabricated roof beam hoist and mount hole block structure of assembling of festival section
CN209924121U (en) Independent supporting structure for assembly type building construction
CN113982262A (en) Beam bottom support and template support system of cast-in-place concrete frame structure and assembly method
CN214419109U (en) Pre-tensioning method T-shaped beam tensioning pedestal
CN211480873U (en) Suspension protection device for underground existing telecommunication pipe block
CN220364865U (en) Integral cast-in-situ concrete bracket structure
CN209466399U (en) A kind of assembling type steel structure beam making bench
CN210066497U (en) Prefabricated I-beam side-span bridge deck pavement formwork support device
CN205296579U (en) Combination reinforcing bar girder construction
CN215405540U (en) Off-standard span cast-in-place beam support strides valley
CN109594718A (en) The assembled steel reinforced concrete column of prefabricated standard assembly piece and application the assembly piece
CN220247720U (en) Socket-type disc buckle type steel pipe scaffold beam bottom supporting system conversion device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant