CN214195596U - Fixing device of intelligent building beam column manufacturing equipment - Google Patents

Fixing device of intelligent building beam column manufacturing equipment Download PDF

Info

Publication number
CN214195596U
CN214195596U CN202022669881.XU CN202022669881U CN214195596U CN 214195596 U CN214195596 U CN 214195596U CN 202022669881 U CN202022669881 U CN 202022669881U CN 214195596 U CN214195596 U CN 214195596U
Authority
CN
China
Prior art keywords
vertical
fixing device
inner cavity
building beam
manufacturing equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022669881.XU
Other languages
Chinese (zh)
Inventor
焦心飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
AIA Zhumei Cultural Construction (Liaoning) Co.,Ltd.
Original Assignee
Shenyang Aia Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Aia Decoration Engineering Co ltd filed Critical Shenyang Aia Decoration Engineering Co ltd
Priority to CN202022669881.XU priority Critical patent/CN214195596U/en
Application granted granted Critical
Publication of CN214195596U publication Critical patent/CN214195596U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a fixing device of intelligent building beam column manufacturing equipment, which belongs to the field of fixing devices of intelligent building beam column manufacturing equipment and comprises a vertical baffle, wherein an inner cavity is arranged inside the vertical baffle, a vertical splint is movably arranged inside the inner cavity, an inner hollow clamping block is welded on the side surface of one end of the vertical splint, a screw rod is movably sleeved inside the inner hollow clamping block, the other end of the screw rod penetrates through the middle part of one side of the vertical baffle, a spring is fixedly arranged inside the other side of the vertical splint, a bearing rod is fixedly and movably arranged at one end of the spring, a hinge rod is hinged inside one end of the bearing rod, the hinge rod is fixedly arranged inside the vertical splint, and the fixing device of the intelligent building beam column manufacturing equipment can limit and clamp stirrups with different diameters, the construction cost is reduced, and the labor intensity of workers is reduced.

Description

Fixing device of intelligent building beam column manufacturing equipment
Technical Field
The utility model relates to a fixing device field of building beam column manufacture equipment, more specifically say, relate to a fixing device of intelligent manufacture equipment of building beam column.
Background
In the existing technology for assembling building beam columns, the required beam column components are manufactured by pouring concrete. In the process of building the beam steel bar, the column longitudinal bar and the transverse column stirrup of the beam steel bar need to be bound together, but in construction, the stirrup of the beam steel bar can fall into the template integrally, the stirrup needs to be positioned by the fixture firstly, so that the movement of the stirrup is prevented, and then the ribs and the reinforcing bars are installed. And finally, binding the main reinforcements, the auxiliary reinforcements and the stirrups together to form the beam steel bar support frame.
And the spacing reinforcing bar group among foretell stirrup location fixture can only fix a position and the centre gripping to a stirrup, if need fix a position the stirrup of different diameters with when the centre gripping, need choose for use the location fixture of different diameters for use to carry on spacingly, so not only increase construction cost, but also increase staff's intensity of labour.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
To the problem that exists among the prior art, the utility model aims to provide a fixing device of intelligent manufacture equipment of building beam column, it can realize that this fixing device of intelligent manufacture equipment of building beam column can carry on spacingly and press from both sides tightly to the stirrup of different diameters, reduces construction cost, reduces staff's intensity of labour.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
A fixing device of intelligent building beam column manufacturing equipment comprises a vertical baffle, wherein a box body is fixedly installed on one side of the vertical baffle, an outer cavity is formed in the box body, a bottom plate is welded on the bottom surface of the box body, the vertical baffle is welded on one side of the upper surface of the bottom plate, an inner cavity is formed in the vertical baffle, a vertical clamping plate is movably installed in the inner cavity, an upper pulley and a lower pulley are fixedly installed at the top end and the bottom end of one side of the vertical clamping plate respectively, the upper pulley is movably installed at the top of the inner cavity, the lower pulley is movably installed on the upper surface of the bottom plate, a hollow clamping block is welded on one side face of one end of the vertical clamping plate, a spiral rod is movably sleeved in the hollow clamping block, the other end of the spiral rod penetrates through the middle part of one side of the vertical baffle in a threaded manner, a spring is fixedly installed in the other side of the vertical clamping plate, spring one end fixed movable mounting has the carrier bar, the inside of carrier bar one end is run through to articulate there is the hinge bar, hinge bar fixed mounting is in the inside of vertical splint, one side activity joint that the carrier bar is close to the hinge bar has the gag lever post, the gag lever post runs through the spiro union in vertical splint one side.
Furthermore, a first screw thread is formed in the side surface of the screw rod, the hollow clamping block is cylindrical, and the diameter of the cylinder protruding from one end of the screw rod is the same as the inner diameter of the hollow clamping block.
Furthermore, the diameter of the screw rod is smaller than the thickness of the inner cavity, and the diameter of the inner hollow fixture block is equal to the thickness of the inner cavity.
Furthermore, the second screw thread has been seted up to the gag lever post side surface, the diameter size of gag lever post is the same with the diameter size of carrier bar.
Furthermore, the limiting rods are all located on the same vertical line, the bearing rods are all located on the same vertical line, and the bearing rods corresponding to the opposite bearing rods are located at the same height.
Further, the length of the vertical clamping plate is smaller than the height of the inner cavity.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of:
(1) this scheme is through placing the inside of outer cavity with the stirrup that produces, place vertical splint in the both sides of beam reinforcement and carry out the distance adjustment, the user holds the screw pole with the hand and makes vertical splint take place the removal of horizontal direction, treat that the distance between the vertical splint transfers to the muscle and bone diameter the same back that will place, constructor can take out the muscle and bone from outer cavity the inside, put into the outside of beam reinforcement to the muscle and bone, can realize that this building beam column intelligent manufacture equipment's fixing device can carry on spacingly and pressing from both sides the stirrup of different diameters, construction cost is reduced, reduce staff's intensity of labour.
(2) The bearing rod can be turned and moved under the action of the hinge rod, so that the tendons and bones can be placed from top to bottom conveniently, after the tendons and bones placed at the bottom are placed on the bearing rod, a constructor holds the limiting rod with hands to rotate so that the limiting rod can be screwed, the screwing limiting rod can limit and fix the bearing rod, the bearing rod can keep horizontal fixation, the stirrups placed at the first are limited and fixed, and according to the same operation, the constructor can limit and fix the stirrups placed at the back in sequence, so that the tendons and bones cannot be overlapped or deformed in the house process, the process of adjusting the distance between column stirrups again is omitted, and the engineering efficiency is improved.
Drawings
Fig. 1 is a schematic top sectional view of the present invention;
FIG. 2 is a schematic sectional view of the front view of the present invention;
fig. 3 is a left side view structure diagram of the present invention;
FIG. 4 is a schematic sectional view of the present invention;
fig. 5 is a partial structural schematic view of a of the present invention;
fig. 6 is a schematic partial structure diagram of a component B of the present invention;
fig. 7 is a partial structural schematic diagram of the present invention C.
The reference numbers in the figures illustrate:
1. a box body; 2. an outer cavity; 3. a vertical baffle; 4. a screw rod; 5. a hollow clamping block; 6. a limiting rod; 7. a carrier bar; 8. a vertical splint; 9. a hinged lever; 10. a spring; 11. a bottom panel; 12. an upper pulley; 13. a lower pulley; 14. an inner cavity.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention; obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention based on the embodiments of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top/bottom", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "sleeved/connected", "connected", and the like are to be understood in a broad sense, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-7, the device comprises a vertical baffle 3, a box body 1 is fixedly installed on one side of the vertical baffle 3, an outer cavity 2 is formed in the box body 1, the outer cavity 2 is used for pre-installing stirrups required during construction and is convenient for constructors to take, a bottom plate 11 is welded on the bottom surface of the box body 1, the bottom plate 11 is used for ensuring better stability of the device, the vertical baffle 3 is welded on one side of the upper surface of the bottom plate 11, an inner cavity 14 is formed in the vertical baffle 3, a vertical clamping plate 8 is movably installed in the inner cavity 14, an upper pulley 12 and a lower pulley 13 are respectively fixedly installed at the top end and the bottom end of one side of the vertical clamping plate 8, the two pulleys provide sliding force for the vertical clamping plate 8, the upper pulley 12 is movably installed at the top of the inner cavity 14, the lower pulley 13 is movably installed on the upper surface of the bottom plate 11, and a clamping block 5 is welded on one side surface of the vertical clamping plate 8, the spiral shell pole 4 has been cup jointed in the inside activity of interior hollow fixture block 5, the spiral shell pole 4 other end runs through the spiro union at 3 one side middle parts of vertical baffle, because spiral shell pole 4 is the screw thread spiro union with the lateral wall of vertical baffle 3, so spiral shell pole 4 not only provides the drive force but also provides stable power for vertical splint 8, the inside fixed mounting of 8 opposite sides of vertical splint has spring 10, the fixed movable mounting of 10 one end of spring has carrier bar 7, spring 10 provides answer elasticity for carrier bar 7, the inside of 7 one ends of carrier bar runs through to articulate has hinge bar 9, hinge bar 9 fixed mounting is in the inside of vertical splint 8, hinge bar 9 is the back shaft of carrier bar 7, one side activity joint that carrier bar 7 is close to hinge bar 9 has gag lever post 6, gag lever post 6 runs through the spiro union in vertical splint 8 one side, it keeps fixedly in order to make carrier bar 7.
Specifically, first screw thread has been seted up to 4 side surfaces of spiral shell movable rod, and interior hollow fixture block 5 is cylindricly, and the bellied cylinder diameter size of 4 one ends of spiral shell movable rod is the same with interior hollow fixture block 5's internal diameter size, guarantees when the spiral promotes spiral shell movable rod 4, and vertical splint 8 keeps the stability of removal.
Specifically, the diameter of the screw rod 4 is smaller than the thickness of the inner cavity 14, and the diameter of the inner hollow fixture block 5 is equal to the thickness of the inner cavity 14, so that the screw rod 4 can be screwed conveniently.
Specifically, the second screw thread has been seted up to the 6 side surfaces of gag lever post, and the diameter size of gag lever post 6 is the same with the diameter size of carrier bar 7, makes things convenient for gag lever post 6 to carry out spacing joint to carrier bar 7.
Specifically, gag lever post 6 all is located same plumb line, and carrier bar 7 and opposite carrier bar 7 that correspond are located same height, guarantee homogeneity and stability that the stirrup of beam reinforcement side was tied up.
Specifically, the length of the vertical clamping plate 8 is smaller than the height of the inner cavity 14, and a space is reserved for installing pulleys at the upper end and the lower end of one side of the vertical clamping plate 8.
When in use: the produced stirrups are placed in the outer cavity 2, the vertical clamping plates 8 are placed on two sides of the beam reinforcing steel bar for distance adjustment, a user holds the screw rod 4 by hand to enable the vertical clamping plates 8 to move in the horizontal direction, after the distance between the vertical clamping plates 8 is adjusted to be the same as the diameter of a tendon to be placed, a constructor can take the tendon out of the outer cavity 2 and place the tendon into the outer side of the beam reinforcing steel bar, the fixing device of the intelligent building beam column manufacturing equipment can limit and clamp the stirrups with different diameters, construction cost is reduced, labor intensity of the constructor is reduced, the bearing rod 7 can turn over and move under the action of the hinge rod 9, the tendon can be conveniently placed from top to bottom, after the tendon placed firstly is placed on the bearing rod 7 at the bottom layer, the constructor holds the limiting rod 6 by hand to rotate so as to enable the limiting rod to screw, spiral precession gag lever post 6 will bear futilely 7 and carry out spacing fixed, bear futilely 7 will keep the level fixed, the stirrup of placing at first this moment is by spacing fixed, according to same operation, constructor can carry out spacing fixed to the stirrup of putting into after in proper order, make the muscles and bones can not produce the coincide or warp at the house in-process, the process of adjusting the distance between post stirrup once more has been saved, the engineering efficiency is improved, the convenience is binded roof beam reinforcing bar and stirrup, to next roof beam reinforcing bar as required, operation more than the repetition can.
The above description is only the preferred embodiment of the present invention; the scope of the present invention is not limited thereto. Any person skilled in the art should also be able to cover the technical scope of the present invention by replacing or changing the technical solution and the improvement concept of the present invention with equivalents and modifications within the technical scope of the present invention.

Claims (6)

1. The utility model provides a fixing device of intelligent manufacture equipment of building beam column, includes vertical baffle (3), its characterized in that: the improved structure is characterized in that a box body (1) is fixedly mounted on one side of a vertical baffle (3), an outer cavity (2) is formed in the box body (1), a bottom panel (11) is welded on the bottom surface of the box body (1), the vertical baffle (3) is welded on one side of the upper surface of the bottom panel (11), an inner cavity (14) is formed in the vertical baffle (3), a vertical clamping plate (8) is movably mounted in the inner cavity (14), an upper pulley (12) and a lower pulley (13) are fixedly mounted at the top end and the bottom end of one side of the vertical clamping plate (8) respectively, the upper pulley (12) is movably mounted at the top of the inner cavity (14), the lower pulley (13) is movably mounted on the upper surface of the bottom panel (11), an inner hollow clamping block (5) is welded on one side of one end of the vertical clamping plate (8), and a screw rod (4) is movably sleeved in the inner cavity (5), the utility model discloses a bolt, including screw rod (4), spring (8), bearing rod (7), hinge bar (9), one side activity joint that the spiro union is run through at vertical baffle (3) one side middle part to the screw rod (4) other end, the inside fixed mounting of vertical splint (8) opposite side has spring (10), spring (10) one end fixed movable mounting has bearing bar (7), the inside of bearing bar (7) one end is run through articulated hinge bar (9), hinge bar (9) fixed mounting is in the inside of vertical splint (8), one side activity joint that bearing bar (7) are close to hinge bar (9) has gag lever post (6), gag lever post (6) run through the spiro union in vertical splint (8) one side.
2. The fixing device of the intelligent building beam-column manufacturing equipment according to claim 1, wherein: first screw threads are formed in the side surface of the screw rod (4), the hollow clamping block (5) is cylindrical, and the diameter size of a cylinder protruding from one end of the screw rod (4) is the same as the inner diameter size of the hollow clamping block (5).
3. The fixing device of the intelligent building beam-column manufacturing equipment according to claim 1, wherein: the diameter of the screw rod (4) is smaller than the thickness of the inner cavity (14), and the diameter of the inner hollow fixture block (5) is equal to the thickness of the inner cavity (14).
4. The fixing device of the intelligent building beam-column manufacturing equipment according to claim 1, wherein: second screw thread has been seted up to gag lever post (6) side surface, the diameter size of gag lever post (6) is the same with the diameter size of carrier bar (7).
5. The fixing device of the intelligent building beam-column manufacturing equipment according to claim 1, wherein: the limiting rods (6) are located on the same vertical line, the bearing rods (7) are located on the same vertical line, and the bearing rods (7) corresponding to the opposite bearing rods (7) are located at the same height.
6. The fixing device of the intelligent building beam-column manufacturing equipment according to claim 1, wherein: the length of the vertical clamping plate (8) is less than the height of the inner cavity (14).
CN202022669881.XU 2020-11-18 2020-11-18 Fixing device of intelligent building beam column manufacturing equipment Active CN214195596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022669881.XU CN214195596U (en) 2020-11-18 2020-11-18 Fixing device of intelligent building beam column manufacturing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022669881.XU CN214195596U (en) 2020-11-18 2020-11-18 Fixing device of intelligent building beam column manufacturing equipment

Publications (1)

Publication Number Publication Date
CN214195596U true CN214195596U (en) 2021-09-14

Family

ID=77646028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022669881.XU Active CN214195596U (en) 2020-11-18 2020-11-18 Fixing device of intelligent building beam column manufacturing equipment

Country Status (1)

Country Link
CN (1) CN214195596U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115540759A (en) * 2022-11-16 2022-12-30 南京科天力电子科技有限公司 Detection method and detection system for modifying metal based on image recognition technology

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115540759A (en) * 2022-11-16 2022-12-30 南京科天力电子科技有限公司 Detection method and detection system for modifying metal based on image recognition technology
CN115540759B (en) * 2022-11-16 2023-05-09 江西滕创洪科技有限公司 Detection method and detection system for modifying metal based on image recognition technology

Similar Documents

Publication Publication Date Title
CN214195596U (en) Fixing device of intelligent building beam column manufacturing equipment
CN110424636A (en) Assembled architecture conversion layer reserves casing joint bar positioning device and construction method
CN111252679A (en) Tower crane wall-attached anchoring structure for old-fashioned buildings
CN208056050U (en) A kind of steel reinforcement cage spacer bar structure
CN213980263U (en) Enclosure for civil engineering
CN214302954U (en) Magnetic positioning clamp device for steel pipe concrete column penetrating steel bar
CN208844881U (en) A kind of limit leg structure of construction tool rack
CN219931628U (en) Reverse bank template reinforcing apparatus
CN208618249U (en) Deck type steel arch bridge steel reinforced concrete continuous composite beam
CN209780316U (en) Building structure design roof beam reinforced structure
CN207296440U (en) A kind of three Pin skeleton installation fixators of curtain wall
CN216921326U (en) Building engineering template fixing device
CN209637110U (en) A kind of clear-water concrete batter post external means of support
CN212613267U (en) High-limit formwork fixing device for ribbed formworks
CN217531211U (en) Prefabricated frame of assembled concrete
CN221031418U (en) Integrated device is consolidated to vertical post muscle of cushion cap and template
CN216690080U (en) Green energy-saving prestressed concrete roof beam
CN211714575U (en) Cement is fixed with building templates mechanism
CN210369577U (en) Supporting and limiting device for mounting double-limb columns of mold table
CN216891954U (en) Pier column reinforcing apparatus is used in road and bridge construction
CN216275875U (en) Bridge pile foundation integration mechanical detection butt-joint equipment
CN221218502U (en) Large cantilever bent cap prestressing secondary tensioning platform
CN216665009U (en) Tripod for building reinforcement
CN209704023U (en) A kind of connection structure of concrete structure formwork
CN217600201U (en) Steel bar hoisting and clamping equipment for civil construction engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: Room 2026-049, No. 7A Tawan Street, Huanggu District, Shenyang City, Liaoning Province, 110000

Patentee after: AIA Zhumei Cultural Construction (Liaoning) Co.,Ltd.

Country or region after: China

Address before: 110000 West Railway Station comprehensive market, Yuhong District, Shenyang City, Liaoning Province (No. 128, Xunye 3rd road, Chonggong street, Tiexi District)

Patentee before: Shenyang AIA Decoration Engineering Co.,Ltd.

Country or region before: China