CN214144753U CN202022172034.2U CN202022172034U CN214144753U CN 214144753 U CN214144753 U CN 214144753U CN 202022172034 U CN202022172034 U CN 202022172034U CN 214144753 U CN214144753 U CN 214144753U
Authority
CN
China
Prior art keywords
fixedly connected
heating cabinet
concrete
fixed
fixed cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202022172034.2U
Other languages
Chinese (zh)
Inventor
韦艳燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Junding Urban Construction Group Co ltd
Original Assignee
Juxian Jiuli Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Juxian Jiuli Building Materials Co ltd filed Critical Juxian Jiuli Building Materials Co ltd
Priority to CN202022172034.2U priority Critical patent/CN214144753U/en
Application granted granted Critical
Publication of CN214144753U publication Critical patent/CN214144753U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a concrete rapid solidification device relates to the building engineering field. Including fixed cover, the roof beam post has been placed to the inside of fixed cover, the right flank fixedly connected with heating cabinet of fixed cover, the inlet port has all been seted up with the left surface of heating cabinet to the right flank of fixed cover, the common fixedly connected with heater strip of the interior diapire of heating cabinet and heating cabinet, the inside wall fixedly connected with fan of heating cabinet, the scavenge port that the equidistance was arranged is seted up to the right flank of heating cabinet, and this concrete rapid solidification device can surround around the roof beam post that the concrete was built with the hot-air, plays the effect of intensification acceleration concrete cooling, can spray water on the roof beam post, avoids the concrete to take place the problem of dry crack because of drying and high temperature, can keep apart the concrete in a relatively independent space, avoids the concrete because of the problem that external environment factor can not solidify fast.

Description

Concrete rapid solidification device
Technical Field
The utility model relates to a building engineering technical field specifically is a concrete rapid solidification device.
Background
The construction engineering refers to an engineering entity formed by the construction of various house buildings and their auxiliary facilities and the installation activities of lines, pipes and equipment matched with the various house buildings and their auxiliary facilities, the construction engineering refers to the engineering entity of planning, surveying, designing, constructing and completing the various technical works and the installation engineering of the lines, pipes and equipment matched with the various house buildings and building facilities for new construction, reconstruction or extension of the house buildings and the auxiliary structures, so the construction workload is also called as construction workload, concrete is often used in the construction engineering, and the existing top beam columns built by the concrete are all naturally air-dried, have slow cooling efficiency, are not beneficial to the quick expansion of construction projects, and cannot meet the requirements of the existing construction, therefore, a concrete quick solidification device is provided to solve the problems.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a concrete rapid solidification device has solved the roof beam post that present concrete was built and all is natural air-dry, and cooling efficiency is slower, is unfavorable for the problem that the construction project expanded fast.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: a concrete rapid solidification device comprises a fixed sleeve, a top beam column is placed inside the fixed sleeve, a heating box is fixedly connected to the right side face of the fixed sleeve, air inlet holes are formed in the right side face of the fixed sleeve and the left side face of the heating box, heating wires are fixedly connected to the inner top wall of the heating box and the inner bottom wall of the heating box, a fan is fixedly connected to the inner side wall of the heating box, ventilating holes which are arranged at equal intervals are formed in the right side face of the heating box, a protective door is fixedly hinged to the front face of the heating box through a hinge, a pull handle is fixedly connected to the front face of the protective door, a scattering type spray head is fixedly connected to the inner side wall of the fixed sleeve, a through hole is formed in the right side face of the fixed sleeve, a water pipe is fixedly communicated with the input end of the scattering type spray head, one end of the water pipe, far away from the scattering type spray head, penetrates through the through hole and extends to the right side of the fixed sleeve, the left side fixedly connected with square of fixed cover, the front of square has fixedly articulated the buckle through the round pin axle, the front fixedly connected with handle of fixed cover, the upper surface of handle and the bottom surface of handle are fixed articulated jointly and have been connected the buckle, and the buckle is fixed articulated with the buckle.
Preferably, the front surface of the scattering type spray head is fixedly connected with a fixed block, and the right side surface of the fixed block is fixedly connected with the inner side wall of the fixed sleeve.
Preferably, the inner side wall of the fixed sleeve is fixedly connected with symmetrical pushing blocks, and one side face, close to each other, of each of the two pushing blocks is in contact with the outer surface of the top beam column.
Preferably, the bottom surface fixedly connected with pillar of heating cabinet, the one end that the heating cabinet was kept away from to the pillar is with the right flank fixed connection of fixed cover.
Preferably, a filter screen is arranged on the right side of the ventilation hole, and the left side face of the filter screen is fixedly connected with the right side face of the heating box.
Preferably, the outer fixed surface of fan is connected with solid fixed ring, gu fixed ring's right flank and the inside wall fixed connection of heating cabinet.
Preferably, the anti-skidding sleeve is placed on the right side of the handle, and the inner wall of the anti-skidding sleeve is fixedly connected with the outer surface of the handle.
(III) advantageous effects
The utility model provides a concrete rapid solidification device. The method has the following beneficial effects:
(1) this concrete rapid solidification device, through the fan, can let the flabellum rotatory and drive the air flow, cooperation heater strip intensification air, can produce the hot-air that flows, can surround around the roof beam post that the concrete was built with the hot-air, play and heat up the effect of concrete cooling with higher speed, through scattering type shower nozzle, can spray water on to the roof beam post, avoid the concrete because of the problem of dry crack takes place for drying and high temperature, through fixed cover, can keep apart the concrete in a relatively independent space, avoid the concrete because of the problem that external environment factor can not the rapid solidification.
(2) This concrete rapid solidification device through the ejector pad, can fix the back beam column, has played the effect of moulding the type to the back beam column, through the cooperation of buckle and buckle, can be fixed when needs use and open when need not use, reaches convenient to use's effect, through guard gate and pull handle, can adjust the equipment in the heating cabinet, has played the effect of maintenance of equipment and convenient to use.
Drawings
Fig. 1 is a sectional view of the front view of the fixing sleeve of the present invention;
fig. 2 is a front view of the fixing sleeve of the present invention;
fig. 3 is a sectional view of a front view of the heating chamber of the present invention;
fig. 4 is a front view of the heating box of the present invention.
In the figure: 1. an air inlet; 2. a heating box; 3. a pillar; 4. a filter screen; 5. a scattering type shower head; 6. a fixed block; 7. a through hole; 8. a water pipe; 9. fixing a sleeve; 10. a roof beam column; 11. a push block; 12. a square block; 13. buckling; 14. a pin shaft; 15. a retaining ring; 16. a protective door; 17. a handle; 18. an anti-slip sleeve; 19. heating wires; 20. a fan; 21. a ventilation hole; 22. a fixing ring; 23. and (5) pulling the handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1-4, the utility model provides a technical solution: a concrete rapid solidification device comprises a fixed sleeve 9, symmetrical push blocks 11 are fixedly connected to the inner side wall of the fixed sleeve 9, one side face, close to each other, of each of the two push blocks 11 is in contact with the outer surface of a top beam column 10, the top beam column 10 can be supported by arranging the push blocks 11, the top beam column 10 is placed inside the fixed sleeve 9, a heating box 2 is fixedly connected to the right side face of the fixed sleeve 9, a support column 3 is fixedly connected to the bottom face of the heating box 2, one end, far away from the heating box 2, of the support column 3 is fixedly connected with the right side face of the fixed sleeve 9, the heating box 2 can be supported by arranging the support column 3, the problem that the heating box 2 drops to influence operation is avoided, the right side face of the fixed sleeve 9 and the left side face of the heating box 2 are respectively provided with a heating wire 1, the inner top wall of the heating box 2 and the inner bottom wall of the heating box 2 are fixedly connected with a heating wire 19, the heating wire 19 can be called as an electric heating wire or a heating wire, the novel air conditioner is small in size, high in heating power, wide in application range, long in service life, high in reliability, energy conversion is the core of the principle, the most extensive is that electric energy is converted into heat energy, a fan 20 is fixedly connected to the inner side wall of a heating box 2, a fixing ring 22 is fixedly connected to the outer surface of the fan 20, the right side face of the fixing ring 22 is fixedly connected with the inner side wall of the heating box 2, the fan 20 can be fixed by arranging the fixing ring 22, the effect of stabilizing the structure of the fan 20 is achieved, ventilating holes 21 are formed in the right side face of the heating box 2 and are arranged at equal intervals, a filter screen 4 is placed on the right side of the ventilating holes 21, the left side face of the filter screen 4 is fixedly connected with the right side face of the heating box 2, the filter screen 4 can be used for filtering during air exchange, the problem that dust enters the heating box 2 is avoided, a protective door 16 is fixedly hinged to the front face of the heating box 2, a pull handle 23 is fixedly connected to the front surface of the protective door 16.
The inside wall of fixed cover 9 is fixedly connected with scattering type shower nozzle 5, the front of scattering type shower nozzle 5 is fixedly connected with fixed block 6, the right flank of fixed block 6 and the inside wall of fixed cover 9 are fixedly connected, through setting up fixed block 6, scattering type shower nozzle 5 can be further fixed, avoid the problem of fixed insecure accident, the right flank of fixed cover 9 has seted up through-hole 7, the fixed intercommunication of input of scattering type shower nozzle 5 has water pipe 8, the one end that water pipe 8 keeps away from scattering type shower nozzle 5 runs through-hole 7 and extends to the right side of fixed cover 9, the left surface of fixed cover 9 is fixedly connected with square 12, the front of square 12 is fixedly articulated through round pin axle 14 has buckle 13, the front of fixed cover 9 is fixedly connected with handle 17, antiskid cover 18 has been placed on the right side of handle 17, the inner wall of antiskid cover 18 is fixedly connected with the surface of handle 17, through setting up antiskid cover 18, prevent that handle 17 from slipping excessively, reach the effect of increase handle 17 friction, the upper surface of handle 17 and the bottom surface of handle 17 fix the hinge joint jointly has buckle 15, and buckle 15 is fixed articulated with buckle 13.
When the spraying type water-cooling device is used, the heating wires 19 and the fan 20 are respectively communicated with a power supply, the heating wires 19 are firstly operated, the air in the heating box 2 is gradually heated under the action of the heating wires 19, then the fan 20 is operated, the fan blades can rotate at a high speed under the action of the fan 20, meanwhile, the hot air starts to flow, the heated air enters the fixing sleeve 9 through the air inlet holes 1, along with the continuous operation of the heating wires 19 and the fan 20, the hot air can fill the whole fixing sleeve 9 and surround the top beam column 10, the concrete is rapidly cooled through heating, after the concrete is continuously heated, the scattering type spray head 5 is operated, the other end of the water pipe 8 is connected with municipal water, the top beam column 10 can be sprayed with water, and the phenomenon that the dry high-temperature air enables the water of the top beam column 10 to evaporate and dry cracking occurs is avoided.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a concrete rapid solidification device, includes fixed cover (9), its characterized in that: the roof beam column (10) has been placed to the inside of fixed cover (9), the right flank fixedly connected with heating cabinet (2) of fixed cover (9), inlet port (1) has all been seted up with the left surface of heating cabinet (2) to the right flank of fixed cover (9), the common fixedly connected with heater strip (19) of the interior roof of heating cabinet (2) and the interior diapire of heating cabinet (2), the inside wall fixedly connected with fan (20) of heating cabinet (2), the venthole (21) that the equidistance was arranged has been seted up to the right flank of heating cabinet (2), the front of heating cabinet (2) has been fixedly articulated guard gate (16) through the hinge, the front fixedly connected with pull handle (23) of guard gate (16), the inside wall fixedly connected with scattering type shower nozzle (5) of fixed cover (9), through-hole (7) have been seted up to the right flank of fixed cover (9), the input end of the scattering type spray head (5) is fixedly communicated with a water pipe (8), one end, far away from the scattering type spray head (5), of the water pipe (8) penetrates through the through hole (7) and extends to the right side of the fixing sleeve (9), the left side face of the fixing sleeve (9) is fixedly connected with a square block (12), the front face of the square block (12) is fixedly hinged with a buckle (13) through a pin shaft (14), the front face of the fixing sleeve (9) is fixedly connected with a handle (17), the upper surface of the handle (17) and the bottom face of the handle (17) are fixedly hinged with a retaining ring (15) together, and the retaining ring (15) is fixedly hinged with the buckle (13).
2. The concrete rapid-setting device of claim 1, wherein: the front surface of the scattering type spray head (5) is fixedly connected with a fixed block (6), and the right side surface of the fixed block (6) is fixedly connected with the inner side wall of a fixed sleeve (9).
3. The concrete rapid-setting device of claim 1, wherein: the inner side wall of the fixed sleeve (9) is fixedly connected with symmetrical push blocks (11), and one side face, close to each other, of each push block (11) is in contact with the outer surface of the top beam column (10).
4. The concrete rapid-setting device of claim 1, wherein: the bottom surface fixedly connected with pillar (3) of heating cabinet (2), the one end that heating cabinet (2) were kept away from in pillar (3) is with the right flank fixed connection of fixed cover (9).
5. The concrete rapid-setting device of claim 1, wherein: a filter screen (4) is arranged on the right side of the ventilation hole (21), and the left side surface of the filter screen (4) is fixedly connected with the right side surface of the heating box (2).
6. The concrete rapid-setting device of claim 1, wherein: the outer fixed surface of fan (20) is connected with solid fixed ring (22), the right flank of solid fixed ring (22) and the inside wall fixed connection of heating cabinet (2).
7. The concrete rapid-setting device of claim 1, wherein: an anti-slip sleeve (18) is arranged on the right side of the handle (17), and the inner wall of the anti-slip sleeve (18) is fixedly connected with the outer surface of the handle (17).
CN202022172034.2U 2020-09-28 2020-09-28 Concrete rapid solidification device Withdrawn - After Issue CN214144753U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022172034.2U CN214144753U (en) 2020-09-28 2020-09-28 Concrete rapid solidification device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022172034.2U CN214144753U (en) 2020-09-28 2020-09-28 Concrete rapid solidification device

Publications (1)

Publication Number Publication Date
CN214144753U true CN214144753U (en) 2021-09-07

Family

ID=77557882

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022172034.2U Withdrawn - After Issue CN214144753U (en) 2020-09-28 2020-09-28 Concrete rapid solidification device

Country Status (1)

Country Link
CN (1) CN214144753U (en)

Similar Documents

Publication Publication Date Title
TWM456393U (en) Improved roof structure of building
CN205776825U (en) A kind of movable plank house tap water kind of refrigeration cycle roof cooling system
CN214144753U (en) Concrete rapid solidification device
CN107905578A (en) Steel structure mill construction with heat sink
CN203099983U (en) Complete set equipment formed by combining solar energy heat source wall and heat pump
CN207262522U (en) A kind of building energy conservation Solar wall heating plant
CN201750060U (en) Box-type substation box body
CN206205516U (en) A kind of improved steel plant structure
CN108104366A (en) Photovoltaic heat collector integration assembling type outer wall and its production method
CN211514972U (en) Novel woodwork sprays paint device
CN204753851U (en) Cooling structure of activity board house
CN211424602U (en) Anti-condensation cold radiation system with dehumidification system
CN208618589U (en) A kind of polyisocyanurate foaming
CN208430647U (en) A kind of house architectural structure convenient for heat dissipation
CN206693477U (en) A kind of modified current conversion station air cooler moist closet roof structure
CN213014643U (en) Temperature-adjustable color steel house
CN214632026U (en) Building heat preservation curtain self-cleaning device
CN210468435U (en) Power distribution cabinet for hydraulic equipment
CN200949934Y (en) Split pressure-bearing type solar energy water heater
CN210562768U (en) Building outer wall structure with strong corrosion resistance
CN213088282U (en) Tunnel fire control smoke exhaust fan
CN221402696U (en) Storage tank supercharger capable of improving supercharging efficiency
CN204880534U (en) Cold and hot wind of factory building exchange wind gap and wind channel
CN213092965U (en) Can reduce rain-proof sound arrester of outdoor transformer noise
CN213062671U (en) Roof heat radiation structure of imitation three-dimensional plane power generation tile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240412

Address after: 1301, 13th Floor, Comprehensive Building 1, Xinqiao Chuangye Jiayuan, Xinqiao International Industrial Park, Shouxian County, Huainan City, Anhui Province, 232000 RMB

Patentee after: Junding Urban Construction Group Co.,Ltd.

Country or region after: China

Address before: 276800 Zhoujia Guanzhuang village, zhuangtuan community, fulaishan street, Ju county, Rizhao City, Shandong Province (No. 26, Fulai Industrial Park)

Patentee before: Juxian Jiuli building materials Co.,Ltd.

Country or region before: China

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20210907

Effective date of abandoning: 20240509

AV01 Patent right actively abandoned

Granted publication date: 20210907

Effective date of abandoning: 20240509