CN214117645U - 35KW prefabricated cabin - Google Patents

35KW prefabricated cabin Download PDF

Info

Publication number
CN214117645U
CN214117645U CN202023150328.1U CN202023150328U CN214117645U CN 214117645 U CN214117645 U CN 214117645U CN 202023150328 U CN202023150328 U CN 202023150328U CN 214117645 U CN214117645 U CN 214117645U
Authority
CN
China
Prior art keywords
prefabricated cabin
water pipe
bolt
roof
rotating shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023150328.1U
Other languages
Chinese (zh)
Inventor
孟超
刘广洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cangzhou Zhonghe Container Manufacturing Co ltd
Original Assignee
Cangzhou Zhonghe Container Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cangzhou Zhonghe Container Manufacturing Co ltd filed Critical Cangzhou Zhonghe Container Manufacturing Co ltd
Priority to CN202023150328.1U priority Critical patent/CN214117645U/en
Application granted granted Critical
Publication of CN214117645U publication Critical patent/CN214117645U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a 35KW prefabricated cabin, which belongs to the field of container devices and comprises a prefabricated cabin, wherein a fixed seat is fixedly welded on one side surface of the prefabricated cabin, a rotating shaft is sleeved in the fixed seat in a sliding manner, a bolt is tightly attached to one side of the rotating shaft, a crawling ladder is fixedly sleeved on the outer side of the bolt, a box door is fixedly installed on one side surface of the prefabricated cabin, a roof is fixedly installed at the upper end of the prefabricated cabin, an eave is fixedly installed on the side surface of the roof, the 35KW prefabricated cabin can be conveniently maintained by climbing the roof through rotating the crawling ladder, and can be vertical to the wall surface of the prefabricated cabin, and the bolt can be rotated due to the design to be tightly attached to the end surface of the rotating shaft, so that the damping property of the rotating shaft can be adjusted; through using the screw to turn round prefabricated cabin tightly, drive the conduit saddle and compress tightly the water pipe in the wall in prefabricated cabin for guiding gutter, water leakage mouth and water pipe intercommunication can make the rainwater flow to ground from the water pipe direction, and the design of water pipe can prevent to get wet the people through eave below easily when the water drips from the eave.

Description

35KW prefabricated cabin
Technical Field
The utility model relates to a container device field, more specifically say, relate to a prefabricated cabin of 35 KW.
Background
The assembled intelligent substation is also called a prefabricated cabin, the technology is further deepened, the construction standard is unified, the engineering construction quality is improved, safety and efficiency are improved, a national power grid company develops the construction of a standard distribution type intelligent substation, the technical principle of standardized design, industrialized processing mechanical construction and assembled construction is provided, the construction is an 'first-class power grid', the important measure is the deepening of standardized construction, the construction period can be effectively shortened, the engineering quality is improved, the construction period cost is reduced, the environment is better protected, the efficiency of the intelligent substation is improved, the construction capacity of the power grid is comprehensively improved, the construction of the power substation is made to move towards a road with high technological content, low resource consumption, less environmental pollution and fine construction.
Present 35KW prefabricated cabin, maintenance personal need carry the ladder in addition and climb to prefabricated cabin roof and maintain the operation, and inconvenient maintenance personal maintains the roof, and simultaneously, the rainwater that prefabricated cabin roof flowed down drenches the people through eaves below easily, brings the puzzlement for the pedestrian. Accordingly, there is a need for improvements in the art.
SUMMERY OF THE UTILITY MODEL
Aiming at the problems in the prior art, the utility model aims to provide a 35KW prefabricated cabin, which is vertical to the wall surface by rotating a crawling ladder, so that maintenance personnel can conveniently climb to a roof for maintenance operation, and a bolt can be designed to rotate to be tightly attached to the end surface of a rotating shaft, so that the damping property of the rotating shaft can be adjusted; through using the screw to turn round prefabricated cabin tightly, drive the conduit saddle and compress tightly the water pipe in the wall in prefabricated cabin for guiding gutter, water leakage mouth and water pipe intercommunication can make the rainwater flow to ground from the water pipe direction, and the design of water pipe can prevent to get wet the people through eave below easily when the water drips from the eave.
In order to solve the above problems, the utility model adopts the following technical proposal.
A35 KW prefabricated cabin comprises a prefabricated cabin, a fixed seat is fixedly welded on one side surface of the prefabricated cabin, a rotating shaft is sleeved in the fixed seat in a sliding manner, a bolt is tightly attached to one side of the rotating shaft, a ladder stand is fixedly sleeved on the outer side of the bolt, a box door is fixedly arranged on one side surface of the prefabricated cabin, the upper end of the prefabricated cabin is fixedly provided with a roof, the side surface of the roof is fixedly provided with an eave, a water guide groove is arranged in the eave, a water leaking port is arranged in one side of the water guide groove, the lower end of the water leaking port is connected with a water pipe, a pipe bracket is tightly clamped and connected on the outer side of the water pipe, according to the 35KW prefabricated cabin, the crawling ladder is rotated to be perpendicular to the wall surface, so that maintenance personnel can conveniently climb to a roof to perform maintenance operation, and the bolts can be designed to rotate to be tightly attached to the end surface of the rotating shaft, so that the damping property of the rotating shaft is adjusted; through using the screw to turn round prefabricated cabin tightly, drive the conduit saddle and compress tightly the water pipe in the wall in prefabricated cabin for guiding gutter, water leakage mouth and water pipe intercommunication can make the rainwater flow to ground from the water pipe direction, and the design of water pipe can prevent to get wet the people through eave below easily when the water drips from the eave.
Furthermore, the surface of cat ladder is provided with anti-skidding line, through rotating the cat ladder, makes its perpendicular wall, can make things convenient for maintenance personal to climb to the roof and carry out the maintenance operation.
Furthermore, the bolt is connected to the inside of the fixed seat through threads, and the bolt can rotate due to design, so that the bolt is tightly attached to the end face of the rotating shaft, and the damping performance of the rotating shaft is adjusted.
Furthermore, screws are sleeved inside two ends of the pipe bracket.
Further, the screw is connected with the prefabricated cabin through threads.
Furthermore, the inner sides of the two ends of the pipe support are tightly attached to the wall surface of the prefabricated cabin, the prefabricated cabin is tightly twisted by using screws, and the pipe support is driven to press the water pipe on the wall surface of the prefabricated cabin, so that the water guide groove, the water leakage port and the water pipe are communicated, and rainwater can flow to the ground from the water pipe in a guiding mode.
Furthermore, the water pipe is made of polyethylene materials, and the water pipe can be designed to prevent people passing below the eave from being easily wetted when water drips from the eave.
Compared with the prior art, the utility model has the advantages of:
(1) according to the scheme, the crawling ladder is rotated to be perpendicular to the wall surface, so that maintenance personnel can conveniently climb to a roof for maintenance operation, and the bolt can be rotated to be tightly attached to the end surface of the rotating shaft, so that the damping property of the rotating shaft is adjusted; through using the screw to turn round prefabricated cabin tightly, drive the conduit saddle and compress tightly the water pipe in the wall in prefabricated cabin for guiding gutter, water leakage mouth and water pipe intercommunication can make the rainwater flow to ground from the water pipe direction, and the design of water pipe can prevent to get wet the people through eave below easily when the water drips from the eave.
(2) The surface of cat ladder is provided with anti-skidding line, through rotating the cat ladder, makes its perpendicular wall, can make things convenient for maintenance personal to climb to the roof and maintain the operation.
(3) The inside of fixing base is through threaded connection bolt, and the design of bolt can rotate, makes it hug closely the axis of rotation terminal surface to adjust the damping nature of axis of rotation.
(4) The screw passes through the prefabricated cabin of threaded connection, and the prefabricated cabin wall is hugged closely to the both ends inboard of conduit saddle, through using the screw to turn round tight prefabricated cabin, drives the conduit saddle and compresses tightly the water pipe in the wall in prefabricated cabin for guiding gutter, leaking mouth and water pipe intercommunication can make the rainwater follow the water pipe direction flow to ground.
(5) The water pipe is made of polyethylene materials, and the design of the water pipe can prevent people passing through the lower part of the eave from being easily wetted when water drops from the eave.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a top enlarged cross-sectional view of the ladder of the present invention;
fig. 3 is a partially overlooked enlarged view of the eave of the present invention.
The reference numbers in the figures illustrate:
1 prefabricated cabin, 11 fixed seats, 12 rotating shafts, 13 bolts, 14 crawling ladders, 15 box doors, 2 roofs, 21 eaves, 22 water guide grooves, 23 water leakage ports, 24 water pipes, 25 pipe brackets and 26 screws.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention; obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention based on the embodiments of the present invention.
Referring to fig. 1-3, a 35KW prefabricated cabin comprises a prefabricated cabin 1, a fixed seat 11 is fixedly welded on one side surface of the prefabricated cabin 1, a rotating shaft 12 is slidably sleeved inside the fixed seat 11, a bolt 13 is tightly attached to one side of the rotating shaft 12, a ladder 14 is fixedly sleeved outside the bolt 13, a box door 15 is fixedly installed on one side surface of the prefabricated cabin 1, a roof 2 is fixedly installed at the upper end of the prefabricated cabin 1, an eave 21 is fixedly installed on the side surface of the roof 2, a water guide groove 22 is arranged inside the eave 21, a water leakage port 23 is arranged inside one side of the water guide groove 22, a water pipe 24 is connected to the lower end of the water leakage port 23, a pipe support 25 is fastened and clamped on the outer side of the water pipe 24, and screws 26 are sleeved inside two ends of the pipe support 25.
Referring to fig. 1-2, the outer surface of the ladder 14 is provided with anti-slip lines, the ladder 14 is rotated to be perpendicular to the wall surface, so that maintenance personnel can conveniently climb to the roof 2 for maintenance, the inside of the fixed seat 11 is connected with the bolt 13 through threads, and the bolt 13 is designed to be rotatable so as to be tightly attached to the end surface of the rotating shaft 12, so that the damping performance of the rotating shaft 12 is adjusted.
Referring to fig. 1 and 3, the screw 26 is connected with the prefabricated cabin 1 through threads, the inner sides of the two ends of the pipe bracket 25 are tightly attached to the wall surface of the prefabricated cabin 1, the prefabricated cabin 1 is tightly screwed through the screw 26, the pipe bracket 25 is driven to press the water pipe 24 to the wall surface of the prefabricated cabin 1, the water chute 22, the water leaking port 23 and the water pipe 24 are communicated, rainwater can be guided to flow to the ground from the water pipe 24, the water pipe 24 is made of polyethylene materials, and the water pipe 24 is designed to prevent people passing below the eave 21 from being easily wetted when water drips from the eave 21.
This prefabricated cabin of 35KW, through rotating bolt 13, make it hug closely the 12 terminal surfaces of axis of rotation, thereby adjust the damping nature of axis of rotation 12, rotate cat ladder 14, make its perpendicular wall, can make things convenient for maintenance personal to climb to roof 2 and maintain the operation, through using screw 26 to turn round tight prefabricated cabin 1, drive conduit saddle 25 and compress tightly water pipe 24 in the wall of prefabricated cabin 1, make guiding gutter 22, leak mouth 23 and water pipe 24 intercommunication, can make the rainwater follow water pipe 24 direction flow direction ground, water pipe 24's design can prevent to get wet easily the people through eaves 21 below when the water drips from eaves 21.
The above description is only the preferred embodiment of the present invention; the scope of the present invention is not limited thereto. Any person skilled in the art should also be able to cover the technical scope of the present invention by replacing or changing the technical solution and the improvement concept of the present invention with equivalents and modifications within the technical scope of the present invention.

Claims (7)

1. A35 KW prefabricated cabin comprises a prefabricated cabin (1) and is characterized in that: the fixed welding of a side of prefabricated cabin (1) has fixing base (11), the inside slip of fixing base (11) has cup jointed axis of rotation (12), bolt (13) have been hugged closely to one side of axis of rotation (12), the outside of bolt (13) is fixed has cup jointed cat ladder (14), prefabricated cabin (1) a side fixed mounting has chamber door (15), the upper end fixed mounting of prefabricated cabin (1) has roof (2), the side fixed mounting of roof (2) has eaves (21), the inside of eaves (21) is provided with guiding gutter (22), one side inside of guiding gutter (22) is provided with mouth of leaking (23), the lower extreme of mouth of leaking (23) is connected with water pipe (24), the outside fastening joint of water pipe (24) has conduit saddle (25).
2. A 35KW prefabricated cabin according to claim 1, characterised in that: the outer surface of the ladder stand (14) is provided with anti-skid lines.
3. A 35KW prefabricated cabin according to claim 1, characterised in that: the interior of the fixed seat (11) is connected with a bolt (13) through threads.
4. A 35KW prefabricated cabin according to claim 1, characterised in that: and screws (26) are sleeved inside two ends of the pipe bracket (25).
5. A35 KW prefabricated cabin according to claim 4, characterized in that: the screw (26) is connected with the prefabricated cabin (1) through threads.
6. A 35KW prefabricated cabin according to claim 1, characterised in that: the inner sides of the two ends of the pipe bracket (25) are tightly attached to the wall surface of the prefabricated cabin (1).
7. A 35KW prefabricated cabin according to claim 1, characterised in that: the water pipe (24) is made of polyethylene material.
CN202023150328.1U 2020-12-24 2020-12-24 35KW prefabricated cabin Expired - Fee Related CN214117645U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023150328.1U CN214117645U (en) 2020-12-24 2020-12-24 35KW prefabricated cabin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023150328.1U CN214117645U (en) 2020-12-24 2020-12-24 35KW prefabricated cabin

Publications (1)

Publication Number Publication Date
CN214117645U true CN214117645U (en) 2021-09-03

Family

ID=77514103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023150328.1U Expired - Fee Related CN214117645U (en) 2020-12-24 2020-12-24 35KW prefabricated cabin

Country Status (1)

Country Link
CN (1) CN214117645U (en)

Similar Documents

Publication Publication Date Title
CN1737361A (en) Method for reutilizing water supply line excess pressure and tube type turbine
CN214117645U (en) 35KW prefabricated cabin
CN113073795B (en) Photovoltaic module fastening structure and BIPV roofing support system
CN208670852U (en) A kind of environment protection solar street lamp with depositing dust function
CN101021293A (en) Sealed ball shape compensating device
CN111425003A (en) Utilize roof cleaning device of wind energy
CN110752522A (en) Motor train unit overhead high-voltage equipment box top cover sealing structure and method
CN213114923U (en) Buried pump station with external valve well
CN211576177U (en) Scalable non-contact sensor installation device
CN210530169U (en) Straight line type double-opening skylight
CN207121822U (en) A kind of foldable bridge highway guard rail
CN206004600U (en) A kind of waterproof solar battery component
CN220301491U (en) Detection well for preventing groundwater pollution
CN210899004U (en) Waterproof BIPV subassembly support of structure
CN216488464U (en) Antenna mounting structure
CN214090285U (en) A prevent stifled cistern for hydraulic engineering
CN213485292U (en) 5GBBU outdoor cabinet based on Internet of things
CN214061982U (en) Building facade node that drips
CN212908542U (en) Detachable wind and sand prevention door hopper for prefabricated cabin
CN217153387U (en) Leak protection drainage pipe for hydraulic and hydroelectric engineering
CN217734618U (en) Valve plate side-open type ventilation skylight structure
CN211605795U (en) Security protection intelligent power supply
CN217974036U (en) Bridge drainage pipeline convenient to maintain and replace
CN218771066U (en) High-stability cable support frame special for hydraulic engineering
CN218078353U (en) Vertical roller mill of slay water spray structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210903