CN214116674U - Composite construction water conservancy pile foundation - Google Patents

Composite construction water conservancy pile foundation Download PDF

Info

Publication number
CN214116674U
CN214116674U CN202120020968.6U CN202120020968U CN214116674U CN 214116674 U CN214116674 U CN 214116674U CN 202120020968 U CN202120020968 U CN 202120020968U CN 214116674 U CN214116674 U CN 214116674U
Authority
CN
China
Prior art keywords
pile
fixed
water conservancy
cap
composite construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120020968.6U
Other languages
Chinese (zh)
Inventor
高小军
陈继斌
高利军
宋国华
郭虹俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202120020968.6U priority Critical patent/CN214116674U/en
Application granted granted Critical
Publication of CN214116674U publication Critical patent/CN214116674U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a composite construction water conservancy pile foundation, its technical scheme main points are: including pile cap and spud pile, the connecting hole has been seted up on the spud pile, the fixed column that is provided with in below of spud pile, the fixed connecting block that is provided with in below of pile cap, the side central point of connecting block puts and has seted up the through-hole, the through-hole internalization is provided with the spliced pole, the spliced pole passes through cable fixed connection with the spud pile, the below fixedly connected with stake of connecting block, the fixed sleeve that is provided with in outside of stake, telescopic fixed antiskid ribbed tile that is provided with all around, the utility model discloses a stability of whole pile foundation has been strengthened greatly in the cable connection, the sleeve protects the stake not receive the impact of rivers, the service life of improving device, antiskid ribbed tile through the installation, stake and underground frictional force strengthen for the condition down can not appear in the stake, further improve the durability of device, simple structure is convenient for operation and maintenance.

Description

Composite construction water conservancy pile foundation
Technical Field
The utility model relates to a hydraulic engineering technical field, a composite construction water conservancy pile foundation specifically says so.
Background
The pile foundation has the advantages of high bearing capacity, small and uniform settlement and slow settlement rate, can bear vertical load, horizontal load, uplift force and vibration or power action of machines, and is widely applied to projects such as water conservancy and the like.
The existing cement pile foundation adopts an integrated pouring mode, the method is relatively troublesome in construction, the stability and the durability of the pile foundation are not good, the pile foundation requirement in the aspect of water conservancy is more strict, and potential safety hazards exist if the quality of the engineering is greatly influenced by disqualified pile foundations.
SUMMERY OF THE UTILITY MODEL
To the problem of mentioning in the background art, the utility model aims at providing a composite construction water conservancy pile foundation to solve the poor problem of stability and durability that mentions in the background art.
The utility model discloses a realize through following technical scheme:
the utility model provides a composite construction water conservancy pile foundation, including pile cap and spud pile, the fixed connecting hole of having seted up in bottom surface of pile cap, the fixed column that is provided with in below of spud pile, the fixed connecting block that is provided with in below of pile cap, the last fixed surface of connecting block is provided with first transportation rings, the side central point of connecting block puts and has seted up the through-hole, the through-hole internalization is provided with the spliced pole, the fixed draw-in groove that is provided with of column cap of spliced pole, the spliced pole passes through cable fixed connection with the spud pile, the below fixedly connected with stake of connecting block, the fixed sleeve that is provided with in the outside of stake, telescopic fixed antiskid ribbed tile that is provided with all around.
Furthermore, a first connecting plate is fixedly arranged on the left side of the pile cap, a second connecting plate is fixedly arranged on the right side of the pile cap, and the length and the width of the first connecting plate and the second connecting plate are the same.
Through adopting above-mentioned technical scheme, overlap joint the first connecting plate of a pile cap and the second connecting plate of another pile cap each other, get up first connecting plate and second connecting plate fixed connection again, just can realize the installation of two pile caps, very convenient and fast.
Further, the fixing piles are fixedly provided with two fixing piles.
Through adopting above-mentioned technical scheme, can guarantee the balance of pile cap, further improve the steadiness of device.
Furthermore, a plurality of lightening holes are formed in the pile cap, and fixed reinforcing ribs are fixedly mounted in the lightening holes.
Through adopting above-mentioned technical scheme, the lightening hole of seting up can alleviate the weight of pile cap self, through the fixed strengthening rib of installation for some lightening holes can not influence the fastness of whole pile cap is seted up to the pile cap, and make the pile cap resist compression more.
Furthermore, the positions of the left end and the right end of the upper surface of the pile cap are fixedly provided with second transportation hanging rings.
Through adopting above-mentioned technical scheme, the second transportation rings of installation can be convenient for the transport means to carry the pile cap.
Furthermore, the first transportation hanging ring is made of reinforcing ribs.
Through adopting above-mentioned technical scheme, sturdy and durable can also be used as the fixture block and blocks pile cap.
To sum up, the utility model discloses mainly have following beneficial effect:
a composite construction water conservancy pile foundation, including pile cap and spud pile, fix the spud pile in the appropriate geographical position first, then connect the handling pile cap, connecting block, pile and bush to make up through the tool bogie such as the crane, the joint pin has run through in the connecting block, connecting block and spud pile pass the fixed connection of the connecting cable, have strengthened the stability of the whole pile foundation greatly through the connection of the connecting cable, the outside of the pile is fixed with the bush, the bush is fixed with the antiskid sheet all around, the bush protects the pile from the impact of the rivers, improve the service life of the apparatus, the surface of the general pile is comparatively smooth, get off and make the connecting pile easy to sink for a long time, thus destroy the pile cap structure above, through the antiskid sheet installed, the friction between pile and underground is increased, make the pile not appear the situation of sinking, further improve the durability of the apparatus, simple structure and convenient operation and maintenance.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural diagram of an embodiment of the present invention;
fig. 2 is a cross-sectional view taken at a-a in fig. 1.
In the figure: 1. a pile cap; 101. a groove; 2. fixing the pile; 201. connecting holes; 202. fixing a column; 3. connecting blocks; 301. a first transport hoist ring; 302. a through hole; 303. connecting columns; 4. a card slot; 5. a connecting cable; 6. pile columns; 7. a sleeve; 8. an anti-skid plate; 9. a first connecting plate; 10. a second connecting plate; 11. lightening holes; 12. fixing the reinforcing ribs; 13. and a second transport sling.
Detailed Description
In order to make the objects and technical solutions of the present invention clear and fully described, and the advantages thereof more clearly understood, the embodiments of the present invention are described in further detail below with reference to the accompanying drawings.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal", and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," "third," "fourth," "fifth," and "sixth" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Example 1
Referring to fig. 1-2, a composite water conservancy pile foundation comprises a pile cap 1 and a fixing pile 2, a groove 101 is fixedly formed on the bottom surface of the pile cap 1, a connecting hole 201 is formed on the fixing pile 2, a fixing column 202 is fixedly arranged below the fixing pile 2, a connecting block 3 is fixedly arranged below the pile cap 1, a first transportation hanging ring 301 is fixedly arranged on the upper surface of the connecting block 3, a through hole 302 is formed in the side center of the connecting block 3, a connecting column 303 is movably arranged in the through hole 302, a clamping groove 4 is fixedly arranged on the column head of the connecting column 303, the connecting column 303 is fixedly connected with the fixing pile 2 through a connecting cable 5, a pile 6 is fixedly connected below the connecting block 3, a sleeve 7 is fixedly arranged on the outer side of the pile 6, and an anti-skid plate 8 is fixedly arranged around the sleeve 7, the sleeve 7 is made of stainless steel, has higher strength and is close to or exceeds high-quality steel, has good plasticity and corrosion resistance, can keep the surface from being corroded in the underwater sludge environment, and improves the service life of the device.
Referring to fig. 1, a first connecting plate 9 is fixedly arranged on the left side of a pile cap 1, a second connecting plate 10 is fixedly arranged on the right side of the pile cap 1, the first connecting plate 9 and the second connecting plate 10 are the same in length and width, the first connecting plate 9 of one pile cap 1 is mutually overlapped with the second connecting plate 10 of the other pile cap 1, and then the first connecting plate 9 and the second connecting plate 10 are fixedly connected, so that the installation of the two pile caps 1 can be realized, and the installation is very convenient and fast.
Referring to fig. 1, two fixing piles 2 are fixedly arranged, so that the balance of the pile cap 1 can be ensured, and the stability of the device is further improved.
Referring to fig. 2, a plurality of lightening holes 11 are formed in the pile cap 1, fixed reinforcing ribs 12 are fixedly mounted in the lightening holes 11, the weight of the pile cap 1 can be reduced by the lightening holes 11, the firmness of the whole pile cap 1 cannot be affected by the lightening holes 11 formed in the pile cap 1 through the installed fixed reinforcing ribs 12, and the pile cap 1 can be more resistant to pressure.
Referring to fig. 1 and 2, the left end and the right end of the upper surface of the pile cap 1 are both fixedly provided with a second transportation hanging ring 13, and the second transportation hanging ring 13 can be used for facilitating transportation of the pile cap 1 by transportation tools.
Referring to fig. 1, the first transportation hanging ring 301 is made of a reinforcing rib, is sturdy and durable, and can also be used as a clamping block to clamp the pile cap 1.
To sum up, the utility model is a composite construction water conservancy pile foundation, simple structure, reasonable design, including pile platform 1 and spud pile 2, when using, fix the spud pile 2 in the appropriate geographical position first, then connect the handling pile platform 1, connecting block 3, pile 6 and sleeve 7 to make up through the tool bogie such as the crane, the spliced pole 303 has run through in the connecting block 3, the connecting block 3 and spud pile 2 are fixedly connected through the connecting cable 5, connect through the connecting cable 5 and greatly strengthened the stability of the whole pile foundation, the outside of pile 6 is fixedly provided with sleeve 7, sleeve 7 is fixedly provided with antiskid ribbed tile 8 all around, sleeve 7 protects pile 6 from the impact of rivers, improve the service life of the device, the surface of general pile 6 is comparatively smooth, make the connecting pile 6 sink easily for a long time, thus destroy the pile platform 1 structure above, through the antiskid ribbed tile 8 of installation, the frictional force of pile 6 and underground increases for the condition that the pile 6 can not appear going down, further improves the durability of device, and simple structure is convenient for operation and maintenance.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a composite construction water conservancy pile foundation, includes pile cap (1) and spud pile (2), its characterized in that: a groove (101) is fixedly arranged on the bottom surface of the pile cap (1), a connecting hole (201) is arranged on the fixed pile (2), a fixed column (202) is fixedly arranged below the fixed pile (2), a connecting block (3) is fixedly arranged below the pile cap (1), a first conveying hanging ring (301) is fixedly arranged on the upper surface of the connecting block (3), a through hole (302) is arranged at the center of the side surface of the connecting block (3), a connecting column (303) is movably arranged in the through hole (302), a clamping groove (4) is fixedly arranged on the column head of the connecting column (303), the connecting column (303) is fixedly connected with the fixed pile (2) through a connecting cable (5), the lower part of the connecting block (3) is fixedly connected with a pile column (6), the outer side of the pile column (6) is fixedly provided with a sleeve (7), and the periphery of the sleeve (7) is fixedly provided with an anti-skid plate (8).
2. The composite construction water conservancy pile foundation of claim 1, characterized in that: the left side of pile cap (1) is fixed and is provided with first connecting plate (9), the right side of pile cap (1) is fixed and is provided with second connecting plate (10), just first connecting plate (9) with the length and the width of second connecting plate (10) are the same.
3. The composite construction water conservancy pile foundation of claim 1, characterized in that: the number of the fixing piles (2) is two.
4. The composite construction water conservancy pile foundation of claim 1, characterized in that: a plurality of lightening holes (11) are formed in the pile cap (1), and fixing reinforcing ribs (12) are fixedly mounted in the lightening holes (11).
5. The composite construction water conservancy pile foundation of claim 1, characterized in that: and second transportation lifting rings (13) are fixedly arranged at the left end and the right end of the upper surface of the pile cap (1).
6. The composite construction water conservancy pile foundation of claim 1, characterized in that: the first transportation hanging ring (301) is made of reinforcing ribs.
CN202120020968.6U 2021-01-06 2021-01-06 Composite construction water conservancy pile foundation Active CN214116674U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120020968.6U CN214116674U (en) 2021-01-06 2021-01-06 Composite construction water conservancy pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120020968.6U CN214116674U (en) 2021-01-06 2021-01-06 Composite construction water conservancy pile foundation

Publications (1)

Publication Number Publication Date
CN214116674U true CN214116674U (en) 2021-09-03

Family

ID=77493776

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120020968.6U Active CN214116674U (en) 2021-01-06 2021-01-06 Composite construction water conservancy pile foundation

Country Status (1)

Country Link
CN (1) CN214116674U (en)

Similar Documents

Publication Publication Date Title
CN102251534B (en) Ocean engineering foundation adopting pile-barrel foundation structure
CN214116674U (en) Composite construction water conservancy pile foundation
CN101736907B (en) Jacking cushion block for building
CN102587377B (en) Drop hammer type pile sinking device and pile sinking method thereof
CN210438260U (en) Major diameter steel protects a hoisting structure
CN214994007U (en) Bridge steel protects a section of thick bamboo and steel reinforcement cage and is connected locating rack
CN214993830U (en) Matching device of hydraulic hammer of ultra-large piling ship
CN111794211A (en) Prefabricated assembly tubular pile convenient to hoist and mount and concatenation
CN109577323B (en) Tubular pile reinforcing method
CN202492846U (en) Drop hammer pile-sinking device
CN106120880A (en) A kind of offshore wind farm single-pile foundation Compressive Bearing Capacity assay device
CN209875153U (en) Small-section shaft lining supporting device
CN216947817U (en) Transition connection system of bent cap and pier
CN218860148U (en) Special holding pole and lifting system for hoisting shaft of Yangtze river large-span tower
CN210827610U (en) Be suitable for integral type pile extension ware of PHC tubular pile
CN206887792U (en) A kind of bridge strengthening device for improving bearing capacity
CN216840666U (en) Pump pipe fixing device for super high-rise tower
CN210341664U (en) Small-size sea area cushion cap pier shaft framework of steel reinforcement fixing device
CN218346229U (en) Offshore pile foundation construction device
CN217172934U (en) Major diameter concrete pipe lifting device
CN211369628U (en) Movable type matched anchor sleeve
CN219548805U (en) Polygonal variable cross section mast
CN217104691U (en) Novel supporting template for highway bridge pier
CN219488400U (en) Suction bucket basis transportation fixing device
CN214883630U (en) Temporary pile suspension structure of offshore independent pile driving platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant