Info

Publication number
CN214031529U
CN214031529U CN202023045977.5U CN202023045977U CN214031529U CN 214031529 U CN214031529 U CN 214031529U CN 202023045977 U CN202023045977 U CN 202023045977U CN 214031529 U CN214031529 U CN 214031529U
Authority
CN
China
Prior art keywords
fixedly connected
base
lifting device
electric putter
placing box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023045977.5U
Other languages
Chinese (zh)
Inventor
王蔚峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202023045977.5U priority Critical patent/CN214031529U/en
Application granted granted Critical
Publication of CN214031529U publication Critical patent/CN214031529U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a material lifting device for building engineering in the technical field of building engineering, the on-line screen storage device comprises a base, the left side fixedly connected with riser at base top, the top fixedly connected with diaphragm on riser right side, diaphragm bottom front side and rear side all are connected with the threaded rod through the bearing rotation, two the bottom of threaded rod is connected through the bearing rotation with the top of base, the top of base just is located two fixedly connected with servo motor between the threaded rod; the utility model discloses servo motor who is equipped with can drive the driving gear and rotate, and the rethread driving gear is connected with driven gear's meshing and is driven the threaded rod and rotate, and threaded connection through threaded rod and thread bush drives thread bush and first electric putter goes up and down to it places the case lift to drive the material, promotes the material, and the first electric putter that is equipped with can drive the material and place the case and remove about, and the staff of being convenient for gets the material.

Description

Material lifting device for building engineering
Technical Field
The utility model relates to a building engineering technical field specifically is a material lifting device for building engineering.
Background
In the building engineering trade, when building higher building, often need carry the building material to a take the altitude for the building to use, generally carry through the manpower among the prior art or carry through the loop wheel machine, carry through the manpower low in efficiency, the human cost is high, wastes time and energy, another kind, hoists because the structure is complicated through the loop wheel machine, and the operation is complicated, uses the trouble, for this reason, we propose a material hoisting device for building engineering.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a material hoisting device for building engineering to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a material lifting device for building engineering, includes the base, the left side fixedly connected with riser at base top, the top fixedly connected with diaphragm on riser right side, diaphragm bottom front side all rotates through the bearing with the rear side and is connected with the threaded rod, two the bottom of threaded rod is passed through the bearing with the top of base and is rotated and be connected, the top of base just is located two fixedly connected with servo motor between the threaded rod, servo motor's output welding has the driving gear, two the bottom cover on threaded rod surface is equipped with driven gear, the driving gear is connected with driven gear meshing, the surperficial threaded connection of threaded rod has the thread bush, the right side welding of thread bush has first electric putter, the flexible end welding of first electric putter has the material to place the case.
Preferably, the top fixedly connected with slide bar of driving gear, the top of slide bar is passed through the bearing rotation with the bottom of diaphragm and is connected, the sliding surface connection of slide bar has the sliding sleeve, the right side fixedly connected with lagging of sliding sleeve, the inner chamber of lagging is provided with L shape movable plate, the right side of L shape movable plate runs through the lagging and extends to the outside of lagging, case and L shape movable plate fixed connection are placed to the material.
Preferably, the two sides of the bottom of the material placing box are fixedly connected with pulleys, and the bottoms of the pulleys are connected with the sleeve plate and the top of the L-shaped moving plate in a sliding mode.
Preferably, the left side fixedly connected with second electric putter of incasement chamber bottom is placed to the material, second electric putter's top is rotated through the pivot and is connected with the baffle, the right side of baffle bottom is rotated through the pivot and is connected with the bracing piece, the right side fixed connection of incasement chamber bottom is placed with the material to the bottom of bracing piece.
Preferably, the equal fixedly connected with gyro wheel in both sides of base bottom, the switch is installed in the left side of riser, the electrical property output of switch pass through the wire respectively with first electric putter, servo motor and second electric putter's electrical property input electric connection.
Preferably, the right side of the material placing box is communicated with a material discharging pipe, and a valve is arranged on the surface of the material discharging pipe.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses servo motor who is equipped with can drive the driving gear and rotate, the rethread driving gear is connected with driven gear's meshing and is driven the threaded rod and rotate, threaded connection through threaded rod and thread bush drives thread bush and first electric putter goes up and down, thereby it places the case lift to drive the material, promote the material, and the first electric putter who is equipped with can drive the material and place the case and control, the staff of being convenient for gets the material, thereby effectually solved through manpower conveying efficiency low, the human cost is high, waste time and energy, another kind, hoist and mount because the structure is complicated through the loop wheel machine, the operation is complicated, the trouble problem of use.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a left side view structural schematic diagram of the servo motor of the present invention;
fig. 3 is the schematic view of the sectional structure of the material placing box of the present invention.
In the figure: 1. a base; 2. a vertical plate; 3. a transverse plate; 4. a threaded rod; 5. a servo motor; 6. a driving gear; 7. a driven gear; 8. a threaded sleeve; 9. a first electric push rod; 10. a material placing box; 11. a slide bar; 12. a sliding sleeve; 13. sheathing; 14. an L-shaped moving plate; 15. a pulley; 16. a partition plate; 17. a second electric push rod; 18. a support bar; 19. a roller; 20. and (4) switching.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1, fig. 2 and fig. 3, the present invention provides a technical solution: the utility model provides a material lifting device for building engineering, the on-line screen storage device comprises a base 1, the left side fixedly connected with riser 2 at 1 top of base, the top fixedly connected with diaphragm 3 on riser 2 right side, 3 bottom front sides of diaphragm are all rotated through the bearing with the rear side and are connected with threaded rod 4, the bottom of two threaded rods 4 is passed through the bearing with base 1's top and is rotated and be connected, base 1's top just is located fixedly connected with servo motor 5 between two threaded rods 4, servo motor 5's output welding has driving gear 6, the bottom cover on two threaded rods 4 surfaces is equipped with driven gear 7, driving gear 6 is connected with driven gear 7 meshing, the surperficial threaded connection of threaded rod 4 has thread bush 8, the right side welding of thread bush 8 has first electric putter 9, the flexible end welding of first electric putter 9 has the material to place case 10.
Referring to fig. 2, a slide rod 11 is fixedly connected to the top of a driving gear 6, the top of the slide rod 11 is rotatably connected to the bottom of a transverse plate 3 through a bearing, a slide sleeve 12 is slidably connected to the surface of the slide rod 11, a sleeve plate 13 is fixedly connected to the right side of the slide sleeve 12, an L-shaped moving plate 14 is arranged in an inner cavity of the sleeve plate 13, the right side of the L-shaped moving plate 14 penetrates through the sleeve plate 13 and extends to the outside of the sleeve plate 13, and a material placing box 10 is fixedly connected to the L-shaped moving plate 14, so that the material placing box 10 can be supported when being lifted, the situation that a first electric push rod 9 is broken due to shaking when the material placing box 10 is lifted is avoided, and the L-shaped moving plate 14 is fixedly connected to the material placing box 10, so that the material placing box 10 can be lifted and lifted along with the lifting;
referring to fig. 1, pulleys 15 are fixedly connected to both sides of the bottom of the material placing box 10, and the bottom of the pulley 15 is slidably connected to the sleeve plate 13 and the top of the L-shaped moving plate 14, so that the sliding effect can be increased when the material placing box 10 moves left and right;
referring to fig. 3, a second electric push rod 17 is fixedly connected to the left side of the bottom of the inner cavity of the material placing box 10, a partition plate 16 is rotatably connected to the top of the second electric push rod 17 through a rotating shaft, a support rod 18 is rotatably connected to the right side of the bottom of the partition plate 16 through a rotating shaft, and the bottom of the support rod 18 is fixedly connected to the right side of the bottom of the inner cavity of the material placing box 10, so that the material in the inner cavity of the material placing box 10 can be conveniently discharged, and the situation that the material remains in the inner cavity of the material placing box 10 and needs to be manually cleaned is avoided;
referring to fig. 1, rollers 19 are fixedly connected to both sides of the bottom of the base 1, a switch 20 is installed on the left side of the vertical plate 2, and an electrical output end of the switch 20 is electrically connected to electrical input ends of the first electric push rod 9, the servo motor 5 and the second electric push rod 17 through wires;
referring to fig. 3, the right side of the material placing box 10 is communicated with a material discharging pipe, and a valve is arranged on the surface of the material discharging pipe;
when using, the utility model discloses servo motor 5 that is equipped with can drive driving gear 6 and rotate, rethread driving gear 6 is connected with driven gear 7's meshing and is driven threaded rod 4 and rotate, threaded connection through threaded rod 4 and thread bush 8 drives thread bush 8 and first electric putter 9 and goes up and down, thereby it places case 10 lift to drive the material, promote the material, and the first electric putter 9 that is equipped with can drive the material and place case 10 and control, the staff of being convenient for gets the material, thereby effectual solution is low through manpower conveying efficiency, the human cost is high, waste time and energy, another kind, hoist and mount because the structure is complicated through the loop wheel machine, the operation is complicated, the problem of troublesome to use.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a material lifting device for building engineering, includes base (1), its characterized in that: the left side of the top of the base (1) is fixedly connected with a vertical plate (2), the top on the right side of the vertical plate (2) is fixedly connected with a transverse plate (3), the front side and the rear side of the bottom of the transverse plate (3) are both connected with threaded rods (4) through bearing rotation, the bottoms of the two threaded rods (4) are connected with the top of the base (1) through bearing rotation, the top of the base (1) is positioned between the two threaded rods (4) and is fixedly connected with a servo motor (5), the output end of the servo motor (5) is welded with a driving gear (6), the bottom of the surface of the two threaded rods (4) is sleeved with a driven gear (7), the driving gear (6) is meshed with the driven gear (7), the surface of the threaded rod (4) is connected with a threaded sleeve (8), and the right side of the threaded sleeve (8) is welded with a first electric push rod (9), the telescopic end of the first electric push rod (9) is welded with a material placing box (10).
2. A material lifting device for construction engineering according to claim 1, characterized in that: the top fixedly connected with slide bar (11) of driving gear (6), the top of slide bar (11) is passed through the bearing rotation with the bottom of diaphragm (3) and is connected, the sliding surface connection of slide bar (11) has sliding sleeve (12), the right side fixedly connected with lagging (13) of sliding sleeve (12), the inner chamber of lagging (13) is provided with L shape movable plate (14), the outside that lagging (13) and extending to lagging (13) are run through on the right side of L shape movable plate (14), case (10) and L shape movable plate (14) fixed connection are placed to the material.
3. A material lifting device for construction engineering according to claim 1, characterized in that: the material placing box is characterized in that pulleys (15) are fixedly connected to two sides of the bottom of the material placing box (10), and the bottoms of the pulleys (15) are connected with the sleeve plate (13) and the top of the L-shaped moving plate (14) in a sliding mode.
4. A material lifting device for construction engineering according to claim 1, characterized in that: the left side fixedly connected with second electric putter (17) of case (10) inner chamber bottom is placed to the material, the top of second electric putter (17) is rotated through the pivot and is connected with baffle (16), the right side of baffle (16) bottom is rotated through the pivot and is connected with bracing piece (18), the right side fixed connection of case (10) inner chamber bottom is placed to the bottom and the material of bracing piece (18).
5. A material lifting device for construction engineering according to claim 1, characterized in that: the equal fixedly connected with gyro wheel (19) in both sides of base (1) bottom, switch (20) are installed in the left side of riser (2), the electrical property output of switch (20) pass through the wire respectively with the electrical property input electric connection of first electric putter (9), servo motor (5) and second electric putter (17).
6. A material lifting device for construction engineering according to claim 1, characterized in that: the right side of the material placing box (10) is communicated with a material discharging pipe, and a valve is arranged on the surface of the material discharging pipe.
CN202023045977.5U 2020-12-17 2020-12-17 Material lifting device for building engineering Expired - Fee Related CN214031529U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023045977.5U CN214031529U (en) 2020-12-17 2020-12-17 Material lifting device for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023045977.5U CN214031529U (en) 2020-12-17 2020-12-17 Material lifting device for building engineering

Publications (1)

Publication Number Publication Date
CN214031529U true CN214031529U (en) 2021-08-24

Family

ID=77338042

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023045977.5U Expired - Fee Related CN214031529U (en) 2020-12-17 2020-12-17 Material lifting device for building engineering

Country Status (1)

Country Link
CN (1) CN214031529U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114084848A (en) * 2021-10-22 2022-02-25 贵州师范大学 Obstacle-crossing type manual forklift
CN114592699A (en) * 2022-03-23 2022-06-07 无锡革新幕墙装饰工程有限公司 Stone material curtain is with supplementary installation device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114084848A (en) * 2021-10-22 2022-02-25 贵州师范大学 Obstacle-crossing type manual forklift
CN114592699A (en) * 2022-03-23 2022-06-07 无锡革新幕墙装饰工程有限公司 Stone material curtain is with supplementary installation device
CN114592699B (en) * 2022-03-23 2024-04-02 无锡革新建设工程有限公司 Auxiliary installation device for stone curtain wall

Similar Documents

Publication Publication Date Title
CN214031529U (en) Material lifting device for building engineering
CN212075107U (en) Slag powder elevator hopper
CN207314758U (en) A kind of building coating bucket easy to use
CN209891271U (en) Hydraulic engineering river trash remover
CN213976873U (en) Lifting device for maintaining cliff painting
CN211338569U (en) Construction lifting device
CN211225833U (en) Cable draw gear for electric power construction
CN211309942U (en) Conveying equipment with height adjusting function
CN212315377U (en) Chemical industry equipment maintenance hoist and mount frame convenient to installation
CN214989910U (en) Improved tail pulley of mixture hoister
CN216512530U (en) Good spare part lifting device of stability for building engineering
CN211946081U (en) Bulk cargo lifting equipment with supplementary anti-overturning mechanism
CN218841585U (en) Novel vertical elevator
CN211589769U (en) Sand blasting equipment for auto-parts
CN213141285U (en) Lifting machine with outward-turning structure
CN210827370U (en) Energy-concerving and environment-protective small-size water sluicegate
CN211357977U (en) Sewage treatment device of paper mill
CN218873058U (en) Aluminum hydroxide washing equipment
CN213434691U (en) Be used for refuse treatment recovery unit
CN218841090U (en) Iron pipe carrying equipment for building construction
CN214178959U (en) Frozen food unfreezing and cleaning equipment
CN210751606U (en) Sewage treatment plant is used in fire control
CN213326464U (en) Auxiliary hoisting equipment for power distribution
CN217971754U (en) Waste plastic material loading lifting machine
CN214453895U (en) Garbage recycling device based on EPC internet of things management

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee