CN213953050U CN202022548945.0U CN202022548945U CN213953050U CN 213953050 U CN213953050 U CN 213953050U CN 202022548945 U CN202022548945 U CN 202022548945U CN 213953050 U CN213953050 U CN 213953050U
Authority
CN
China
Prior art keywords
curtain wall
glass curtain
wall construction
groups
plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022548945.0U
Other languages
Chinese (zh)
Inventor
胡敏达
刘惠蓉
胡财宽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Southwest Industrial Construction Engineering Co ltd
Original Assignee
Jiangxi Southwest Industrial Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Southwest Industrial Construction Engineering Co ltd filed Critical Jiangxi Southwest Industrial Construction Engineering Co ltd
Priority to CN202022548945.0U priority Critical patent/CN213953050U/en
Application granted granted Critical
Publication of CN213953050U publication Critical patent/CN213953050U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a glass curtain wall construction equipment in energy-conserving glass curtain wall construction of high daylighting type, including placement mechanism and coupling mechanism, the coupling mechanism that the multiunit is equidistant distribution is installed respectively to placement mechanism's both sides, placement mechanism includes bottom plate, mount and baffle, the mount has been welded respectively to the both sides at bottom plate top, and wherein is a set of the mount has two sets of baffles that are the symmetric distribution through hinged joint, another group all the welding has two sets of connecting seats that are the symmetric distribution on one side that the mount is close to the baffle and the baffle, it has the multiunit to be equidistant distribution's curtain plate, multiunit to peg graft at the top of bottom plate the curtain plate all is located between two sets of baffles. This glass curtain wall construction equipment in energy-conserving glass curtain wall of high daylighting type construction does not need frequent lift adjustment of lift platform when realizing the high altitude construction installation to glass curtain wall, reduces the equipment burden, prolongs the life of equipment.

Description

Glass curtain wall construction equipment in high-lighting energy-saving glass curtain wall construction
Technical Field
The utility model belongs to the technical field of the glass curtain wall construction, the glass curtain wall construction equipment in the energy-conserving glass curtain wall construction of concretely relates to high daylighting type.
Background
The curtain wall is the outer wall enclosure of the building, does not bear the weight, hangs like a curtain, so is also called as a curtain wall, and is a light wall with decorative effect commonly used by modern large-scale and high-rise buildings. The outer building envelope structure or decorative structure consists of a panel and a support structure system, can have certain displacement capacity or certain deformation capacity relative to a main structure, and does not bear the function of the main structure (an outer wall frame type support system is also one type of a curtain wall system). And high daylighting and energy-conserving glass curtain wall are on the basis of decorating, increase daylighting effect, thereby reduce indoor outer heat transfer speed, improve indoor energy-conserving effect, in the installation to glass curtain wall, but at the bottom of the curtain plate weight, easy to assemble, but when being in large quantity, whole weight is heavier, it is great to the lift burden, so need be after single curtain plate installation, get once more and take, come and go the in-process many times, cause the energy waste easily and increase the impaired degree of equipment, reduce life.
Therefore, in order to meet the current situation, the glass curtain wall construction equipment in the construction of the high-lighting energy-saving glass curtain wall is urgently needed to be designed and produced so as to meet the requirement of practical use.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a glass curtain wall construction equipment in the energy-conserving glass curtain wall construction of high daylighting type to solve the problem that provides in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the glass curtain wall construction equipment in the high-lighting energy-saving glass curtain wall construction comprises a placing mechanism and connecting mechanisms, wherein a plurality of groups of connecting mechanisms which are distributed at equal intervals are respectively arranged on two sides of the placing mechanism;
the placing mechanism comprises a bottom plate, fixing frames and baffle plates, wherein the fixing frames are welded on two sides of the top of the bottom plate respectively, one group of fixing frames are connected with two groups of baffle plates which are symmetrically distributed through hinges, one side, close to the baffle plates, of the other group of fixing frames and the baffle plates are both welded with two groups of connecting seats which are symmetrically distributed, multiple groups of curtain wall plates which are equidistantly distributed are inserted into the top of the bottom plate, the multiple groups of curtain wall plates are located between the two groups of baffle plates, connecting blocks are connected to the tops of the two groups of fixing frames through bolts, clamping plates are welded on the opposite sides of the two groups of connecting blocks, threaded holes are formed in the clamping plates, and clamping screws are screwed on the inner peripheries of the threaded holes;
coupling mechanism includes mounting panel, pivot and the gyro wheel support of multiunit welding on one side of keeping away from the curtain plate at the mount, the interior week of mounting panel is pegged graft and is had the pivot, and the wire-wrap has outside haulage rope in the periphery of pivot, the back welding of mount has two sets of gyro wheel supports that are the symmetric distribution, and installs the pulley in the interior week of gyro wheel support.
Preferably, the fixing frame is provided with a plurality of groups of clamping grooves which are distributed at equal intervals on one side of the curtain wall plate, rubber plates are bonded in the clamping grooves, and the curtain wall plate is clamped between two adjacent groups of rubber plates.
Preferably, [ a1] extrusion grooves are formed in one side of the baffle plate, which is attached to the curtain wall plate, four groups of connecting holes distributed in a rectangular array are formed in an inner cavity of each extrusion groove, connecting screws are screwed in the inner cavities of the connecting holes, extrusion pads are clamped in the inner cavities of the extrusion grooves, and the connecting screws are connected with fixing holes formed in the extrusion pads.
Preferably, the cross section of the pulley is concave, and a buffer rubber ring is bonded on the periphery of the pulley.
Preferably, the number of the mounting plates is at least two, and the cross section of the mounting plates is U-shaped.
The utility model discloses a technological effect and advantage: according to the glass curtain wall construction equipment in the high-lighting energy-saving glass curtain wall construction, the curtain wall plate can be fixed in the fixing frames at two sides through the arrangement of the bottom plate and the fixing frames, so that the storage is convenient; the baffle and the connecting block are arranged, so that the fixing frame moving high above the ground is protected from the front side and the rear side, and the possibility that curtain wall plates fall off from the inside in the high-altitude movement process to cause falling objects is reduced; through being equipped with a plurality of mounting panels and pivot, increase the distance of wire-wrap with the haulage rope to improve the stability in the transportation, reduce single rope head and directly pull, cause the mount to rock easily and lead to the possibility that the object falls from the high altitude, this glass curtain wall construction equipment in the construction of high daylighting type energy-conserving glass curtain wall, when the high altitude construction installation of realization to glass curtain wall, do not need frequent lift adjustment of lift platform, reduce the equipment burden, the life of extension equipment.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a top view of the fixing frame of the present invention;
fig. 3 is a rear view of the baffle of the present invention.
In the figure: 1 placing mechanism, 2 connecting mechanism, 3 bottom plate, 4 fixing frame, 5 mounting plate, 6 rotating shaft, 7 roller bracket, 8 pulley, 9 baffle, 10 connecting seat, 11 curtain wall plate block, 12 connecting block, 13 clamping plate and [ A2 ].
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Unless defined otherwise, all references to up, down, left, right, front, back, inner and outer directions herein are to be interpreted as referring to up, down, left, right, front, back, inner and outer directions in the drawings to which the invention is applied, and all references are hereby incorporated herein by reference.
The utility model provides a glass curtain wall construction device in the construction of a high lighting energy-saving glass curtain wall as shown in figures 1-3, which comprises a placing mechanism 1 and connecting mechanisms 2, wherein a plurality of groups of connecting mechanisms 2 which are distributed at equal intervals are respectively arranged on two sides of the placing mechanism 1;
the placing mechanism 1 comprises a bottom plate 3, fixing frames 4 and baffle plates 9, wherein the fixing frames 4 are welded on two sides of the top of the bottom plate 3 respectively, one group of the fixing frames 4 are connected with two groups of baffle plates 9 which are symmetrically distributed through hinges, the other group of the fixing frames 4 are welded on one side close to the baffle plates 9 and the baffle plates 9 respectively and are provided with two groups of connecting seats 10 which are symmetrically distributed, the connecting of the baffle plates 9 and the fixing frames 4 can be completed through the connecting seats 10 under the action of bolts or bolts matched with nuts, so that the falling of curtain wall plates 11 from the baffle plates 9 is reduced, the hidden installation danger is caused, a plurality of groups of curtain wall plates 11 which are equidistantly distributed are inserted in the top of the bottom plate 3, the plurality of groups of the curtain wall plates 11 are positioned between the two groups of the baffle plates 9, the tops of the two groups of the fixing frames 4 are connected with connecting blocks 12 through bolts, and clamping plates 13 are welded on the opposite sides of the two groups of the connecting blocks 12, the clamping plate 13 is provided with a threaded hole, the inner periphery of the threaded hole is in threaded connection with a clamping screw, the curtain wall plate 11 is clamped and fixed, the front, the back, the left and the right and the bottom of the curtain wall plate can be fixed, the upper side of the curtain wall plate is convenient to disassemble and assemble (a lifting platform is limited, and the situation that the baffle 9 cannot be normally opened through a hinge can exist), a hollow design is adopted, in order to avoid the situation that the curtain wall plate 11 falls off when strong wind drives the fixing frame 4 to rotate at a large angle in high-altitude operation, the top of the fixing frame 4 is connected with a detachable connecting block 12 and a clamping plate 13 through bolts, the curtain wall plate 11 with a certain size is fixed from the upper side, and the fastening effect is improved;
coupling mechanism 2 includes that the multiunit welding keeps away from mounting panel 5, pivot 6 and the gyro wheel support 7 of 11 one sides of curtain plate at mount 4, the interior week of mounting panel 5 is pegged graft and is had pivot 6, and the wire-wrap has outside haulage rope in the periphery of pivot 6, the back welding of mount 4 has two sets of gyro wheel supports 7 that are the symmetric distribution, and installs pulley 8 in the interior week of gyro wheel support 7, can be connected with outside pulling equipment respectively in the pivot 6 of both sides to provide lift power from both sides, the convenient transportation to mount 4 is adjusted, improves stability, pulley 8 is used for and the wall contact, reduces to lead to the mount 4 to appear waving in the effect of wind, and then leads to the glass wall of processing generation to the striking damage.
Specifically, the draw-in groove that the multiunit is equidistant distribution is seted up to mount 4 and one side that curtain plate 11 was laminated mutually, and bonds in the draw-in groove and have the rubber slab, 11 joints of curtain plate improve the clamping force degree between adjacent two sets of rubber slabs, reduce rocking of curtain plate 11 and lead to the possibility of a large amount of wearing and tearing of contact surface.
Specifically, [ a3] extrusion groove has been seted up to one side that baffle 9 and curtain plate 11 laminated mutually, and set up four groups in the inner chamber in extrusion groove and be the connecting hole that the rectangular array distributes, and the spiro union has connecting screw 14 in the inner chamber of connecting hole, the joint has extrusion pad 15 in the inner chamber in extrusion groove, connecting screw 14 is connected with the fixed orifices of seting up on the extrusion pad 15, conveniently accomodate fixedly at baffle 9, extrude fixedly curtain plate 11, and conveniently according to the space that mount 4 left behind the installed curtain plate 11, change different extrusion pads, improve fixed dynamics.
Specifically, pulley 8's cross-section is the spill, and bonds on pulley 8's the periphery and has the cushion rubber circle, at the in-process of transmission, rocks the phenomenon around probably appearing in mount 4, and the cushion rubber circle is used for reducing the impact damage to high building glass wall.
Specifically, the quantity of mounting panel 5 is two sets of at least, and mounting panel 5's cross-section is the U-shaped, realizes transporting from top to bottom under outside traction equipment.
The working principle of the glass curtain wall construction equipment in the high-lighting energy-saving glass curtain wall construction is that when the equipment is used, a worker on a top floor stacks curtain wall plates 11 in a fixing frame 4, sponge plates can be filled between the curtain wall plates 11 to improve the buffering protection effect, then a baffle plate 9 is folded and then is fixedly connected with the fixing frame 4 through a connecting seat 10 under the action of a bolt or a bolt and a nut, then a rotating shaft 6 is in transmission connection with external traction equipment, in the energy-saving glass curtain wall construction process, transmission descending is carried out along a guide rail chain preassembled on an external lifting platform to ensure the transmission direction, and the pulley 8 is in contact with the glass wall surface to reduce the damage to the glass wall surface, in the descending process, the worker on the lifting platform conducts height command through wireless equipment, after the glass curtain wall reaches the lifting platform, the connecting block 12 and the clamping plate 13 are detached, take curtain wall plate 11 out from the top, perhaps under the sufficient condition in lift platform space, directly open the baffle 9 of one side, carry out dismantling of curtain wall plate 11 from the side, conveniently carry out the installation use of curtain wall plate 11.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (5)

1. Glass curtain wall construction equipment in energy-conserving glass curtain wall construction of high daylighting type, including placing mechanism (1) and coupling mechanism (2), its characterized in that: a plurality of groups of connecting mechanisms (2) which are distributed at equal intervals are respectively arranged on two sides of the placing mechanism (1);
the placing mechanism (1) comprises a bottom plate (3), fixing frames (4) and baffle plates (9), the fixing frames (4) are welded on two sides of the top of the bottom plate (3) respectively, one fixing frame (4) is connected with two groups of baffle plates (9) which are symmetrically distributed through hinges, the other fixing frame (4) is welded on one side close to the baffle plates (9) and the baffle plates (9) with two groups of connecting seats (10) which are symmetrically distributed, the top of the bottom plate (3) is inserted with a plurality of groups of curtain wall plates (11) which are equidistantly distributed, the plurality of groups of curtain wall plates (11) are positioned between the two groups of baffle plates (9), the tops of the two groups of fixing frames (4) are connected with connecting blocks (12) through bolts, clamping plates (13) are welded on one opposite sides of the two groups of connecting blocks (12), and threaded holes are formed in the clamping plates (13), the inner periphery of the threaded hole is in threaded connection with a clamping screw;
coupling mechanism (2) include that the multi-unit welding keeps away from mounting panel (5), pivot (6) and gyro wheel support (7) of curtain plate (11) one side in mount (4), the interior week of mounting panel (5) is pegged graft and is had pivot (6), and the wire winding has outside haulage rope in the periphery of pivot (6), the back welding of mount (4) has two sets of gyro wheel supports (7) that are the symmetric distribution, and installs pulley (8) in the interior week of gyro wheel support (7).
2. The glass curtain wall construction equipment in the high lighting energy-saving glass curtain wall construction according to claim 1, characterized in that: the curtain wall plate is characterized in that a plurality of groups of clamping grooves which are distributed at equal intervals are formed in one side, which is attached to the curtain wall plate (11), of the fixing frame (4), rubber plates are bonded in the clamping grooves, and the curtain wall plate (11) is connected between two adjacent groups of rubber plates in a clamping mode.
3. The glass curtain wall construction equipment in the high lighting energy-saving glass curtain wall construction according to claim 1, characterized in that: one side that a set of baffle (9) and curtain plate (11) are laminated mutually has seted up the extrusion groove, and has seted up four groups in the inner chamber in extrusion groove and be the connecting hole that rectangular array distributes, and the spiro union has connecting screw (14) in the inner chamber of connecting hole, and the joint has extrusion pad (15) in the inner chamber in extrusion groove, and the fixed orifices that sets up on connecting screw (14) and the extrusion pad (15) are connected.
4. The glass curtain wall construction equipment in the high lighting energy-saving glass curtain wall construction according to claim 1, characterized in that: the section of the pulley (8) is concave, and a buffer rubber ring is bonded on the periphery of the pulley (8).
5. The glass curtain wall construction equipment in the high lighting energy-saving glass curtain wall construction according to claim 1, characterized in that: the quantity of mounting panel (5) is two sets of at least, and the cross-section of mounting panel (5) is the U-shaped.
CN202022548945.0U 2020-11-06 2020-11-06 Glass curtain wall construction equipment in high-lighting energy-saving glass curtain wall construction Active CN213953050U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022548945.0U CN213953050U (en) 2020-11-06 2020-11-06 Glass curtain wall construction equipment in high-lighting energy-saving glass curtain wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022548945.0U CN213953050U (en) 2020-11-06 2020-11-06 Glass curtain wall construction equipment in high-lighting energy-saving glass curtain wall construction

Publications (1)

Publication Number Publication Date
CN213953050U true CN213953050U (en) 2021-08-13

Family

ID=77207750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022548945.0U Active CN213953050U (en) 2020-11-06 2020-11-06 Glass curtain wall construction equipment in high-lighting energy-saving glass curtain wall construction

Country Status (1)

Country Link
CN (1) CN213953050U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113550539A (en) * 2021-09-22 2021-10-26 南通易和科技有限公司 Mounting bracket convenient to change curtain wall glass

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113550539A (en) * 2021-09-22 2021-10-26 南通易和科技有限公司 Mounting bracket convenient to change curtain wall glass

Similar Documents

Publication Publication Date Title
CN213953050U (en) Glass curtain wall construction equipment in high-lighting energy-saving glass curtain wall construction
CN211201311U (en) Photovoltaic bicycle shed
CN215519415U (en) Corner connecting device for glass curtain wall
CN108775099A (en) A kind of glass curtain wall mounting structure
CN214899601U (en) Over-and-under type block terminal
CN212802424U (en) Aluminum alloy movable type external-suspension scaffold
CN214246247U (en) Stone curtain wall system without cross beam
CN207211451U (en) A kind of stone material dry suspending structure
CN220377607U (en) Anti-collision curtain wall
CN216587197U (en) Building curtain expansion joint processing structure
CN220909094U (en) Construction support with safeguard function
CN212802138U (en) Connecting bottom plate of curtain wall channel
CN215711575U (en) Hanging basket anti-swing device for curtain wall decoration
CN220683205U (en) Curtain wall protection mechanism for preventing transportation damage
CN219322315U (en) Photovoltaic support tail plate
CN216157231U (en) Building engineering that easy to assemble is with protection canopy
CN218264875U (en) Hanging flower basket is used in elevator installation with safety protection
CN212129874U (en) High-safety hanging basket
CN218323383U (en) Energy-saving environment-friendly adjustable photovoltaic curtain wall
CN214125197U (en) High steadiness photovoltaic support
CN218829763U (en) Intelligent power supply system for building curtain wall
CN219960466U (en) Angle-adjustable photovoltaic bracket
CN214989476U (en) Building construction safety device
CN215802515U (en) Positioning mechanism for mounting building curtain wall
CN215410971U (en) Building security protection system is with monitoring device who has angle modulation structure

Legal Events