CN213952647U - Install curtain steel construction fast - Google Patents
Install curtain steel construction fast Download PDFInfo
- Publication number
- CN213952647U CN213952647U CN202022886352.5U CN202022886352U CN213952647U CN 213952647 U CN213952647 U CN 213952647U CN 202022886352 U CN202022886352 U CN 202022886352U CN 213952647 U CN213952647 U CN 213952647U
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- wall
- thick bamboo
- spout
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 20
- 239000010959 steel Substances 0.000 title claims abstract description 20
- 238000010276 construction Methods 0.000 title claims abstract description 12
- 238000007789 sealing Methods 0.000 claims abstract description 42
- 230000007246 mechanism Effects 0.000 claims abstract description 22
- 235000017166 Bambusa arundinacea Nutrition 0.000 claims abstract description 14
- 235000017491 Bambusa tulda Nutrition 0.000 claims abstract description 14
- 241001330002 Bambuseae Species 0.000 claims abstract description 14
- 235000015334 Phyllostachys viridis Nutrition 0.000 claims abstract description 14
- 239000011425 bamboo Substances 0.000 claims abstract description 14
- 230000001815 facial effect Effects 0.000 claims abstract description 7
- 238000003780 insertion Methods 0.000 abstract description 13
- 230000037431 insertion Effects 0.000 abstract description 13
- 230000000694 effects Effects 0.000 description 5
- 238000009434 installation Methods 0.000 description 3
- 239000011521 glass Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000005012 migration Effects 0.000 description 2
- 238000013508 migration Methods 0.000 description 2
- 229910052782 aluminium Inorganic materials 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000000919 ceramic Substances 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The utility model discloses an install curtain steel construction fast, including erecting roof beam group and setting a plurality of crossbeam between it, erect and be equipped with a plurality of slot on the roof beam group inside wall, be equipped with the spout on the terminal surface of crossbeam both sides, sliding connection has the inserted block in the spout, the built-in thrusting mechanism and its one side dress of being equipped with of spout are established on the inserted block, spout inner wall facial make-up is equipped with fixed establishment and its one end and installs on the inserted block, crossbeam both sides cover is equipped with sealed section of thick bamboo, the hoop is equipped with the annular on the terminal surface at slot place, sealed section of thick bamboo one side is inserted and is established in the annular, crossbeam both sides outer wall facial make-up is equipped with moving mechanism, sealed section of thick bamboo dress is established on moving mechanism. The insertion blocks at two sides of the cross beam are respectively inserted into the insertion grooves in the vertical beam group, the insertion blocks are inserted into the insertion grooves under the action of the pushing springs, the insertion blocks are fixed through the fixing screw rods, the sealing cylinders sleeved on the outer sides of the insertion blocks are inserted into the annular grooves under the action of the return springs, and the cross beam mounting device has the advantage of being convenient for fast mounting of the cross beam.
Description
Technical Field
The utility model belongs to the technical field of the steel construction installation, concretely relates to install curtain steel construction fast.
Background
The building curtain wall refers to the non-bearing outer wall enclosure of a building and generally comprises a panel, glass, a metal plate, a stone plate, a ceramic plate and the like, a rear supporting structure aluminum beam column, a steel structure, a glass rib and the like.
The building curtain wall is composed of a supporting structure system and a panel, can have certain displacement capacity relative to the main body structure, and does not share the external protective structure or the decorative structure of the building acted on the main body structure. The curtain wall is an outer wall enclosure of a building, does not bear load, is hung like a curtain, is also called a hanging wall, and is a light wall with decoration effect commonly used by modern large-scale and high-rise buildings. The building envelope structure consists of a structural frame and an embedded plate, and does not bear the load and the action of a main structure. In-process of installing the curtain, need install steel structural framework in advance, steel structural framework comprises crossbeam and perpendicular roof beam, erects to be equipped with horizontal migration mechanism between roof beam and wall body, can make to erect the roof beam and carry out horizontal migration in the certain limit, and this setting is used for the fixed mounting to the crossbeam, and the weak point that exists has: in order to facilitate the installation of the cross beam, the vertical beam is installed on the wall body after the horizontal moving mechanism is installed on the wall body in advance, and then the cross beam can be fixed under the moving of the vertical beam, so that the construction process is complex, the cross beam is installed slowly, and the problem that the cross beam in a curtain wall steel structure is inconvenient to install quickly is solved.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an install curtain steel construction fast to solve the inconvenient problem of installing fast of crossbeam in the curtain steel construction that exists among the prior art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an install curtain steel construction fast, includes erecting roof beam group and sets up a plurality of crossbeam between it, be equipped with a plurality of slot on the roof beam group inside wall, be equipped with the spout on the terminal surface of crossbeam both sides, sliding connection has the inserted block in the spout, the inserted block stretches out the end and inserts and establish in the slot, the built-in pushing mechanism and its one side dress of being equipped with of spout are established on the inserted block, spout inner wall facial make-up is equipped with fixed establishment and its one end and installs on the inserted block, crossbeam both sides cover is equipped with sealed section of thick bamboo, the hoop is equipped with the annular on the terminal surface of slot place, sealed section of thick bamboo one side is inserted and is established in the annular, crossbeam both sides outer wall facial make-up is equipped with moving mechanism, sealed section of thick bamboo dress is established moving mechanism is last.
Preferably, a plurality of sealing grooves are formed in the slot, a plurality of sealing strips are arranged at the extending end of the inserting block, and the sealing strips are inserted in the sealing grooves.
Preferably, the pushing mechanism includes the top and pushes away the spring, top pushes away the spring inboard and installs on the spout inner wall, the spout is the shoulder hole structure, the inserted block is the ladder block structure, top pushes away the spring housing and establishes on the inserted block.
Preferably, the fixing mechanism comprises a fixing screw rod, a plurality of fixing grooves are formed in the outer wall of the inserting block, threaded holes are formed in the inner wall of the sliding groove, the fixing screw rod is inserted into the threaded holes, and the extending end of the fixing screw rod is inserted into the fixing grooves.
Preferably, the moving mechanism comprises a fixed block group, the fixed block group is arranged at two ends of the outer wall of the cross beam, a guide rod is arranged on the fixed block group in an assembled mode, sliding holes are symmetrically formed in the sealing cylinder, the sealing cylinder is connected to the guide rod through the sliding holes in a sliding mode, a return spring is sleeved on the guide rod, and two sides of the return spring are respectively arranged on the fixed block group and the sealing cylinder.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model provides an install curtain steel construction fast, stretch out the end through stretching out at the inserted block and installed a plurality of sealing strip, the sealing strip is inserted and is sealed the processing to the slot in the seal groove, and the sealed section of thick bamboo outside is inserted in the annular on the perpendicular roof beam group, seals the processing to inserted block place terminal surface, has and plays better sealed water-proof effects to the crossbeam junction.
The utility model provides an install curtain steel construction fast, through with inserted block sliding connection in the spout, when needs are installed the crossbeam, only need insert the slot on erecting the roof beam group respectively with the inserted block of crossbeam both sides in, the inserted block inserts in the slot under the top pushes away spring action, and the inserted block fixes through clamping screw, the cover is established and is established in the annular is inserted to the sealed section of thick bamboo in its outside under the reset spring effect, seals the crossbeam junction, has the characteristics of being convenient for install the crossbeam fast.
Drawings
FIG. 1 is a partially cut-away front view of the present invention;
FIG. 2 is an enlarged view of a portion a of FIG. 1;
FIG. 3 is an enlarged view of FIG. 2 at b;
FIG. 4 is an enlarged schematic view of FIG. 2 at c;
fig. 5 is an enlarged schematic view of fig. 2 at d.
In the figure: the device comprises a vertical beam group 1, a cross beam 2, a slot 3, a sliding groove 4, an inserting block 5, a sealing cylinder 6, a ring groove 7, a sealing groove 8, a sealing strip 9, a pushing spring 10, a fixing screw 11, a fixing groove 12, a threaded hole 13, a fixing block group 14, a guide rod 15, a sliding hole 16 and a return spring 17.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
Referring to fig. 1, 2 and 3, a steel structure for fast mounting a curtain wall comprises a vertical beam set 1 and two beams 2 arranged between the vertical beam set 1, wherein two slots 3 are arranged on the inner side wall of the vertical beam set 1, sliding grooves 4 are arranged on the end surfaces of two sides of the beams 2, an insertion block 5 is slidably connected in the sliding grooves 4, the extending end of the insertion block 5 is inserted into the slot 3, two sealing grooves 8 are arranged in the slot 3, two sealing strips 9 are bonded on the extending end of the insertion block 5, the sealing strips 9 are made of rubber and have good sealing and waterproof properties, the sealing strips 9 are inserted into the sealing grooves 8, a pushing mechanism is arranged in the sliding grooves 4 and is welded on the insertion block 5 at the outer side thereof, the pushing mechanism comprises a pushing spring 10, the inner side of the pushing spring 10 is welded on the inner wall of the sliding grooves 4, the sliding grooves 4 are of stepped hole structures, the insertion block 5 is of stepped block structures, the pushing spring 10 is sleeved on the outer wall of the insertion block 5, the pushing spring 10 generates outward spring thrust to the insertion block 5, make it stretch out the end firm insert slot 3 in fix, improve the sealed effect of sealing strip 9 simultaneously, install fixed establishment on the 4 inner walls of spout and insert on inserted block 5 its inner end, fixed establishment includes fixing screw 11, be equipped with five fixed slots 12 on the 5 outer walls of inserted block, be equipped with screw hole 13 on the 4 inner walls of spout, fixing screw 11 has been inserted in the screw hole 13, fixing screw 11 stretches out the end and inserts in fixed slot 12, fixing screw 11 fixes inserted block 5, and fixing screw 11 inserts in the fixed slot 12 of different positions, adjust the volume of stretching out of inserted block 5.
Referring to fig. 1, 2, 4 and 5, sealing cylinders 6 are sleeved on two sides of a cross beam 2, an annular groove 7 is annularly arranged on an end surface where a slot 3 is located, the outer side of each sealing cylinder 6 is inserted into the annular groove 7, the sealing cylinders 6 perform sealing treatment on the surface where an insert block 5 is located, moving mechanisms are installed on outer walls of two sides of the cross beam 2, the sealing cylinders 6 are installed on the moving mechanisms, each moving mechanism comprises a fixed block group 14, the fixed block groups 14 are welded at two ends of the outer wall of the cross beam 2, guide rods 15 are welded on the fixed block groups 14, sliding holes 16 are symmetrically arranged on the sealing cylinders 6, the sealing cylinders 6 are slidably connected to the guide rods 15 through the sliding holes 16, return springs 17 are sleeved on the guide rods 15, the return springs 17 are in an initial state, the initial spring force of the return springs 17 is 30N, two sides of the return springs 17 are respectively welded on the fixed block groups 14 and the sealing cylinders 6, and generate outward spring thrust on the sealing cylinders 6, the sealing cylinder 6 is tightly inserted into the ring groove 7, and the sealing effect is improved.
When the cross beam 2 needs to be installed, an operator inserts the left insert block 5 of the cross beam 2 into the left slot 3 of the corresponding vertical beam group 1, then inserts the right insert block 5 into the right slot 3 of the corresponding vertical beam group 1, the insert block 5 is stably inserted into the corresponding slot 3 under the action of spring thrust generated by the pushing spring 10, the sealing strip 9 on the insert block 5 is inserted into the sealing groove 8 in the slot 3 to seal the slot 3, the sealing cylinder 6 is held by hand to prevent the sealing cylinder 6 from moving outwards to expose the threaded hole 13, then the fixing screw 11 is screwed into the threaded hole 13 to insert the extending end into the fixing groove 12 on the insert block 5 to fix the insert block 5, further, the hand holding the sealing cylinder 6 is loosened, the sealing cylinder 6 moves towards the annular groove 7 under the action of spring thrust generated by the return spring 17, and finally is inserted into the annular groove 7 to seal the end face where the insert block 5 is located, has the characteristic of quick installation of the cross beam 2.
Claims (5)
1. The utility model provides an install curtain steel construction fast, includes vertical beam group (1) and sets up a plurality of crossbeam (2) between it, its characterized in that: be equipped with a plurality of slot (3) on erect roof beam group (1) inside wall, be equipped with spout (4) on crossbeam (2) both sides terminal surface, sliding connection has inserted block (5) in spout (4), inserted block (5) stretch out the end and insert and establish in slot (3), the built-in thrusting mechanism and its one side of being equipped with of spout (4) are established on inserted block (5), spout (4) inner wall facial make-up is equipped with fixed establishment and its one end and installs on inserted block (5), crossbeam (2) both sides cover is equipped with sealed section of thick bamboo (6), the hoop is equipped with annular (7) on the terminal surface in slot (3) place, sealed section of thick bamboo (6) one side is inserted and is established in annular (7), crossbeam (2) both sides outer wall facial make-up is equipped with moving mechanism, sealed section of thick bamboo (6) are installed moving mechanism is last.
2. The steel structure of the curtain wall capable of being rapidly installed according to claim 1, is characterized in that: the novel sealing structure is characterized in that a plurality of sealing grooves (8) are formed in the inserting grooves (3), a plurality of sealing strips (9) are arranged at the extending ends of the inserting blocks (5), and the sealing strips (9) are inserted into the sealing grooves (8).
3. The steel structure of the curtain wall capable of being rapidly installed according to claim 1, is characterized in that: the pushing mechanism comprises a pushing spring (10), the inner side of the pushing spring (10) is installed on the inner wall of the sliding groove (4), the sliding groove (4) is of a stepped hole structure, the inserting block (5) is of a stepped block structure, and the pushing spring (10) is sleeved on the inserting block (5).
4. The steel structure of the curtain wall capable of being rapidly installed according to claim 1, is characterized in that: the fixing mechanism comprises a fixing screw rod (11), a plurality of fixing grooves (12) are formed in the outer wall of the inserting block (5), threaded holes (13) are formed in the inner wall of the sliding groove (4), the fixing screw rod (11) is inserted into the threaded holes (13), and the extending end of the fixing screw rod (11) is inserted into the fixing grooves (12).
5. The steel structure of the curtain wall capable of being rapidly installed according to claim 1, is characterized in that: moving mechanism includes fixed block group (14), fixed block group (14) are installed both ends on crossbeam (2) outer wall, fixed block group (14) facial make-up is equipped with guide arm (15), the symmetry is equipped with slide opening (16) on sealed section of thick bamboo (6), sealed section of thick bamboo (6) are in through slide opening (16) sliding connection on guide arm (15), the cover is equipped with reset spring (17) on guide arm (15), reset spring (17) both sides are installed respectively on fixed block group (14) and sealed section of thick bamboo (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022886352.5U CN213952647U (en) | 2020-12-04 | 2020-12-04 | Install curtain steel construction fast |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022886352.5U CN213952647U (en) | 2020-12-04 | 2020-12-04 | Install curtain steel construction fast |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213952647U true CN213952647U (en) | 2021-08-13 |
Family
ID=77214961
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022886352.5U Expired - Fee Related CN213952647U (en) | 2020-12-04 | 2020-12-04 | Install curtain steel construction fast |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213952647U (en) |
-
2020
- 2020-12-04 CN CN202022886352.5U patent/CN213952647U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN216713515U (en) | Modular curtain wall combined structure | |
CN213952647U (en) | Install curtain steel construction fast | |
CN214117139U (en) | Architectural decoration curtain quick connecting device | |
CN212224326U (en) | Stress-resistant building curtain wall | |
CN211341347U (en) | Closed unit curtain wall system | |
CN211597267U (en) | Energy-saving waterproof curtain wall | |
CN219343659U (en) | Fireproof heat-insulating curtain wall | |
CN215907128U (en) | Architectural decoration curtain quick connecting device | |
CN214034250U (en) | Architectural decoration curtain wall | |
CN215888770U (en) | Novel green ecological building curtain wall with good energy-saving effect | |
CN212336440U (en) | Splicing type energy-saving curtain wall | |
CN213329602U (en) | Novel glass curtain wall unit type device | |
CN217537482U (en) | Shuttle-shaped modeling curtain wall system | |
CN217232330U (en) | Simple curtain wall of aluminum alloy frame-type | |
CN105863133A (en) | Building curtain wall | |
CN215211748U (en) | Novel curtain aluminium veneer installation skeleton texture | |
CN214835714U (en) | Can splice type thermal-insulated curtain door and window | |
CN212271335U (en) | Unit type energy-saving combined curtain wall | |
CN211341341U (en) | Glass curtain wall mounting system | |
CN219298551U (en) | Decorate curtain steel construction | |
CN218508762U (en) | Building curtain wall easy to install | |
CN213869599U (en) | Structural accessory for window-opening optimization design of building curtain wall | |
CN219508966U (en) | Honeycomb panel furred ceiling installed part | |
CN219690832U (en) | Archaize copper curtain wall convenient to install | |
CN211397221U (en) | Glass partition window based on door and window system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210813 |
|
CF01 | Termination of patent right due to non-payment of annual fee |