CN213937225U - Cable laying traction equipment for construction - Google Patents

Cable laying traction equipment for construction Download PDF

Info

Publication number
CN213937225U
CN213937225U CN202022987364.7U CN202022987364U CN213937225U CN 213937225 U CN213937225 U CN 213937225U CN 202022987364 U CN202022987364 U CN 202022987364U CN 213937225 U CN213937225 U CN 213937225U
Authority
CN
China
Prior art keywords
driving motor
cable
install
construction
cable laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022987364.7U
Other languages
Chinese (zh)
Inventor
王璞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Fengxin Electrical Engineering Co ltd
Original Assignee
Beijing Fengxin Electrical Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Fengxin Electrical Engineering Co ltd filed Critical Beijing Fengxin Electrical Engineering Co ltd
Priority to CN202022987364.7U priority Critical patent/CN213937225U/en
Application granted granted Critical
Publication of CN213937225U publication Critical patent/CN213937225U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model provides a construction is with cable laying pulling equipment, including installation base, cable receiving and releasing rim plate, bearing frame and second support, installation base upper end surface is fixed with two bearing frames, two install first axis of rotation between the bearing frame, the cable receiving and releasing rim plate is installed on first axis of rotation, the welding of installation base lower extreme surface right side has two first supports, installation base lower extreme surface middle part is installed the fixed plate, install second driving motor and battery below the fixed plate, the welding of installation base lower extreme surface left side has two second supports, two install the second axis of rotation between the second support, the gyro wheel is all installed at the both ends of second axis of rotation; compared with the prior art, the utility model discloses following beneficial effect has: can place the required position with the cable fast, replace the manual work to promote or pull, reduce working strength.

Description

Cable laying traction equipment for construction
Technical Field
The utility model belongs to the technical field of cable laying, in particular to cable laying pulling equipment for construction.
Background
Cables are generally rope-like cables made by stranding several wires or groups of wires, each group insulated from the other and often twisted around a center, the entire outer surface being covered with a highly insulating covering. The device is erected in the air or installed underground or underwater for telecommunication or power transmission.
In the cable laying process, due to the limitation of a construction site, a worker usually needs to drag a cable with a hand to lay the cable, when the cable is long, the resistance of the cable is large when the cable is dragged, the hand is difficult to hold the cable tightly to drag the cable for a long time, the labor intensity is high, and the working efficiency is low
Therefore, a cable laying traction apparatus for construction is needed to solve the problem.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art exists, the utility model aims at providing a cable laying pulling equipment for construction to solve the problem that provides in the above-mentioned background art.
The technical scheme of the utility model is realized like this: a cable laying traction device for construction comprises an installation base, a cable take-up and pay-off wheel disc, bearing seats and a second support, wherein two bearing seats are fixed on the surface of the upper end of the installation base, a first rotating shaft is installed between the two bearing seats, the cable take-up and pay-off wheel disc is installed on the first rotating shaft, a first driven belt wheel is installed on the first rotating shaft, an installation plate is installed on the surface of the upper end of the installation base, a first driving motor is installed on the installation plate, a first driving belt wheel is installed on an output shaft of the first driving motor, a tool placing box is installed on the right side of the surface of the upper end of the installation base, two first supports are welded on the right side of the surface of the lower end of the installation base, a universal wheel is installed at the bottom of each first support, a fixing plate is installed in the middle of the surface of the lower end of the installation base, and a second driving motor and a storage battery are installed below the fixing plate, the output shaft of the second driving motor is provided with a second driving belt wheel, the left side of the surface of the lower end of the mounting base is welded with two second supports, a second rotating shaft is mounted between the two second supports, rollers are mounted at two ends of the second rotating shaft, and a second driven belt wheel is mounted in the middle of the second rotating shaft.
In a preferred embodiment, the first driven pulley and the first driving pulley are connected by a first belt, and the second driven pulley and the second driving pulley are connected by a second belt.
As a preferred embodiment, a push rod is installed on the right side of the installation base, a handle is installed on the push rod, switches of a first driving motor and a second driving motor are installed on the push rod, and a rubber sleeve is installed on the handle.
In a preferred embodiment, a rolling bearing is mounted in the second bracket, and the second rotating shaft is fixed to the second bracket by two rolling bearings.
In a preferred embodiment, the first driving motor and the second driving motor are connected to the battery through power lines.
In a preferred embodiment, the surface of the cable take-up and pay-off wheel disc is provided with anti-skid lines.
After the technical scheme is adopted, the beneficial effects of the utility model are that: the cable placing device is simple in structure and convenient to operate, and can be used for rapidly placing a cable to a required position to replace a human hand to drag the cable through the arranged first rotating shaft and the cable placing disc; through second driving motor, second driven pulleys and the second driving pulley that sets up for the gyro wheel rotates, replaces the manual work to promote or stimulate, has reduced working strength, and is convenient for adjust the walking direction through the universal wheel that sets up, in the middle of the in-service use process, more be applicable to cable laying technical field.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Fig. 1 is the utility model relates to a construction is with cable laying pulling equipment's overall structure schematic diagram.
Fig. 2 is the utility model relates to a top view of cable laying pulling equipment for construction.
Fig. 3 is the utility model relates to a profile schematic diagram of second axis of rotation of equipment for drawing is laid to cable for construction.
In the figure, 1-universal wheel, 2-first bracket, 3-push rod, 4-handle, 5-tool placing box, 6-mounting plate, 7-first driving motor, 8-first driving pulley, 9-first belt, 10-bearing seat, 11-first rotating shaft, 12-mounting base, 13-second bracket, 14-roller, 15-second rotating shaft, 16-second belt, 17-fixing plate, 18-second driving pulley, 19-second driving motor, 20-storage battery, 21-cable take-up and pay-off wheel disc, 22-first driven pulley, 23-second driven pulley.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1, fig. 2 and fig. 3, the present invention provides a technical solution: a cable laying traction device for construction comprises a mounting base 12, a cable take-up and pay-off wheel disc 21, bearing seats 10 and a second support 13, wherein the upper end surface of the mounting base 12 is fixed with the two bearing seats 10, a first rotating shaft 11 is installed between the two bearing seats 10, the cable take-up and pay-off wheel disc 21 is installed on the first rotating shaft 11, a first driven belt wheel 22 is installed on the first rotating shaft 11, an installation plate 6 is installed on the upper end surface of the mounting base 12, a first driving motor 7 is installed on the installation plate 6, a first driving belt wheel 8 is installed on an output shaft of the first driving motor 7, a tool placing box 5 is installed on the right side of the upper end surface of the mounting base 12, the right side of the lower end surface of the mounting base 12 is welded with the two first supports 2, the bottom of each first support 2 is provided with a universal wheel 1, a fixing plate 17 is installed in the middle part of the lower end surface of the mounting base 12, a second driving motor 19 and a storage battery 20 are installed below the fixing plate 17, a second driving pulley 18 is mounted on an output shaft of the second driving motor 19, two second supports 13 are welded on the left side of the surface of the lower end of the mounting base 12, a second rotating shaft 15 is mounted between the two second supports 13, rollers 14 are mounted at two ends of the second rotating shaft 15, and a second driven pulley 23 is mounted in the middle of the second rotating shaft 15.
The first driven pulley 22 is connected to the first driving pulley 8 via a first belt 9, and the second driven pulley 23 is connected to the second driving pulley via a second belt 16.
The push rod 3 is installed on the right side of the installation base 12, the handle 4 is installed on the push rod 3, the first driving motor 7 and the second driving motor 19 are installed on the push rod 3, and the rubber sleeve is installed on the handle 4.
The second bracket 13 is internally provided with a rolling bearing, and the second rotating shaft 15 is fixed on the second bracket 13 through two rolling bearings.
The first drive motor 7 and the second drive motor 19 are connected to the battery 20 through power lines.
The surface of the cable take-up and pay-off wheel disc 21 is provided with anti-skid lines.
As an embodiment of the present invention: in actual use, a cable is wound on the cable take-up and pay-off disc firstly, then the equipment is moved to the position where the cable is laid, one end of the cable is fixed at the laid position, then the switch of the first driving motor 7 is pressed, at the moment, the first driving motor 7 starts to work, under the action of the first driving pulley 8 and the first driven pulley 22, the first rotating shaft 11 starts to rotate, the cable wound on the cable take-up and pay-off disc is laid down, then the switch of the second driving motor 19 is pressed, under the action of the second driving pulley 18 and the second driven pulley 23, the second rotating shaft 15 rotates, and a worker holds the handle 4 to move the equipment along the required laying position.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a construction is with cable laying pulling equipment, includes installation base (12), cable receive and releases rim plate (21), bearing frame (10) and second support (13), its characterized in that: the cable winding and unwinding device is characterized in that two bearing seats (10) are fixed on the upper end surface of the mounting base (12), a first rotating shaft (11) is installed between the two bearing seats (10), a cable winding and unwinding wheel disc (21) is installed on the first rotating shaft (11), a first driven belt pulley (22) is installed on the first rotating shaft (11), a mounting plate (6) is installed on the upper end surface of the mounting base (12), a first driving motor (7) is installed on the mounting plate (6), a first driving belt pulley (8) is installed on an output shaft of the first driving motor (7), an instrument placing box (5) is installed on the right side of the upper end surface of the mounting base (12), two first supports (2) are welded on the right side of the lower end surface of the mounting base (12), a universal wheel (1) is installed at the bottom of each first support (2), and a fixing plate (17) is installed in the middle position of the lower end surface of the mounting base (12), second driving motor (19) and battery (20) are installed to fixed plate (17) below, install second driving pulley (18) on the output shaft of second driving motor (19), installation base (12) lower extreme surface left side welding has two second supports (13), two install second axis of rotation (15) between second support (13), gyro wheel (14) are all installed at the both ends of second axis of rotation (15), second driven pulley (23) are installed to the middle part of second axis of rotation (15).
2. The construction cable laying traction apparatus as claimed in claim 1, wherein: the first driven belt wheel (22) is connected with the first driving belt wheel (8) through a first belt (9), and the second driven belt wheel (23) is connected with the second moving belt wheel through a second belt (16).
3. The construction cable laying traction apparatus as claimed in claim 1, wherein: install push rod (3) on installation base (12) right side, install handle (4) on push rod (3), install the switch of first driving motor (7) and second driving motor (19) on push rod (3), install the rubber sleeve on handle (4).
4. The construction cable laying traction apparatus as claimed in claim 1, wherein: and a rolling bearing is installed in the second support (13), and the second rotating shaft (15) is fixed on the second support (13) through two rolling bearings.
5. The construction cable laying traction apparatus as claimed in claim 1, wherein: the first driving motor (7), the second driving motor (19) and the storage battery (20) are connected through power lines.
6. The construction cable laying traction apparatus as claimed in claim 1, wherein: and anti-skid lines are arranged on the surface of the cable take-up and pay-off wheel disc (21).
CN202022987364.7U 2020-12-11 2020-12-11 Cable laying traction equipment for construction Active CN213937225U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022987364.7U CN213937225U (en) 2020-12-11 2020-12-11 Cable laying traction equipment for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022987364.7U CN213937225U (en) 2020-12-11 2020-12-11 Cable laying traction equipment for construction

Publications (1)

Publication Number Publication Date
CN213937225U true CN213937225U (en) 2021-08-10

Family

ID=77151606

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022987364.7U Active CN213937225U (en) 2020-12-11 2020-12-11 Cable laying traction equipment for construction

Country Status (1)

Country Link
CN (1) CN213937225U (en)

Similar Documents

Publication Publication Date Title
CN213265038U (en) Electric power installation pay-off
CN213937225U (en) Cable laying traction equipment for construction
CN214934812U (en) Energy-saving transmission equipment cable auxiliary laying device
CN217126506U (en) A novel cabling machine for wire and cable processing
CN211930115U (en) Cable erecting device for building electromechanical installation
CN215516109U (en) Multifunctional cable laying device
CN210064749U (en) Cable collecting box for power grid construction
CN210193021U (en) Quick wire drawing device for power distribution network cable
CN108777447B (en) Walking trolley for overhead cable
CN210985441U (en) Overhead wiring and wiring guide for cable
CN212151137U (en) Cable coiling mechanism for communication engineering
CN211456495U (en) Mechanical equipment for laying ground optical cable
CN211151353U (en) Cable laying equipment
CN211456499U (en) Communication pipeline installation equipment
CN219259209U (en) Line paying-off vehicle
CN221079715U (en) Wire burying device for wire production
CN217148166U (en) Coal-winning machine cable fixing device
CN219918224U (en) Portable cable insulation electric stripping and cutting device
CN214012612U (en) Semi-automatic winding device for wire harness insulating adhesive tape
CN219708791U (en) Wire and cable paying-off device
CN214780013U (en) Cantilever crane structure for cable transmission
CN216770598U (en) Cable channel for hydrological monitoring
CN214100620U (en) Cable traction device for cable laying
CN216785351U (en) Cable construction draw gear for power engineering
CN217126488U (en) Cable storage device convenient to transport

Legal Events

Date Code Title Description
GR01 Patent grant