CN213854776U - Civil engineering construction waste treatment device - Google Patents

Civil engineering construction waste treatment device Download PDF

Info

Publication number
CN213854776U
CN213854776U CN202022476530.7U CN202022476530U CN213854776U CN 213854776 U CN213854776 U CN 213854776U CN 202022476530 U CN202022476530 U CN 202022476530U CN 213854776 U CN213854776 U CN 213854776U
Authority
CN
China
Prior art keywords
wall
box
construction waste
box body
inlet pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022476530.7U
Other languages
Chinese (zh)
Inventor
周海艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022476530.7U priority Critical patent/CN213854776U/en
Application granted granted Critical
Publication of CN213854776U publication Critical patent/CN213854776U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a civil engineering construction waste material processing apparatus, the power distribution box comprises a box body, the top outer wall of box is opened there is the round hole, and pegs graft in the inside of round hole and have the inlet pipe, the cross section of inlet pipe is the arc, and the both sides inner wall of box all is provided with crushing tooth, the both sides inner wall of box all is provided with the fixed block. The utility model discloses can add it to the box inside through the inlet pipe when people need carry out shredding to construction waste, the cross section of inlet pipe is the arc simultaneously, and one side inner wall of inlet pipe is provided with first baffle, can block the dust at the in-process of adding construction waste, avoid a large amount of dust excessive to cause the injury to staff's health on every side, the inside second spring and the buffer board that sets up of inlet pipe can play the effect of good building buffering to adding to the inside waste material of box simultaneously, avoid the waste material lump head great to cause the damage to the box inside.

Description

Civil engineering construction waste treatment device
Technical Field
The utility model relates to a civil engineering technical field especially relates to a civil engineering construction waste material processing apparatus.
Background
Civil engineering is a general term for scientific and technical techniques for building various engineering facilities, and refers to both applied materials, equipment, and technical activities such as surveying, designing, constructing, maintaining, and repairing, and also refers to objects of engineering construction. I.e. various engineering facilities, such as houses, roads, railways, pipes, tunnels, bridges, canals, dams, ports, power stations, airports, ocean platforms, water supply and drainage and protection projects, which are built on or under the ground, on the land or in water, and serve for human life, production, military affairs and scientific research directly or indirectly.
Can produce a large amount of construction waste at civil engineering construction's in-process, general waste material processing apparatus is at the in-process of handling it, often can produce a large amount of dusts, has not only increased the pollution degree of building site environment, has still caused very big injury to workman's health on every side, can not satisfy people to the processing demand of construction waste. Therefore, there is a need for a civil engineering construction waste treatment apparatus to solve the above problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a civil engineering construction waste treatment device.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a civil engineering construction waste material processing apparatus, includes the box, the top outer wall of box is opened there is the round hole, and pegs graft in the inside of round hole and have the inlet pipe, the cross section of inlet pipe is the arc, and the both sides inner wall of box all is provided with crushing tooth, the both sides inner wall of box all is provided with the fixed block, and one side outer wall of fixed block is provided with the first tooth piece that the equidistance distributes, the spout has all been opened to the both sides inner wall of box, and one side inner wall sliding connection of spout has the slider, one side outer wall of slider is provided with the connecting plate, and one side outer wall that the slider was kept away from to the connecting plate is provided with the filter screen, one side outer wall of box is opened there is the opening, and the inside of open-ended is pegged graft and is had the discharge tube.
Preferably, the inner walls of the two sides of the box body are provided with supporting plates, the outer wall of the top of each supporting plate is provided with a first spring, and one end, far away from the supporting plates, of each first spring is welded on the outer wall of the bottom of each connecting plate.
Preferably, one side inner wall of inlet pipe is provided with the mounting panel, and one side outer wall of mounting panel rotates and is connected with the pivot, and one side outer wall of pivot is provided with first baffle, and the top inner wall of inlet pipe is provided with first baffle.
Preferably, one side inner wall of inlet pipe is provided with the second spring, and the one end that the inlet pipe was kept away from to the second spring is provided with the buffer board.
Preferably, the outer wall of one side of the box body is provided with a hinge, and the outer wall of one side of the hinge is provided with a box door.
Preferably, the inner wall of one side of the box body is provided with a second baffle, and the outer wall of one side of the second baffle, which is far away from the box body, is in contact with the outer wall of the top of the filter screen.
The utility model has the advantages that:
1. through the inlet pipe that sets up, first baffle, second spring and buffer board, can add it to the box inside through the inlet pipe when people need carry out shredding to construction waste, the cross section of inlet pipe is the arc simultaneously, and one side inner wall of inlet pipe is provided with first baffle, can block the dust at the in-process of adding construction waste, avoid a large amount of dust excessive to cause the injury to staff's health on every side, the effect of good building buffering can be played to the waste material of adding to the box inside to second spring and buffer board that the inside setting of inlet pipe simultaneously, avoid the waste material piece head great to cause the damage inside the box.
2. Through crushing tooth, spout, slider, filter screen and the spring that sets up, the waste material that adds from the inlet pipe falls in the top of smashing the tooth, smashes the intermeshing between the tooth through two and can carry out abundant crushing to the waste material, and the construction waste after smashing simultaneously can sieve it through the filter screen, has guaranteed the crushing effect of device to construction waste.
3. Through the second baffle that sets up, when the filter screen carries out shale shaker to the waste material after smashing, the second baffle that filter screen top outer wall set up can play good effect of blockking to the waste material, avoids inside it falls into the spout, causes the dead condition of slider card, has guaranteed the stability of device operation in-process.
Drawings
FIG. 1 is a schematic view showing the construction of a civil engineering construction waste treatment apparatus according to example 1;
FIG. 2 is an enlarged schematic view of the waste treatment apparatus for civil engineering construction according to example 1 at the point A;
FIG. 3 is a schematic view showing the overall construction of a civil engineering construction waste treatment apparatus according to example 1;
fig. 4 is a schematic view of a second baffle structure of the civil engineering construction waste treatment device provided in embodiment 2.
In the figure: the device comprises a box body 1, a fixed block 2, a discharge pipe 3, a filter screen 4, a connecting plate 5, a sliding chute 6, a supporting plate 7, a first spring 8, a sliding block 9, a first tooth block 10, crushing teeth 11, a feeding pipe 12, a first baffle 13, a mounting plate 14, a second spring 15, a buffer plate 16, a box door 17 and a second baffle 18.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Example 1
Referring to fig. 1-3, a civil engineering construction waste treatment device, including box 1, the top outer wall of box 1 is opened there is the round hole, and the inside of round hole is pegged graft there is inlet pipe 12, the cross section of inlet pipe 12 is the arc, and the both sides inner wall of box 1 all is provided with crushing tooth 11, the both sides inner wall of box 1 all has fixed block 2 through bolted connection, and the welding of one side outer wall of fixed block 2 has first tooth piece 10 that the equidistance distributes, spout 6 has all been opened to the both sides inner wall of box 1, and one side inner wall sliding connection of spout 6 has slider 9, one side outer wall of slider 9 has connecting plate 5 through bolted connection, and one side outer wall that slider 9 was kept away from to connecting plate 5 has filter screen 4 through bolted connection, one side outer wall of box 1 is opened there is the opening, and the discharge tube 3 has been pegged graft in the open-ended inside.
The utility model discloses in, box 1's both sides inner wall all has backup pad 7 through bolted connection, and the welding of the top outer wall of backup pad 7 has first spring 8, the one end welding that backup pad 7 was kept away from to first spring 8 is on the bottom outer wall of connecting plate 5, one side inner wall welding of inlet pipe 12 has mounting panel 14, and one side outer wall rotation of mounting panel 14 is connected with the pivot, the welding of one side outer wall of pivot has first baffle 13, the welding of the top inner wall of inlet pipe 12 has first baffle 13, one side inner wall welding of inlet pipe 12 has second spring 15, and the welding of the one end of inlet pipe 12 was kept away from to second spring 15 has buffer board 16, one side outer wall of box 1 has the hinge through bolted connection, and one side outer wall of hinge has chamber door 17 through bolted connection.
The working principle is as follows: when people need to crush the construction waste, the construction waste can be added into the box body 1 through the feeding pipe 12, meanwhile, the cross section of the feeding pipe 12 is arc-shaped, a first baffle 13 is arranged on the inner wall of one side of the feeding pipe 12, can block dust in the process of adding construction waste, avoids the damage to the bodies of surrounding workers due to the overflow of a large amount of dust, meanwhile, the second spring 15 and the buffer plate 16 arranged in the feeding pipe 12 can play a good role in building and buffering the waste materials added into the box body 1, the situation that the waste material blocks are large and damage the inside of the box body 1 is avoided, the waste materials added from the feeding pipe 12 fall above the crushing teeth 11, the waste materials can be fully crushed through the mutual meshing between the two crushing teeth 11, meanwhile, the crushed construction waste can be screened through the filter screen 4, and the crushing effect of the device on the construction waste is guaranteed.
Example 2
Referring to fig. 4, in the present embodiment, compared to embodiment 1, the inner wall of one side of the box body 1 is connected to the second baffle 18 through the bolt, and the outer wall of one side of the second baffle 18 away from the box body 1 contacts with the outer wall of the top of the filter screen 4.
The working principle is as follows: when the filter screen 4 carries out vibrating screen to the waste material after smashing, the second baffle 18 that the outer wall in 4 tops of filter screen set up can play good effect of blockking to the waste material, avoids it to fall into inside spout 6, causes the dead condition of slider 9 card, has guaranteed the stability of device operation in-process.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The civil engineering construction waste treatment device comprises a box body (1) and is characterized in that a round hole is formed in the outer wall of the top of the box body (1), a feeding pipe (12) is inserted into the round hole, the cross section of the feeding pipe (12) is arc-shaped, crushing teeth (11) are arranged on the inner walls of two sides of the box body (1), fixed blocks (2) are arranged on the inner walls of two sides of the box body (1), first tooth blocks (10) distributed equidistantly are arranged on the outer wall of one side of each fixed block (2), sliding grooves (6) are formed in the inner walls of two sides of the box body (1), sliding blocks (9) are connected to the inner walls of one sides of the sliding grooves (6) in a sliding mode, a connecting plate (5) is arranged on the outer wall of one side of each sliding block (9) far away from the corresponding connecting plate (5), a filter screen (4) is arranged on the outer wall of one side of the box body (1), and a discharge pipe (3) is inserted in the opening.
2. The civil engineering construction waste treatment device according to claim 1, wherein the inner walls of the two sides of the box body (1) are provided with support plates (7), the outer wall of the top of each support plate (7) is provided with a first spring (8), and one end of each first spring (8) far away from each support plate (7) is welded on the outer wall of the bottom of each connecting plate (5).
3. The civil engineering construction waste treatment device of claim 2, wherein the inlet pipe (12) is provided with a mounting plate (14) on one side of the inner wall, the mounting plate (14) is rotatably connected with a rotating shaft on one side of the outer wall, the rotating shaft is provided with a first baffle (13) on one side of the outer wall, and the inlet pipe (12) is provided with a first baffle (13) on the top of the inner wall.
4. The civil engineering construction waste treatment device of claim 3, wherein the feed pipe (12) is provided with a second spring (15) on one side of the inner wall, and a buffer plate (16) is arranged on one end of the second spring (15) far away from the feed pipe (12).
5. The civil engineering construction waste treatment device according to claim 4, wherein one side outer wall of the box body (1) is provided with a hinge, and one side outer wall of the hinge is provided with a box door (17).
6. The civil engineering construction waste treatment device according to claim 4 or 5, wherein the inner wall of one side of the box body (1) is provided with a second baffle (18), and the outer wall of one side of the second baffle (18) far away from the box body (1) is contacted with the outer wall of the top of the filter screen (4).
CN202022476530.7U 2020-11-01 2020-11-01 Civil engineering construction waste treatment device Expired - Fee Related CN213854776U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022476530.7U CN213854776U (en) 2020-11-01 2020-11-01 Civil engineering construction waste treatment device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022476530.7U CN213854776U (en) 2020-11-01 2020-11-01 Civil engineering construction waste treatment device

Publications (1)

Publication Number Publication Date
CN213854776U true CN213854776U (en) 2021-08-03

Family

ID=77051650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022476530.7U Expired - Fee Related CN213854776U (en) 2020-11-01 2020-11-01 Civil engineering construction waste treatment device

Country Status (1)

Country Link
CN (1) CN213854776U (en)

Similar Documents

Publication Publication Date Title
CN107335498A (en) A kind of construction waste crushing screening plant
CN213854776U (en) Civil engineering construction waste treatment device
CN212441499U (en) Civil engineering construction waste treatment device
CN208679301U (en) A kind of civil engineering work waste treatment device
CN212493137U (en) A garbage collection device for green building construction
CN212549743U (en) Breaker is used in hydraulic engineering construction
CN210159732U (en) High-efficient rubble device is used to mining machinery
CN215655624U (en) Civil engineering is with construction waste processing apparatus of built-in sieve material structure
CN212189268U (en) Waste material reducing mechanism for civil engineering
CN217368555U (en) Building rubbish shredding device
CN109317290A (en) A kind of energy-efficient screening vertical-shaft sand making machine
CN209901384U (en) Stone breaker for construction
CN216879560U (en) Rubble device that civil engineering used
CN216368196U (en) Building waste treatment equipment that civil engineering used
CN215694312U (en) Building waste grading reducing mechanism for civil engineering
CN214288700U (en) Solid waste reducing mechanism that civil engineering used
CN221733616U (en) Civil engineering construction waste treatment device
CN214681989U (en) Civil engineering construction waste material processing apparatus
CN219291534U (en) Stone crushing device for civil engineering
CN212396846U (en) Breaker for water conservancy construction with safeguard function
CN215940115U (en) Construction waste treatment recovery unit for engineering
CN214320265U (en) Civil engineering green construction waste treatment device
CN214210668U (en) Four-roller crusher with protective structure
CN219111723U (en) Rubbish recovery unit for construction
CN212524858U (en) Civil engineering is with portable screening sand device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210803