CN213837769U - Spraying dust-settling and cooling device for construction working face of building - Google Patents

Spraying dust-settling and cooling device for construction working face of building Download PDF

Info

Publication number
CN213837769U
CN213837769U CN202022784894.1U CN202022784894U CN213837769U CN 213837769 U CN213837769 U CN 213837769U CN 202022784894 U CN202022784894 U CN 202022784894U CN 213837769 U CN213837769 U CN 213837769U
Authority
CN
China
Prior art keywords
fixedly connected
frame
fixed
convenient
elevating gear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022784894.1U
Other languages
Chinese (zh)
Inventor
闫磊
时昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Zhongxin Construction Engineering Co Ltd
Original Assignee
China Construction Zhongxin Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Zhongxin Construction Engineering Co Ltd filed Critical China Construction Zhongxin Construction Engineering Co Ltd
Priority to CN202022784894.1U priority Critical patent/CN213837769U/en
Application granted granted Critical
Publication of CN213837769U publication Critical patent/CN213837769U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a construction operation face sprays dust fall heat sink is built in room, comprising a base plate, the bottom fixedly connected with universal wheel of bottom plate, the top fixedly connected with water storage frame of bottom plate, the utility model relates to a construction technical field. This construction operation face sprays dust fall heat sink is built in room, whole removal of being convenient for has been reached, utilize the water storage frame to carry out the water storage, water pump work, pass through the pipe with the water in the storing frame, spout through the shower head, be convenient for spray the dust fall to the construction face, set up the handle, make things convenient for the staff to operate, spray the assigned position, set up elevating gear, be convenient for adjust holistic height, install mount and elevating gear through fixing device, utilize elevating gear to adjust, be convenient for spray different high, improve the spray range, set up stop device, be convenient for fix elevating gear, make things convenient for the staff to operate, satisfy user demand's purpose.

Description

Spraying dust-settling and cooling device for construction working face of building
Technical Field
The utility model relates to a construction field, more specifically say, relate to a construction working face sprays dust fall heat sink is built in room.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like. In the process of building construction, a spraying device is needed to be used for spraying, reducing dust and cooling a construction working face. At present, the construction working face sprays dust fall heat sink is built in current room, and overall structure is fixed relatively, and the staff of being not convenient for removes the use, and highly is not convenient for adjust, and the influence sprays the dust fall effect, can't satisfy the user demand.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
Aiming at the problems that the prior spraying dust-settling and cooling device for the construction working face of house construction in the prior art has relatively fixed integral structure, is inconvenient for workers to move and use, has inconvenient height adjustment, influences the spraying dust-settling effect and cannot meet the use requirement, the utility model aims to provide a spraying dust-settling and cooling device for the construction working face of house construction, which can realize that a bottom plate, universal wheels, a water storage frame, a handle, a water pump, a conduit, a fixing frame, a spraying head and a handle form an integral body, is convenient to move integrally, utilizes the water storage frame to store water, enables the water pump to work, sprays water in a storage frame through the conduit and the spraying head, is convenient to spray and settle dust on the construction face, is provided with a handle, is convenient for the workers to operate, sprays at a designated position, is provided with a lifting device, is convenient for adjusting the integral height, and installs the fixing frame and the lifting device through a fixing device, utilize elevating gear to adjust, be convenient for spray different high, improve the spray range, set up stop device, be convenient for fix elevating gear, make things convenient for the staff to operate, satisfy the user demand.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
The utility model provides a construction working face sprays dust fall heat sink is built in room, includes the bottom plate, the bottom fixedly connected with universal wheel of bottom plate, the top fixedly connected with water storage frame of bottom plate, the lateral wall fixedly connected with handle of water storage frame, the inside of water storage frame is provided with the water pump, the output fixedly connected with pipe of water pump, the one end fixedly connected with mount of water pump is kept away from to the pipe, the fixed surface of mount is connected with the shower head, the top fixedly connected with handle of mount.
Preferably, the top of the bottom plate is fixedly connected with a lifting device, the side wall of the lifting device is provided with a limiting device, the top of the lifting device is fixedly connected with a fixing device, and the fixing device is fixedly connected with a fixing frame.
Preferably, elevating gear includes the stand, the top fixedly connected with fixed plate of stand, fixed plate sliding connection has the motion pole, the bottom fixedly connected with slider of motion pole, slider and stand sliding connection, the lateral wall fixedly connected with action bars of motion pole, the top and the stop device fixed connection of stand, the top and the fixing device fixed connection of motion pole.
Preferably, the limiting device comprises a limiting frame, the limiting frame is fixedly connected with the stand column, a supporting spring is fixedly connected to the inner wall of the limiting frame, the limiting frame is fixedly connected with a supporting block through the supporting spring, a pull rod is fixedly connected to the side wall of the supporting block, the pull rod is slidably connected with the limiting frame, a pull block is fixedly connected to the end portion of the pull rod, a clamping rod is fixedly connected to the surface of the supporting block, the clamping rod is slidably connected with the stand column, a clamping groove is formed in the surface of the moving rod, and the clamping rod is clamped with the clamping groove.
Preferably, fixing device includes fixed frame, fixed frame and motion pole fixed connection, the top of fixed frame is provided with the installing frame, installing frame top and mount fixed connection, the installing frame docks with fixed frame, fixed frame is installed through construction bolt and installing frame.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of: the water storage device is characterized in that the device is integrated with a handle through a bottom plate, universal wheels, a water storage frame, a handle, a water pump, a guide pipe, a fixing frame, a spray head and the handle, the whole device is convenient to move, water is stored by the water storage frame, the water pump works to spray water in the storage frame through the guide pipe and the spray head to facilitate spraying and dust falling on a construction surface, the handle is arranged to facilitate operation of workers, a designated position is sprayed, a lifting device is arranged to facilitate adjustment of the whole height, the fixing frame and the lifting device are installed through a fixing device and are adjusted by the lifting device to facilitate spraying at different heights, the spraying range is improved, a limiting device is arranged to facilitate fixing of the lifting device, after the fixing frame and the top of the lifting device are installed, the fixed position is convenient to spray, when the spraying height needs to be changed, the limitation of the limiting device is removed, the operating rod is held by the handle, the movable rod is driven to move upwards to further adjust the height of the spray head, the movable rod is driven to move upwards, the use is convenient, when the integral height needs to be adjusted, the pull block is pulled to drive the pull rod to move, the support block is driven to move, the elastic potential energy of the support spring is increased, the clamping rod is driven to contract, the limitation on the clamping groove is removed, the position of the lifting device can be adjusted, the pull block is loosened, the elastic potential energy of the support spring is converted into kinetic energy to drive the support block to reset, the clamping rod and the clamping groove are clamped again, the height of the lifting device can be fixed, the mounting frame arranged at the bottom of the fixing frame corresponds to the fixing frame at the top of the movable rod, the spray head can be fixed through the mounting bolt, the use by workers is convenient, the base plate, the universal wheel, the water storage frame, the handle, the water pump, the guide pipe, the fixing frame, the spray head and the handle form an integral body, wholly be convenient for remove, utilize the water storage frame to carry out the water storage, water pump work, pass through the pipe with the water in the storing frame, spout through the shower head, be convenient for spray the dust fall to the construction face, set up the handle, make things convenient for the staff to operate, spray the assigned position, set up elevating gear, be convenient for adjust holistic height, install mount and elevating gear through fixing device, utilize elevating gear to adjust, be convenient for spray the co-altitude, improve the spray range, set up stop device, be convenient for fix elevating gear, make things convenient for the staff to operate, satisfy user demand's purpose.
Drawings
Fig. 1 is a schematic view of the overall external structure of the present invention;
FIG. 2 is a schematic view of the overall internal structure of the present invention;
fig. 3 is a schematic view of a partial enlarged structure at a in fig. 2 according to the present invention;
fig. 4 is a schematic diagram of a partial enlarged structure at B of fig. 2 according to the present invention.
The reference numbers in the figures illustrate:
1. a base plate; 2. a universal wheel; 3. a water storage frame; 4. a handle; 5. a water pump; 6. a conduit; 7. a fixed mount; 8. a shower head; 9. a grip; 10. a lifting device; 101. a column; 102. a fixing plate; 103. a motion bar; 104. a slider; 105. an operating lever; 11. a limiting device; 111. a limiting frame; 112. a support spring; 113. a support block; 114. a pull rod; 115. pulling the block; 116. a clamping rod; 117. a card slot; 12. a fixing device; 121. a fixing frame; 122. installing a frame; 123. and (6) installing a bolt.
Detailed Description
The drawings in the embodiments of the present invention will be combined; the technical scheme in the embodiment of the utility model is clearly and completely described; obviously; the described embodiments are only some of the embodiments of the present invention; rather than all embodiments. Based on the embodiment of the utility model; all other embodiments obtained by a person skilled in the art without making any inventive step; all belong to the protection scope of the utility model.
Example 1:
referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a construction operation face sprays dust fall heat sink is built in room, comprising a base plate 1, the bottom fixedly connected with universal wheel 2 of bottom plate 1, the top fixedly connected with water storage frame 3 of bottom plate 1, the lateral wall fixedly connected with handle 4 of water storage frame 3, the inside of water storage frame 3 is provided with water pump 5, water pump 5's output fixedly connected with pipe 6, water pump 5's one end fixedly connected with mount 7 is kept away from to pipe 6, the fixed surface of mount 7 is connected with shower head 8, the top fixedly connected with handle 9 of mount 7. Bottom plate 1, universal wheel 2, water storage frame 3, handle 4, water pump 5, pipe 6, mount 7, shower head 8 and handle 9 constitute a whole, and the whole removal of being convenient for utilizes water storage frame 3 to carry out the water storage, and water pump 5 work passes through pipe 6 with the water in the storage frame 3, through 8 blowout of shower head, is convenient for spray the dust fall to the construction face, sets up handle 9, makes things convenient for the staff to hand and operates, sprays the assigned position.
Example 2:
referring to fig. 2, a spraying dust-settling and cooling device for a construction working surface of a building is substantially the same as that of embodiment 1, and further, a lifting device 10 is fixedly connected to the top of the bottom plate 1, a limiting device 11 is disposed on a side wall of the lifting device 10, a fixing device 12 is fixedly connected to the top of the lifting device 10, and the fixing device 12 is fixedly connected to the fixing frame 7. Set up elevating gear 10, be convenient for adjust holistic height, install mount 7 and elevating gear 10 through fixing device 12, utilize elevating gear 10 to adjust, be convenient for spray different highly, improve the spray range, set up stop device 11, be convenient for fix elevating gear 10, and then spray fixed position.
Example 3:
referring to fig. 2, a spraying dust-settling and cooling device for a construction working surface of a building is substantially the same as that of embodiment 2, and further, the lifting device 10 includes a column 101, a fixing plate 102 is fixedly connected to the top of the column 101, the fixing plate 102 is slidably connected to a moving rod 103, a slider 104 is fixedly connected to the bottom of the moving rod 103, the slider 104 is slidably connected to the column 101, an operating rod 105 is fixedly connected to the side wall of the moving rod 103, the top of the column 101 is fixedly connected to a limiting device 11, and the top of the moving rod 103 is fixedly connected to a fixing device 12. When the spraying height needs to be changed, the limit of the limiting device 11 is removed, the operating rod 105 is held by a hand, the sliding block 104 is driven to move upwards, the moving rod 103 is driven to move upwards, and then the height of the spraying head 8 is adjusted, so that the spraying height is convenient to use.
Example 4:
referring to fig. 3, a spraying dust-settling and cooling device for a building construction working surface is substantially the same as that in embodiment 3, and further, the limiting device 11 includes a limiting frame 111, the limiting frame 111 is fixedly connected to the upright post 101, a supporting spring 112 is fixedly connected to an inner wall of the limiting frame 111, the limiting frame 111 is fixedly connected to a supporting block 113 through the supporting spring 112, a pull rod 114 is fixedly connected to a side wall of the supporting block 113, the pull rod 114 is slidably connected to the limiting frame 111, a pull block 115 is fixedly connected to an end of the pull rod 114, a clamping rod 116 is fixedly connected to a surface of the supporting block 113, the clamping rod 116 is slidably connected to the upright post 101, a clamping groove 117 is formed in a surface of the moving rod 103, and the clamping rod 116 is clamped to the clamping groove 117. When the overall height needs to be adjusted, the pulling block 115 is pulled to drive the pulling rod 114 to move, the supporting block 113 is driven to move, the elastic potential energy of the supporting spring 112 is increased, the clamping rod 116 is driven to contract, the limitation on the clamping groove 117 is removed, the position of the lifting device 10 can be adjusted, the pulling block 115 is loosened, the elastic potential energy of the supporting spring 112 is converted into kinetic energy, the supporting block 113 is driven to reset, the clamping rod 116 and the clamping groove 117 are clamped again, and the height of the lifting device 10 can be fixed.
Example 5:
referring to fig. 4, a spraying dust-settling and cooling device for a construction working face of a building is substantially the same as that in embodiment 3, and further, the fixing device 12 includes a fixing frame 121, the fixing frame 121 is fixedly connected to the moving rod 103, a mounting frame 122 is disposed above the fixing frame 121, the top of the mounting frame 122 is fixedly connected to the fixing frame 7, the mounting frame 122 is in butt joint with the fixing frame 121, and the fixing frame 121 is mounted to the mounting frame 122 through a mounting bolt 123. The mounting frame 122 that the bottom of mount 7 set up is corresponding with the fixed frame 121 at motion pole 103 top, installs through construction bolt 123, can fix shower head 8, makes things convenient for the staff to use.
The above; is only a preferred embodiment of the present invention; however, the scope of protection of the present invention is not limited thereto; any person skilled in the art is within the technical scope of the present disclosure; according to the technical scheme of the utility model and the improvement conception, equivalent substitution or change is carried out; are all covered by the protection scope of the utility model.

Claims (5)

1. The utility model provides a construction working face sprays dust fall heat sink is built in room, includes bottom plate (1), its characterized in that: the bottom fixedly connected with universal wheel (2) of bottom plate (1), the top fixedly connected with water storage frame (3) of bottom plate (1), the lateral wall fixedly connected with handle (4) of water storage frame (3), the inside of water storage frame (3) is provided with water pump (5), the output fixedly connected with pipe (6) of water pump (5), the one end fixedly connected with mount (7) of water pump (5) are kept away from in pipe (6), the fixed surface of mount (7) is connected with shower head (8), the top fixedly connected with handle (9) of mount (7).
2. The spraying dust-reducing and temperature-reducing device for the construction working surface of the house building according to claim 1, which is characterized in that: the top fixedly connected with elevating gear (10) of bottom plate (1), the lateral wall of elevating gear (10) is provided with stop device (11), the top fixedly connected with fixing device (12) of elevating gear (10), fixing device (12) and mount (7) fixed connection.
3. The spraying dust-reducing and temperature-reducing device for the construction working surface of the house building according to claim 2, which is characterized in that: lifting device (10) includes stand (101), top fixedly connected with fixed plate (102) of stand (101), fixed plate (102) sliding connection has motion pole (103), bottom fixedly connected with slider (104) of motion pole (103), slider (104) and stand (101) sliding connection, the lateral wall fixedly connected with action bars (105) of motion pole (103), the top and stop device (11) fixed connection of stand (101), the top and fixing device (12) fixed connection of motion pole (103).
4. The spraying dust-reducing and temperature-reducing device for the construction working surface of the house building according to claim 3, which is characterized in that: stop device (11) include spacing frame (111), spacing frame (111) and stand (101) fixed connection, the inner wall fixedly connected with supporting spring (112) of spacing frame (111), spacing frame (111) are through supporting spring (112) fixedly connected with supporting shoe (113), the lateral wall fixedly connected with pull rod (114) of supporting shoe (113), pull rod (114) and spacing frame (111) sliding connection, the tip fixedly connected with of pull rod (114) draws piece (115), the fixed surface of supporting shoe (113) is connected with kelly (116), kelly (116) and stand (101) sliding connection, the surface of motion pole (103) is provided with draw-in groove (117), kelly (116) and draw-in groove (117) joint.
5. The spraying dust-reducing and temperature-reducing device for the construction working surface of the house building according to claim 3, which is characterized in that: fixing device (12) are including fixed frame (121), fixed frame (121) and motion pole (103) fixed connection, the top of fixed frame (121) is provided with installing frame (122), installing frame (122) top and mount (7) fixed connection, installing frame (122) and fixed frame (121) butt joint, fixed frame (121) are installed through construction bolt (123) and installing frame (122).
CN202022784894.1U 2020-11-26 2020-11-26 Spraying dust-settling and cooling device for construction working face of building Expired - Fee Related CN213837769U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022784894.1U CN213837769U (en) 2020-11-26 2020-11-26 Spraying dust-settling and cooling device for construction working face of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022784894.1U CN213837769U (en) 2020-11-26 2020-11-26 Spraying dust-settling and cooling device for construction working face of building

Publications (1)

Publication Number Publication Date
CN213837769U true CN213837769U (en) 2021-07-30

Family

ID=76993503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022784894.1U Expired - Fee Related CN213837769U (en) 2020-11-26 2020-11-26 Spraying dust-settling and cooling device for construction working face of building

Country Status (1)

Country Link
CN (1) CN213837769U (en)

Similar Documents

Publication Publication Date Title
CN213837769U (en) Spraying dust-settling and cooling device for construction working face of building
CN211007949U (en) Dustproof device for constructional engineering
CN110810217A (en) Dendrobii officmalis caulis sprinkling irrigation equipment
CN213953070U (en) Security protection device for civil construction
CN214809476U (en) Raise dust detects and sprays dust fall system
CN213683292U (en) Civil engineering construction working face sprays dust fall heat sink in room
CN210152317U (en) Aluminum plate curtain wall repair tools
CN212999072U (en) Civil engineering construction is with air dust fall equipment
CN217389474U (en) Flowerpot rack for landscape
CN213804761U (en) Concrete strickle device for civil engineering construction
CN210164248U (en) Building construction working face sprays dust fall heat sink
CN214914519U (en) Environment-friendly dust collector for construction
CN213710652U (en) Building engineering construction safety control rail
CN213719187U (en) Supply equipment in aspect of afforestation maintenance
CN213486191U (en) Agricultural is spray set for seedling
CN220572115U (en) Indoor automatic dust removal sprinkler for construction
CN218281086U (en) Dust collector that construction used
CN214424086U (en) Building construction working face sprays dust fall heat sink
CN211558317U (en) Environment-friendly gardens sprinkler
CN217540153U (en) Energy storage equipment with regulatory function
CN211991058U (en) Horizontal crane span structure perforating device
CN211297930U (en) Gravity self-hanging telescopic sprinkler
CN213475109U (en) Elevator car roof maintenance protection device
CN214167181U (en) Light hoisting equipment for power transmission line
CN214222626U (en) Building electrical construction erection equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210730

CF01 Termination of patent right due to non-payment of annual fee