CN213837726U - Reinforced concrete post preparation auxiliary device for building - Google Patents

Reinforced concrete post preparation auxiliary device for building Download PDF

Info

Publication number
CN213837726U
CN213837726U CN202022051919.7U CN202022051919U CN213837726U CN 213837726 U CN213837726 U CN 213837726U CN 202022051919 U CN202022051919 U CN 202022051919U CN 213837726 U CN213837726 U CN 213837726U
Authority
CN
China
Prior art keywords
plate
reinforced concrete
mounting plate
wood
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022051919.7U
Other languages
Chinese (zh)
Inventor
王海坡
杜晓景
张朋
包春晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Karamay Dabang Building Materials Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022051919.7U priority Critical patent/CN213837726U/en
Application granted granted Critical
Publication of CN213837726U publication Critical patent/CN213837726U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an auxiliary device for manufacturing a reinforced concrete column for buildings, which relates to the technical field of manufacturing the reinforced concrete column, and comprises a bottom plate, the four corners at the bottom of the bottom plate are respectively provided with a steel pin, one side of the top of the bottom plate is provided with a first wood plate, the other side of the top of the bottom plate is provided with a second wood plate, one side of the bottom between the first wood plate and the second wood plate is provided with a second mounting plate, and the outer wall of the second mounting plate is provided with a second limiting block, the first mounting plate is arranged on the first wood plate close to the upper position of the second mounting plate, the first limiting block is arranged on the first mounting plate, so that the concrete can not overflow the mould and can not be wasted in the process of pouring the concrete, through having set up the solid fixed cylinder of second on first mounting panel, saved the time with the fixed reinforcing bar of wire, improved the preparation efficiency of reinforced concrete post.

Description

Reinforced concrete post preparation auxiliary device for building
Technical Field
The utility model belongs to the technical field of reinforced concrete column preparation, concretely relates to reinforced concrete column preparation auxiliary device for building.
Background
The reinforced concrete column is in the process of building, the reinforced concrete column generally needs to be woven into a cylinder with a large amount of reinforcing bars, then constitute a mould with the template around the reinforcing bar, pour into the concrete in the mould, at last after the concrete dries, can make reinforced concrete column, current reinforced concrete column preparation is the in-process on-the-spot preparation at the building of building, auxiliary device need be used usually, but current auxiliary device still can not satisfy the operation requirement when using, the plank around the reinforcing bar needs to be fixed with the nail, it is time-consuming and laborious, and when two reinforcing bars are connected, need to carry out the winding with many wires and fix, the operation is complicated.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a reinforced concrete post preparation auxiliary device for building to the plank installation of proposing is hard consuming time in solving above-mentioned background art, and during two bar connections, need carry out the fixed problem of winding with many wires.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a reinforced concrete post preparation auxiliary device for building, includes the bottom plate, the steel round pin is all installed to four corners in the bottom of bottom plate, first plank is installed to top one side of bottom plate, and the second plank is installed to the opposite side, the second mounting panel is installed to bottom one side between first plank and the second plank, and the outer wall of second mounting panel installs the second stopper, be close to the top position department of second mounting panel on the first plank and install first mounting panel, and the outer wall of first mounting panel installs first stopper, the third plank is all installed to the front surface of first mounting panel and second mounting panel, and the rear surface of first mounting panel and second mounting panel all installs the fourth plank, spout 16 has all been seted up on first plank, second plank, third plank and the fourth plank.
Preferably, the steel wire is installed to the inner wall of first mounting panel, and installs the solid fixed cylinder of second on the steel wire, install first solid fixed cylinder on the second mounting panel, the mounting hole has all been seted up to the inside of the solid fixed cylinder of first solid fixed cylinder and second, and one side of mounting hole is provided with pours the hole.
Preferably, the number of the second limiting blocks is eight, and every two of the eight second limiting blocks are divided into four groups and are respectively arranged on the outer walls of the four sides of the first mounting plate.
Preferably, the second fixed cylinder is provided with at least ten, and the second fixed cylinder is distributed on the steel wire in a rectangular array.
Preferably, the first fixed cylinder is provided with a first steel bar body, and the second fixed cylinder is provided with a second steel bar body.
Preferably, the width and thickness of the first plank and the width and thickness of the second plank are the same.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) the utility model discloses a set up first stopper on first mounting panel, set up the second stopper on the second mounting panel, be favorable to fixing the plank fast on first mounting panel and second mounting panel, need not consume a large amount of time, the installation plank, the leakproofness between four planks is better simultaneously, the in-process of concreting, the concrete can not spill over the mould, can not extravagant concrete.
(2) The utility model discloses a set up the solid fixed cylinder of second on first mounting panel, set up first solid fixed cylinder on the second mounting panel, be convenient for link together first reinforcing bar body and second reinforcing bar body, saved the time with the fixed reinforcing bar of wire, improved the preparation efficiency of reinforced concrete post, improve the building speed of building.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a top view of the present invention with a third plank and a fourth plank installed;
FIG. 3 is a top view of a third plank of the present invention;
fig. 4 is a schematic structural view of a second fixed cylinder of the present invention;
in the figure: 1-a first fixed cylinder; 2-a first steel bar body; 3-a first limiting block; 4-a second fixed cylinder; 5-a second steel bar body; 6-a first wood board; 7-a first mounting plate; 8-a second wood board; 9-a second limiting block; 10-a second mounting plate; 11-a steel pin; 12-a base plate; 13-a third wood board; 14-steel wire; 15-fourth wood board; 16-a chute; 17-mounting holes; 18-pouring holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top/bottom", and the like indicate orientations or positional relationships based on trivial matters in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the referred device or element must have a specific orientation, is easy to have a specific orientation configuration and operation, and thus are not to be construed as being obvious limitations of the present invention, and furthermore, the terms "first" and "second" are only used for descriptive purposes and are not to be construed as indicating or implying relative importance.
In the description of the present invention, unless otherwise expressly specified or limited, the terms "mounted," "disposed," "sleeved/connected," "connected," and the like are to be construed broadly, e.g., "connected," which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; either directly or indirectly through intervening profiles, or both. To those of ordinary skill in the art, the above-described meanings specifically in the present invention may be cleaved in specific outline.
Referring to fig. 1-4, the present invention provides the following technical solutions: an auxiliary device for manufacturing a reinforced concrete column for building comprises a bottom plate 12, wherein steel pins 11 are respectively arranged at four corners of the bottom plate 12, a first wood plate 6 is arranged at one side of the top of the bottom plate 12, a second wood plate 8 is arranged at the other side of the top of the bottom plate 12, a second mounting plate 10 is arranged at one side of the bottom between the first wood plate 6 and the second wood plate 8, a second limiting block 9 is arranged on the outer wall of the second mounting plate 10, a first mounting plate 7 is arranged at the position, close to the upper part of the second mounting plate 10, on the first wood plate 6, a first limiting block 3 is arranged on the outer wall of the first mounting plate 7, third wood plates 13 are arranged on the front surfaces of the first mounting plate 7 and the second mounting plate 10, fourth wood plates 15 are arranged on the rear surfaces of the first mounting plate 7 and the second mounting plate 10, sliding grooves 16 are respectively formed in the first wood plate 6, the second wood plate 8, the third wood plates 13 and the fourth wood plates 15, when installing first reinforcing bar body 2 and second reinforcing bar body 5, need install first mounting panel 7 and second mounting panel 10 on first plank 6 in advance, install first stopper 3 and second stopper 9 on first mounting panel 7 and second mounting panel 10 in the spout 16 of first plank 6 respectively, first stopper 3 and second stopper 9 and spout 16 transition fit, when pushing first mounting panel 7 and second mounting panel 10 with external force not, first stopper 3 and second stopper 9 can not slide on spout 16.
Further, steel wire 14 is installed to the inner wall of first mounting panel 7, and installs the solid fixed cylinder 4 of second on the steel wire 14, installs first solid fixed cylinder 1 on the second mounting panel 10, and mounting hole 17 has all been seted up to the inside of first solid fixed cylinder 1 and the solid fixed cylinder 4 of second, and one side of mounting hole 17 is provided with pours hole 18.
Furthermore, the number of the second limiting blocks 9 is eight, and every two of the eight second limiting blocks 9 are divided into four groups and are respectively arranged on the outer walls of the four sides of the first mounting plate 7.
Further, the second fixing cylinder 4 is provided with ten at least, and the second fixing cylinder 4 is rectangular array and distributes on the steel wire 14, when the reinforced concrete column is made, according to the length of reinforced concrete column, install a plurality of first mounting panels 7 and second mounting panel 10 between first plank 6 and second plank 8 for consolidate first reinforcing bar body 2 and second reinforcing bar body 5, all install first reinforcing bar body 2 and second reinforcing bar body 5 in the inside mounting hole 17 of every first fixing cylinder 1 and second fixing cylinder 4 simultaneously.
Further, install first reinforcing bar body 2 on the first fixed cylinder 1, install second reinforcing bar body 5 on the second fixed cylinder 4, when first reinforcing bar body 2 and second reinforcing bar body 5 are connected, in first reinforcing bar body 2 and the second reinforcing bar body 5 inserted the second fixed cylinder 4 simultaneously, after the concreting, the hole 18 is pour in the concrete entering, the concrete simultaneously with first reinforcing bar body 2 and the contact of second reinforcing bar body 5, first reinforcing bar body 2 and second reinforcing bar body 5 are together fixed this moment.
Further, the width and thickness of the first plank 6 and the width and thickness of the second plank 8 are the same.
The utility model discloses a theory of operation and use flow: during the use, insert steel round pin 11 the ground, then fix bottom plate 12 subaerial, then insert first reinforcing bar body 2 in the mounting hole 17 of first fixed cylinder 1, then install first plank 6 on first stopper 3 on the first mounting panel 7 outer wall, install first mounting panel 7 on the top of first reinforcing bar body 2, then install second plank 8 on first stopper 3 on first mounting panel 7 outer wall, then install third plank 13 and fourth plank 15 respectively on first stopper 3 on first mounting panel 7 outer wall, first plank 6 at this moment, second plank 8 and third plank 13 and fourth plank 15 constitute a mould, pour into the concrete from the top of mould, after the concrete dries up, the preparation of reinforced concrete post is accomplished.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a reinforced concrete post preparation auxiliary device for building, includes bottom plate (12), steel round pin (11), its characterized in that are all installed to four corners in the bottom of bottom plate (12): a first wood board (6) is arranged on one side of the top of the bottom plate (12), a second wood board (8) is arranged on the other side of the top of the bottom plate, a second mounting plate (10) is arranged on one side of the bottom between the first wood plate (6) and the second wood plate (8), a second limiting block (9) is arranged on the outer wall of the second mounting plate (10), a first mounting plate (7) is arranged on the first wood plate (6) and is close to the upper part of the second mounting plate (10), and the outer wall of the first mounting plate (7) is provided with a first limiting block (3), the front surfaces of the first mounting plate (7) and the second mounting plate (10) are provided with a third wood plate (13), and the rear surfaces of the first mounting plate (7) and the second mounting plate (10) are both provided with a fourth wood plate (15), the first wood board (6), the second wood board (8), the third wood board (13) and the fourth wood board (15) are all provided with sliding grooves (16).
2. The reinforced concrete column for building as claimed in claim 1, wherein the auxiliary device is characterized in that: steel wire (14) are installed to the inner wall of first mounting panel (7), and install the solid fixed cylinder of second (4) on steel wire (14), install first solid fixed cylinder (1) on second mounting panel (10), mounting hole (17) have all been seted up to the inside of first solid fixed cylinder (1) and the solid fixed cylinder of second (4), and one side of mounting hole (17) is provided with pours hole (18).
3. The reinforced concrete column for building as claimed in claim 1, wherein the auxiliary device is characterized in that: the number of the second limiting blocks (9) is eight, and every two of the eight second limiting blocks (9) are divided into four groups and are arranged on the outer walls of the four sides of the first mounting plate (7).
4. The reinforced concrete column for building as claimed in claim 2, wherein the auxiliary device is characterized in that: the number of the second fixed cylinders (4) is at least ten, and the second fixed cylinders (4) are distributed on the steel wires (14) in a rectangular array.
5. The reinforced concrete column for building as claimed in claim 2, wherein the auxiliary device is characterized in that: install first reinforcing bar body (2) on first fixed section of thick bamboo (1), install second reinforcing bar body (5) on the fixed section of thick bamboo of second (4).
6. The reinforced concrete column for building as claimed in claim 1, wherein the auxiliary device is characterized in that: the width and thickness of the first wood board (6) are the same as the width and thickness of the second wood board (8).
CN202022051919.7U 2020-09-18 2020-09-18 Reinforced concrete post preparation auxiliary device for building Active CN213837726U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022051919.7U CN213837726U (en) 2020-09-18 2020-09-18 Reinforced concrete post preparation auxiliary device for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022051919.7U CN213837726U (en) 2020-09-18 2020-09-18 Reinforced concrete post preparation auxiliary device for building

Publications (1)

Publication Number Publication Date
CN213837726U true CN213837726U (en) 2021-07-30

Family

ID=77005315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022051919.7U Active CN213837726U (en) 2020-09-18 2020-09-18 Reinforced concrete post preparation auxiliary device for building

Country Status (1)

Country Link
CN (1) CN213837726U (en)

Similar Documents

Publication Publication Date Title
CN106223606A (en) Wall column formwork system and join mould method
CN201574504U (en) Paper mold armoured concrete wall
CN213837726U (en) Reinforced concrete post preparation auxiliary device for building
CN202380723U (en) Plastic exposed-corner molding board for building
CN210002852U (en) Novel template for combined use of aluminum wood
CN208518132U (en) A kind of T-shaped mould block shear wall
CN2923899Y (en) Building formboard
CN210850729U (en) One-way superimposed sheet bending resistance mould and side forms thereof
CN211873831U (en) Quick assembly disassembly's ground beam template mounting structure
CN113530213A (en) Formwork for fair-faced concrete, formwork mounting structure and construction method
CN211775787U (en) Non-standard layer aluminum mould and wood pattern combined node structure
CN213806555U (en) Bare concrete composite formwork
CN210589827U (en) Mould of precast concrete board class component
CN218541515U (en) Cast-in-place stair template reinforcing structure of marking time
CN211548745U (en) Self-reinforcing building template
CN213897667U (en) Frame-shear wall building structure
CN215212303U (en) Heavy building template frame
CN216893465U (en) Integrative angle-bearing aluminum template for building wall end convex pressure groove
CN210002887U (en) dog teeth aluminum mould
CN212795346U (en) Template is pour to assembled stair
CN213952960U (en) Prevent building templates of deformation
CN101936066A (en) Hollow floor formwork used in construction
CN113524381B (en) Steel-wood combined type prefabricated laminated slab universal mold and manufacturing method of prefabricated laminated slab
CN213226781U (en) Mould is used in wallboard production for assembly type structure
CN219509170U (en) Supporting structure capable of preventing top plate from deforming and serving as bottom die

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230809

Address after: No. 16, Youyi Road, Karamay, Xinjiang Uygur Autonomous Region, 834000 (Boda Yindu Hotel)

Patentee after: Karamay Dabang Building Materials Co.,Ltd.

Address before: 137400 no.041, aozhalaga Aili, bayinhuagachaqian, badarhu Town, zhalaid banner, Xing'an League, Inner Mongolia Autonomous Region

Patentee before: Bao Chunxiao