CN213837585U - Plastering device for building construction - Google Patents

Plastering device for building construction Download PDF

Info

Publication number
CN213837585U
CN213837585U CN202022098300.1U CN202022098300U CN213837585U CN 213837585 U CN213837585 U CN 213837585U CN 202022098300 U CN202022098300 U CN 202022098300U CN 213837585 U CN213837585 U CN 213837585U
Authority
CN
China
Prior art keywords
plastering
block
groove
connecting block
receiver
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022098300.1U
Other languages
Chinese (zh)
Inventor
韩建松
谭佳佳
赵琰
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022098300.1U priority Critical patent/CN213837585U/en
Application granted granted Critical
Publication of CN213837585U publication Critical patent/CN213837585U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a plastering device for building construction, which comprises a supporting mechanism and a plastering mechanism, wherein the plastering mechanism is arranged at the upper end of the supporting mechanism, a main connecting block is enabled to carry out lifting motion by rotating a threaded rod, and then the plastering mechanism is matched, so that the plastering operation can be carried out on a wall body for building construction within a certain height range, the labor burden of constructors is reduced, the plastering work efficiency is accelerated, the contact area of the back surface of the plastering block is smaller than that of a discharge port, an elastic movable connection is formed between an elastic block and a storage box through a spring, when plastering is carried out, the plastering block is attached to the wall body and is plastered by pushing upwards, when the plastering block is pushed upwards, the plastering block is rubbed with the wall body, the plastering block moves downwards relative to the storage box, the discharge port is exposed to discharge mortar, the plastering block is matched to carry out mortar, and the discharge of the mortar is quantitatively controlled through the discharge port, and the slurry leakage phenomenon is reduced.

Description

Plastering device for building construction
Technical Field
The utility model relates to a building technical field specifically is a construction plastering unit.
Background
The plastering engineering comprises internal plastering and external plastering. Plastering at various indoor parts is generally called inner plastering, such as floor, ceiling, dado, skirting line, inner stairs and the like; the plastering at various outdoor positions is called external plastering, such as external walls, rainsheds, balconies, roofs and the like.
Present building construction plastering unit needs the manual work to plaster, if the area of building construction is great, very big increase constructor's work burden, when plastering, the phenomenon of the grout leakage appears easily to plastering unit, causes the problem of material waste and ground pollution.
To solve the above problems. Therefore, a plastering device for building construction is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a construction plastering unit to solved among the prior art construction plastering unit and needed the manual work to plaster, if the area of construction is great, very big increase constructor's work burden, when plastering, the phenomenon of leaking the thick liquid appears easily to plastering unit, causes the problem of material waste and ground pollution.
In order to achieve the above object, the utility model provides a following technical scheme: a plastering device for building construction comprises a supporting mechanism and a plastering mechanism, wherein the plastering mechanism is arranged at the upper end of the supporting mechanism, the supporting mechanism comprises a base and a lifting assembly, and the lifting assembly is arranged on the upper surface of the base;
plastering the mechanism and including receiver, plastering piece and spring, plastering the piece and establishing in the front of receiver, and plastering the piece and being connected with the receiver through the spring.
Preferably, the base comprises a collecting box and a placing groove, the placing groove is formed in the base, the collecting box is arranged in the placing groove, and an embedded structure is formed between the collecting box and the base.
Preferably, lifting unit includes servo motor, threaded rod, bracing piece and main connecting block, servo motor establishes in the inside of base, and servo motor's upper end installation threaded rod, the bracing piece sets up the upper surface at the base, and the bracing piece is located the both sides of threaded rod, the threaded rod is connected with the bracing piece through main connecting block.
Preferably, a roller groove is formed in one side of the inner wall of the supporting rod.
Preferably, main connecting block includes the screw hole, accomodates connecting block, supporting connection piece, spread groove and running roller, the inside threaded hole of seting up of main connecting block, and screw hole and threaded rod phase-match, the both sides of main connecting block set up the supporting connection piece, and the one end of supporting connection piece has seted up the spread groove, and the running roller is installed in the inside of spread groove, and running roller and roll groove phase-match, main connecting block is connected with the receiver through accomodating the connecting block.
Preferably, the receiver is including accomodating cavity, elastic groove and discharge gate, the accomodating cavity has been seted up to the inside of receiver, and the elastic groove has been seted up to the positive both sides of receiver, the discharge gate has been seted up in the front of receiver, the discharge gate is less than the area of contact at the plastering block back.
Preferably, the plastering block comprises an elastic block, a cut-off groove and a through hole, the elastic block is arranged on two sides of the back surface of the plastering block, the cut-off groove is formed in the surface of the plastering block, and the through hole is formed in the bottom of the cut-off groove.
Preferably, the through-hole is located and collects the box directly over, and the elastic block passes through to constitute elasticity swing joint between spring and the receiver.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model provides a building construction plastering unit establishes in the inside of base through servo motor, and servo motor's upper end installation threaded rod, and the bracing piece sets up the upper surface at the base, and the bracing piece is located the both sides of threaded rod, cooperates the main connecting block, through the rotation of threaded rod, makes the main connecting block carry out the elevating movement, and the mechanism of plastering of deuterogamying can, in certain height range, to the wall body of building construction operation of plastering, reduce constructor's work burden, accelerate the work efficiency of plastering;
2. the utility model provides a plastering device for building construction, the roller groove has been seted up through inner wall one side of bracing piece, the spread groove has been seted up to the one end of supporting the connecting block, the running roller is installed in the inside of spread groove, and running roller and roller groove phase-match, main connecting block is connected with the receiver through accomodating the connecting block, when guaranteeing to carry out the stable support to plastering mechanism through supporting the connecting block, cooperate the roller groove, when plastering mechanism goes up and down, reduce the friction between supporting the connecting block and the main connecting block, make plastering mechanism more smooth in the in-process of going up and down;
3. the utility model provides a building construction plastering unit, set up through the inside of receiver and accomodate the cavity, and the front both sides of receiver have seted up the elasticity groove, the discharge gate has been seted up in the front of receiver, the discharge gate is less than the area of contact at plastering piece back, the elasticity piece passes through to constitute elasticity swing joint between spring and the receiver, when plastering, the plastering piece will attach the wall body, it plasters to pass upward, when advancing upward, the plastering piece passes through the friction with the wall body, carry out the downward motion for the receiver, make the discharge gate expose and carry out the ejection of compact of mortar, cooperate plastering piece to plaster, the ejection of compact of discharge gate ration control mortar, reduce the hourglass thick liquid phenomenon;
4. the utility model provides a pair of plastering unit for building construction has seted up the truncation groove through the surface of plastering piece, and has seted up the through-hole in the bottom of truncation groove, and the through-hole is located collects the box directly over, when plastering, intercepts the mortar that is about to overflow through the truncation groove, avoids appearing the phenomenon of mortar adhesion to spring, and the mortar that is intercepted drops through the through-hole and retrieves to collecting box inside, avoids the mortar to drop to ground, causes the pollution to ground.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the three-dimensional structure of the supporting mechanism of the present invention;
FIG. 3 is an enlarged schematic view of the structure at the position A of the present invention;
FIG. 4 is a schematic perspective view of a plastering mechanism of the present invention;
FIG. 5 is a schematic view of the enlarged three-dimensional structure at the position B of the present invention;
fig. 6 is a schematic view of the three-dimensional structure of the storage box of the present invention;
fig. 7 is a schematic view of the three-dimensional structure of the plastering block of the present invention.
In the figure: 1. a support mechanism; 11. a base; 111. a collection box; 112. a placement groove; 12. a lifting assembly; 121. a servo motor; 122. a threaded rod; 123. a support bar; 1231. a roller groove; 124. a main connecting block; 1241. a threaded hole; 1242. a receiving connecting block; 1243. supporting the connecting block; 1244. connecting grooves; 1245. a roller; 2. a plastering mechanism; 21. a storage box; 211. a receiving cavity; 212. an elastic groove; 213. a discharge port; 22. plastering blocks; 221. an elastic block; 222. a cut-off groove; 223. a through hole; 23. a spring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, a plastering device for building construction comprises a supporting mechanism 1 and a plastering mechanism 2, wherein the plastering mechanism 2 is arranged at the upper end of the supporting mechanism 1, the supporting mechanism 1 comprises a base 11 and a lifting assembly 12, the lifting assembly 12 is arranged on the upper surface of the base 11, the plastering mechanism 2 comprises a containing box 21, a plastering block 22 and a spring 23, the plastering block 22 is arranged on the front surface of the containing box 21, the plastering block 22 is connected with the containing box 21 through the spring 23, the lifting assembly 12 comprises a servo motor 121, a threaded rod 122, a supporting rod 123 and a main connecting block 124, the servo motor 121 is arranged in the base 11, the threaded rod 122 is arranged at the upper end of the servo motor 121, the supporting rod 123 is arranged on the upper surface of the base 11, the supporting rod 123 is arranged at two sides of the threaded rod 122, the threaded rod 122 is connected with the supporting rod 123 through the main connecting block 124, and by the rotation of the threaded rod 122, the main connecting block 124 is made to perform lifting movement and then matched with the plastering mechanism 2, plastering operation can be performed on a wall body of building construction within a certain height range, labor burden of construction personnel is reduced, and plastering work efficiency is improved, a roller groove 1231 is formed in one side of the inner wall of the supporting rod 123, the main connecting block 124 comprises a threaded hole 1241, a containing connecting block 1242, a supporting connecting block 1243, a connecting groove 1244 and a roller 1245, the threaded hole 1241 is formed in the main connecting block 124, the threaded hole 1241 is matched with the threaded rod 122, the supporting connecting blocks 1243 are arranged on two sides of the main connecting block 124, the connecting groove 1244 is formed in one end of the supporting connecting block 1243, the roller 1245 is installed in the connecting groove 1244, the roller 1245 is matched with the roller groove 1231, the main connecting block 124 is connected with the containing box 21 through the containing connecting block 1242, and the supporting connecting block 1243 ensures stable support of the plastering mechanism 2, the cooperation roller groove 1231 when plastering mechanism 2 goes up and down, reduces the friction between support connecting block 1243 and the main connecting block 124, makes plastering mechanism 2 more smooth at the in-process that goes up and down.
Referring to fig. 4-6, a plastering apparatus for building construction, wherein a storage box 21 comprises a storage cavity 211, an elastic groove 212 and a discharge port 213, the storage cavity 211 is formed in the storage box 21, the elastic grooves 212 are formed on two sides of the front surface of the storage box 21, the discharge port 213 is formed in the front surface of the storage box 21, the discharge port 213 is smaller than the contact area of the back surface of a plastering block 22, and the elastic block 221 is elastically movably connected with the storage box 21 through a spring 23.
Referring to fig. 1 and 7, a plastering device for building construction, wherein a base 11 comprises a collecting box 111 and a placing groove 112, the placing groove 112 is formed in the base 11, the collecting box 111 is arranged in the placing groove 112, an embedded structure is formed between the collecting box 111 and the base 11, a plastering block 22 comprises an elastic block 221, a cut-off groove 222 and a through hole 223, the elastic block 221 is arranged on both sides of the back surface of the plastering block 22, the cut-off groove 222 is formed in the surface of the plastering block 22, the through hole 223 is formed in the bottom of the cut-off groove 222, the through hole 223 is positioned right above the collecting box 111, the elastic block 221 is elastically movably connected with a receiving box 21 through a spring 23, when plastering is performed, mortar about to overflow is intercepted through the cut-off groove 222, the phenomenon that mortar is adhered to the spring 23 is avoided, the mortar intercepted by the mortar falls into the collecting box 111 through the through hole 223 to be recovered, and the mortar is prevented from falling to the ground, causing pollution to the ground.
In summary, the following steps: the utility model provides a plastering device for building construction, including supporting mechanism 1 and plastering mechanism 2, plastering mechanism 2 is arranged at the upper end of supporting mechanism 1, establish in the inside of base 11 through servo motor 121, and the upper end of servo motor 121 installs threaded rod 122, bracing piece 123 is arranged at the upper surface of base 11, and bracing piece 123 is located the both sides of threaded rod 122, cooperate main connecting block 124, through the rotation of threaded rod 122, make main connecting block 124 carry out the up-and-down motion, and then cooperate plastering mechanism 2, can be in certain height range, the wall body of building construction is plastered the operation, reduce constructor's work burden, accelerate the work efficiency of plastering, through the roller groove 1231 of seting up on one side of the inner wall of bracing piece 123, the spread groove 1244 has been seted up to the one end of supporting connecting block 1243, roller 1245 is installed in the inside of spread groove 1244, and roller 1245 and roller 1231 phase-match, the main connecting block 124 is connected with the containing box 21 through the containing connecting block 1242, when the plastering mechanism 2 is lifted and lowered through the supporting connecting block 1243, the friction between the supporting connecting block 1243 and the main connecting block 124 is reduced by matching the roller groove 1231, when the plastering mechanism 2 is lifted and lowered, the plastering mechanism 2 is more smoothly lifted and lowered, the containing cavity 211 is formed inside the containing box 21, the elastic grooves 212 are formed on two sides of the front surface of the containing box 21, the discharge hole 213 is formed on the front surface of the containing box 21, the discharge hole 213 is smaller than the contact area of the back surface of the plastering block 22, the elastic block 221 forms elastic movable connection with the containing box 21 through the spring 23, when plastering, the plastering block 22 is attached to a wall body and pushed upwards to move, when pushed upwards, the plastering block 22 moves downwards relative to the containing box 21 through the friction with the wall body, make discharge gate 213 expose and carry out the ejection of compact of mortar, the cooperation is plastered by plastering piece 22, lead to the ejection of compact of discharge gate 213 quantitative control mortar, reduce the hourglass thick liquid phenomenon, cut-off groove 222 has been seted up through the surface of plastering piece 22, and the through-hole 223 has been seted up to the bottom of cut-off groove 222, through-hole 223 is located and collects the box 111 directly over, when plastering, intercept the mortar that is about to overflow through cut-off groove 222, avoid appearing the phenomenon of mortar adhesion to spring 23, the mortar that is intercepted drops to collection box 111 inside through-hole 223 and retrieves, avoid the mortar to drop to ground, cause the pollution to ground.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a construction plastering unit, includes supporting mechanism (1) and plastering unit (2), plastering unit (2) set up the upper end at supporting mechanism (1), its characterized in that: the supporting mechanism (1) comprises a base (11) and a lifting assembly (12), wherein the lifting assembly (12) is arranged on the upper surface of the base (11);
plastering mechanism (2) including receiver (21), plastering piece (22) and spring (23), plastering piece (22) are established in the front of receiver (21), and plastering piece (22) are connected with receiver (21) through spring (23).
2. A plastering apparatus for construction work according to claim 1, wherein: the base (11) comprises a collecting box (111) and a placing groove (112), the placing groove (112) is formed in the base (11), the collecting box (111) is arranged in the placing groove (112), and an embedded structure is formed between the collecting box (111) and the base (11).
3. A plastering apparatus for construction work according to claim 1, wherein: lifting unit (12) include servo motor (121), threaded rod (122), bracing piece (123) and main connecting block (124), establish in the inside of base (11) servo motor (121), and the upper end installation threaded rod (122) of servo motor (121), bracing piece (123) set up the upper surface at base (11), and bracing piece (123) are located the both sides of threaded rod (122), threaded rod (122) are connected with bracing piece (123) through main connecting block (124).
4. A plastering apparatus for construction work according to claim 3, wherein: and a roller groove (1231) is formed in one side of the inner wall of the supporting rod (123).
5. A plastering apparatus for construction work according to claim 3, wherein: the utility model discloses a connecting box, including main connecting block (124), connecting block (1241), accomodate connecting block (1242), supporting connection piece (1243), spread groove (1244) and running roller (1245), threaded hole (1241) has been seted up to the inside of main connecting block (124), and threaded hole (1241) and threaded rod (122) phase-match, the both sides of main connecting block (124) set up supporting connection piece (1243), and spread groove (1244) have been seted up to the one end of supporting connection piece (1243), and the inside at spread groove (1244) is installed in running roller (1245), and running roller (1245) and roll groove (1231) phase-match, main connecting block (124) are connected with receiver (21) through accomodating connecting block (1242).
6. A plastering apparatus for construction work according to claim 1, wherein: receiver (21) including taking in cavity (211), elastic groove (212) and discharge gate (213), the inside of receiver (21) has been seted up and has been taken in cavity (211), and elastic groove (212) have been seted up to the positive both sides of receiver (21), discharge gate (213) have been seted up in the front of receiver (21), discharge gate (213) are less than the area of contact at the plastering cake (22) back.
7. A plastering apparatus for construction work according to claim 1, wherein: the plastering block (22) comprises an elastic block (221), a cut-off groove (222) and a through hole (223), wherein the elastic block (221) is arranged on two sides of the back surface of the plastering block (22), the cut-off groove (222) is formed in the surface of the plastering block (22), and the through hole (223) is formed in the bottom of the cut-off groove (222).
8. A construction plastering apparatus as claimed in claim 7, wherein: the through hole (223) is located right above the collecting box (111), and the elastic block (221) is elastically movably connected with the storage box (21) through the spring (23).
CN202022098300.1U 2020-09-23 2020-09-23 Plastering device for building construction Expired - Fee Related CN213837585U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022098300.1U CN213837585U (en) 2020-09-23 2020-09-23 Plastering device for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022098300.1U CN213837585U (en) 2020-09-23 2020-09-23 Plastering device for building construction

Publications (1)

Publication Number Publication Date
CN213837585U true CN213837585U (en) 2021-07-30

Family

ID=77005612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022098300.1U Expired - Fee Related CN213837585U (en) 2020-09-23 2020-09-23 Plastering device for building construction

Country Status (1)

Country Link
CN (1) CN213837585U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114264187A (en) * 2022-01-26 2022-04-01 中国一冶集团有限公司 Plastering device for unshaped materials on vertical surface of limited space

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114264187A (en) * 2022-01-26 2022-04-01 中国一冶集团有限公司 Plastering device for unshaped materials on vertical surface of limited space
CN114264187B (en) * 2022-01-26 2023-11-24 中国一冶集团有限公司 Plastering device for unshaped material on vertical plane of limited space

Similar Documents

Publication Publication Date Title
CN213837585U (en) Plastering device for building construction
CN210947080U (en) Bathroom floor drain with adjustable
CN208363527U (en) A kind of building wall apparatus of plastering
CN213087358U (en) Vertical automatic wall tile sticking device for building construction
CN215631378U (en) Portable wall plastering unit
CN216196774U (en) Building engineering auxiliary device that builds a wall
CN209384589U (en) Ceramic tile mechanical float
CN212583305U (en) Mortar smearing device for building blocks
CN215254314U (en) Building field wall plastering unit
CN219548285U (en) Plastering machine for building engineering fitment
CN217175843U (en) Building brickwork is with quick cloth ash device
CN218779886U (en) Plastering device
CN113323421B (en) Brick plastering device and brick laying robot
CN2234982Y (en) Automatic plastering machine for wall masonry
CN220434278U (en) Mortar joint mortar paving device
CN213625307U (en) Environment-friendly noise reduction device for building construction management
CN208168281U (en) A kind of plastering machine that can consolidate placement
CN218028793U (en) Wall cement floating device for building construction
CN210152176U (en) Wall plastering muffin thinness positioner
CN219794449U (en) Eave structure of archaize building
CN211817730U (en) Scraper device of construction machinery
CN216810805U (en) Interior wall plastering unit is used to bathroom antiseep
CN214033737U (en) Civil engineering foundation pit supporting device
CN214498285U (en) Plastering machine for indoor building decoration
CN216558896U (en) Newly-built building settlement observation device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210730