CN213806519U - Scaffold steel pipe interval control fixture - Google Patents

Scaffold steel pipe interval control fixture Download PDF

Info

Publication number
CN213806519U
CN213806519U CN202021898580.8U CN202021898580U CN213806519U CN 213806519 U CN213806519 U CN 213806519U CN 202021898580 U CN202021898580 U CN 202021898580U CN 213806519 U CN213806519 U CN 213806519U
Authority
CN
China
Prior art keywords
steel pipe
clamping plate
cardboard
measuring scale
scaffold steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021898580.8U
Other languages
Chinese (zh)
Inventor
施看栋
向远航
武彦杰
朱守泰
温杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd, CCCC Fourth Highway Engineering Co Ltd filed Critical Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
Priority to CN202021898580.8U priority Critical patent/CN213806519U/en
Application granted granted Critical
Publication of CN213806519U publication Critical patent/CN213806519U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to a scaffold steel pipe interval control fixture, including a board-like measuring tape, a fixed cardboard and a activity cardboard, along vertically being equipped with a spout on the measuring tape, the one end fixed connection of fixed cardboard and measuring tape, activity cardboard one end is equipped with a bolt, and the bolt activity alternates in the spout on the measuring tape to can follow the spout and slide, the spiro union has fixation nut on the bolt. When the support was set up, the interval adjustment with activity cardboard and fixed cardboard was for setting for the interval unanimously with the scaffold steel pipe, will fix cardboard card in installed fixed steel pipe one side, will treat that the steel pipe of installation pastes tight activity cardboard towards fixed cardboard one side, can accurate control scaffold steel pipe interval.

Description

Scaffold steel pipe interval control fixture
Technical Field
The utility model relates to a construction is set up to the scaffold frame in the construction, concretely relates to a fixture for controlling scaffold steel pipe interval.
Background
In the process of building the steel pipe scaffold, a constructor measures and positions steel pipes by using a common steel ruler according to the steel pipe intervals set by the scaffold, errors are not easy to control, the steel pipe intervals are inconsistent, and construction quality is affected.
Disclosure of Invention
The utility model aims at the above-mentioned problem, provide a special scaffold steel pipe interval control fixture, improve steel pipe installation accuracy, guarantee construction quality.
The technical scheme of the utility model as follows:
the utility model provides a scaffold steel pipe interval control fixture which characterized in that: comprises a plate-type measuring scale, a fixed clamping plate and a movable clamping plate; a sliding groove is longitudinally arranged on the measuring scale, and scales are arranged on one side or two sides of the sliding groove; one end of the fixed clamping plate is fixedly connected or welded with one end of the measuring scale through a bolt, the other end of the fixed clamping plate extends out of one side of the measuring scale by a certain length, and one side of the fixed clamping plate, which faces the middle of the measuring scale, is provided with an arc-shaped positioning clamping groove; one end of the movable clamping plate is provided with a bolt, the bolt is inserted into the sliding groove in the measuring scale in a sliding mode, and the bolt is connected with a fixing nut in a threaded mode.
The utility model discloses simple structure, convenient to use can not only the accurate control scaffold steel pipe interval, can also measure whether the steel pipe wall thickness meets the requirements, guarantees construction quality.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Detailed Description
As shown in fig. 1, the utility model comprises a plate-type measuring tape 1, a fixed clamping plate 2 and a movable clamping plate 3; a sliding groove 4 is longitudinally arranged on the measuring scale, and length scales are arranged on one side or two sides of the sliding groove; one end of the fixed clamping plate 2 is fixedly connected or welded with one end of the measuring scale through a bolt, the other end of the fixed clamping plate 2 extends out of one side of the measuring scale 1 by a certain length, and one side of the fixed clamping plate facing the middle of the measuring scale is provided with an arc-shaped positioning clamping groove 5; one end of the movable clamping plate 3 is provided with a bolt 6, the bolt 6 is movably inserted into the sliding groove 4 on the measuring scale and can slide along the sliding groove, and the bolt is screwed with a fixing nut for temporarily fixing the movable clamping plate and the measuring scale.
The utility model discloses during the implementation, the circular arc radius of positioning slot 5 on the fixed cardboard will generally equal to or be greater than the radius of scaffold steel pipe, is convenient for go into the draw-in groove with the steel pipe card.
For carrying, the measuring tape 1 can be transversely divided into two parts, the two parts are connected through the hinge 7, and the measuring tape can be folded when being carried.
The utility model discloses during the use, according to the steel pipe interval that the scaffold was set for, loosen the nut on the activity cardboard fixing bolt, make the activity cardboard slide along the spout, according to the scale on the measuring tape, will move about the cardboard with the interval adjustment of fixed cardboard for set for the interval unanimous with the steel pipe, then tighten the nut and will fix cardboard and measuring tape temporary fixation. The positioning clamping grooves on the fixing clamping plates are clamped on the installed and fixed steel pipes, the steel pipes to be installed are tightly attached to the movable clamping plates and face one side of the fixing clamping plates, and the steel pipe intervals can be controlled to meet the design requirements.
The utility model discloses during the concrete implementation, still can be equipped with the bayonet socket 8 of a rectangle in the one end that fixed cardboard 2 extends to the measuring tape outside, this bayonet socket can be used to carry out the auxiliary detection to the steel wall thickness.
Because the wall thickness of the steel pipe that sets up the scaffold frame and adopt will accord with certain requirement, set up the width of bayonet socket to equal to the minimum that accords with the steel pipe wall thickness requirement, generally be 3.6mm, when installing every steel pipe, block the bayonet socket on the steel pipe wall department card, if can just or can not insert the bayonet socket with the pipe wall, then prove that the steel pipe wall thickness accords with the requirement, if the steel pipe wall inserts the bayonet socket and can rock, prove that the steel pipe wall thickness is unqualified.

Claims (4)

1. The utility model provides a scaffold steel pipe interval control fixture which characterized in that: comprises a plate-type measuring scale, a fixed clamping plate and a movable clamping plate; a sliding groove is longitudinally arranged on the measuring scale, and scales are arranged on one side or two sides of the sliding groove; one end of the fixed clamping plate is fixedly connected with one end of the measuring scale, the other end of the fixed clamping plate extends out of one side of the measuring scale by a certain length, and one side of the fixed clamping plate facing the middle of the measuring scale is provided with an arc-shaped positioning clamping groove; one end of the movable clamping plate is provided with a bolt, the bolt is movably inserted into a sliding groove in the measuring scale, and a fixing nut is screwed on the bolt.
2. The scaffold steel tube spacing control jig of claim 1, wherein: the arc radius of the positioning clamping groove on the fixing clamping plate is equal to or larger than the radius of the scaffold steel pipe.
3. The scaffold steel tube spacing control jig of claim 1, wherein: the measuring scale is transversely divided into two parts which are connected through a hinge.
4. The scaffold steel tube spacing control jig of claim 1, wherein: one end of the fixed clamping plate extending out of the measuring tape is provided with a rectangular bayonet.
CN202021898580.8U 2020-09-02 2020-09-02 Scaffold steel pipe interval control fixture Active CN213806519U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021898580.8U CN213806519U (en) 2020-09-02 2020-09-02 Scaffold steel pipe interval control fixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021898580.8U CN213806519U (en) 2020-09-02 2020-09-02 Scaffold steel pipe interval control fixture

Publications (1)

Publication Number Publication Date
CN213806519U true CN213806519U (en) 2021-07-27

Family

ID=76952376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021898580.8U Active CN213806519U (en) 2020-09-02 2020-09-02 Scaffold steel pipe interval control fixture

Country Status (1)

Country Link
CN (1) CN213806519U (en)

Similar Documents

Publication Publication Date Title
CN110296641B (en) Vernier caliper for measuring pitch of holes
CN213806519U (en) Scaffold steel pipe interval control fixture
CN108330841B (en) Accurate positioning device and positioning method for cable guide pipe of concrete cable tower
CN214444842U (en) Part machining auxiliary positioning device
CN109944332A (en) A kind of system and operating method suitable for there is the pre-embedded bolt of high-precision requirement quickly to position
CN211948770U (en) Device for installing flowmeter on municipal drainage pipeline
CN217384477U (en) Positioning device for thermocouple
CN212095032U (en) Liquid level meter flange group is to frock on chemical industry equipment
CN219624633U (en) Correction guiding ruler for elevator guide rail installation
CN219137770U (en) Adjustable fixing device for steel plate water stop
CN219444809U (en) Node steel sheet chamfer processing fixing device
CN216206174U (en) Reinforced concrete structure steel bar protection layer detection device
CN214248529U (en) Cold and hot water pipe installation positioner
CN215859067U (en) Right-angle ruler-shaped template fixing device
CN216503096U (en) Anti-shaking support machining platform
CN217949748U (en) Novel beam steel template connecting and positioning mechanism
CN219674963U (en) Auxiliary positioning device for railway track side equipment
CN219864664U (en) Anti-leakage structure of window auxiliary frame
CN219387267U (en) Portable rag bolt location rigid frame
CN219599288U (en) Adjustable clamp for glass workpiece detection
CN219491071U (en) Frock clamp of utility tunnel built-in fitting installation
CN209485202U (en) Mill roll track installation measuring tool
CN218155981U (en) Automobile accessory connecting rod rack size detection device
CN214373842U (en) Clamping and positioning device for plate tensile test
CN219826221U (en) Auxiliary limiting device for mounting embedded part

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant