CN213770455U CN202020622374.8U CN202020622374U CN213770455U CN 213770455 U CN213770455 U CN 213770455U CN 202020622374 U CN202020622374 U CN 202020622374U CN 213770455 U CN213770455 U CN 213770455U
Authority
CN
China
Prior art keywords
prefab
adjusting
frame
road surface
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020622374.8U
Other languages
Chinese (zh)
Inventor
周兴华
聂一岷
潘承楼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020622374.8U priority Critical patent/CN213770455U/en
Application granted granted Critical
Publication of CN213770455U publication Critical patent/CN213770455U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Hooks, Suction Cups, And Attachment By Adhesive Means (AREA)

Abstract

The utility model discloses a prefab handling tool for highway pavement reconstruction, which comprises a sucker lifting tool body, wherein the bottom of the sucker lifting tool body is connected with a beam, two sides of the beam are connected with installation adjusting parts for protecting the outer wall of a prefab, the bottom of the installation adjusting part is connected with a spongy cushion for buffering, and the prefab handling device for highway pavement reconstruction is characterized in that when a vacuum sucker lifting tool is used for handling prefabs, the top of the prefab is adsorbed by the sucker lifting tool body, the installation adjusting parts are convenient for protecting two ends of the prefab, the bottom of the prefab is buffered and protected by the arranged spongy cushion, so as to avoid the impact hardness between the prefab and the ground and reduce the impact damage between the prefab and the ground, and meanwhile, the telescopic parts arranged in the scheme are convenient to adjust according to different thicknesses of the carried prefabs and convenient to wrap the prefabs with different thicknesses, the two ends of the prefabricated member with different thicknesses are protected conveniently, and the sponge of the prefabricated member plays a role in buffering protection.

Description

Prefabricated part carrying tool for highway pavement reconstruction
Technical Field
The utility model relates to the technical field, specifically be a prefab handling tool is used in highway road surface transformation.
Background
PC is an english abbreviation of precast concrete, and is called PC member in the field of housing industrialization, such as precast reinforced concrete column foundation, precast steel structure steel column foundation, street lamp billboard column reinforced concrete foundation, precast floor slab. The corresponding traditional cast-in-place concrete needs site moulding, site pouring and site maintenance. The concrete prefabricated member is widely applied to the fields of buildings, traffic, water conservancy and the like, plays an important role in national economy, and is used for improving the engineering efficiency and quality when a road surface is improved.
Because the volume and the weight of prefab are general great, the transport prefab generally seeks fork truck, the prefab is hoisted such as vacuum chuck hoist, comparatively level fine and close to the surface, all kinds of prefabs of comparatively regular shape, generally adopt the transport of vacuum chuck hoist, when the transport, hold the prefab top through vacuum chuck, after carrying to needs the position, after blowing in the gas again through the vacuum chuck hoist, make sucking disc and prefab break away from, the transport is simple, nevertheless because the prefab generally has certain weight, put to required ground in the transport, the prefab is because gravity and the hard striking in ground after loosening the sucking disc, the striking damage when leading to the fact prefab and ground easily, for this, we propose a prefab handling tool for highway road surface transformation.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a prefab handling tool is used in highway road surface transformation to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a prefab handling tool is used in highway road surface transformation, includes sucking disc hoist body, sucking disc hoist body bottom is connected with the crossbeam, the crossbeam both sides are connected with the installation adjustment piece that is used for protecting the prefab outer wall, installation adjustment piece bottom is connected with the foam-rubber cushion that the buffering was used, is favorable to playing the effect of buffering protection to prefab and ground.
Preferably, the installation adjusting part comprises an installation frame and a fixed plate, the installation frame is connected to one side of the cross beam, the fixed plate is connected to one side of the installation frame, the two sides of the fixed plate are connected with telescopic parts, and the two telescopic parts are connected to the inside of the installation frame, so that two ends of the prefabricated part can be protected conveniently.
Preferably, the extensible member is including adjusting the frame, installing frame one side is equipped with the spacing groove, adjustment frame one side is connected with the stopper, and the stopper slides and runs through the spacing groove, stopper one side is connected with the fixed plate, the inside sliding connection of adjustment frame has the adjusting plate, the adjustment frame both sides are equipped with the adjustment hole, the adjusting plate both sides are connected with the bolt, and bolt one end and adjustment hole threaded connection, the adjusting plate bottom is connected in the foam-rubber cushion, is convenient for adjust adjusting plate and adjustment frame junction to different heights, is suitable for the prefab of different thickness.
Preferably, one side that the stopper was kept away from to the adjustment frame is connected with the flange, one side that the spacing groove was kept away from to the installing frame is equipped with the recess, and flange sliding connection is inside the recess, is favorable to adjusting the inside slip of board year installing frame.
Preferably, one side that the adjustment frame is located the stopper is connected with the pulling handle, is favorable to pulling open two adjustment frames after the transport.
Compared with the prior art, the beneficial effects of the utility model are that:
when using the vacuum chuck hoist transport prefab, adsorb the prefab top through sucking disc hoist body, install the adjustment piece simultaneously and be convenient for protect prefab both ends department, cushion the protection through the foam-rubber cushion who establishes in the prefab bottom, avoid the rigid impact between prefab and the ground, reduce the striking damage on prefab and ground, the extensible member that establishes is convenient for adjust according to the different thickness of the prefab of transport in this scheme simultaneously, be convenient for wrap up the prefab of different thickness, be convenient for protect the both ends of the prefab of different thickness, play the cushioning protection at the sponge of prefab.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic top view of the present invention;
FIG. 3 is a schematic view of the structure of the installation adjustment member of the present invention;
fig. 4 is a schematic view of the installation adjusting member of the present invention in a partially cut-away view.
In the figure: 1-a sucker sling body; 2-a cross beam; 3-installing an adjusting piece; 4-a spongy cushion; 5, mounting a frame; 6, fixing a plate; 7-a telescopic member; 8-adjusting the frame; 9-a limiting groove; 10-a limiting block; 11-an adjusting plate; 12-an adjustment hole; 13-a bolt; 14-a convex plate; 15-a groove; 16-pull handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a prefab handling tool for highway road surface transformation, the design mainly solves current vacuum chuck hoist when lifting the transport to the prefab in this scheme, after the transport, need loosen the sucking disc power of sucking disc hoist body 1 for the prefab breaks away from sucking disc hoist body 1, under the gravity of prefab itself, causes the rigid contact with ground easily, makes prefab and ground impact damage, and the design in this scheme includes sucking disc hoist body 1, 1 bottom of sucking disc hoist body is connected with crossbeam 2, 2 both sides of crossbeam are connected with the installation adjustment piece 3 that is used for protecting the prefab outer wall, 3 bottoms of installation adjustment piece are connected with the foam-rubber cushion 4 that the buffering was used.
When this scheme of use's 1 transport prefab of sucking disc hoist body, adsorb at the prefab top through the sucking disc on the sucking disc hoist body 1, through sucking disc hoist body 1 with the sucking disc evacuation, be convenient for adsorb the prefab in sucking disc department, cup joint at the prefab both ends through the installation adjustment piece 3 that establishes simultaneously, be convenient for play the effect of protection to the prefab both ends, simultaneously because installation adjustment piece 3 bottoms are connected with the foam-rubber cushion 4 of buffering usefulness, the contact of prefab and foam-rubber cushion 4, the effect of buffering protection has been played to prefab and ground, the direct rigid contact on prefab and ground has been reduced, the impact damage on prefab and ground has been reduced.
In this scheme installation adjustment piece 3 includes installing frame 5 and fixed plate 6, installing frame 5 is connected in 2 one sides of crossbeam, and fixed plate 6 connects in installing frame 5 one side, 6 both sides of fixed plate are connected with extensible member 7, and two telescopic connection are inside installing frame 5, extensible member 7 is including adjusting frame 8, installing frame 5 one side is equipped with spacing groove 9, adjusting frame 8 one side is connected with stopper 10, and stopper 10 slides and runs through spacing groove 9, stopper 10 one side is connected with fixed plate 6, the inside sliding connection of adjusting frame 8 has adjusting plate 11, adjusting frame 8 both sides are equipped with adjustment hole 12, adjusting plate 11 both sides are connected with bolt 13, and 13 one end of bolt and 12 threaded connection of adjustment hole, adjusting plate 11 bottom is connected in foam-rubber cushion 4.
The specific implementation mode is as follows: when the sucker lifting tool body 1 in the scheme is used for carrying out adsorption, the top of the prefabricated member is adsorbed by the sucker of the sucker lifting tool body 1, an appropriate fixing plate 6 is selected according to the width of the prefabricated member, two adjusting frames 8 are respectively slid in the installation frame 5, because the limiting block 10 is connected with the adjusting frames 8, when the adjusting frames 8 are slid and adjusted, the limiting block 10 slides along the limiting groove 9, when the two adjusting frames 8 are close to each other, the fixing connection is carried out by the fixing plate 6 and the adjusting frames 8, the top of the fixing plate 6 is fixedly connected with the installation frame 5, the adjusting frames 8 and the installation frame 5 are in the fixed connection relation, meanwhile, the adjusting plate 11 can be pulled out of one end distance of the adjusting frames 8 according to the thickness of the prefabricated member, so that the lengths of the adjusting frames 8 and the adjusting plates 11 are about smaller than the thickness of the prefabricated member, at the moment, the adjusting frames 8 and the adjusting plates 11 are fixed by the bolts 13, simultaneously prefab bottom and foam-rubber cushion 4 contact, because the total length of adjusting plate 11 and adjusting frame 8 is about less than the thickness of prefab, after prefab and foam-rubber cushion 4 contact each other, the prefab plays certain extrusion effect to foam-rubber cushion 4, cushioning effect through foam-rubber cushion 4, the rigid contact on prefab and ground has been reduced, the direct impact damage on prefab and ground has been reduced, simultaneously after the transport, through loosening fixed plate 6, stimulate pulling handle 16 simultaneously, with two 8 to both sides stimulations of adjusting frame, make adjusting frame 8 break away from prefab both ends department.
In this scheme one side that stopper 10 was kept away from to adjustment frame 8 is connected with flange 14, one side that spacing groove 9 was kept away from to installing frame 5 is equipped with recess 15, and flange 14 sliding connection is inside recess 15, is convenient for improve adjustment frame 8 at the inside sliding stability of installing frame 5.
In this scheme one side that adjustment frame 8 is located stopper 10 is connected with pulling handle 16, is favorable to pulling adjustment frame 8.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a prefab handling tool is used in highway road surface transformation, includes sucking disc hoist body (1), sucking disc hoist body (1) bottom is connected with crossbeam (2), its characterized in that: the prefabricated member outer wall protection device is characterized in that two sides of the cross beam (2) are connected with installation adjusting pieces (3) used for protecting the outer wall of the prefabricated member, and the bottom of each installation adjusting piece (3) is connected with a sponge cushion (4) for buffering.
2. The precast member handling tool for road surface modification according to claim 1, characterized in that: installation adjusting part (3) are including installing frame (5) and fixed plate (6), crossbeam (2) one side is connected in installing frame (5), and fixed plate (6) are connected in installing frame (5) one side, fixed plate (6) both sides are connected with extensible member (7), and two flexible connections are inside installing frame (5).
3. The precast member handling tool for road surface modification according to claim 2, characterized in that: extensible member (7) are including adjusting frame (8), installing frame (5) one side is equipped with spacing groove (9), adjusting frame (8) one side is connected with stopper (10), and stopper (10) slide and run through spacing groove (9), stopper (10) one side is connected with fixed plate (6), adjusting frame (8) inside sliding connection has adjusting plate (11), adjusting frame (8) both sides are equipped with adjustment hole (12), adjusting plate (11) both sides are connected with bolt (13), and bolt (13) one end and adjustment hole (12) threaded connection, adjusting plate (11) bottom is connected in foam-rubber cushion (4).
4. The precast member handling tool for road surface modification according to claim 3, characterized in that: one side of the adjusting frame (8) far away from the limiting block (10) is connected with a convex plate (14), one side of the mounting frame (5) far away from the limiting groove (9) is provided with a groove (15), and the convex plate (14) is connected inside the groove (15) in a sliding manner.
5. The precast member handling tool for road surface modification according to claim 3, characterized in that: one side of the adjusting frame (8) positioned on the limiting block (10) is connected with a pulling handle (16).
CN202020622374.8U 2020-04-23 2020-04-23 Prefabricated part carrying tool for highway pavement reconstruction Expired - Fee Related CN213770455U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020622374.8U CN213770455U (en) 2020-04-23 2020-04-23 Prefabricated part carrying tool for highway pavement reconstruction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020622374.8U CN213770455U (en) 2020-04-23 2020-04-23 Prefabricated part carrying tool for highway pavement reconstruction

Publications (1)

Publication Number Publication Date
CN213770455U true CN213770455U (en) 2021-07-23

Family

ID=76865603

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020622374.8U Expired - Fee Related CN213770455U (en) 2020-04-23 2020-04-23 Prefabricated part carrying tool for highway pavement reconstruction

Country Status (1)

Country Link
CN (1) CN213770455U (en)

Similar Documents

Publication Publication Date Title
CN213770455U (en) Prefabricated part carrying tool for highway pavement reconstruction
CN101922158A (en) Device and method for integral underpinned vibration isolation of subway underpass building foundation
CN213106620U (en) Urban rail transit is location installation device for electrical engineering
CN213742290U (en) Civil engineering is with template supporting mechanism of circulated use
CN202055211U (en) Concrete guardrail plate and mold thereof
CN210370471U (en) Electrician is with climbing frame
CN209260563U (en) A kind of Bailey beam truss entirety transverse sliding device for cast-in-situ continuous beam
CN112193994A (en) Rubber protection device for hoisting cold-rolled steel coil
CN219174990U (en) Light abutment structure
CN210561622U (en) Portable curb transportation mounting tool
CN218798757U (en) Reinforcing bar equipment of bending
CN220847711U (en) Granite cover plate for indoor cable duct of transformer substation
CN216663686U (en) Auxiliary construction equipment for roadbed pouring
CN201686405U (en) Rail supporting device of building
CN220414811U (en) Decoration hanging basket for exterior wall decoration
CN215794150U (en) Adjusting carrier loader for precast beam transport height
CN216190316U (en) Mobile device of wastewater treatment equipment
CN218621840U (en) Tuyere installation and construction platform for bridge
CN219344067U (en) Building environment-friendly plate
CN220645233U (en) Concrete pouring lifting trolley device
CN213538708U (en) Push type totally-enclosed hanging basket applied to maintenance of overpass bridge
CN212270742U (en) Warning device is used in colleges and universities' building engineering construction
CN209457158U (en) A kind of beam for building rod structure
CN219384723U (en) Sinking type manhole cover lever type maintenance vehicle
CN212837127U (en) Pouring mold for windproof fence base

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210723