CN213742619U - Connecting mechanism of power steel pipe tower - Google Patents
Connecting mechanism of power steel pipe tower Download PDFInfo
- Publication number
- CN213742619U CN213742619U CN202022269918.XU CN202022269918U CN213742619U CN 213742619 U CN213742619 U CN 213742619U CN 202022269918 U CN202022269918 U CN 202022269918U CN 213742619 U CN213742619 U CN 213742619U
- Authority
- CN
- China
- Prior art keywords
- ring flange
- tower
- registration arm
- steel pipe
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 25
- 239000010959 steel Substances 0.000 title claims abstract description 25
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims abstract description 18
- 229910052742 iron Inorganic materials 0.000 claims abstract description 9
- 230000008878 coupling Effects 0.000 claims abstract description 6
- 238000010168 coupling process Methods 0.000 claims abstract description 6
- 238000005859 coupling reaction Methods 0.000 claims abstract description 6
- 230000002349 favourable effect Effects 0.000 abstract description 3
- 238000009434 installation Methods 0.000 abstract description 3
- 238000010276 construction Methods 0.000 abstract description 2
- 239000007787 solid Substances 0.000 description 4
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000006978 adaptation Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
Images
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The utility model relates to an electric power construction technical field just discloses a coupling mechanism of electric power steel pipe tower, including iron tower body, iron tower body includes body and lower body, first ring flange and second ring flange are installed respectively to the one end that body, lower body are close to each other, one side that first ring flange, second ring flange are close to each other is overlapped respectively and is equipped with registration arm and fixed pipe, the registration arm closely pegs graft with fixed pipe. The utility model discloses utilize pegging graft of registration arm and fixed pipe for upper tube body and lower body can closely combine, the inside installation locating component of body under the rethread, utilize the grafting of spacing post and registration arm bottom, can improve the compactness of being connected between registration arm and the lower body, the rethread bolt is connected first ring flange and second ring flange, realize connecting fast and steadily between upper tube body and the lower body, be favorable to improving the connection stability of steel pipe, thereby improve the overall stability of electric power steel pipe tower.
Description
Technical Field
The utility model relates to an electric power construction technical field specifically is a coupling mechanism of electric power steel pipe tower.
Background
The power steel pipe tower is a common power iron tower, a main body of the power steel pipe tower is generally composed of a plurality of steel pipes, the steel pipes are used as main supporting structures, and the stability of the joints of the power steel pipe tower is particularly important.
SUMMERY OF THE UTILITY MODEL
In view of the above problems existing in the prior art, the utility model provides a coupling mechanism of electric power steel pipe tower.
In order to realize the above-mentioned purpose, the utility model provides a pair of coupling mechanism of electric power steel pipe tower, including iron tower body, iron tower body includes body and low body, first ring flange and second ring flange are installed respectively to the one end that body, low body are close to each other, one side that first ring flange, second ring flange are close to each other is equipped with registration arm and fixed pipe respectively to the cover, the registration arm closely pegs graft with fixed pipe.
Preferably, the lower pipe body is provided with a positioning assembly near the inner wall of the top opening, and the bottom end of the positioning pipe is inserted into the lower pipe body and is tightly inserted into the positioning assembly.
Preferably, locating component is including solid fixed ring and spacing post, gu fixed ring installs on the body is close to open-ended inner wall down, spacing post fixed mounting just is the annular distribution at solid fixed ring's upper surface, the bottom and the spacing post of registration arm closely peg graft.
Preferably, the bottom end of the positioning tube is provided with a limiting hole matched with the limiting column, and the limiting column is tightly spliced with the limiting hole.
Preferably, the first flange plate and the second flange plate are mutually attached and fixed through bolts.
Compared with the prior art, the utility model provides a coupling mechanism of electric power steel pipe tower has following beneficial effect:
the utility model discloses an install registration arm and fixed pipe at the medial surface of first ring flange and second ring flange, utilize the grafting of registration arm and fixed pipe, make upper tube body and lower body can closely combine, the inside installation locating component of body under the rethread, utilize the grafting of spacing post and registration arm bottom, can improve the closeness of being connected between registration arm and the lower body, the rethread bolt is connected first ring flange and second ring flange, realize the quick and stable connection between upper tube body and the lower body, be favorable to improving the connection stability of steel pipe, thereby improve the overall stability of electric power steel pipe tower.
Drawings
FIG. 1 is a schematic structural view of a power steel pipe tower according to the present invention;
FIG. 2 is a schematic structural view of the upper tube body and the lower tube body of the present invention;
FIG. 3 is a schematic view of the connection structure of the upper tube and the lower tube of the present invention;
fig. 4 is a schematic structural diagram of the positioning assembly of the present invention.
In the figure: 1. a pipe body is arranged; 2. a lower pipe body; 3. a first flange plate; 4. a second flange plate; 5. a positioning tube; 6. a fixed tube; 7. a positioning assembly; 8. a fixing ring; 9. a limiting column.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present disclosure more clear, the technical solutions of the embodiments of the present disclosure will be described below clearly and completely with reference to the accompanying drawings of the embodiments of the present disclosure.
Referring to fig. 1-4, a connection mechanism for an electric steel pipe tower includes an iron tower body, the iron tower body includes an upper pipe body 1 and a lower pipe body 2, a first flange 3 and a second flange 4 are respectively installed at the ends of the upper pipe body 1 and the lower pipe body 2 close to each other, a positioning pipe 5 and a fixing pipe 6 are respectively sleeved at the sides of the first flange 3 and the second flange 4 close to each other, and the positioning pipe 5 is tightly inserted into the fixing pipe 6.
The first flange plate 3 and the second flange plate 4 are mutually attached and fixed through bolts.
The utility model discloses an install registration arm 5 and fixed pipe 6 at the medial surface of first ring flange 3 and second ring flange 4, utilize registration arm 5 and fixed 6 grafting of managing, make and go up body 1 and lower body 2 can the zonulae occludens, the inside installation locating component 7 of body 2 under the rethread, utilize the grafting of spacing post 9 and registration arm 5 bottom, can improve the compactness of being connected between registration arm 5 and the lower body 2, the rethread bolt is connected first ring flange 3 and second ring flange 4, realize going up quick and stably connecting between body 1 and the lower body 2, be favorable to improving the connection stability of steel pipe, thereby improve the overall stability of electric power steel pipe tower.
The above description is only an exemplary embodiment of the present invention, and is not intended to limit the present invention, the scope of which is defined by the appended claims. Various modifications and equivalents of the invention can be made by those skilled in the art within the spirit and scope of the invention, and such modifications and equivalents should also be considered as falling within the scope of the invention.
Claims (5)
1. The utility model provides a coupling mechanism of electric power steel pipe tower, includes iron tower body, its characterized in that, iron tower body includes body (1) and lower body (2), first ring flange (3) and second ring flange (4) are installed respectively to the one end that body (1), lower body (2) are close to each other, one side that first ring flange (3), second ring flange (4) are close to each other is overlapped respectively and is equipped with registration arm (5) and fixed pipe (6), registration arm (5) closely peg graft with fixed pipe (6).
2. The connecting mechanism of the electric steel tube tower as claimed in claim 1, wherein a positioning assembly (7) is installed on the inner wall of the lower tube body (2) close to the top opening, and the bottom end of the positioning tube (5) is inserted into the lower tube body (2) and is tightly inserted into the positioning assembly (7).
3. The connecting mechanism of the electric steel tube tower as recited in claim 2, wherein the positioning assembly (7) comprises a fixing ring (8) and a limiting post (9), the fixing ring (8) is mounted on the inner wall of the lower tube body (2) close to the top end opening, the limiting post (9) is fixedly mounted on the upper surface of the fixing ring (8) and distributed annularly, and the bottom end of the positioning tube (5) is tightly inserted into the limiting post (9).
4. The connecting mechanism of the electric steel pipe tower as claimed in claim 3, wherein the bottom end of the positioning pipe (5) is provided with a limiting hole matched with the limiting post (9), and the limiting post (9) is tightly inserted into the limiting hole.
5. The connecting mechanism of the electric steel tube tower as claimed in claim 1, wherein the first flange (3) and the second flange (4) are attached to each other and fixed by bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022269918.XU CN213742619U (en) | 2020-10-13 | 2020-10-13 | Connecting mechanism of power steel pipe tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022269918.XU CN213742619U (en) | 2020-10-13 | 2020-10-13 | Connecting mechanism of power steel pipe tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213742619U true CN213742619U (en) | 2021-07-20 |
Family
ID=76849388
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022269918.XU Expired - Fee Related CN213742619U (en) | 2020-10-13 | 2020-10-13 | Connecting mechanism of power steel pipe tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213742619U (en) |
-
2020
- 2020-10-13 CN CN202022269918.XU patent/CN213742619U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN213742619U (en) | Connecting mechanism of power steel pipe tower | |
CN215797962U (en) | Steel-pipe pile triangle gallows | |
CN214357371U (en) | Suction cylinder jacket tray | |
CN111593934B (en) | Supporting leg hoop device for electric power tower | |
CN207781349U (en) | A kind of novel transformer forced air cooler support construction | |
CN220645420U (en) | Electric power concrete pole with earth connection | |
CN220522701U (en) | Connecting assembly and wind power generation tower | |
CN218560838U (en) | Tower drum lifting appliance | |
CN219864358U (en) | Combined power transmission tower with small root opening | |
CN206524231U (en) | A kind of transformer oil storage supporting construction | |
CN218850333U (en) | Be used for electric power design cable support | |
CN215862180U (en) | Stainless steel anti-corrosion flange convenient to position and disassemble | |
CN220956330U (en) | Connection structure of stand and platform | |
CN218441244U (en) | Split type antidetonation pipe clamp structure | |
CN219107338U (en) | Photovoltaic support and photovoltaic device | |
CN216850305U (en) | Be applied to 5G basic station connecting piece and road of pole are synthesized to road | |
CN219954488U (en) | Hydraulic engineering pipeline reinforcing apparatus | |
CN213927768U (en) | Three-section rod | |
CN211366688U (en) | Novel photovoltaic installation high strength platform sling | |
CN214479998U (en) | Motor rain cover convenient to dismantle | |
CN217323170U (en) | Wind-powered electricity generation hoist and mount tower machine bearing convenient to transition | |
CN220122232U (en) | Circular electric connector convenient to installation | |
CN214619856U (en) | Stable H-shaped multifunctional supporting chassis | |
CN217051391U (en) | Tower crane jib loading boom pull rod support device | |
CN215409596U (en) | Square pipe connecting piece |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210720 |