CN213726728U - Breaker that building engineering used - Google Patents

Breaker that building engineering used Download PDF

Info

Publication number
CN213726728U
CN213726728U CN202021741112.XU CN202021741112U CN213726728U CN 213726728 U CN213726728 U CN 213726728U CN 202021741112 U CN202021741112 U CN 202021741112U CN 213726728 U CN213726728 U CN 213726728U
Authority
CN
China
Prior art keywords
motor
control box
transmission
crushing
drive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021741112.XU
Other languages
Chinese (zh)
Inventor
郭丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021741112.XU priority Critical patent/CN213726728U/en
Application granted granted Critical
Publication of CN213726728U publication Critical patent/CN213726728U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Crushing And Pulverization Processes (AREA)

Abstract

The utility model discloses a breaker that building engineering used, including C template and control box, one side of C template is provided with first motor, the output swing joint of first motor has first transmission pole, the one end swing joint of first transmission pole has the drive wheel, the surperficial swing joint of drive wheel has the drive belt, the fixed surface of C template is connected with the control box, one side of control box is provided with the second motor. This breaker that building engineering used, through the setting of first motor, during the use, the constructor places building material on the drive belt, then with first motor external power supply, the work of first motor makes first drive lever drive the drive wheel and rotates, and the drive wheel rotates and makes the drive belt rotate, and then makes the building material on the drive belt transport to the control box in to made construction worker transmit building material, saved operating time for construction worker and improved work efficiency.

Description

Breaker that building engineering used
Technical Field
The utility model relates to a building engineering technical field specifically is a breaker that building engineering used.
Background
The building engineering major is mainly responsible for teaching and management of civil engineering major building engineering directions, mainly cultures and masters the basic theories and basic knowledge of engineering mechanics, soil mechanics, surveying, housing architecture and structural engineering subjects, and is a general term for various buildings and engineering facilities providing material technology foundation for human life and production.
When carrying out building engineering, often can carry out broken handle to building equipment and use, but most breaker on the existing market, crushing effect is relatively poor, and crushing efficiency is low, and crushing speed is slow, brings the trouble of work for construction worker, reduces work efficiency, consequently, the utility model provides a breaker that building engineering used.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a breaker that building engineering used has solved the problem of proposing in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: including C template and control box, one side of C template is provided with first motor, the output swing joint of first motor has first transfer line, the one end swing joint of first transfer line has the drive wheel, the surperficial swing joint of drive wheel has the drive belt, the fixed surface of C template is connected with the control box, one side of control box is provided with the second motor, the output swing joint of second motor has the second transfer line, the one end swing joint of second transfer line has first crushing pole, the opposite side of control box is provided with the third motor, the output swing joint of third motor has the third transfer line, the one end swing joint of third transfer line has the second crushing pole.
Optionally, one side fixedly connected with first transmission board of C template, the inside wall fixedly connected with second transmission board of control box.
Optionally, an output port is formed in the front face of the control box, and a guide plate is fixedly connected to one side of the output port.
Optionally, the bottom of the C-shaped plate is fixedly connected with a supporting leg, and one side of the supporting leg is fixedly connected with an X-shaped connecting rod.
Optionally, the surface of first motor is provided with fixed frame, one side of fixed frame is fixed in one side of C template through the stationary blade.
Optionally, the surfaces of the second motor and the third motor are both provided with a motor cover.
(III) advantageous effects
The utility model provides a breaker that building engineering used possesses following beneficial effect:
the crushing device for the building engineering is characterized in that a first motor is arranged, when the crushing device is used, building workers place building materials on a transmission belt, then the first motor is externally connected with a power supply, the first motor works to enable a first transmission rod to drive a transmission wheel to rotate, the transmission wheel rotates to enable the transmission belt to rotate, and further the building materials on the transmission belt are transported into a control box, so that the building workers can conveniently transport the building materials, the working time of the building workers is saved, the working efficiency is improved, when the crushing device is used, the second motor and a third motor are externally connected with the power supply, when the building materials are transported into the control box, the second motor enables a second transmission rod to drive a first crushing rod to move clockwise, the third motor enables a second transmission rod to drive a second crushing rod to rotate anticlockwise, and further the first crushing rod and the second crushing rod are meshed to rotate, therefore, the building materials are crushed in the control box, and the crushing effect and the crushing speed of the device are greatly improved.
Drawings
FIG. 1 is a perspective view of the present invention;
FIG. 2 is a schematic view of the cross-sectional structure of the transmission belt of the present invention;
FIG. 3 is a schematic structural view of a section of the console box of the present invention;
fig. 4 is an enlarged schematic structural view of a portion a in fig. 1 according to the present invention.
In the figure: 1. c-shaped plates; 2. a console box; 3. a first motor; 4. a first drive lever; 5. a driving wheel; 6. a transmission belt; 7. a second motor; 8. a second transmission rod; 9. a first crushing bar; 10. a third motor; 11. a third transmission rod; 12. a second crushing bar; 13. a first transfer plate; 14. a second transmission plate; 15. an output port; 16. a guide plate; 17. supporting legs; 18. an X-shaped connecting rod; 19. a fixing frame; 20. a fixing sheet; 21. a motor cover.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 4, the present invention provides a technical solution: a crushing device for constructional engineering comprises a C-shaped plate 1 and a control box 2, wherein a first motor 3 is arranged on one side of the C-shaped plate 1, the output end of the first motor 3 is movably connected with a first transmission rod 4, one end of the first transmission rod 4 is movably connected with a transmission wheel 5, and the surface of the transmission wheel 5 is movably connected with a transmission belt 6;
through the arrangement of the first motor 3, when the building material conveying device is used, building workers place building materials on the conveying belt 6, then the first motor 3 is externally connected with a power supply, the first motor 3 works to enable the first transmission rod 4 to drive the driving wheel 5 to rotate, the driving wheel 5 rotates to enable the conveying belt 6 to rotate, and further the building materials on the conveying belt 6 are conveyed into the control box 2, so that the building workers can conveniently convey the building materials, the working time is saved for the building workers, and the working efficiency is improved;
the surface of the C-shaped plate 1 is fixedly connected with a control box 2, one side of the control box 2 is provided with a second motor 7, the output end of the second motor 7 is movably connected with a second transmission rod 8, one end of the second transmission rod 8 is movably connected with a first crushing rod 9, the other side of the control box 2 is provided with a third motor 10, the output end of the third motor 10 is movably connected with a third transmission rod 11, and one end of the third transmission rod 11 is movably connected with a second crushing rod 12;
through the arrangement of the second motor 7 and the third motor 10, when the device is used, the second motor 7 and the third motor 10 are externally connected with a power supply, when building materials are transported into the control box 2, the second motor 7 enables the second transmission rod 8 to drive the first crushing rod 9 to move clockwise, the third motor 10 enables the second transmission rod 8 to drive the second crushing rod 12 to rotate anticlockwise, and further the first crushing rod 9 and the second crushing rod 12 are meshed to rotate, so that the building materials are crushed and used in the control box 2, and the crushing effect and the crushing speed of the device are greatly improved;
one side of the C-shaped plate 1 is fixedly connected with a first transmission plate 13, the inner side wall of the control box 2 is fixedly connected with a second transmission plate 14, building materials on the transmission belt 6 are transported into the control box 2 through the first transmission plate 13 and the second transmission plate 14 by the arrangement of the first transmission plate 13 and the second transmission plate 14, the transportation and the use of the building materials are convenient, an output port 15 is arranged on the front side of the control box 2, one side of the output port 15 is fixedly connected with a guide plate 16, after the building materials are crushed in the control box 2 through the output port 15 and the guide plate 16, the building materials are then output from the output port 15 along the guide plate 16, so that the collection and the use of construction workers are convenient, the bottom of the C-shaped plate 1 is fixedly connected with a support leg 17, one side of the support leg 17 is fixedly connected with an X-shaped connecting rod 18, the surface of the first motor 3 is provided with a fixing frame 19, one side of the fixing frame 19 is fixed on one side of the C-shaped plate 1 through a fixing plate 20, the surfaces of the second motor 7 and the third motor 10 are provided with motor covers 21.
The utility model discloses in, the device's working procedure as follows:
1. through the arrangement of the first motor 3, when the building material conveying device is used, building workers place building materials on the conveying belt 6, then the first motor 3 is externally connected with a power supply, the first motor 3 works to enable the first transmission rod 4 to drive the driving wheel 5 to rotate, the driving wheel 5 rotates to enable the conveying belt 6 to rotate, and further the building materials on the conveying belt 6 are conveyed into the control box 2, so that the building workers can conveniently convey the building materials, the working time is saved for the building workers, and the working efficiency is improved;
2. through the setting of second motor 7 and third motor 10, during the use, with second motor 7 and third motor 10 external power supply, when building material transports in control box 2, second motor 7 makes second transfer line 8 drive first crushing pole 9 clockwise motion, third motor 10 makes second transfer line 8 drive second crushing pole 12 anticlockwise rotation, and then makes first crushing pole 9 and second crushing pole 12 mesh and rotate, thereby make building material carry out broken use in control box 2, the broken effect and the broken rate of the device have been improved greatly.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. A breaker that building engineering used, includes C template (1) and control box (2), its characterized in that: a first motor (3) is arranged on one side of the C-shaped plate (1), the output end of the first motor (3) is movably connected with a first transmission rod (4), one end of the first transmission rod (4) is movably connected with a transmission wheel (5), the surface of the transmission wheel (5) is movably connected with a transmission belt (6), the surface of the C-shaped plate (1) is fixedly connected with a control box (2), one side of the control box (2) is provided with a second motor (7), the output end of the second motor (7) is movably connected with a second transmission rod (8), one end of the second transmission rod (8) is movably connected with a first crushing rod (9), a third motor (10) is arranged on the other side of the control box (2), the output end of the third motor (10) is movably connected with a third transmission rod (11), one end of the third transmission rod (11) is movably connected with a second crushing rod (12).
2. A crushing plant for construction works according to claim 1, characterized in that: one side fixedly connected with first transmission board (13) of C template (1), the inside wall fixedly connected with second transmission board (14) of control box (2).
3. A crushing plant for construction works according to claim 1, characterized in that: an output port (15) is formed in the front face of the control box (2), and a guide plate (16) is fixedly connected to one side of the output port (15).
4. A crushing plant for construction works according to claim 1, characterized in that: the bottom fixedly connected with supporting leg (17) of C template (1), one side fixedly connected with X type connecting rod (18) of supporting leg (17).
5. A crushing plant for construction works according to claim 1, characterized in that: the surface of first motor (3) is provided with fixed frame (19), one side of fixed frame (19) is fixed in one side of C template (1) through stationary blade (20).
6. A crushing plant for construction works according to claim 1, characterized in that: and motor covers (21) are arranged on the surfaces of the second motor (7) and the third motor (10).
CN202021741112.XU 2020-08-19 2020-08-19 Breaker that building engineering used Expired - Fee Related CN213726728U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021741112.XU CN213726728U (en) 2020-08-19 2020-08-19 Breaker that building engineering used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021741112.XU CN213726728U (en) 2020-08-19 2020-08-19 Breaker that building engineering used

Publications (1)

Publication Number Publication Date
CN213726728U true CN213726728U (en) 2021-07-20

Family

ID=76840516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021741112.XU Expired - Fee Related CN213726728U (en) 2020-08-19 2020-08-19 Breaker that building engineering used

Country Status (1)

Country Link
CN (1) CN213726728U (en)

Similar Documents

Publication Publication Date Title
CN108160289B (en) High-efficient breaker of building rubbish
CN213726728U (en) Breaker that building engineering used
CN212682026U (en) Contaminated soil remediation equipment for garden construction
CN110216000B (en) Clean breaker of engineering place waste residue
CN213761459U (en) Civil engineering is with agitating unit convenient to wash
CN210757665U (en) Civil engineering pipe fitting rack
CN205201803U (en) A intelligent industrial robot for cement stirring
CN211104179U (en) Cutting device for processing release paper and convenient for equidistant cutting
CN211081699U (en) Drilling rig for geotechnical engineering investigation
CN211499903U (en) Device is demolishd in directional harmless quiet power cutting of reinforced concrete board
CN207435852U (en) A kind of levelling means of construction of the highway
CN213264701U (en) Electric pusher for constructional engineering
CN219257360U (en) Hopper car for building engineering
CN213079718U (en) High-speed drilling production line of numerical control angle steel
CN218715409U (en) Constructional engineering structure gap cementer
CN215598462U (en) Plant factory environment detection device
CN220565671U (en) Stable building construction material is with room construction carrier frame
CN219172457U (en) Portable feedway of water conservancy hydropower construction
CN213590768U (en) Dustless stone crusher that building engineering used
CN212956345U (en) Water conservancy automation mechanical equipment scheduling device
CN212144633U (en) Positioning and punching equipment for civil engineering construction
CN213943322U (en) Garbage disposal device for building engineering construction
CN213323945U (en) Pipe fitting conveying and distributing structure
CN213349004U (en) Environment-friendly waste residue recovery processing equipment for construction
CN218440970U (en) Pipeline laying auxiliary device for fire-fighting construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210720