CN213709382U - Construction board is consolidated to bank protection for hydraulic engineering - Google Patents

Construction board is consolidated to bank protection for hydraulic engineering Download PDF

Info

Publication number
CN213709382U
CN213709382U CN202022034959.0U CN202022034959U CN213709382U CN 213709382 U CN213709382 U CN 213709382U CN 202022034959 U CN202022034959 U CN 202022034959U CN 213709382 U CN213709382 U CN 213709382U
Authority
CN
China
Prior art keywords
plate
reinforcing
groove
reinforcing plate
hydraulic engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022034959.0U
Other languages
Chinese (zh)
Inventor
陈延湖
廖斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022034959.0U priority Critical patent/CN213709382U/en
Application granted granted Critical
Publication of CN213709382U publication Critical patent/CN213709382U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a slope protection reinforcing construction plate for hydraulic engineering, including the gusset plate, the gusset plate is provided with the through-hole, wears to be equipped with the installation section of thick bamboo in the through-hole, and the installation section of thick bamboo endotheca is equipped with connecting seat and mount pad, is provided with the spring between connecting seat and the mount pad, and the bottom of connecting seat is connected with two second connecting rods through the round pin axle, and the top of mount pad is connected with two head rods through the round pin axle, and the one end of two head rods is connected with the one end of two second connecting rods respectively; a support rod is arranged in the mounting cylinder; the reinforcing plate is provided with a fixing groove and a clamping groove, and a connecting block and a clamping block are respectively clamped in the fixing groove and the clamping groove; three pouring holes are arranged on the reinforcing plate. The utility model has the advantages that the reinforcing mechanism is arranged on the reinforcing plate, so that the connection between the reinforcing plate and the ground is more stable, and the fixing groove is arranged on the reinforcing plate, so that the horizontal displacement of the reinforcing plate can be limited after the fixing groove and the connecting block are assembled; through setting up the draw-in groove, can restrict gusset plate vertical direction displacement after draw-in groove and fixture block equipment.

Description

Construction board is consolidated to bank protection for hydraulic engineering
Technical Field
The utility model relates to a construction board technical field is consolidated to the bank protection, and specific is a construction board is consolidated to bank protection for hydraulic engineering.
Background
Hydraulic engineering is an engineering built for controlling and allocating surface water and underground water in the nature to achieve the purpose of removing harm and benefiting, is also called water engineering, water is a valuable resource essential for human production and life, but the naturally existing state of the water does not completely meet the needs of human beings, and only when the hydraulic engineering is built, water flow can be controlled to prevent flood disasters, and water quantity regulation and distribution are performed to meet the needs of people's life and production on water resources. When the existing slope protection reinforcing construction plate is used for a long time, concrete for reinforcing the bottom is corroded by water flow, so that the stability of a concrete plate is weakened, and the effect of protection and reinforcement is reduced; the concrete plate can influence the integrating degree and the stability of the whole anti-collapse reinforcing mechanism in the process of rain washing, so that the whole plate can be settled or slid.
SUMMERY OF THE UTILITY MODEL
The utility model provides a not enough to prior art, the utility model provides a construction board is consolidated to bank protection for hydraulic engineering to solve prior art, the concrete under the construction board appears the cavity phenomenon easily under long-term rivers erode, causes stability to weaken, and the concrete plate can influence whole anti-collapse square strengthening mechanism's degree of agreeing with and stability at the in-process of rainwash, makes whole plate subside or the technical problem who slides.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a slope protection reinforcing construction plate for hydraulic engineering comprises a reinforcing plate, wherein a through hole is formed in the reinforcing plate, an installation cylinder penetrates through the through hole, a connecting seat and an installation seat are sleeved in the installation cylinder, a spring is arranged between the connecting seat and the installation seat, the bottom end of the connecting seat is connected with two second connecting rods through a pin shaft, the top end of the installation seat is connected with two first connecting rods through a pin shaft, and one ends of the two first connecting rods are respectively connected with one ends of the two second connecting rods; a butting rod is arranged in the mounting cylinder, an external thread is arranged at the joint of the butting rod and the mounting cylinder, and an internal thread is arranged on the inner wall of the mounting cylinder; the abutting rod is connected with the mounting cylinder through threads; a fixing groove and a clamping groove are formed in the reinforcing plate, and a connecting block and a clamping block are respectively clamped in the fixing groove and the clamping groove; three pouring holes are formed in the reinforcing plate.
As the utility model discloses a preferred technical scheme, the bottom mounting of gusset plate is provided with three pointed column, the fixed solid fixed ring that is provided with on the pointed column, the cover is equipped with the strengthening rib on the pointed column, the strengthening rib is located two between the solid fixed ring.
As the utility model discloses an optimized technical scheme, logical groove has been seted up on the installation section of thick bamboo.
As the utility model discloses a preferred technical scheme, be provided with the inflation body on the connecting block, the inflation body is the sponge of hydroscopicity.
As the utility model discloses an optimized technical scheme, the casting trough has been seted up to the bottom of gusset plate.
As the preferred technical scheme of the utility model, the fixed slot with the draw-in groove is the dovetail.
Has the advantages that:
the utility model provides a construction board is consolidated to bank protection for hydraulic engineering possesses following beneficial effect: the reinforcing plate is provided with a through hole, an installation cylinder is sleeved in the through hole, a supporting rod, an installation seat and a connecting seat are sleeved in the installation cylinder, two groups of symmetrical connecting rods are connected between the installation seat and the connecting seat, the bottom end of the supporting rod tightly supports the connecting seat by screwing in the supporting rod, so that the connecting seat moves downwards in the installation cylinder, the two groups of symmetrical connecting rods are enabled to be outwards propped out of the installation cylinder, and the connecting rods are pricked into the soil, so that the reinforcing plate can be more stably installed on the ground; the reinforcing plates are arranged to be hexagonal, so that the assembly of workers is facilitated, fixing grooves are formed in four side surfaces of each reinforcing plate, and connecting blocks are clamped in the fixing grooves, so that the movement in the horizontal direction can be limited after the plurality of reinforcing plates are connected together; clamping grooves are formed in two side faces of the reinforcing plates, and clamping blocks are clamped in the clamping grooves, so that the plurality of reinforcing plates can be limited to move in the vertical direction after being connected together; the whole assembled reinforcing plate is more stable.
Drawings
Fig. 1 is a perspective view of a slope protection reinforcing construction plate for hydraulic engineering of the present invention;
fig. 2 is an exploded view of the slope protection reinforcing construction plate for hydraulic engineering of the present invention;
fig. 3 is the utility model relates to a bottom surface structure schematic diagram of gusset plate in construction board is consolidated with bank protection to hydraulic engineering.
In the figure: 1. a spring; 2. a mounting seat; 3. a first connecting rod; 4. a barb; 5. a second connecting rod; 7. a connecting seat; 8. a support rod; 9. a card slot; 10. fixing grooves; 11. a reinforcing plate; 12. a through hole; 13. a clamping block; 14. a pouring hole; 15. an expansion body; 16. connecting blocks; 17. a fixing ring; 18. a tip post; 19. reinforcing ribs; 20. mounting the cylinder; 21. a through groove; 22. and (4) pouring a trough.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution: a slope protection reinforcing construction plate for hydraulic engineering comprises a reinforcing plate 11, wherein a through hole 12 is formed in the reinforcing plate 11, an installation cylinder 20 penetrates through the through hole 12, a connecting seat 7 and an installation seat 2 are sleeved in the installation cylinder 20, a spring 1 is arranged between the connecting seat 7 and the installation seat 2, the bottom end of the connecting seat 7 is connected with two second connecting rods 5 through pin shafts, the top end of the installation seat 2 is connected with two first connecting rods 3 through pin shafts, and one end of each of the two first connecting rods 3 is connected with one end of each of the two second connecting rods 5; a supporting rod 8 is arranged in the mounting cylinder 20, an external thread is arranged at the joint of the supporting rod 8 and the mounting cylinder 20, and an internal thread is arranged on the inner wall of the mounting cylinder 20; the abutting rod 8 is connected with the mounting cylinder 20 through threads; a fixing groove 10 and a clamping groove 9 are formed in the reinforcing plate 11, and a connecting block 16 and a clamping block 13 are clamped in the fixing groove 10 and the clamping groove 9 respectively; three pouring holes 14 are formed in the reinforcing plate 11.
When the slope protection reinforcing construction plate for the hydraulic engineering is used, the through hole 12 is formed in the reinforcing plate 11, the installation cylinder 20 is sleeved in the through hole 12, the abutting rod 8, the installation seat 2 and the connecting seat 7 are sleeved in the installation cylinder 20, two groups of symmetrical connecting rods are connected between the installation seat 2 and the connecting seat 7, the bottom end of the abutting rod 8 abuts against the connecting seat 7 by screwing in the abutting rod 8, the connecting seat 7 moves downwards in the installation cylinder 20, the two groups of symmetrical connecting rods are enabled to be supported out of the installation cylinder 20, and the connecting rods are inserted into soil, so that the reinforcing plate 11 can be installed on the ground more stably; the reinforcing plates 11 are arranged in a hexagon shape, so that the assembly of workers is facilitated, fixing grooves 10 are formed in four side surfaces of each reinforcing plate 11, and connecting blocks 16 are clamped in the fixing grooves 10, so that the movement in the horizontal direction can be limited after the plurality of reinforcing plates 11 are connected together; clamping grooves 9 are formed in two side faces of the reinforcing plates 11, and clamping blocks 13 are clamped in the clamping grooves 9, so that the plurality of reinforcing plates 11 can be limited to move in the vertical direction after being connected together; the whole assembled reinforcing plate 11 is more stable.
Referring to fig. 2, three pointed columns 18 are fixedly arranged at the bottom end of the reinforcing plate 11, two fixing rings 17 are fixedly arranged on the pointed columns 18, reinforcing ribs 19 are sleeved on the pointed columns 18, and the reinforcing ribs 19 are located between the two fixing rings 17. Set up three pointed post 18, when the installation with pointed post 18 insert subaerial, make gusset plate 11 fixed subaerial, then through pouring hole 14 to the fixed thick liquid of pouring into in gusset plate 11, make to be full of between the bottom of gusset plate 11 and the ground fixed thick liquid, fixed thick liquid is with strengthening rib 19 package inside, makes the intensity of the good reinforced thick liquid of pouring better, strengthens just type, consolidates the condition that the thick liquid can not produce the fracture.
Referring to fig. 2, a through slot 21 is formed on the mounting cylinder 20. The through groove 21 is formed to facilitate the first connecting rod 3 and the second connecting rod 5 to be externally supported outside the mounting cylinder 20 when the connecting seat 7 moves in the mounting cylinder 20.
Referring to fig. 2, an expansion body 15 is arranged on the connecting block 16, and the expansion body 15 is a water-absorbent sponge. The expansion body 15 is arranged, so that the connecting block 16 clamped in the fixing groove 10 is more stable; the sponge body with water absorption is selected as the expansion body 15, and the sponge body has better water absorption expansion effect.
Referring to fig. 3, a pouring slot 22 is formed at the bottom end of the reinforcing plate 11. The pouring groove 22 is arranged, when reinforcing slurry is poured into the reinforcing plate 11, the reinforcing plate 11 is connected with the ground by the reinforcing slurry, and the reinforcing slurry is filled in the pouring groove 22 at the bottom end of the reinforcing plate 11, so that the reinforcing plate 11 is connected with the ground more stably.
Referring to fig. 2, the fixing groove 10 and the engaging groove 9 are dovetail-shaped. Set up fixed slot 10 and draw-in groove 9 into the forked tail shape groove, have the eave tile because of the forked tail shape groove, enable to be connected between every gusset plate 11 and more fasten, the phenomenon of slippage can not appear.
In summary, the reinforcing plate 11 is provided with the through hole 12, the through hole 12 is internally sleeved with the mounting cylinder 20, the installation cylinder 20 is internally sleeved with the abutting rod 8, the mounting seat 2 and the connecting seat 7, two groups of symmetrical connecting rods are connected between the mounting seat 2 and the connecting seat 7, and the bottom end of the abutting rod 8 abuts against the connecting seat 7 by screwing in the abutting rod 8, so that the connecting seat 7 moves downwards in the mounting cylinder 20, the two groups of symmetrical connecting rods are enabled to be outwards supported out of the mounting cylinder 20, and the barbs 4 on the connecting rods are enabled to be pricked into soil, so that the reinforcing plate 11 can be more stably installed on the ground; the reinforcing plates 11 are arranged in a hexagon shape, so that the assembly of workers is facilitated, fixing grooves 10 are formed in four side surfaces of each reinforcing plate 11, and connecting blocks 16 are clamped in the fixing grooves 10, so that the movement in the horizontal direction can be limited after the plurality of reinforcing plates 11 are connected together; clamping grooves 9 are formed in two side faces of the reinforcing plates 11, and clamping blocks 13 are clamped in the clamping grooves 9, so that the plurality of reinforcing plates 11 can be limited to move in the vertical direction after being connected together; the whole assembled reinforcing plate 11 is more stable. The reinforcing plate 11 is provided with a pouring hole 14, after a plurality of reinforcing plates 11 are assembled, the reinforcing plates 11 are paved on the ground in a sheet mode, reinforcing slurry is poured into the pouring hole 14, the reinforcing slurry is filled between the bottom end of the reinforcing plate 11 and the ground, and a cavity between the reinforcing plate 11 and the ground is filled with the reinforcing slurry, so that the reinforcing plate 11 is attached to the ground more tightly, and the stability of the reinforcing plate is not damaged due to water erosion caused by gaps.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a construction board is consolidated to bank protection for hydraulic engineering which characterized in that: the fixing device comprises a reinforcing plate (11), wherein a through hole (12) is formed in the reinforcing plate (11), an installation cylinder (20) penetrates through the through hole (12), a connecting seat (7) and an installation seat (2) are sleeved in the installation cylinder (20), a spring (1) is arranged between the connecting seat (7) and the installation seat (2), the bottom end of the connecting seat (7) is connected with two second connecting rods (5) through a pin shaft, the top end of the installation seat (2) is connected with two first connecting rods (3) through a pin shaft, and one end of each of the two first connecting rods (3) is connected with one end of each of the two second connecting rods (5); a supporting rod (8) is arranged in the mounting cylinder (20), an external thread is arranged at the joint of the supporting rod (8) and the mounting cylinder (20), and an internal thread is arranged on the inner wall of the mounting cylinder (20); the abutting rod (8) is connected with the mounting cylinder (20) through threads; a fixing groove (10) and a clamping groove (9) are formed in the reinforcing plate (11), and a connecting block (16) and a clamping block (13) are respectively clamped in the fixing groove (10) and the clamping groove (9); three pouring holes (14) are formed in the reinforcing plate (11).
2. The slope protection reinforcing construction plate for the hydraulic engineering according to claim 1, wherein: the bottom mounting of gusset plate (11) is provided with three pointed column (18), the fixed two solid fixed rings (17) that are provided with on pointed column (18), the cover is equipped with strengthening rib (19) on pointed column (18), strengthening rib (19) are located two gu between fixed ring (17).
3. The slope protection reinforcing construction plate for the hydraulic engineering according to claim 1, wherein: the mounting cylinder (20) is provided with a through groove (21).
4. The slope protection reinforcing construction plate for the hydraulic engineering according to claim 1, wherein: an expansion body (15) is arranged on the connecting block (16), and the expansion body (15) is a water-absorbing sponge.
5. The slope protection reinforcing construction plate for the hydraulic engineering according to claim 1, wherein: and a pouring groove (22) is formed in the bottom end of the reinforcing plate (11).
6. The slope protection reinforcing construction plate for the hydraulic engineering according to claim 1, wherein: the fixing groove (10) and the clamping groove (9) are in a dovetail shape.
CN202022034959.0U 2020-09-16 2020-09-16 Construction board is consolidated to bank protection for hydraulic engineering Expired - Fee Related CN213709382U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022034959.0U CN213709382U (en) 2020-09-16 2020-09-16 Construction board is consolidated to bank protection for hydraulic engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022034959.0U CN213709382U (en) 2020-09-16 2020-09-16 Construction board is consolidated to bank protection for hydraulic engineering

Publications (1)

Publication Number Publication Date
CN213709382U true CN213709382U (en) 2021-07-16

Family

ID=76794496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022034959.0U Expired - Fee Related CN213709382U (en) 2020-09-16 2020-09-16 Construction board is consolidated to bank protection for hydraulic engineering

Country Status (1)

Country Link
CN (1) CN213709382U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114606901A (en) * 2022-04-02 2022-06-10 山东泽涛复合材料有限公司 Slope protection synthesized by waste mulching films and modified red mud

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114606901A (en) * 2022-04-02 2022-06-10 山东泽涛复合材料有限公司 Slope protection synthesized by waste mulching films and modified red mud

Similar Documents

Publication Publication Date Title
CN213709382U (en) Construction board is consolidated to bank protection for hydraulic engineering
CN109457800B (en) Assembled concrete column connection node
CN221142515U (en) Temporary bridge slab construction
CN211547696U (en) Steel pipe pile
CN210141147U (en) Prefabricated reinforced concrete anchor rod
CN215858149U (en) Adjustable base is laid to stone material
CN210766846U (en) Novel transmission tower foundation
CN206090822U (en) Concrete supporting frame and assembled concrete wall
CN213682542U (en) Building structure design wall column base quick connecting device
CN210976604U (en) Dysmorphism pier stud template reinforced structure
CN110132376B (en) Water level alarm device for hydraulic engineering construction
CN218405024U (en) Anti-seismic device for bridge
CN220266432U (en) Hydraulic engineering side slope reinforcing apparatus
CN221627126U (en) Composite construction water conservancy pile foundation
CN213627614U (en) Waterproof supporting device for tunnel to penetrate through rock area
CN221193456U (en) Anti-buoyancy foundation of green building
CN219033183U (en) Connection structure of drilling pile
CN218060145U (en) Horizontal stock reinforced structure of multistage bank protection
CN220598490U (en) Assembled antidetonation cushion cap structure
CN211571781U (en) Retaining wall for hydraulic engineering
CN212507731U (en) Water conservancy construction safety device
CN221837839U (en) Building reinforced concrete prefabricated part
CN219691507U (en) Plugging device for reducing overflow slurry pollution rate in drilling construction
CN214530149U (en) Energy-saving environment-friendly tractor-ploughing bridge
CN217103256U (en) Floating bed for river channel ecological management

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210716