CN213657232U - Water cooling circulation system of intelligent clean workshop - Google Patents

Water cooling circulation system of intelligent clean workshop Download PDF

Info

Publication number
CN213657232U
CN213657232U CN202022880181.5U CN202022880181U CN213657232U CN 213657232 U CN213657232 U CN 213657232U CN 202022880181 U CN202022880181 U CN 202022880181U CN 213657232 U CN213657232 U CN 213657232U
Authority
CN
China
Prior art keywords
cooling
water
pipeline
workshop
filtering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022880181.5U
Other languages
Chinese (zh)
Inventor
钟喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jinxin Purification Technology Co ltd
Original Assignee
Guangdong Jinxin Purification Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jinxin Purification Technology Co ltd filed Critical Guangdong Jinxin Purification Technology Co ltd
Priority to CN202022880181.5U priority Critical patent/CN213657232U/en
Application granted granted Critical
Publication of CN213657232U publication Critical patent/CN213657232U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filtration Of Liquid (AREA)

Abstract

A water cooling circulation system of an intelligent cleaning workshop comprises a cooling pond, a water pump, a filtering pond, a water circulation pipeline and a condenser, wherein the condenser is connected with a workshop water outlet pipeline, a water outlet of the condenser is connected with the cooling pond, the cooling pond is connected with the filtering pond, the water pump is arranged on a connecting pipeline of the cooling pond and the filtering pond, the filtering pond is connected with a workshop water inlet pipeline through a water circulation cooling pipe, a filter screen in the filtering pond is arranged in the liquid level in the filtering pond, the filter screens are arranged in parallel, and a liquid outlet of the filtering pond is arranged on one side above the filter screen; the steam of delivery port in from clean workshop is collected through the condenser cooling, gets into the cooling tank after the cooling is collected, and the filtering ponds is connected to the cooling tank, and the water of delivery port filters the back among the clean workshop and then enters into clean workshop, satisfies clean workshop water requirement, and simultaneously, the hydrologic cycle pipeline is connected with water supply pipeline, can guarantee that clean workshop water source is sufficient.

Description

Water cooling circulation system of intelligent clean workshop
Technical Field
The utility model relates to a water cooler circulation technical field, especially a water cooling circulation system in intelligent clean workshop.
Background
A clean room is a space having air filtration, distribution, optimization, construction materials and devices, and is classified into several registrations according to factors such as the environment and the degree of purification.
In the production of clean workshops, the generated surplus heat is generally cooled by water with good heat-conducting property and low cost, and a circulating cooling system is formed by adopting proper cooling measures as cooling water, so that the industrial water is saved, and the natural environment is protected.
SUMMERY OF THE UTILITY MODEL
In order to overcome the above disadvantages of the prior art, the present invention provides a water cooling circulation system for an intelligent clean room.
The utility model provides a technical scheme that its technical problem adopted is: the utility model provides a water cooling circulation system in clean workshop of intelligence, includes cooling tank, water pump, filtering ponds, hydrologic cycle pipeline and condenser, workshop outlet conduit is connected to the condenser, the cooling tank is connected to the condenser delivery port, the filtering ponds are connected to the cooling tank, the water pump is established on cooling tank and filtering ponds connecting tube, the filtering ponds passes through hydrologic cycle cooling union coupling workshop inlet channel, the filter screen in the filtering ponds is established in the liquid level in the filtering ponds, filter screen parallel arrangement, the liquid outlet of filtering ponds is established in filter screen top one side.
As a further improvement of the utility model: the filtering tank is connected with a second filtering pipeline, the second filtering pipeline is connected with the cooling tank, and a one-way valve is arranged on the second filtering pipeline.
As a further improvement of the utility model: the condenser comprises a first condenser and a standby condenser, and a control valve is arranged between the standby condenser and a workshop water outlet pipeline.
As a further improvement of the utility model: and flow meters are arranged on the connecting pipeline of the cooling tank and the filtering tank and the water circulating pipeline.
As a further improvement of the utility model: the cooling pool is connected with the heat exchanger.
As a further improvement of the utility model: and a refrigerating machine is arranged in the cooling pool and is connected with a power supply.
As a further improvement of the utility model: and drain outlets are arranged on the lower sides of the filtering tank and the cooling tank and are connected with a drain valve.
As a further improvement of the utility model: and a steam valve is arranged on the condenser and is fixedly connected with the condenser.
As a further improvement of the utility model: the water circulation pipeline is connected with a water replenishing pipeline, and an electromagnetic valve is arranged on the water replenishing pipeline.
As a further improvement of the utility model: the water pump, the electromagnetic valve and the one-way valve are connected with a controller, and the controller is connected with a power supply.
Compared with the prior art, the beneficial effects of the utility model are that: the steam of delivery port in from clean workshop is collected through the condenser cooling, gets into the cooling tank after the cooling is collected, and the filtering ponds is connected to the cooling tank, and the water of delivery port filters the back among the clean workshop and then enters into clean workshop, satisfies clean workshop water requirement, and simultaneously, the hydrologic cycle pipeline is connected with water supply pipeline, can guarantee that clean workshop water source is sufficient.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural diagram of an embodiment of the present invention.
Detailed Description
The invention will now be further described with reference to the accompanying drawings, in which: as shown in fig. 1-2 a water cooling circulation system in clean workshop of intelligence, including cooling tank 1, water pump 5, filtering ponds 2, hydrologic cycle pipeline 3 and condenser 4, workshop outlet conduit 101 is connected to condenser 4, cooling tank 1 is connected to condenser 4 delivery port, filtering ponds 2 are connected to cooling tank 1, water pump 5 is established on cooling tank 1 and filtering ponds 2 connecting tube, filtering ponds 2 passes through hydrologic cycle cooling pipe 3 and connects workshop inlet conduit, filter screen 21 in the filtering ponds is established in filtering ponds 2 liquid level, filter screen 21 parallel arrangement, the liquid outlet 22 of filtering ponds 2 is established in filter screen 21 top one side.
The condenser 4 comprises a first condenser 41 and a standby condenser 42, a control valve 401 is arranged between the standby condenser 42 and a workshop water outlet pipeline, a steam valve 107 is arranged on the condenser 4, the steam valve 107 is fixedly connected with the condenser 4, a flow meter 104 is arranged on a connecting pipeline of the cooling pond 1 and a filtering pond 2 and a water circulating pipeline 3, the cooling pond 1 is connected with a heat exchanger, a refrigerator 11 is arranged in the cooling pond 1, the refrigerator 11 is connected with a power supply, the filtering pond 2 is connected with a second filtering pipeline 102, the second filtering pipeline 102 is connected with the cooling pond 1, a one-way valve 103 is arranged on the second filtering pipeline 102, sewage outlets 105 are arranged on the lower sides of the filtering pond 1 and the cooling pond 2, the sewage outlets 105 are connected with a sewage valve 106, the water circulating pipeline 3 is connected with a water replenishing pipeline 108, and an electromagnetic valve 109 is arranged on the water replenishing pipeline 108, the water pump 5, the electromagnetic valve 109 and the one-way valve 103 are connected with a controller, and the controller is connected with a power supply.
The implementation case is as follows:
the water cooling circulation system of the intelligent clean workshop as shown in fig. 2 comprises a cooling pool, a water pump, a filtering pool, a water circulation pipeline and a condenser, wherein the condenser comprises a first condenser and a standby condenser, the condenser is connected with a workshop water outlet pipeline, a control valve is arranged between the standby condenser and the workshop water outlet pipeline, the workshop water outlet pipeline is divided into the first condenser and the standby condenser, a water outlet of the condenser is connected with the cooling pool, condensed water is reserved to the cooling pool, a steam valve is arranged on the condenser and fixedly connected with the condenser, the cooling pool is connected with the filtering pool, the filtering pool is connected with a second filtering pipeline, the second filtering pipeline is connected with the cooling pool, a one-way valve is arranged on the second filtering pipeline, the water pump is arranged on a connecting pipeline of the cooling pool and the filtering pool, and a refrigerator is arranged in the cooling pool, the refrigerator is connected with a power supply, the filtering tank is connected with a workshop water inlet pipeline through a water circulation cooling pipe, flowmeters are arranged on the cooling tank, the filtering tank connecting pipeline and the water circulation pipeline, a filtering net in the filtering tank is arranged in the liquid level in the filtering tank, the filtering net is arranged in parallel, a liquid outlet of the filtering tank is arranged on one side above the filtering net, sewage drains are arranged on the lower sides of the filtering tank and the cooling tank, the sewage drains are connected with a sewage drain valve, the water circulation pipeline is connected with a water replenishing pipeline, an electromagnetic valve is arranged on the water replenishing pipeline, a water pump, the electromagnetic valve and a one-way valve are connected with a controller, and the power.
The utility model discloses a main function: the steam of delivery port in from clean workshop is collected through the condenser cooling, gets into the cooling tank after the cooling is collected, and the filtering ponds is connected to the cooling tank, and the water of delivery port filters the back among the clean workshop and then enters into clean workshop, satisfies clean workshop water requirement, and simultaneously, the hydrologic cycle pipeline is connected with water supply pipeline, can guarantee that clean workshop water source is sufficient.
In conclusion, after the ordinary skilled in the art reads the document of the present invention, according to the present invention, the technical solution and technical concept of the present invention do not need creative mental labor to make other various corresponding transformation schemes, which all belong to the protection scope of the present invention.

Claims (7)

1. The utility model provides a water cooling circulation system in clean workshop of intelligence, its characterized in that, includes cooling tank, water pump, filtering ponds, hydrologic cycle pipeline and condenser, workshop outlet conduit is connected to the condenser, the cooling tank is connected to the condenser delivery port, the filtering ponds are connected to the cooling tank, the water pump is established on cooling tank and filtering ponds connecting tube, the filtering ponds passes through hydrologic cycle cooling pipe and connects workshop inlet channel, the filter screen in the filtering ponds is established in the liquid level in the filtering ponds, filter screen parallel arrangement, the liquid outlet of filtering ponds is established in filter screen top one side.
2. The water cooling circulation system of the intelligent clean workshop as claimed in claim 1, wherein the filter tank is connected to a second filter pipeline, the second filter pipeline is connected to the cooling tank, and the second filter pipeline is provided with a check valve.
3. The water cooling circulation system of an intelligent clean workshop as claimed in claim 1, wherein flow meters are arranged on the connecting pipeline of the cooling tank and the filtering tank and the water circulation pipeline.
4. The water cooling circulation system of an intelligent clean room as claimed in claim 3, wherein the cooling tank is connected with a heat exchanger.
5. The water cooling circulation system of an intelligent clean room as claimed in claim 4, wherein a refrigerator is arranged in the cooling tank, and the refrigerator is connected with a power supply.
6. The water cooling circulation system of the intelligent clean workshop as claimed in claim 1, wherein the filter tank and the cooling tank are provided with drain outlets at lower sides thereof, and the drain outlets are connected with drain valves.
7. The water cooling circulation system of an intelligent clean room as claimed in claim 2, wherein the water pump and the one-way valve are connected with a controller, and the controller is connected with a power supply.
CN202022880181.5U 2020-12-03 2020-12-03 Water cooling circulation system of intelligent clean workshop Active CN213657232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022880181.5U CN213657232U (en) 2020-12-03 2020-12-03 Water cooling circulation system of intelligent clean workshop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022880181.5U CN213657232U (en) 2020-12-03 2020-12-03 Water cooling circulation system of intelligent clean workshop

Publications (1)

Publication Number Publication Date
CN213657232U true CN213657232U (en) 2021-07-09

Family

ID=76688555

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022880181.5U Active CN213657232U (en) 2020-12-03 2020-12-03 Water cooling circulation system of intelligent clean workshop

Country Status (1)

Country Link
CN (1) CN213657232U (en)

Similar Documents

Publication Publication Date Title
CN203837331U (en) Mine water heat exchange device and system supplying heat through mine water
CN109611386A (en) A kind of hydraulic power unit fuel tank for shield machine
CN107270742B (en) Shower waste water waste heat exchanger
CN100582605C (en) Native sewage water heat pump air conditioning system
CN212457074U (en) Environment home system with hydraulic integrated module
CN213657232U (en) Water cooling circulation system of intelligent clean workshop
CN211261192U (en) Central air conditioning hydrologic cycle control equipment
CN205245612U (en) Normal water recovery system with energy recuperation structure
CN201221877Y (en) Native sewage water heat pump air conditioning system
CN206818020U (en) Shower waste afterheat heat exchanger
CN202254562U (en) Laser chiller with purification function
CN105258399B (en) Middle water reclamation system with energy regenerating structure
CN212246569U (en) Brewing cooling water recovery and waste heat utilization system
CN211261137U (en) Zero-resistance efficient machine room framework
CN204963627U (en) Direct primary sewage pipe plate heat exchanger
CN209604336U (en) Hydraulic power unit fuel tank for shield machine
CN206222688U (en) A kind of efficient idle air source heat pump system
CN102261769B (en) Solar-energy-aided air energy heat pump system
CN201227561Y (en) Combination type perfume refrigeration filter
CN206817820U (en) A kind of twin-stage direct-heating-type sewage source heat pump unit
CN217715503U (en) Automatic back-flushing cooler
CN204043142U (en) A kind of bootstrap system based on heat pump principle
CN221526709U (en) Steam-water sampling water recycling system
CN218210196U (en) On-line filtering device of chilled water system
CN203704211U (en) Special energy-saving air conditioner machine room

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant