CN213625480U - Water conservancy construction waterproof construction - Google Patents

Water conservancy construction waterproof construction Download PDF

Info

Publication number
CN213625480U
CN213625480U CN202021619103.3U CN202021619103U CN213625480U CN 213625480 U CN213625480 U CN 213625480U CN 202021619103 U CN202021619103 U CN 202021619103U CN 213625480 U CN213625480 U CN 213625480U
Authority
CN
China
Prior art keywords
casing
support
water
pivot
board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021619103.3U
Other languages
Chinese (zh)
Inventor
王冬君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021619103.3U priority Critical patent/CN213625480U/en
Application granted granted Critical
Publication of CN213625480U publication Critical patent/CN213625480U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model belongs to the technical field of it is waterproof, especially, water conservancy construction waterproof construction to current problem that has ponding outflow when dismantling and overhaul, the following scheme is proposed at present, and it includes the casing, set up big recess on the inner wall of casing top, all seted up the sliding tray on the big recess both sides inner wall, sliding installation has same pivot in two sliding trays, rotates in the pivot and installs the water removal board, and water removal board and casing looks adaptation, in the pivot respectively fixed mounting have first support and second support, first support and second support are located the both sides of water removal board respectively, first support and second support homonymy fixed mounting have a shelves pole, and a shelves pole is located one side of water removal board. The utility model discloses install out the water board in the casing, can push away unnecessary water in the casing, can not have rivers to flow and lead to the danger of damaging equipment when dismantling.

Description

Water conservancy construction waterproof construction
Technical Field
The utility model relates to a waterproof technology field especially relates to a water conservancy construction waterproof construction.
Background
Hydraulic engineering is an engineering aiming at removing harmful substances and benefiting, which is generally used for controlling and allocating surface water and underground water in the nature, and requires a lot of equipment.
The patent with the application number of CN201920037705.9 discloses a water conservancy construction throttling arrangement, concretely relates to throttling arrangement technical field, which comprises a housin, the inside one side of casing is provided with the water inlet, water inlet one side is provided with the throttle piece, the inside orifice that is provided with of throttle piece, throttle piece one side is provided with the delivery port, delivery port one side is provided with the butt joint ring, the butt joint ring outer wall is provided with the draw-in groove, the butt joint ring outside is provided with the clamp plate, clamp plate one end inner wall is provided with the catching groove, the clamp plate both sides are provided with fixed establishment. The utility model discloses a be equipped with fixed establishment, sandwich panel, butt joint ring and draw-in groove, can be under the condition of not moving the water pipe the utility model discloses pull down, this just makes the utility model discloses when overhauing, be convenient for with the utility model discloses dismantle from the water pipe and get off for the maintenance degree of difficulty is lower, and maintainer's work load is less, and the time that consumes simultaneously is also less relatively, makes the efficiency of overhauing higher.
However, the patent has no waterproof measures, so that water flows out during disassembly and maintenance, and the equipment is possibly damaged due to water inflow, and accordingly loss of courser is caused.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a water conservancy construction waterproof structure.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a water conservancy construction waterproof construction, which comprises a housin, seted up big recess on the casing top inner wall, all seted up the sliding tray on the big recess both sides inner wall, slidable mounting has same pivot in two sliding trays, rotate in the pivot and install the water removal board, and water removal board and casing looks adaptation, there are first support and second support fixed mounting respectively in the pivot, first support and second support are located the both sides of water removal board respectively, first support and second support homonymy fixed mounting have the shelves pole, and the shelves pole is located one side of water removal board.
Preferably, the sliding holes are formed in the inner wall of the top of the sliding groove, the same push rod is slidably mounted in the two sliding holes and is of an inverted U-shaped structure, and two ends of the push rod are fixedly connected with two sides of the top of the rotating shaft respectively.
Preferably, the both ends of pivot are the cuboid structure, and the mid portion of pivot is the cylinder structure, and the cylinder structure of the mid portion of pivot is cup jointed in the activity of dewatering board.
Preferably, the through-hole has been seted up at the casing top, and water trap top fixed mounting has the quarter butt, and the top of quarter butt passes the through-hole and extends to outside the casing, and quarter butt and through-hole looks adaptation.
Preferably, the casing top has been seted up the fixed orifices, and the one side fixed mounting who keeps away from the pivot in water trap top has the screw, and the top of screw passes the fixed orifices and extends to outside the casing, and screw top movable mounting has the nut that is located fixed orifices department, and screw and nut looks adaptation.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses in, a water conservancy construction waterproof construction, after the use, loosen the nut and the screw at casing top, then promote the push rod, the push rod drives the pivot, and the pivot drives the board that removes water, then the shelves pole on first support and the second support together drives the board that removes water to big recess opposite side motion, thereby the board that removes water pushes away unnecessary water in with the casing and reaches the purpose that can not have rivers to go out when dismantling.
The utility model discloses install out the water board in the casing, can push away unnecessary water in the casing, can not have rivers to flow and lead to the danger of damaging equipment when dismantling.
Drawings
Fig. 1 is a schematic front structural view of a water conservancy construction waterproof structure provided by the utility model;
fig. 2 is a schematic side structure view of a water conservancy construction waterproof structure provided by the utility model;
fig. 3 is the utility model provides a pivot structure schematic diagram of water conservancy construction waterproof construction.
Fig. 4 is the utility model provides a water conservancy construction waterproof construction overlook the schematic structure.
In the figure: the water-saving device comprises a shell 1, a large groove 2, a rotating shaft 3, a water-removing plate 4, a first support 5, a sliding hole 6, a push rod 7, a sliding groove 8, a stop rod 9, a through hole 10, a short rod 11, a second support 12, a fixing hole 13, a screw 14 and a nut 15.
Detailed Description
In the technical scheme:
(3 rotating shafts, 4 water removing plates) are the novel water-saving water.
(1 casing, 2 big recesses, 5 first supports, 6 sliding holes, 7 push rods, 8 sliding tray, 9 shelves poles, 10 through-holes, 11 quarter butts, 12 second supports, 13 fixed orificess, 14 screws, 15 nuts) for realizing the utility model discloses the essential connectivity component of technical scheme.
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Example one
Referring to fig. 1-4, a water conservancy construction waterproof construction, including casing 1, big recess 2 has been seted up on the inner wall of casing 1 top, sliding tray 8 has all been seted up on the inner wall of big recess 2 both sides, slidable mounting has same pivot 3 in two sliding tray 8, it installs except that water board 4 to rotate on the pivot 3, and remove water board 4 and casing 1 looks adaptation, there are first support 5 and second support 12 in the pivot 3 respectively fixed mounting, first support 5 and second support 12 are located the both sides of removing water board 4 respectively, first support 5 and 12 homonymy fixed mounting of second support have shelves pole 9, and shelves pole 9 is located one side of removing water board 4, pivot 3 is used for rotating, sliding tray 8 is used for sliding, first support 5 and second support 12 are used for supporting, shelves pole 9 is used for fixing.
The utility model discloses in, seted up slide opening 6 on the 8 top inner walls of sliding tray, slidable mounting has same push rod 7 in two slide openings 6, and push rod 7 is the type of falling U structure, the both ends of push rod 7 respectively with 3 top both sides fixed connection of pivot, slide opening 6 is used for sliding.
The utility model discloses in, the both ends of pivot 3 are the cuboid structure, and the intermediate portion of pivot 3 is the cylinder structure, and the cylinder of the intermediate portion of pivot 3 is cup jointed in the activity of dewatering board 4 structurally, and dewatering board 4 is used for the dewatering.
The utility model discloses in, through-hole 10 has been seted up at 1 top of casing, and except that 4 top fixed mounting of water board have quarter butt 11, the top of quarter butt 11 is passed through-hole 10 and is extended to casing 1 outside, and quarter butt 11 and through-hole 10 looks adaptation.
The utility model discloses in, fixed orifices 13 have been seted up at 1 top of casing, and one side fixed mounting who keeps away from pivot 3 except that 4 tops of water board has screw 14, and outside fixed orifices 13 extended to casing 1 was passed at the top of screw 14, 14 top movable mounting of screw had the nut 15 that is located fixed orifices 13 department, and screw 14 and 15 looks adaptations of nut, and screw 14 and nut 15 are used for fixing.
Example two
The utility model provides a water conservancy construction waterproof construction, which comprises a housin 1, chisel big recess 2 on the 1 top inner wall of casing, all chisel sliding tray 8 on the 2 both sides inner walls of big recess, slidable mounting has same pivot 3 in two sliding tray 8, it installs except that water board 4 to rotate on the pivot 3, and remove water board 4 and 1 looks adaptation of casing, fixed welding respectively has first support 5 and second support 12 in the pivot 3, first support 5 and second support 12 are located the both sides of removing water board 4 respectively, the fixed welding of first support 5 and second support 12 homonymy has shelves pole 9, and shelves pole 9 is located one side of removing water board 4.
The utility model discloses in, the chisel has sliding hole 6 on the 8 top inner walls of sliding tray, and slidable mounting has same push rod 7 in two sliding hole 6, and push rod 7 is the type of falling U structure, the both ends of push rod 7 respectively with 3 top both sides fixed connection of pivot.
The utility model discloses in, the both ends of pivot 3 are the cuboid structure, and the mid portion of pivot 3 is the cylinder structure, and the cylinder of the mid portion of pivot 3 is structural to the activity of dewatering board 4 cup joints.
The utility model discloses in, 1 top chisel of casing has through-hole 10, and except that 4 top fixed welds of water board have quarter butt 11, the top of quarter butt 11 is passed through-hole 10 and is extended to outside casing 1, and quarter butt 11 and through-hole 10 looks adaptation.
The utility model discloses in, 1 top chisel of casing has fixed orifices 13, and the fixed welding of one side that pivot 3 was kept away from at 4 tops of water trap has screw 14, and outside fixed orifices 13 extended to casing 1 was passed at the top of screw 14, 14 top movable mounting of screw had the nut 15 that is located fixed orifices 13 department, and screw 14 and 15 looks adaptations of nut.
The utility model discloses in, a water conservancy construction waterproof construction, after the use, loosen nut 15 and screw 14 at 1 top of casing, then promote push rod 7, push rod 7 drives pivot 3, pivot 3 drives except that the board 4, then shelves pole 9 on first support 5 and the second support 12 together drive except that board 4 moves to 2 opposite sides of big recess, shelves pole 9 blocks out board 4 and can not lead to the slope because of the pressure of water to thereby use push rod 7 to drive except that board 4 pushes away the internal unnecessary water of casing 1 smoothly and reach the mesh that can not have rivers to go out when dismantling.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (5)

1. The utility model provides a water conservancy construction waterproof construction, including casing (1), a serial communication port, big recess (2) have been seted up on casing (1) top inner wall, sliding tray (8) have all been seted up on the inner wall of big recess (2) both sides, slidable mounting has same pivot (3) in two sliding trays (8), it installs except that water board (4) to rotate on pivot (3), and remove water board (4) and casing (1) looks adaptation, there are first support (5) and second support (12) respectively fixed mounting on pivot (3), first support (5) and second support (12) are located the both sides that remove water board (4) respectively, first support (5) and second support (12) homonymy fixed mounting have shelves pole (9), and shelves pole (9) are located the one side that removes water board (4).
2. The water conservancy construction waterproof structure of claim 1, characterized in that, slide opening (6) have been seted up on the inner wall of sliding tray (8) top, and slidable mounting has same push rod (7) in two slide opening (6), and push rod (7) are the type of falling U structure, the both ends of push rod (7) respectively with pivot (3) top both sides fixed connection.
3. The water conservancy construction waterproof structure of claim 1, wherein the two ends of the rotating shaft (3) are of cuboid structures, the middle part of the rotating shaft (3) is of a cylindrical structure, and the water removal plate (4) is movably sleeved on the cylindrical structure of the middle part of the rotating shaft (3).
4. The water conservancy construction waterproof structure of claim 1, characterized in that, through-hole (10) has been seted up at casing (1) top, except that water board (4) top fixed mounting has quarter butt (11), outside through-hole (10) is passed and is extended to casing (1) in the top of quarter butt (11), and quarter butt (11) and through-hole (10) looks adaptation.
5. The water conservancy construction waterproof structure of claim 1, characterized in that, casing (1) top has seted up fixed orifices (13), and except that one side fixed mounting that pivot (3) was kept away from at water board (4) top has screw (14), the top of screw (14) passes fixed orifices (13) and extends to casing (1), and screw (14) top movable mounting has nut (15) that are located fixed orifices (13) department, and screw (14) and nut (15) looks adaptation.
CN202021619103.3U 2020-08-06 2020-08-06 Water conservancy construction waterproof construction Active CN213625480U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021619103.3U CN213625480U (en) 2020-08-06 2020-08-06 Water conservancy construction waterproof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021619103.3U CN213625480U (en) 2020-08-06 2020-08-06 Water conservancy construction waterproof construction

Publications (1)

Publication Number Publication Date
CN213625480U true CN213625480U (en) 2021-07-06

Family

ID=76643712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021619103.3U Active CN213625480U (en) 2020-08-06 2020-08-06 Water conservancy construction waterproof construction

Country Status (1)

Country Link
CN (1) CN213625480U (en)

Similar Documents

Publication Publication Date Title
CN207788413U (en) A kind of mechanical processing iron filings dust-removing recovery device
CN213625480U (en) Water conservancy construction waterproof construction
CN207905096U (en) Sewage draw-out device in a kind of sewage
CN208844644U (en) A kind of riverway sludge cleaning plant
CN208950010U (en) A kind of rain dirt drainpipe leakage-resistant device
CN110844974A (en) Water treatment tank and automatic scale scraping electrochemical water treatment system
CN108467182A (en) A kind of device for dehydrating sladge waste of the sewage disposal system of environmental protection
CN201454913U (en) unpowered flusher
CN211357995U (en) High-efficiency energy-saving water filtering device
CN210389702U (en) Assembled building wallboard drilling equipment
CN211971487U (en) Dismantle convenient hydraulic turbine nozzle lifting support
CN213965353U (en) Energy-concerving and environment-protective sewage treatment device
CN215742065U (en) Hydraulic engineering pump station structure
CN216948151U (en) Hydraulic engineering is with multi-functional trash equipment that blocks
CN214635087U (en) Dust collector of fertilizer production
JP3246531U (en) Multiple parallel closed water cooling units
CN216336962U (en) Environment-friendly sludge treatment sedimentation tank
CN216055799U (en) Novel dust removal variable frequency control cabinet
CN217794751U (en) High-efficient dust collector is used in feed production
CN221030588U (en) Water conservancy construction drainage equipment
CN214848224U (en) Zero-crossing switching capacitor bank device
CN220433061U (en) Filtering device for electroplating solution
CN213475454U (en) Buried sewage complete treatment equipment with remote monitoring function
CN220978504U (en) High-stability connecting device for curtain wall engineering
CN218188752U (en) A dust removal filtration equipment for VOC gas absorption spray column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant