CN213573051U - Concrete placement structure convenient to it is spacing - Google Patents
Concrete placement structure convenient to it is spacing Download PDFInfo
- Publication number
- CN213573051U CN213573051U CN202021846150.1U CN202021846150U CN213573051U CN 213573051 U CN213573051 U CN 213573051U CN 202021846150 U CN202021846150 U CN 202021846150U CN 213573051 U CN213573051 U CN 213573051U
- Authority
- CN
- China
- Prior art keywords
- concrete
- concrete structure
- connecting pipe
- reinforcing bar
- structure convenient
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a concrete placement structure convenient to it is spacing, there is horizontal reinforcing bar including concrete structure and last surface mounting, vertical reinforcing bar is installed to the vertical position of horizontal reinforcing bar, the base has been placed at the top of the reinforcing bar at concrete structure top, the pivot unit is installed at the top of base, the axle is installed in the rotation of pivot unit's top, the top welding installation antenna boom of axle, one side fixed mounting that concrete structure was kept away from to the antenna boom has the pump, the bottom installation of pump is fixed with the extraction pipeline, the mutual conduction connection installation between extraction pipeline and the external connecting pipe, the other end winding of connecting pipe is installed on orbital surface, the other end of connecting pipe is pegged graft and is installed on the surface of unloading pipe device. The utility model discloses a portable filling device in location fills the section bar position of concrete structure, and it is effectual to fix a position, is difficult for the situation that the everywhere splash appears.
Description
Technical Field
The utility model relates to a concrete placement technical field specifically is a concrete placement structure convenient to it is spacing.
Background
Concrete is a general name of composite materials which are prepared by mixing gel materials, aggregates and water according to a proper proportion and then are hardened for a certain time, and is the artificial civil engineering and construction material with the largest usage amount in the world.
The concrete has high hardness, wide raw material sources and low cost, and is widely used for buildings, roads, military engineering, nuclear power plants and other structures.
In the blowing process of concrete, one-step operation is needed to flush the concrete in the concrete tank into the profile structure, but the existing filling devices are hoses which are not easy to control the swinging of the hoses in the discharging process so as to cause the uneven discharging position of the device; therefore, a position limiting device capable of positioning a pipeline is needed.
For this reason, we propose a concrete pouring structure convenient for limiting to solve the above problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a concrete placement structure convenient to it is spacing to solve the problem of proposing among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a concrete placement structure convenient to it is spacing, including concrete structure and surface mounting have horizontal reinforcing bar, vertical reinforcing bar is installed to the vertical position of horizontal reinforcing bar, the base has been placed at the top of the reinforcing bar at concrete structure top, the pivot unit is installed at the top of base, the top of pivot unit is rotated and is installed the axle, the top welding installation antenna boom of axle, one side fixed mounting that concrete structure was kept away from to antenna boom has the pump, the bottom installation of pump is fixed with the extraction pipeline, the mutual conduction connection installation between extraction pipeline and the external connecting pipe, the other end winding of connecting pipe is installed on orbital surface, the other end of connecting pipe is pegged graft and is installed on the surface of unloading pipe.
Preferably, unloading pipe device has seted up the feed inlet including being located outside outer tube, the surface of outer tube, and the shank erection weld of outer tube has the handle, and fixed mounting has the installation piece in the middle of the top of outer tube, and the round pin axle is installed in the inside grafting of installation piece, and the end roll of round pin axle installs the ball, and the roll cooperation is connected between ball and the orbital inner chamber.
Preferably, the hole site between the transverse reinforcement and the longitudinal reinforcement is one half square meter in size.
Preferably, the top of the rotating shaft device is provided with a shaft in an inserting mode, the part, matched with the rotating shaft device, of the shaft is provided with an inner ball in a rolling mode, the bottom of the rotating shaft device is fixedly provided with a rotor, and the rotor and the rotating shaft device are fixedly welded and installed through a bolt.
Preferably, a dust removing plate is mounted to the outside of the housing.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model adopts the positioning movable filling device to fill the section bar part of the concrete structure, has good positioning effect and is not easy to splash everywhere;
the utility model discloses a mode of gallows has carried out the head spacing to the blowing device to cooperation handle device, not only greatly reduced artificial operation dynamics, still saved the time of transposition.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of a blanking pipe;
fig. 3 is a schematic structural diagram of the spindle device.
In the figure: 1 concrete structure, 2 transverse steel bars, 3 longitudinal steel bars, 4 bases, 5 rotating shaft devices, 6 shafts, 7 antenna supports, 8 pumps, 9 extraction pipelines, 10 connecting pipes, 11 tracks, 12 blanking pipe devices, 121 outer pipes, 122 feed inlets, 123 handles, 124 mounting blocks, 125 pin shafts, 126 balls, 51 outer covers, 52 inner balls, 53 rotors and 54 bolts.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a concrete placement structure convenient to it is spacing, includes concrete structure 1 that will be used for filling the concrete, the last surface mounting of concrete structure 1 has horizontal reinforcing bar 2, and vertical reinforcing bar 3 is installed to the vertical position of horizontal reinforcing bar 2, and horizontal, vertical reinforcing bar have constituted the filling structure of concrete jointly.
A base 4 used for limiting the top antenna bracket is placed at the top of a steel bar at the top of the concrete structure 1, a rotating shaft device 5 used for rotating a shaft device is installed at the top of the base 4, and a shaft 6 is rotatably installed at the top of the rotating shaft device 5; an antenna bracket 7 for overlapping pipelines is welded and installed at the top of the shaft 6, a pump 8 for pumping concrete at the bottom is fixedly installed at one side of the antenna bracket 7, which is far away from the concrete structure 1, and a pumping pipeline 9 is fixedly installed at the bottom of the pump 8; the extraction pipeline 9 and the external connecting pipe 10 of outwards exporting the concrete are conducted each other and are connected the installation, and the other end winding of connecting pipe 10 is installed on the surface of the track 11 that can the slip removal front end export, and the other end of connecting pipe 10 is pegged graft and is installed on the surface of unloading pipe device 12, and unloading pipe device 12 is used for the accurate unloading of counterpointing.
The blanking pipe device 12 comprises an outer pipe 121 located outside, a feeding hole 122 is formed in the surface of the outer pipe 121, and a handheld control device is installed and welded on the leg of the outer pipe 122: a handle 123; in order to make the blanking pipe device 12 slide in the top rail 11, a mounting block 124 is fixedly mounted in the middle of the top of the outer pipe 122, and a shaft device is inserted into the mounting block 124: the pin shaft 125, the tail end of the pin shaft 125 is provided with a rolling device in a rolling way: the ball 126 is connected with the inner cavity of the track 11 in a rolling fit mode.
The hole site size between the transverse reinforcement 2 and the longitudinal reinforcement 3 is one half square meter, which is the optimal casting size.
In order to realize the circumferential rotation of the top track 11, a shaft 6 is inserted and installed at the top of the rotating shaft device 5, and a matching part is installed on the mutually matched part of the shaft 6 and the rotating shaft device 5 in a rolling way: the inner ball 52 and the bottom of the rotating shaft device 5 are fixedly provided with a power device: the rotor 53, the rotor 53 and the rotating shaft device 5 are fixedly welded and installed through a bolt 54.
The outer part of the housing 51 is provided with a dust removal plate to prevent contamination of the inner rotor.
The working principle is as follows:
this device is to the current simple not enough that adopts the hose to pour of device of pouring, has adopted following device:
firstly, a base 4 is adopted as a stabilizer of the device, and a rotor 53 is arranged in the base to control the track 11 at the top to rotate so as to realize the positioning in the circumferential direction; secondly, a mounting block 124-pin shaft 125-ball 126 device is arranged at the top of the blanking pipe device 12 and used for realizing the front and back movement of the blanking pipe 12 device in the radial direction of the track 11, so that the positioning effect of any radial position is realized;
in order to enhance the controllability of the device, a handle 123 device is arranged on the leg of the blanking pipe 12 device and used for controlling the blanking position of the water pipe and further realizing positioning;
in order to save the operation space, a pump 8 device is arranged on the left side of the track 11, concrete materials on the ground are pumped through the pump 8, a large amount of concrete does not need to be lifted to the top of a concrete structure, and manpower and material resources are greatly saved.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a concrete placement structure convenient to it is spacing, includes concrete structure (1), its characterized in that: the upper surface of the concrete structure (1) is provided with a transverse steel bar (2), the longitudinal position of the transverse steel bar (2) is provided with a longitudinal steel bar (3), a base (4) is placed on the top of the steel bar on the top of the concrete structure (1), a rotating shaft device (5) is arranged at the top of the base (4), a shaft (6) is rotatably arranged at the top of the rotating shaft device (5), an antenna bracket (7) is welded and installed at the top of the shaft (6), a pump (8) is fixedly installed at one side of the antenna bracket (7) far away from the concrete structure (1), an extraction pipeline (9) is fixedly arranged at the bottom of the pump (8), the extraction pipeline (9) and an external connecting pipe (10) are communicated and connected with each other, the other end of the connecting pipe (10) is wound and installed on the surface of the track (11), the other end of the connecting pipe (10) is inserted and installed on the surface of the feeding pipe device (12).
2. The concrete pouring structure convenient for limiting as recited in claim 1, wherein: unloading pipe device (12) is including being located outside outer tube (121), feed inlet (122) have been seted up on the surface of outer tube (121), the shank erection weld of outer tube (121) has handle (123), fixed mounting has installation piece (124) in the middle of the top of outer tube (121), round pin axle (125) are installed to the inside grafting of installation piece (124), the end roll-mounting of round pin axle (125) has ball (126), ball (126) with roll fit connects between the inner chamber of track (11).
3. The concrete pouring structure convenient for limiting as recited in claim 1, wherein: the hole site size between horizontal reinforcing bar (2) and longitudinal reinforcement (3) is one half square meter.
4. The concrete pouring structure convenient for limiting as recited in claim 1, wherein: the top of pivot device (5) is pegged graft and is installed axle (6), axle (6) with interior ball (52) are installed in the position roll that pivot device (5) mutually supported, the bottom fixed mounting of pivot device (5) has rotor (53), rotor (53) with realize fixed welding through bolt (54) and install between pivot device (5).
5. The concrete pouring structure convenient for limiting as recited in claim 1, wherein: a dust removing plate is mounted on the outer part of the outer cover (51).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021846150.1U CN213573051U (en) | 2020-08-30 | 2020-08-30 | Concrete placement structure convenient to it is spacing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021846150.1U CN213573051U (en) | 2020-08-30 | 2020-08-30 | Concrete placement structure convenient to it is spacing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213573051U true CN213573051U (en) | 2021-06-29 |
Family
ID=76556878
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021846150.1U Active CN213573051U (en) | 2020-08-30 | 2020-08-30 | Concrete placement structure convenient to it is spacing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213573051U (en) |
-
2020
- 2020-08-30 CN CN202021846150.1U patent/CN213573051U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN214887216U (en) | Geotechnical engineering slip casting device | |
CN213573051U (en) | Concrete placement structure convenient to it is spacing | |
CN114311310A (en) | Municipal construction is with consolidating native agitator tank | |
CN212772301U (en) | Slip casting device is used in construction of municipal administration road bridge | |
CN112982387A (en) | High-pressure grouting device for cement mixing pile construction | |
CN113059673A (en) | Concrete grouting device for civil engineering construction | |
CN206360703U (en) | A kind of subway shield tunnel construction feeding device | |
CN202265819U (en) | Soil curing device | |
CN209989817U (en) | Grouting device for foundation reinforcement | |
CN217514170U (en) | Steam curing device for high-strength prestressed concrete pipe pile | |
CN113266013B (en) | Pile end pressure grouting construction method for prestressed concrete pipe pile | |
CN211006267U (en) | Concrete pouring and leveling device for highway construction | |
CN110528956B (en) | Intelligent electric pole base, installation device and construction method | |
CN218265933U (en) | High-efficient slip casting device of tunnel vault | |
CN213743434U (en) | Combined type irrigation platform device | |
CN214089811U (en) | Slip casting integrated equipment of usefulness is handled to ground | |
CN212956494U (en) | Earth backfill tamping device | |
CN213107472U (en) | Concrete mixing equipment for civil engineering building | |
CN215520098U (en) | Full-automatic cement mortar grouting machine | |
CN216987243U (en) | Ground source heat pump ground pipe laying backfilling equipment | |
CN220868229U (en) | Water conservancy construction grout ware | |
CN221760661U (en) | Positioning device for embedded bolts of microporous cast-in-place pile | |
CN221879408U (en) | Colliery well protection slip casting device | |
CN215406069U (en) | Underground continuous wall joint grouting device | |
CN110656666B (en) | Small high-pressure jet grouting cement pile machine for test and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |