CN213571417U - Traffic engineering highway construction is with ramming equipment - Google Patents

Traffic engineering highway construction is with ramming equipment Download PDF

Info

Publication number
CN213571417U
CN213571417U CN202022383662.5U CN202022383662U CN213571417U CN 213571417 U CN213571417 U CN 213571417U CN 202022383662 U CN202022383662 U CN 202022383662U CN 213571417 U CN213571417 U CN 213571417U
Authority
CN
China
Prior art keywords
water tank
traffic engineering
ramming
base
movably connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022383662.5U
Other languages
Chinese (zh)
Inventor
宋海滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022383662.5U priority Critical patent/CN213571417U/en
Application granted granted Critical
Publication of CN213571417U publication Critical patent/CN213571417U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a traffic engineering highway construction is with ramming equipment, including base and driving motor, the bottom fixedly connected with ramming plate of base, the top fixedly connected with water tank of base, the surperficial swing joint of water tank has the gyro wheel support frame, one side swing joint of gyro wheel support frame has the gyro wheel, the surperficial swing joint of water tank has the shower nozzle support frame, the internally mounted of shower nozzle support frame has the shower nozzle, the one end threaded connection of shower nozzle has the water pipe, there is protecting sheathing one side of water tank through hinge swing joint, protecting sheathing's internally mounted has driving motor. This traffic engineering is ramming equipment for highway construction, through the setting of gyro wheel and shower nozzle, the shower nozzle can spray water on the road surface that needs the ramming, uses the gyro wheel to carry out level and smooth the pressing treatment in advance on the road surface that will drench, prevents that the local convex-concave unevenness in road surface from influencing the efficiency of construction of ramming the board, has improved the work efficiency of ramming.

Description

Traffic engineering highway construction is with ramming equipment
Technical Field
The utility model relates to a highway ramming device technical field specifically is a traffic engineering is ramming equipment for highway construction.
Background
Tamping is a means of compacting soil layers at a certain depth on the earth surface by means of tamping, vibrating or rolling, a flat plate tamper is a tamper for tamping the road surface by means of vibrating a tamping plate, and the compacted layer is permanently deformed and compacted mainly under the action of power inside machinery, so that the flat plate tamper is suitable for various compaction operations.
When highway construction, need dig the foundation ditch on the ground now, then carry out the compaction to ground through the tamper board, because subaerial have a large amount of earth, current tamping equipment is when just beginning to tamp ground, ground is in the state of virtual floating and unevenness, cause the reduction of efficiency of construction easily, and can produce the raise dust phenomenon, the staff works under the environment of raise dust, can influence staff's work, and the drive arrangement of current tamping equipment is mostly in the exposed state, not only collide with and damage easily, the potential safety hazard is also bigger.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a traffic engineering highway construction is with ramming equipment has solved the problem that proposes in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a traffic engineering highway construction is with ramming equipment, includes base and driving motor, the bottom fixedly connected with ramming plate of base, the top fixedly connected with water tank of base, the surperficial swing joint of water tank has the gyro wheel support frame, one side swing joint of gyro wheel support frame has the gyro wheel, the surperficial swing joint of water tank has the shower nozzle support frame, the internally mounted of shower nozzle support frame has the shower nozzle, the one end threaded connection of shower nozzle has the water pipe, there is protecting sheathing one side of water tank through hinge swing joint, protecting sheathing's internally mounted has driving motor, the vent has all been seted up to protecting sheathing's both sides, the fixed orifices has been seted up to one side of protecting sheathing, the inside swing joint of fixed orifices.
Optionally, one end of the fixing member penetrates through one end of the protective casing and is movably connected to the base.
Optionally, adjusting holes are formed in the two sides of the water tank, and adjusting pieces are connected to the inner threads of the adjusting holes in a threaded mode.
Optionally, a water supply pump is arranged inside the water tank, and a water tank cover is connected to the top of the water tank through threads.
Optionally, an observation port is formed in the surface of the water tank, and scale marks are arranged on one side of the observation port.
Optionally, both sides of the base are movably connected with a hand push rod through a rotating shaft, and the outer surface of the hand push rod is sleeved with a foam cotton handrail.
(III) advantageous effects
The utility model provides a traffic engineering highway construction is with ramming equipment possesses following beneficial effect:
1. this traffic engineering is ramming equipment for highway construction, setting through gyro wheel and shower nozzle, the shower nozzle can spray water on the road surface that needs the ramming, the road surface that uses the gyro wheel to drench is leveled in advance and is pressed down the processing, guarantee its job schedule, prevent that the local convex-concave uneven efficiency of construction who influences the ramming board in road surface, be favorable to shortening the engineering time, the shower nozzle can be with the dust that produces in the course of the work simultaneously, in time moist processing, prevent to raise a large amount of dust and influence staff's work, the work efficiency of ramming has been improved.
2. This traffic engineering is ramming equipment for highway construction, through the setting of protecting sheathing, fixed orifices and mounting, at the work of ramming, equipment is in the shock condition always, and protecting sheathing can protect the internal plant and be difficult for colliding with, damage and losing, and it is difficult for touching the injury during the device when also making the staff use, and fixed orifices and mounting make the swing joint of protecting sheathing and base, can just maintain the internal plant with installation and dismantlement, more make things convenient for people to use.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the protective housing of the present invention;
fig. 3 is a schematic view of the structure of the water tank of the present invention.
In the figure: 1. a base; 2. compacting the plate; 3. a water tank; 4. a roller support frame; 5. a roller; 6. a spray head support frame; 7. a spray head; 8. a water pipe; 9. a protective housing; 10. a drive motor; 11. a vent; 12. a fixing hole; 13. a fixing member; 14. an adjustment hole; 15. an adjustment member; 16. a water supply pump; 17. a water tank cover; 18. a viewing port; 19. a handspike; 20. foam cotton handrail.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution: the tamping equipment for the highway construction of the traffic engineering comprises a base 1 and a driving motor 10, wherein the bottom of the base 1 is fixedly connected with a tamping plate 2, the top of the base 1 is fixedly connected with a water tank 3, adjusting holes 14 are formed in two sides of the water tank 3, an adjusting piece 15 is in threaded connection with the inner part of each adjusting hole 14, and the heights of a roller 5 and a spray head 7 can be conveniently adjusted according to the actual construction current situation through the adjusting holes 14 and the adjusting pieces 15, so that the tamping equipment is flexible and changeable and the practicability of the device is improved;
the surface of the water tank 3 is movably connected with a roller support frame 4, one side of the roller support frame 4 is movably connected with a roller 5, the surface of the water tank 3 is movably connected with a spray head support frame 6, a spray head 7 is installed inside the spray head support frame 6, one end of the spray head 7 is connected with a water pipe 8 in a threaded manner, a water supply pump 16 is arranged inside the water tank 3, the top of the water tank 3 is connected with a water tank cover 17 in a threaded manner, the surface of the water tank 3 is provided with an observation port 18, one side of the observation port 18 is provided with scale marks, and through the arrangement of the observation port 18, a worker can conveniently see the residual condition of water;
there is protecting sheathing 9 one side of water tank 3 through hinge swing joint, protecting sheathing 9's internally mounted has driving motor 10, vent 11 has all been seted up to protecting sheathing 9's both sides, setting through vent 11, can carry out the heat dissipation treatment for the internal plant, prevent that the high temperature from influencing equipment and using, fixed orifices 12 has been seted up to one side of protecting sheathing 9, the inside swing joint of fixed orifices 12 has mounting 13, the one end of mounting 13 runs through protecting sheathing 9's one end, and swing joint is on base 1, base 1's both sides all have handspike 19 through pivot swing joint, the foam cotton handrail 20 has been cup jointed to handspike 19's surface, setting through handspike 19, but two-way push-and-pull the device, make the device more diversified.
The utility model discloses in, the device's working procedure as follows:
1. firstly, the water tank 3 is filled with water source through the arrangement of the water tank cover 17, and the device is moved to the road surface to be tamped;
2. secondly, through the arrangement of the water supply pump 16 and the water pipe 8, the water supply pump 16 is started to work, water is conveyed to the spray head 7 through the water pipe 8, the spray head 7 sprays the water on a road surface to be tamped, and meanwhile, the spray head 7 can timely wet dust generated in the working process, so that the phenomenon that a large amount of dust is raised to influence the work of workers is prevented;
3. and, through the setting of gyro wheel 5, remove the device, gyro wheel 5 levels the road surface of drenching in advance and presses the processing, and driving motor 10 drives the motion of ramming plate 2 simultaneously and tamps ground, prevents that the road surface from floating and local convex-concave unevenness from influencing the efficiency of construction of ramming plate 2 to ramming efficiency has been improved.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a traffic engineering is ramming equipment for highway construction, includes base (1) and driving motor (10), its characterized in that: the bottom of the base (1) is fixedly connected with a tamping plate (2), the top of the base (1) is fixedly connected with a water tank (3), the surface of the water tank (3) is movably connected with a roller supporting frame (4), one side of the roller supporting frame (4) is movably connected with a roller (5), the surface of the water tank (3) is movably connected with a spray head support frame (6), a spray head (7) is arranged in the spray head support frame (6), one end of the spray head (7) is in threaded connection with a water pipe (8), one side of the water tank (3) is movably connected with a protective shell (9) through a hinge, a driving motor (10) is arranged in the protective shell (9), ventilation openings (11) are formed in both sides of the protective shell (9), one side of the protective shell (9) is provided with a fixing hole (12), and a fixing piece (13) is movably connected inside the fixing hole (12).
2. The compaction equipment for traffic engineering road construction according to claim 1, wherein: one end of the fixing piece (13) penetrates through one end of the protective shell (9) and is movably connected to the base (1).
3. The compaction equipment for traffic engineering road construction according to claim 1, wherein: adjusting holes (14) are formed in the two sides of the water tank (3), and adjusting pieces (15) are connected to the inner threads of the adjusting holes (14).
4. The compaction equipment for traffic engineering road construction according to claim 1, wherein: a water supply pump (16) is arranged inside the water tank (3), and a water tank cover (17) is connected to the top of the water tank (3) in a threaded mode.
5. The compaction equipment for traffic engineering road construction according to claim 1, wherein: an observation port (18) is formed in the surface of the water tank (3), and scale marks are arranged on one side of the observation port (18).
6. The compaction equipment for traffic engineering road construction according to claim 1, wherein: both sides of the base (1) are movably connected with hand push rods (19) through rotating shafts, and foam cotton handrails (20) are sleeved on the outer surfaces of the hand push rods (19).
CN202022383662.5U 2020-10-23 2020-10-23 Traffic engineering highway construction is with ramming equipment Active CN213571417U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022383662.5U CN213571417U (en) 2020-10-23 2020-10-23 Traffic engineering highway construction is with ramming equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022383662.5U CN213571417U (en) 2020-10-23 2020-10-23 Traffic engineering highway construction is with ramming equipment

Publications (1)

Publication Number Publication Date
CN213571417U true CN213571417U (en) 2021-06-29

Family

ID=76528257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022383662.5U Active CN213571417U (en) 2020-10-23 2020-10-23 Traffic engineering highway construction is with ramming equipment

Country Status (1)

Country Link
CN (1) CN213571417U (en)

Similar Documents

Publication Publication Date Title
CN213571417U (en) Traffic engineering highway construction is with ramming equipment
CN213014234U (en) Foundation tamping equipment for building
CN210917520U (en) Earthwork levels device
CN211080195U (en) Tamping tool for civil engineering
CN204919282U (en) Light adjustable die mould rolls way device from advancing
CN217537904U (en) Waterproof blanket laying device of bentonite
CN213233399U (en) Foundation leveling equipment for constructional engineering
CN211498812U (en) Road surface rammer compactor for building engineering
CN105178145B (en) A kind of light adjustable die mould voluntarily enters the device that rolls over a road
CN211171910U (en) Synchronous dust removal mechanism of ramming device
CN218990304U (en) Paving and tamping equipment for earth backfilling
CN207775863U (en) A kind of vibratory rammer, vibratory tamper
CN212582351U (en) Floating device of building construction
CN220678688U (en) Cleaning device for vibration roller for water conservancy construction
CN215669431U (en) Ramming equipment for building construction
CN219157626U (en) Mechanical plate compactor for constructional engineering
CN213682070U (en) Tamping equipment for road and bridge construction
CN214940021U (en) Foundation leveling equipment for constructional engineering
CN209323321U (en) A kind of roller surface automatic cleaning type road roller
CN219808661U (en) Leveling equipment for terrace
CN218990239U (en) Diaphragm wall construction platform
CN211689832U (en) Crushing device of multi-hammer crusher
CN213417528U (en) Ground dismantling device
CN217601142U (en) Ramming machine is used in construction of green of environmental protection
CN218779289U (en) Road surface tamping device for road construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant