CN213539774U - Ancient building roofing suspension wire device - Google Patents

Ancient building roofing suspension wire device Download PDF

Info

Publication number
CN213539774U
CN213539774U CN202022279757.2U CN202022279757U CN213539774U CN 213539774 U CN213539774 U CN 213539774U CN 202022279757 U CN202022279757 U CN 202022279757U CN 213539774 U CN213539774 U CN 213539774U
Authority
CN
China
Prior art keywords
short rod
quarter butt
wire device
suspension wire
ancient building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022279757.2U
Other languages
Chinese (zh)
Inventor
马腾飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Chaoxin Construction Engineering Co ltd
Original Assignee
Guangdong Chaoxin Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Chaoxin Construction Engineering Co ltd filed Critical Guangdong Chaoxin Construction Engineering Co ltd
Priority to CN202022279757.2U priority Critical patent/CN213539774U/en
Application granted granted Critical
Publication of CN213539774U publication Critical patent/CN213539774U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of the technique of auxiliary device for the ancient building construction and specifically relates to a relate to an ancient building roofing suspension wire device, it includes the guide arm, a plurality of jib and flexible rope, the guide arm includes the quarter butt of a plurality of sections head and the tail concatenation, the tip that arbitrary two sections adjacent quarter butts are close to each other is connected through a plurality of fixed subassemblies, the jib can be dismantled and connect in the quarter butt, all jibs are worn to establish in proper order along the length direction of quarter butt to flexible rope, flexible rope both ends respectively with be located the relative two sections quarter butt fixed connection in the outside of guide arm. This application has the effect of improving the problem that the messenger wire device is not convenient for transport.

Description

Ancient building roofing suspension wire device
Technical Field
The application relates to the technical field of auxiliary devices for historic building construction, in particular to a line hanging device for a historic building roof.
Background
In the ancient building repairing construction, the repairing of the roof is an important link, wherein tiles are hung on the roof, in order to ensure the regular arrangement of the tiles, a suspension wire needs to be firstly carried out before the tiles are hung, and workers lay the tiles along the suspension wire.
Chinese patent publication No. CN210049634U, open 2020, 02, 11 days, the utility model discloses an ancient building roofing suspension wire device, including the guide arm, a plurality of jibs of arranging along guide arm length direction and the flexible rope that passes each jib in proper order, set up the slide that extends along length direction on the guide arm, it has a plurality of sliders to slide on the slide, the slider includes the slider body and the bottom through threaded connection, form between bottom and the slider body and placed spheroidal holding chamber, the jib upwards passes behind the bottom with the spheroid rigid coupling, it has the bolt that passes the slide to go back the rigid coupling on the slider body, be equipped with the fastening nut who is located the guide arm top on the bolt.
In view of the above-mentioned related art, the inventor believes that the roof in an ancient building is relatively wide, and thus the guide bar used is long, which makes the suspension wire device inconvenient to transport.
SUMMERY OF THE UTILITY MODEL
In order to improve the problem that the messenger wire device is not convenient for transport, this application provides an ancient building roofing messenger wire device.
The application provides a pair of ancient building roofing suspension wire device adopts following technical scheme:
the utility model provides an ancient building roofing suspension wire device, includes guide arm, a plurality of jib and flexible rope, the guide arm includes the quarter butt that a plurality of sections head and the tail spliced in proper order, arbitrary adjacent two the tip that the quarter butt is close to each other is connected through fixed subassembly, the jib can dismantle connect in the quarter butt, flexible rope is followed the length direction of quarter butt wears to establish in proper order all the jib, flexible rope both ends respectively with be located the relative two sections in the outside of guide arm quarter butt fixed connection.
Through adopting above-mentioned technical scheme, the guide arm can be dismantled to a plurality of sections quarter butt, so when not using the guide arm, can accomodate the guide arm through dismantling the guide arm for a plurality of sections quarter butt, the guide arm of being convenient for is accomodate and is transported.
Optionally, two adjacent short rods are respectively a first short rod and a second short rod, a positioning groove is formed in one end, close to the second short rod, of the first short rod, a positioning block is connected to one end, close to the first short rod, of the second short rod, and the positioning block is in inserting fit with the positioning groove; the fixing component comprises a bolt, the bolt penetrates through the first short rod and the positioning block, a nut is connected with the bolt in a threaded mode, and the nut is abutted to the first short rod.
Through adopting above-mentioned technical scheme, bolt and nut simple structure, it is all very convenient to install, dismantle, and stability is good, is favorable to improving efficiency of construction and construction stability.
Optionally, a calibration assembly for calibrating the bolt installation position is connected between the first short rod and the second short rod.
Through adopting above-mentioned technical scheme, through setting up calibration assembly, realize calibration in advance to the position of first quarter butt, second quarter butt, the installation of the bolt of being convenient for to construction speed has been improved.
Optionally, the calibration subassembly includes locking spring and tapered end, the locating piece is seted up and is used for settling locking spring's mounting groove, locking spring one end connect in the tank bottom of mounting groove, the other end with tapered end fixed connection, the locating hole has been seted up to first quarter butt, the tapered end is kept away from locking spring's one end with the cooperation of locating hole joint.
Through adopting above-mentioned technical scheme, the simple structure practicality of locking spring, tapered end, first quarter butt, second quarter butt are also simple through dismantling after locking spring, tapered end calibration, are favorable to improving the efficiency of construction.
Optionally, one end of the lock head, which is far away from the locking spring, is arranged in a round angle manner.
Through adopting above-mentioned technical scheme, the radian that the tapered end that the fillet set up had can let the tapered end lock to the constant head tank in when receiving horizontal shear stress to remove the locking to first quarter butt, made things convenient for the dismantlement between first quarter butt and the second quarter butt.
Optionally, the calibration assembly is a pair of magnets attracted to each other, and the first short rod and the second short rod are connected through the magnets.
Through adopting above-mentioned technical scheme, rely on the appeal between the magnet to calibrate the position of first quarter butt, second quarter butt, simple structure dismantles simply, is favorable to improving the efficiency of construction.
Optionally, the magnets are ring-shaped, one of the magnets is fixedly connected to the second short rod, the other magnet is fixedly connected to the first short rod, and the positioning block penetrates through the middle of the magnets and is inserted into the positioning groove.
Through adopting above-mentioned technical scheme, earlier carry out coarse calibration through locating piece, constant head tank to the position of first quarter butt and second quarter butt, then first quarter butt and second quarter butt pass through magnet and inhale mutually for the position calibration is more accurate, thereby improves the efficiency of construction.
Optionally, the suspender is fixedly connected with a sliding assembly, and the sliding assembly is sleeved and slidably connected with the guide rod.
Through adopting above-mentioned technical scheme, the jib also can be dismantled on the guide arm, is favorable to accomodating and transporting of suspension wire device.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the guide rod can be disassembled into a plurality of short rods, so that when the guide rod needs to be stored or transported, the guide rod can be disassembled into the plurality of short rods which are convenient to store and transport;
2. the construction speed is improved by simplifying the connecting structure between the short rods;
3. the multi-section short rods are fixed through the bolts, and the construction stability is improved.
Drawings
Fig. 1 is a schematic structural diagram of a historic building roof suspension wire device in embodiment 1 of the application.
FIG. 2 is a cross-sectional view of two adjacent short rods in example 1 of the present application.
Fig. 3 is a schematic view of a connection structure of two adjacent short rods in embodiment 1 of the present application.
Fig. 4 is a schematic view of a connection structure of a boom and a short bar in embodiment 1 of the present application.
Fig. 5 is a schematic view of a connection structure of two adjacent short rods in embodiment 2 of the present application.
Description of reference numerals: 1. a guide bar; 11. a first short bar; 111. positioning a groove; 112. positioning holes; 113. a first fixing hole; 12. a second short bar; 121. positioning blocks; 122. mounting grooves; 123. a second fixing hole; 2. a boom; 21. a sliding assembly; 211. a sliding sleeve; 212. fixing the screw rod; 213. a fixed block; 3. a flexible cord; 4. calibrating the component; 41. a locking spring; 42. a lock head; 43. a first magnet; 44. a second magnet; 5. a fixing assembly; 51. a bolt; 52. and a nut.
Detailed Description
The present application is described in further detail below with reference to figures 1-5.
The embodiment of the application discloses ancient building roofing suspension wire device.
Example 1
Referring to fig. 1, the suspension wire device includes a guide rod 1, a plurality of suspenders 2 and a flexible rope 3, in this embodiment, the suspenders 2 are provided with four, the suspenders 2 can be detached and slidably connected to the guide rod 1, the flexible rope 3 sequentially penetrates through all the suspenders 2 along the length direction of the guide rod 1, and two ends of the flexible rope 3 are fixedly connected to two ends of the guide rod 1.
Referring to fig. 1, the guide rod 1 includes several short rods spliced end to end, in this embodiment, the short rods are provided with four sections, the suspension rod 2 is slidably connected to any one short rod, any two adjacent short rods are a first short rod 11 and a second short rod 12, and the first short rod 11 and the second short rod 12 are connected to the calibration assembly 4 and the fixing assembly 5. After the staff alignment assembly 4 aligns the positions of the first short rod 11 and the second short rod 12, the first short rod 11 and the second short rod 12 are fixed by the fixing assembly 5.
Referring to fig. 2 and 3, a positioning groove 111 is formed in one end of the first short rod 11 close to the second short rod 12, a positioning block 121 is connected to one end of the second short rod 12 close to the first short rod 11, a positioning hole 112 is formed in a side wall of the first short rod 11, and the positioning hole 112 is communicated with the positioning groove 111. Calibration assembly 4 includes locking spring 41 and tapered end 42, and mounting groove 122 has been seted up to locating piece 121, and locking spring 41 is located mounting groove 122, and locking spring 41 one end and the tank bottom fixed connection of mounting groove 122, the other end and tapered end 42 fixed connection, the one end that locking spring 41 was kept away from to tapered end 42 are the fillet setting.
Referring to fig. 2 and 3, when the first short rod 11 is separated from the second short rod 12, one end of the locking head 42 away from the locking spring 41 extends from the mounting groove 122; when the first short rod 11 is connected with the second short rod 12, the positioning block 121 is in insertion fit with the positioning groove 111, the positioning block 121 abuts against the inner side wall of the first short rod 11, and one end of the lock head 42, which is far away from the locking spring 41, is in fit clamping with the positioning hole 112, so that the positions of the first short rod 11 and the second short rod 12 are calibrated.
Referring to fig. 2 and 3, the first short rod 11 is provided with a first fixing hole 113 along the opening direction of the vertical positioning slot 111, the first fixing hole 113 is communicated with the positioning slot 111, the positioning block 121 is provided with a second fixing hole 123 along the opening direction of the vertical mounting slot 122, and after the positions of the first short rod 11 and the second short rod 12 are aligned, the first fixing hole 113 is aligned with the second fixing hole 123. The fixing assembly 5 includes a bolt 51 and a nut 52, when the first fixing hole 113 is aligned with the second fixing hole 123, the bolt 51 is inserted into the first fixing hole 113 and the second fixing hole 123, and the nut 52 is screwed to one end of the bolt 51 penetrating through the first fixing hole 113 and tightly abuts against the outer side of the first short rod 11, so as to fix the first short rod 11 and the second short rod 12.
Referring to fig. 4, the suspension rod 2 is slidably connected to the short rod through the sliding assembly 21, the sliding assembly 21 includes a sliding sleeve 211 and a fixed screw 212, the sliding sleeve 211 is fixedly connected to the suspension rod 2, the sliding sleeve 211 can be sleeved on the guide rod 1 and can slide, the fixed screw 212 is threadedly connected to the sliding sleeve 211, and one end of the fixed screw 212 located in the sliding sleeve 211 is connected to a fixed block 213. The sliding sleeve 211 adjusts the position of the suspension rod 2 on the guide rod 1, and then the fixed screw 212 is rotated to make the fixed block 213 tightly abut against the guide rod 1, so that the sliding sleeve 211 is fixed on the guide rod 1 to complete the fixation of the position of the suspension rod 2.
The implementation principle of this application embodiment an ancient building roofing suspension wire device does: when needing to carry out the installation, carry out position calibration with the quarter butt in proper order through calibration subassembly 4, then embolia sliding sleeve 211, adjust the position of jib 2 and fixed, fix two sections adjacent quarter butts through fixed subassembly 5 at last, accomplish the suspension wire construction. When needing to transport, take off fixed subassembly 5 earlier, then lift off all jib 2, at last with the quarter butt separately accomodate can.
Example 2
Referring to fig. 5, the present embodiment is different from embodiment 1 in that: the calibration assembly 4 comprises a first magnet 43 and a second magnet 44 which are identical in shape, the first magnet 43 is annular, the first magnet 43 is fixedly connected to one end of the first short rod 11 close to the second short rod 12, the second magnet 44 is fixedly connected to one end of the second short rod 12 close to the first short rod 11, and the first magnet 43 and the second magnet 44 are mutually attracted. The positioning block 121 is disposed through the second magnet 44, and when the first short rod 11 is connected to the second short rod 12, the positioning block 121 penetrates through the first magnet 43 and is inserted into the positioning groove 111, so as to calibrate the positions of the first short rod 11 and the second short rod 12.
The implementation principle of this application embodiment 2 an ancient building roofing suspension wire device does: when needing to carry out the installation, carry out position calibration with the quarter butt in proper order through calibration subassembly 4, then embolia sliding sleeve 211, adjust the position of jib 2 and fixed, fix two sections adjacent quarter butts through fixed subassembly 5 at last, accomplish the suspension wire construction. When needing to transport, take off fixed subassembly 5 earlier, then lift off all jib 2, at last with the quarter butt separately accomodate can.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides an ancient building roofing suspension wire device which characterized in that: including guide arm (1), a plurality of jib (2) and flexible rope (3), guide arm (1) includes the quarter butt that a plurality of sections head and the tail spliced in proper order, arbitrary adjacent two the tip that the quarter butt is close to each other is connected through fixed subassembly (5), jib (2) can dismantle connect in the quarter butt, flexible rope (3) are followed the length direction of quarter butt wears to establish in proper order all jib (2), flexible rope (3) both ends respectively with be located two sections in the relative outside of guide arm (1) quarter butt fixed connection.
2. The ancient building roof suspension wire device of claim 1, wherein: two adjacent short rods are respectively a first short rod (11) and a second short rod (12), one end of the first short rod (11) close to the second short rod (12) is provided with a positioning groove (111), one end of the second short rod (12) close to the first short rod (11) is connected with a positioning block (121), and the positioning block (121) is in inserted fit with the positioning groove (111); the fixing component (5) comprises a bolt (51), the bolt (51) penetrates through the first short rod (11) and the positioning block (121), a nut (52) is connected to the bolt (51) in a threaded mode, and the nut (52) abuts against the first short rod (11).
3. The ancient building roof suspension wire device of claim 2, wherein: and a calibration assembly (4) for calibrating the installation position of the bolt (51) is connected between the first short rod (11) and the second short rod (12).
4. The ancient building roof suspension wire device of claim 3, wherein: calibration subassembly (4) are including locking spring (41) and tapered end (42), locating piece (121) are offered and are used for settling the mounting groove (122) of locking spring (41), locking spring (41) one end connect in the tank bottom of mounting groove (122), the other end with tapered end (42) fixed connection, locating hole (112) have been seted up in first quarter butt (11), tapered end (42) are kept away from the one end of locking spring (41) with locating hole (112) joint cooperation.
5. The ancient building roof suspension wire device of claim 4, wherein: and one end of the lock head (42) far away from the locking spring (41) is arranged in a round angle manner.
6. The ancient building roof suspension wire device of claim 3, wherein: the calibration component (4) is a pair of magnets attracted to each other, and the first short rod (11) and the second short rod (12) are connected through the magnets.
7. The ancient building roof suspension wire device of claim 6, wherein: the magnets are annular, one of the magnets is fixedly connected to the second short rod (12), the other magnet is fixedly connected to the first short rod (11), and the positioning block (121) penetrates out of the middle of the magnets and is inserted into the positioning groove (111).
8. The historic building roof suspension wire device of any one of claims 5 or 7, wherein: the suspension rod (2) is fixedly connected with a sliding assembly (21), and the sliding assembly (21) is sleeved and slidably connected with the guide rod (1).
CN202022279757.2U 2020-10-13 2020-10-13 Ancient building roofing suspension wire device Active CN213539774U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022279757.2U CN213539774U (en) 2020-10-13 2020-10-13 Ancient building roofing suspension wire device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022279757.2U CN213539774U (en) 2020-10-13 2020-10-13 Ancient building roofing suspension wire device

Publications (1)

Publication Number Publication Date
CN213539774U true CN213539774U (en) 2021-06-25

Family

ID=76497274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022279757.2U Active CN213539774U (en) 2020-10-13 2020-10-13 Ancient building roofing suspension wire device

Country Status (1)

Country Link
CN (1) CN213539774U (en)

Similar Documents

Publication Publication Date Title
CN105805112B (en) A kind of universal joint assembly for the connection of rod piece space structure
CN204715596U (en) Mineral wool board ceiling system
CN213539774U (en) Ancient building roofing suspension wire device
CN203403541U (en) Joint used for connecting beam string structure inhaul cables and jackstays
CN205134929U (en) Scaffold connecting device for civil engineering
CN210800935U (en) Interior decoration ceiling lamp
CN210767791U (en) Scaffold plug-in card rotary telescopic rod for building site
CN208994942U (en) A kind of cell curtain wall lifting balancing pole
CN207259970U (en) A kind of new road science of bridge building protective frame
CN205591357U (en) Telescopic is connecting device for construction
CN209429394U (en) A kind of novel fabricated building connector
CN216195491U (en) High-safety steel structure connecting piece for building
CN108934745A (en) A kind of simple type plant fixing frame
CN218952856U (en) Quick installation device of jib
CN205063349U (en) Building templates prevents down bracing piece
CN220692806U (en) Municipal works are with overhead line of being convenient for maintain
CN213397043U (en) Tunnel clearance convergence monitoring nail
CN203669093U (en) Simple house frame transferring connector
CN202689797U (en) Supporting rod for door sleeve mounting
CN204357226U (en) A kind of structure of fiber cable cross connection box base door bolt
CN107771677A (en) The detachable sheep fixed hurdle of multipurpose
CN209693824U (en) A kind of tea seed weevil trapper suspension arrangement
CN212848847U (en) Telescopic yagi antenna reflector
CN215518435U (en) Temporary replacement stress device for construction of replacing suspender of arch bridge
CN219826223U (en) 5G base station base locating rack that suitability is wide

Legal Events

Date Code Title Description
GR01 Patent grant