- CN213449510U CN213449510U CN202021820074.7U CN202021820074U CN213449510U CN 213449510 U CN213449510 U CN 213449510U CN 202021820074 U CN202021820074 U CN 202021820074U CN 213449510 U CN213449510 U CN 213449510U
- Authority
- CN
- China
- Prior art keywords
- base
- support
- wall form
- concrete filling
- building concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a building concrete filling wall form strutting arrangement, including supporting mechanism, group battery and supplementary slewing mechanism, support the mechanism and run through the front and back terminal surface of base, and the left and right sides of terminal surface all is fixed with the auto-lock gyro wheel under the base, the right side of base up end is rotated and is connected with the revolving rack, and the revolving rack is taken and is put on the mount, supplementary slewing mechanism rotates and connects between base and revolving rack. This building concrete filling wall form strutting arrangement, remove and fix two the same the device after required place, the piston rod can extend under the effect of pneumatic cylinder, the sleeve moves along with the pillar, pneumatic cylinder and sleeve rotate under the effect that corresponds the second axostylus axostyle separately simultaneously, the piston rod, pillar and sleeve play the effect of support to the revolving rack, convenient supplementary revolving rack rotates, the revolving rack rotates the effect that can play the support to the wall form when changeing to the vertical state, can reverse above-mentioned operation of repetition after having used up the device, the convenience is folded the revolving rack and is receive and release.
Description
Technical Field
The utility model relates to a building technical field specifically is a building concrete filling wall form strutting arrangement.
Background
The wall form is a common apparatus in construction engineering, and the wall form needs to be supported and fixed before concrete is filled into the wall form, so that a supporting device is needed.
The existing supporting device is not convenient to move, the stability of the supporting device is difficult to guarantee before the supporting device is used, and the supporting device is inconvenient to fold and store after being used.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building concrete filling wall form strutting arrangement to current strutting arrangement who proposes in solving above-mentioned background art removes not convenient enough, and is difficult to guarantee its stability before using the device, and inconvenient folding problem of receiving and releasing after having used up.
In order to achieve the above object, the utility model provides a following technical scheme: a supporting device for a building concrete filling wall form comprises a supporting mechanism, a battery pack and an auxiliary rotating mechanism,
the supporting mechanism penetrates through the front end face and the rear end face of the base, the self-locking rollers are fixed on the left side and the right side of the lower end face of the base, the right side of the upper end face of the base is rotatably connected with the rotating frame, the rotating frame is arranged on the fixing frame in a lap mode, and meanwhile the fixing frame is fixed on the left side of the upper end face of the base;
and the auxiliary rotating mechanism is rotatably connected between the base and the rotating frame.
Preferably, support the mechanism and include spout, support, screw thread post and support the board, and support sliding connection is in the spout, and the spout is seted up in the front and back terminal surface of base simultaneously, run through threaded connection on the support has the screw thread post, and the bottom of screw thread post is fixed with supports the board.
Preferably, the bottom block of group battery is connected in the inboard of spacing frame, and spacing frame is fixed on the base, and group battery electric connection has the pneumatic cylinder simultaneously.
Preferably, the bottom of the rotating frame is rotatably connected to the base through a first shaft rod.
Preferably, supplementary slewing mechanism includes pneumatic cylinder, second axostylus axostyle, piston rod, pillar, sleeve and stud, and the pneumatic cylinder passes through the second axostylus axostyle and rotates to be connected on the base, and the pneumatic cylinder is located the left side of spacing frame simultaneously, the upside of pneumatic cylinder is connected with the pillar through the piston rod, and the pillar passes through stud to be fixed in telescopic inboard, and the sleeve rotates the interior top of connection at the revolving rack through the second axostylus axostyle simultaneously.
Compared with the prior art, the beneficial effects of the utility model are that: the supporting device for the building concrete filling wall form,
(1) the self-locking roller is utilized to move and attach two same devices to the left end face and the right end face of the wall surface, the bracket is pulled back and forth, then the threaded column is manually screwed downwards, the supporting plate moves downwards along with the threaded column and is fixedly supported on the ground, and at the moment, the self-locking roller fails, so that the device can be stably placed on the ground;
(2) after two identical devices are moved and fixed in a required place, the piston rod can be extended under the action of the hydraulic cylinder, the sleeve moves along with the support, the hydraulic cylinder and the sleeve rotate under the action of the corresponding second shaft rod respectively, the piston rod, the support and the sleeve support the rotating frame, the rotating frame is convenient to assist to rotate, the rotating frame can support a wall formwork when rotating to a vertical state, the operation can be repeated reversely after the device is used, and the rotating frame is convenient to fold and fold.
Drawings
Fig. 1 is a schematic view of the front cross-sectional structure of the present invention;
FIG. 2 is a schematic view of the front view of the present invention;
FIG. 3 is a schematic top view of the cross-sectional structure of the present invention;
fig. 4 is a schematic view of the bottom cross-section structure of the present invention.
In the figure: 1. the base, 2, auto-lock gyro wheel, 3, support the mechanism, 301, spout, 302, support, 303, screw thread post, 304, support the fagging, 4, spacing frame, 5, group battery, 6, revolving rack, 7, first axostylus axostyle, 8, mount, 9, supplementary slewing mechanism, 901, pneumatic cylinder, 902, second axostylus axostyle, 903, piston rod, 904, pillar, 905, sleeve, 906, stud.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a supporting device for a building concrete filling wall mold is disclosed, according to the figures 1, 2 and 3, a supporting mechanism 3 penetrates through the front end face and the rear end face of a base 1, self-locking rollers 2 are fixed on the left side and the right side of the lower end face of the base 1, the supporting mechanism 3 comprises a sliding chute 301, a support 302, a threaded column 303 and a supporting plate 304, the support 302 is connected in the sliding chute 301 in a sliding manner, the sliding chute 301 is arranged in the front end face and the rear end face of the base 1, the threaded column 303 is connected on the support 302 in a penetrating and threaded manner, the supporting plate 304 is fixed at the bottom of the threaded column 303, two identical devices are moved and attached to the left end face and the right end face of a wall surface by using the self-locking rollers 2, the support 302 is pulled back and forth under the auxiliary action of the sliding chute 301, then the threaded column 303 is screwed downwards manually, the supporting plate 304 moves downwards and is attached to the ground, at, the inboard at spacing frame 4 is connected to the bottom block of group battery 5, and spacing frame 4 fixes on base 1, 5 electric connection of group battery has pneumatic cylinder 901 simultaneously, spacing frame 4 plays spacing effect to group battery 5, conveniently improve the stability of group battery 5, group battery 5 can become the alternating current with the direct current under the effect of dc-to-ac converter and supply pneumatic cylinder 901 to use, guarantee the device's normal work with this, the right side of base 1 up end is rotated and is connected with revolving rack 6, and revolving rack 6 is put on mount 8, mount 8 fixes the left side at base 1 up end simultaneously, revolving rack 6's bottom is rotated through first axostylus axostyle 7 and is connected on base 1, revolving rack 6 can rotate under the effect of first axostylus axostyle 7, can play the effect that supports to the wall mould when revolving rack 6 changes to the vertical state.
According to fig. 1, 2 and 4, the auxiliary rotating mechanism 9 is rotatably connected between the base 1 and the rotating frame 6, the auxiliary rotating mechanism 9 comprises a hydraulic cylinder 901, a second shaft 902, a piston rod 903, a support 904, a sleeve 905 and a stud 906, the hydraulic cylinder 901 is rotatably connected to the base 1 through the second shaft 902, the hydraulic cylinder 901 is positioned at the left side of the position limiting frame 4, the upper side of the hydraulic cylinder 901 is connected with the support 904 through the piston rod 903, the support 904 is fixed at the inner side of the sleeve 905 through the stud 906, the sleeve 905 is rotatably connected to the inner top of the rotating frame 6 through the second shaft 902, the stud 906 is screwed to connect and fix the support 904 with the sleeve 905, after two identical devices are moved and fixed at a required place, the piston rod 903 can be extended under the action of the hydraulic cylinder 901, the sleeve 905 moves along with the moving support 904, meanwhile, the hydraulic cylinder 901 and the sleeve 905 rotate under the action of the corresponding second shaft rod 902, and the piston rod 903, the strut 904 and the sleeve 905 play a role in supporting the rotating frame 6, so that the rotation of the rotating frame 6 is facilitated.
The working principle is as follows: when the building concrete filling wall form supporting device is used, firstly, two same devices are moved and attached to the left end face and the right end face of a wall face by using the self-locking idler wheels 2, then the support 302 is pulled back and forth under the auxiliary action of the sliding grooves 301, then the threaded columns 303 are manually screwed downwards, the supporting plates 304 move downwards along with the threaded columns and are fixedly abutted to the ground, at the moment, the self-locking idler wheels 2 fail, the device can be stably placed on the ground, the limiting frames 4 limit the battery pack 5, the stability of the battery pack 5 is conveniently improved, the battery pack 5 converts direct current into alternating current to be used by the hydraulic cylinder 901 under the action of the inverter, after the hydraulic cylinder 901 is started, the hydraulic cylinder 901 drives the piston rod 903 to extend, so as to drive the support 904 to move, the sleeve 905 moves along with the support, and simultaneously the hydraulic cylinder 901 and the sleeve 905 rotate under the, The support column 904 and the sleeve 905 have a supporting effect on the rotating frame 6, so that the rotation of the auxiliary rotating frame 6 is facilitated, the rotating frame 6 can support a wall formwork when rotating to a vertical state, subsequent concrete filling operation is facilitated, after the device is used and the operations are repeated reversely, the rotating frame 6 can be rotated to an original rotating state, the fixing frame 8 supports the rotating frame 6, the whole work is completed, and the content which is not described in detail in the specification belongs to the prior art which is known by professionals in the field.
The terms "central," "longitudinal," "lateral," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientation or positional relationship indicated in the drawings for ease of description, but are not intended to indicate or imply that the device or element so referred to must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the scope of the invention.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.
Claims (5)
1. The utility model provides a building concrete filling wall form strutting arrangement, includes to prop mechanism (3), group battery (5) and supplementary slewing mechanism (9), its characterized in that:
the supporting mechanism (3) penetrates through the front end face and the rear end face of the base (1), the self-locking rollers (2) are fixed on the left side and the right side of the lower end face of the base (1), the right side of the upper end face of the base (1) is rotatably connected with the rotating frame (6), the rotating frame (6) is placed on the fixing frame (8), and meanwhile the fixing frame (8) is fixed on the left side of the upper end face of the base (1);
and the auxiliary rotating mechanism (9), wherein the auxiliary rotating mechanism (9) is rotatably connected between the base (1) and the rotating frame (6).
2. The building concrete filling wall form supporting device according to claim 1, wherein: support mechanism (3) including spout (301), support (302), screw thread post (303) and support board (304), and support (302) sliding connection in spout (301), spout (301) are seted up in the front and back terminal surface of base (1) simultaneously, run through threaded connection on support (302) and have screw thread post (303), and the bottom of screw thread post (303) is fixed with and supports board (304).
3. The building concrete filling wall form supporting device according to claim 1, wherein: the bottom block of group battery (5) is connected in the inboard of spacing frame (4), and just spacing frame (4) are fixed on base (1), and group battery (5) electric connection has pneumatic cylinder (901) simultaneously.
4. The building concrete filling wall form supporting device according to claim 1, wherein: the bottom of the rotating frame (6) is rotatably connected to the base (1) through a first shaft lever (7).
5. The building concrete filling wall form supporting device according to claim 1, wherein: supplementary slewing mechanism (9) include pneumatic cylinder (901), second shaft lever (902), piston rod (903), pillar (904), sleeve (905) and stud (906), and pneumatic cylinder (901) rotate through second shaft lever (902) and connect on base (1), and pneumatic cylinder (901) are located the left side of spacing frame (4) simultaneously, the upside of pneumatic cylinder (901) is connected with pillar (904) through piston rod (903), and pillar (904) are fixed in the inboard of sleeve (905) through stud (906), and sleeve (905) rotate through second shaft lever (902) and connect the interior top in revolving rack (6) simultaneously.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021820074.7U CN213449510U (en) | 2020-08-27 | 2020-08-27 | Building concrete filling wall form strutting arrangement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021820074.7U CN213449510U (en) | 2020-08-27 | 2020-08-27 | Building concrete filling wall form strutting arrangement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213449510U true CN213449510U (en) | 2021-06-15 |
Family
ID=76318532
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021820074.7U Active CN213449510U (en) | 2020-08-27 | 2020-08-27 | Building concrete filling wall form strutting arrangement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213449510U (en) |
-
2020
- 2020-08-27 CN CN202021820074.7U patent/CN213449510U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107214210A (en) | A kind of high performance steel levelling machine with shearing function | |
CN213449510U (en) | Building concrete filling wall form strutting arrangement | |
CN210559132U (en) | Bridge formwork lifting device | |
CN111762729A (en) | Supplementary crane that uses of power maintenance | |
CN215803036U (en) | Liftable scaffold for building construction | |
CN213714335U (en) | Building engineering straightness detection device that hangs down | |
CN210950551U (en) | Auxiliary device for mechanical equipment installation | |
CN211666210U (en) | Scaffold for building engineering | |
CN215213310U (en) | Multifunctional ladder for building construction | |
CN215169674U (en) | Triangular ladder convenient to fold and store for civil construction | |
CN218616685U (en) | Oxygen cylinder travelling bogie | |
CN212954081U (en) | Conveniently fixed jack for automobile | |
CN113107548A (en) | Tunnel waterproof material laying device and method | |
CN206719366U (en) | A kind of multifunction electric bicycle balanced controls | |
CN219100833U (en) | Anti-toppling supporting device for wall surface | |
CN221320655U (en) | Bridge construction suspension structure | |
CN213837629U (en) | Civil engineering construction support | |
CN215631886U (en) | Reinforced concrete frame beam column reinforced structure | |
CN211817824U (en) | Portable building scaffold | |
CN220336397U (en) | Construction frame for building construction | |
CN216042514U (en) | Dual self-lifting type external climbing frame for high-rise building | |
CN213980050U (en) | Self-locking steel structure bracket for building construction | |
CN215358346U (en) | Auxiliary device is stacked to cavity glass door | |
CN214836412U (en) | Movable gate type formwork with variable sections for tunnel | |
CN212398253U (en) | High-precision machining device for limiting step on inner wall of socket flange |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |