CN213423277U - Three-phase guide rail type partition plate for electric energy meter - Google Patents
Three-phase guide rail type partition plate for electric energy meter Download PDFInfo
- Publication number
- CN213423277U CN213423277U CN202021497209.0U CN202021497209U CN213423277U CN 213423277 U CN213423277 U CN 213423277U CN 202021497209 U CN202021497209 U CN 202021497209U CN 213423277 U CN213423277 U CN 213423277U
- Authority
- CN
- China
- Prior art keywords
- electric energy
- energy meter
- wiring board
- sleeve
- phase guide
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Insulating Bodies (AREA)
Abstract
The utility model discloses a baffle for three-phase guide tracked electric energy meter, including main part and sleeve, the main part top is fixed with the cardboard, and is provided with the diaphragm below the cardboard, main part surface connection has the mounting panel, and the mounting panel surface has seted up the connecting hole, the connecting hole below is provided with the wiring board, and the wiring board surface has seted up the through-hole, wiring board fixed surface has an installation section of thick bamboo, and the inside spout of having seted up of an installation section of thick bamboo, the wiring board bottom is connected with the bottom plate. This three-phase guide tracked baffle for electric energy meter passes through an installation section of thick bamboo, the spout, mutually support between slider and the sleeve sets up, make it make things convenient for telescopic installation and dismantlement, and the sleeve passes through mutually supporting between insulating layer and the fire-retardant layer, make it avoid generating heat through the heavy current because of through-hole and installation section of thick bamboo are inside, make the surface take place ageing, the condition that the insulation descends is favorable to reducing the accident such as emergence electric leakage, short circuit, arouse the condition of the emergence of electric fire even, holistic protectiveness has been promoted.
Description
Technical Field
The utility model relates to an inside supplementary technical field of electric energy meter specifically is a three-phase guide tracked baffle for electric energy meter.
Background
The electric energy meter is an instrument for measuring electric energy, also called watt-hour meter, fire meter, kilowatt hour meter, and refers to an instrument for measuring various electric quantities, when using the electric energy meter, it should be noted that under the condition of low voltage (not more than 500V) and small current (dozens of amperes), the electric energy meter can be directly connected into the circuit for measurement, under the condition of high voltage or large current, the electric energy meter can not be directly connected into the circuit, and needs to be used with a voltage transformer or a current transformer, and a partition board is installed inside each electric energy meter to separate the inside and the outside.
The current baffle for three-phase guide rail type electric energy meter is generally of a fixed structure, so that the baffle is very inconvenient in the installation process of the electric energy meter, the baffle made of plastic materials can be damaged due to forced installation, the baffle is not beneficial to use, and the baffle for the three-phase guide rail type electric energy meter is provided for the above conditions.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a three-phase guide tracked baffle for electric energy meter to provide general three-phase guide tracked baffle for electric energy meter in solving above-mentioned background art generally be fixed knot structure, make its in the installation with the electric energy meter inconvenient very, and the condition that the baffle that can cause the plastics material to damage is installed by force, is unfavorable for the problem of the use of this baffle.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a baffle for three-phase guide tracked electric energy meter, includes main part and sleeve, the main part top is fixed with the cardboard, and is provided with the diaphragm below the cardboard, the main part surface is connected with the mounting panel, and the mounting panel surface has seted up the connecting hole, the connecting hole below is provided with the wiring board, and the wiring board surface has seted up the through-hole, wiring board surface mounting has the installation section of thick bamboo, and the inside spout of having seted up of installation section of thick bamboo, the wiring board bottom is connected with the bottom plate, and the bottom plate outside is connected with the fixture block, the fixture block outside is provided with the draw-in groove, the main part both ends all are fixed with fixed ear, and fixed ear surface set up threaded hole, the muffjoint is inside the installation.
Preferably, the main body is of an integrated structure formed by the transverse plate and the clamping plate, and is of a flexible structure.
Preferably, the through holes are uniformly distributed at equal intervals relative to the surface of the wiring board, and seven through holes are arranged.
Preferably, the size of the inner opening of the mounting cylinder is larger than the size of the outer opening of the through hole, and the mounting cylinder is cylindrical.
Preferably, the bottom plate passes through and constitutes the block structure between fixture block, draw-in groove and the wiring board, and is vertical distribution between bottom plate and the wiring board.
Preferably, the fixing lugs are distributed in a bilateral symmetry mode about the vertical center line of the main body, and the fixing lugs are fixedly connected with the main body.
Preferably, the sleeve forms a sliding structure through the sliding blocks, the sliding grooves and the mounting cylinder, and the sliding blocks are uniformly distributed on the surface of the sleeve.
Preferably, the sleeve forms a semi-surrounding structure through the heat insulation layer and the flame retardant layer, and the heat insulation layer and the flame retardant layer are attached to each other.
Compared with the prior art, the beneficial effects of the utility model are that: this baffle for three-phase guide rail type electric energy meter, the main part passes through the mutually supporting setting between the fixture block in draw-in groove and the bottom plate outside, makes and to dismantle between its bottom plate and the main part, is favorable to having made things convenient for the installation between this baffle and the three-phase guide rail type electric energy meter, has also made things convenient for the later stage to the dismantlement process to the baffle of surface when needing the electric energy meter maintenance.
This three-phase guide tracked baffle for electric energy meter passes through an installation section of thick bamboo, the spout, mutually support between slider and the sleeve sets up, make it make things convenient for telescopic installation and dismantlement, and the sleeve passes through mutually supporting between insulating layer and the fire-retardant layer, make it avoid generating heat through the heavy current because of through-hole and installation section of thick bamboo are inside, make the surface take place ageing, the condition that the insulation descends is favorable to reducing the accident such as emergence electric leakage, short circuit, arouse the condition of the emergence of electric fire even, holistic protectiveness has been promoted.
This three-phase guide tracked baffle for electric energy meter passes through a columniform installation section of thick bamboo, makes its inside wiring back, and the wire rod can have a transition process, has avoided the wiring department to leak, causes the emergence of incident, and through mutually supporting between fixed ear, the screw hole main part, makes its this baffle can consolidate and be connected between the electric energy meter.
Drawings
FIG. 1 is a schematic view of the front view of the present invention;
FIG. 2 is a schematic view of the internal structure of the mounting cylinder of the present invention;
fig. 3 is a schematic view of the bottom plate of the present invention.
In the figure: 1. a main body; 2. a sleeve; 3. clamping a plate; 4. a transverse plate; 5. mounting a plate; 6. connecting holes; 7. a wiring board; 8. a through hole; 9. mounting the cylinder; 10. a chute; 11. a base plate; 12. a clamping block; 13. a card slot; 14. fixing the ear; 15. a threaded hole; 16. a slider; 17. a thermal insulation layer; 18. a flame retardant layer.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a partition plate for a three-phase guide rail type electric energy meter comprises a main body 1 and a sleeve 2, wherein a clamping plate 3 is fixed at the top of the main body 1, a transverse plate 4 is arranged below the clamping plate 3, the main body 1 and the clamping plate 3 form an integrated structure through the transverse plate 4, the main body 1 is of a flexible structure, and the transverse plate 4 and the clamping plate 3 are matched with each other, so that the mounting stability between the main body 1 and the electric energy meter is improved;
the surface of the main body 1 is connected with the mounting plate 5, the surface of the mounting plate 5 is provided with the connecting hole 6, the wiring board 7 is arranged below the connecting hole 6, the surface of the wiring board 7 is provided with the through holes 8, the through holes 8 are uniformly distributed on the surface of the wiring board 7 at equal intervals, and seven through holes 8 are arranged, so that the electric energy meter is convenient to use when the electric energy meter is mounted through the wiring board 7 and the through holes 8;
the installation cylinder 9 is fixed on the surface of the wiring board 7, the sliding groove 10 is formed in the installation cylinder 9, the size of the inner opening of the installation cylinder 9 is larger than that of the outer opening of the through hole 8, the installation cylinder 9 is cylindrical, and the installation cylinder 9 and the wire in the electric energy meter can have a transition process after being installed, so that the occurrence of safety accidents caused by leakage of the wiring position is avoided;
the bottom of the wiring board 7 is connected with a bottom board 11, the outer side of the bottom board 11 is connected with a clamping block 12, a clamping groove 13 is arranged outside the clamping block 12, the bottom board 11 forms a clamping structure with the wiring board 7 through the clamping block 12, the clamping groove 13 and the wiring board 7 are vertically distributed, and the main body 1 is detachably arranged between the bottom board 11 and the main body 1 through the mutual matching of the clamping groove 13 and the clamping block 12 on the outer side of the bottom board 11, so that the installation between the partition board and the three-phase guide rail type electric energy meter is facilitated, and the later process of detaching the partition board on the surface when the electric energy meter is required to be maintained is;
the sleeve 2 is connected inside the mounting cylinder 9, the surface of the sleeve 2 is connected with the sliding block 16, the sleeve 2 forms a sliding structure with the mounting cylinder 9 through the sliding block 16 and the sliding groove 10, the sliding blocks 16 are uniformly distributed on the surface of the sleeve 2, and the sliding blocks 16, the sliding groove 10 and the mounting cylinder 9 are matched with each other, so that the mounting and dismounting of the sleeve 2 are facilitated, and the replacement of the worn sleeve 2 in the later period is facilitated;
2 inboard sides of sleeve are connected with insulating layer 17, and insulating layer 17 inboard is connected with fire-retardant layer 18, sleeve 2 passes through insulating layer 17 and constitutes half surrounding structure between the fire-retardant layer 18, and laminate each other between insulating layer 17 and the fire-retardant layer 18, this sleeve 2 passes through insulating layer 17 and mutually supports between the fire-retardant layer 18, it generates heat through the heavy current to make it avoid because of through-hole 8 and installation section of thick bamboo 9 are inside, make the surface take place ageing, the condition of insulating decline, be favorable to reducing the condition of taking place the electric leakage, accidents such as short circuit, arouse the condition of the emergence of electric fire even, holistic protectiveness has been promoted.
The working principle is as follows: when the partition board for the three-phase guide rail type electric energy meter is used, firstly, the main body 1 is attached to the surface of the three-phase guide rail type electric energy meter, and further, the bottom board 11 is clamped and fixed with the clamping groove 13 at the bottom of the main body 1 through the clamping block 12 at the outer side, so that convenience is brought to installation between the partition board and the three-phase guide rail type electric energy meter, and convenience is brought to the dismounting process of the partition board on the surface when the electric energy meter needs to be maintained at the later stage, then, the sleeve 2 is installed in the installation cylinder 9 through the sliding grooves 10 formed in the installation cylinder 9 outside the through holes 8 and the sliding blocks 16 on the outer side of the sleeve 2 through fixing lugs 14 and threaded holes 15 at the two ends of the main body 1, and finally, the sleeve 2 is matched with the flame-retardant layer 18 through the heat-insulating layer 17, make it avoid generating heat through the heavy current because of through-hole 8 and installation section of thick bamboo 9 are inside for the surface takes place to age, the condition of insulating decline, be favorable to reducing the emergence electric leakage, accidents such as short circuit, arouse the condition of the emergence of electric fire even, holistic protectiveness has been promoted, and this baffle is through mutually supporting through slider 16, between spout 10 and the installation section of thick bamboo 9, make it make things convenient for the installation and the dismantlement of sleeve 2, be favorable to the change of later stage to the sleeve 2 of wearing and tearing.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (8)
1. The utility model provides a baffle for three-phase guide tracked electric energy meter, includes main part (1) and sleeve (2), its characterized in that: the clamping plate (3) is fixed at the top of the main body (1), the transverse plate (4) is arranged below the clamping plate (3), the mounting plate (5) is connected to the surface of the main body (1), the connecting hole (6) is formed in the surface of the mounting plate (5), the wiring board (7) is arranged below the connecting hole (6), the through hole (8) is formed in the surface of the wiring board (7), the mounting cylinder (9) is fixed to the surface of the wiring board (7), the sliding groove (10) is formed in the mounting cylinder (9), the bottom of the wiring board (7) is connected with the bottom plate (11), the clamping block (12) is connected to the outer side of the bottom plate (11), the clamping groove (13) is formed in the outer portion of the clamping block (12), the fixing lugs (14) are fixed to both ends of the main body (1), the threaded holes (15) are formed in, and the surface of the sleeve (2) is connected with a sliding block (16), the inner side of the sleeve (2) is connected with a heat insulation layer (17), and the inner side of the heat insulation layer (17) is connected with a flame retardant layer (18).
2. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the main body (1) is of an integrated structure through the transverse plate (4) and the clamping plate (3), and the main body (1) is of a flexible structure.
3. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the through holes (8) are uniformly distributed at equal intervals on the surface of the wiring board (7), and seven through holes (8) are arranged.
4. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the size of the inner opening of the mounting cylinder (9) is larger than that of the outer opening of the through hole (8), and the mounting cylinder (9) is cylindrical.
5. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the bottom plate (11) forms a clamping structure with the wiring board (7) through the clamping block (12), the clamping groove (13), and the bottom plate (11) and the wiring board (7) are vertically distributed.
6. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the fixing lugs (14) are distributed in a bilateral symmetry mode about the vertical center line of the main body (1), and the fixing lugs (14) are fixedly connected with the main body (1).
7. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the sleeve (2) forms a sliding structure through the sliding blocks (16), the sliding grooves (10) and the mounting barrel (9), and the sliding blocks (16) are uniformly distributed on the surface of the sleeve (2).
8. The separator for the three-phase guide rail type electric energy meter according to claim 1, wherein: the sleeve (2) forms a semi-surrounding structure through the heat insulation layer (17) and the flame retardant layer (18), and the heat insulation layer (17) and the flame retardant layer (18) are mutually attached.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021497209.0U CN213423277U (en) | 2020-07-23 | 2020-07-23 | Three-phase guide rail type partition plate for electric energy meter |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021497209.0U CN213423277U (en) | 2020-07-23 | 2020-07-23 | Three-phase guide rail type partition plate for electric energy meter |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213423277U true CN213423277U (en) | 2021-06-11 |
Family
ID=76254906
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021497209.0U Active CN213423277U (en) | 2020-07-23 | 2020-07-23 | Three-phase guide rail type partition plate for electric energy meter |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213423277U (en) |
-
2020
- 2020-07-23 CN CN202021497209.0U patent/CN213423277U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212514730U (en) | Outdoor ammeter convenient to overhaul | |
CN213423277U (en) | Three-phase guide rail type partition plate for electric energy meter | |
CN215267255U (en) | Anticreep structure that block terminal was used | |
CN212847964U (en) | Transformer mounting bracket | |
CN219351043U (en) | Switch board convenient to installation | |
CN220120880U (en) | Modular auxiliary terminal box | |
CN210803556U (en) | Direct current electric energy meter based on internal bus bar fixed connection of up-down run-through | |
CN215833476U (en) | Ready-package electric energy meter | |
CN211236005U (en) | Three-phase electrification indicator of switch cabinet | |
CN210219107U (en) | Multipurpose electric power monitoring instrument mounting rack | |
CN218940398U (en) | Power distribution cabinet internal support structure convenient to install | |
CN209642150U (en) | A kind of switch cabinet bus mounting structure convenient for adjusting | |
CN210271525U (en) | Identification means is used in power equipment installation | |
CN204614651U (en) | Namely modular current transformer inserts mount pad | |
CN109103624B (en) | Mounting base of electronic equipment ground terminal | |
CN201392761Y (en) | Load switch protective masking cover on rod | |
CN214205757U (en) | Adjustable distribution frame | |
CN104242813A (en) | Power supply structure for direct-current transmission line on-line monitoring device | |
CN220122413U (en) | Assembled ammeter case | |
CN214622849U (en) | Thermal stability testing device reasonable in wiring | |
CN216929179U (en) | Electrical box panel with electric wire arrangement function | |
CN221202087U (en) | Buckle formula elasticity copper aluminium composite bar bus duct | |
CN216772065U (en) | Optical fiber wiring sub-frame for pallet | |
CN214479208U (en) | Cable fixing device for municipal works | |
CN204614650U (en) | Namely a kind of spliced current transformer inserts installation module |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |