CN213361925U - Petrochemical instrument mounting structure - Google Patents

Petrochemical instrument mounting structure Download PDF

Info

Publication number
CN213361925U
CN213361925U CN202022144582.4U CN202022144582U CN213361925U CN 213361925 U CN213361925 U CN 213361925U CN 202022144582 U CN202022144582 U CN 202022144582U CN 213361925 U CN213361925 U CN 213361925U
Authority
CN
China
Prior art keywords
annular
ring
flange
groove
install
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022144582.4U
Other languages
Chinese (zh)
Inventor
胡贤坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Hangke Intelligent System Co ltd
Original Assignee
Shenyang Hangke Intelligent System Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Hangke Intelligent System Co ltd filed Critical Shenyang Hangke Intelligent System Co ltd
Priority to CN202022144582.4U priority Critical patent/CN213361925U/en
Application granted granted Critical
Publication of CN213361925U publication Critical patent/CN213361925U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Measuring Fluid Pressure (AREA)

Abstract

The utility model discloses a petrochemical instrument mounting structure, including oil storage pipe and panel board, install fixed pipe on the oil storage pipe, install first ring flange on the fixed pipe, install the connecting pipe on the panel board, install the second ring flange on the connecting pipe, be equipped with annular spout on the connecting pipe, the annular spout endotheca is equipped with the screw thread drum, the screw thread drum passes through the screw thread and installs on first ring flange. The threaded cylinder is installed on the first flange plate through threads, so that the petrochemical instrument can be quickly installed, the operation is simple, and the installation and disassembly efficiency of the petrochemical instrument can be improved; realize petrochemical instrument's double sealing through sealed pad and annular pad, can increase sealed effect.

Description

Petrochemical instrument mounting structure
Technical Field
The utility model belongs to the technical field of petrochemical, specifically be a petrochemical instrument mounting structure.
Background
The petrochemical instrument is used for the oil to transmit and store often and carries out pressure and temperature to transmission pipe and storage cylinder and show, and its kind is various, plays crucial effect to the operation safety.
At present, the existing petrochemical instrument is fixedly installed through a plurality of bolts when being installed and used, so that the petrochemical instrument is relatively troublesome to install and dismantle, and the installation and the disassembly efficiency of the petrochemical instrument are influenced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a petrochemical instrument mounting structure to solve current petrochemical instrument and when installing the use, all install it fixedly through a plurality of bolts, make petrochemical instrument relatively more troublesome when installation, dismantlement, influence the problem of petrochemical instrument installation, the efficiency of dismantlement.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a petrochemical instrument mounting structure, includes oil storage pipe and panel board, install fixed pipe on the oil storage pipe, install first ring flange on the fixed pipe, install the connecting pipe on the panel board, install the second ring flange on the connecting pipe, be equipped with annular spout on the connecting pipe, annular spout endotheca is equipped with the screw thread drum, the screw thread drum passes through the screw thread and installs on first ring flange, is equipped with the screw thread on the first ring flange for the screw thread drum can be fixed through the screw thread installation.
Preferably, all be equipped with first recess on first ring flange and the second ring flange, sealed pad is equipped with to the first recess endotheca, and sealed pad is made by sealing materials such as silica gel, rubber, realizes sealed between first ring flange and the second ring flange through sealed pad.
Preferably, a first annular groove is formed in the first groove, a first annular ring is arranged on the sealing gasket, the first annular ring is sleeved in the first annular groove, and the sealing effect between the sealing gasket and the first groove can be improved by matching the first annular groove and the first annular ring.
Preferably, a second groove is formed in the threaded cylinder, an annular pad is sleeved in the second groove, an inner ring of the annular pad is tightly attached to the first flange plate and the second flange plate, the annular pad is made of sealing materials such as silica gel and rubber, and sealing among the threaded cylinder, the first flange plate and the second flange plate is achieved through the annular pad.
Preferably, the first flange plate and the second flange plate are both provided with second annular grooves, the annular gasket is provided with a second annular ring, the second annular ring is sleeved in the second annular groove, and the sealing effect between the annular gasket and the first flange plate and between the annular gasket and the second flange plate can be increased by matching the second annular groove and the second annular ring.
Compared with the prior art, the beneficial effects of the utility model are that: the threaded cylinder is installed on the first flange plate through threads, so that the petrochemical instrument can be quickly installed, the operation is simple, and the installation and disassembly efficiency of the petrochemical instrument can be improved; realize petrochemical instrument's double sealing through sealed pad and annular pad, can increase sealed effect.
Drawings
Fig. 1 is a top view of the overall structure of the present invention;
fig. 2 is a top sectional view of the overall structure of the present invention.
In the figure: the oil storage device comprises an oil storage pipe 1, an instrument panel 2, a fixed pipe 3, a first flange plate 4, a connecting pipe 5, a second flange plate 6, an annular sliding groove 7, a threaded cylinder 8, a first groove 9, a sealing gasket 10, a first annular groove 11, a first annular ring 12, a second groove 13, an annular gasket 14, a second annular groove 15 and a second annular ring 16.
Detailed Description
Please refer to fig. 1 and 2, a petrochemical instrument mounting structure, including an oil storage tube 1 and a meter panel 2, the oil storage tube 1 is sealed and welded with a fixed tube 3, the fixed tube 3 is sealed and welded with a first flange 4, the meter panel 2 is provided with a connecting tube 5 through a sealing thread, the connecting tube 5 is sealed and welded with a second flange 6, the connecting tube 5 is provided with an annular chute 7, the annular chute 7 is sleeved with a threaded cylinder 8, the threaded cylinder 8 is mounted on the first flange 4 through a thread, the first flange 4 is provided with a thread, so that the threaded cylinder 8 can be mounted and fixed through the thread.
Referring to fig. 2, the first flange 4 and the second flange 6 are both provided with a first groove 9, a sealing gasket 10 is sleeved in the first groove 9, the sealing gasket 10 is made of sealing materials such as silica gel and rubber, and the sealing between the first flange 4 and the second flange 6 is realized through the sealing gasket 10.
Referring to fig. 2, a first annular groove 11 is formed in the first groove 9, a first annular ring 12 is arranged on the sealing gasket 10, the first annular ring 12 is sleeved in the first annular groove 11, and the sealing effect between the sealing gasket 10 and the first groove 9 can be improved by matching the first annular groove 11 with the first annular ring 12.
Referring to fig. 2, a second groove 13 is formed in the threaded cylinder 8, an annular pad 14 is sleeved in the second groove 13, an inner ring of the annular pad 14 is tightly attached to the first flange plate 4 and the second flange plate 6, the annular pad 14 is made of sealing materials such as silica gel and rubber, and sealing between the threaded cylinder 8 and the first flange plate 4 and the second flange plate 6 is achieved through the annular pad 14.
Referring to fig. 2, the first flange plate 4 and the second flange plate 6 are both provided with a second annular groove 15, the annular pad 14 is provided with a second annular ring 16, the second annular ring 16 is sleeved in the second annular groove 15, and the sealing effect between the annular pad 14 and the first flange plate 4 and the second flange plate 6 can be increased by matching the second annular groove 15 with the second annular ring 16.
The working principle of the scheme is as follows: when the installation, with 7 stimulations of annular spout of screw thread drum 8, then rotate screw thread drum 8, make screw thread drum 8 pass through the screw thread and install on first ring flange 4, can realize petrochemical instrument's quick installation, and is simple in operation, can improve petrochemical instrument installation, the efficiency of dismantlement, and, realize sealed between first ring flange 4 and the second ring flange 6 through sealed pad 10, realize screw thread drum 8 and first ring flange 4 through annular pad 14, sealed between the second ring flange 6, thereby realize petrochemical instrument's double sealing, can increase sealed effect.

Claims (5)

1. The utility model provides a petrochemical instrument mounting structure, includes oil storage pipe (1) and panel board (2), its characterized in that: install fixed pipe (3) on oil storage pipe (1), install first ring flange (4) on fixed pipe (3), install connecting pipe (5) on panel board (2), install second ring flange (6) on connecting pipe (5), be equipped with annular spout (7) on connecting pipe (5), annular spout (7) endotheca is equipped with screw thread drum (8), screw thread drum (8) are installed on first ring flange (4) through the screw thread.
2. The petrochemical instrument mounting structure according to claim 1, wherein: all be equipped with first recess (9) on first ring flange (4) and second ring flange (6), sealed pad (10) are equipped with to first recess (9) endotheca.
3. The petrochemical instrument mounting structure according to claim 2, wherein: the sealing structure is characterized in that a first annular groove (11) is formed in the first groove (9), a first annular ring (12) is arranged on the sealing gasket (10), and the first annular ring (12) is sleeved in the first annular groove (11).
4. The petrochemical instrument mounting structure according to claim 1, wherein: and a second groove (13) is arranged in the threaded cylinder (8), an annular pad (14) is sleeved in the second groove (13), and the inner ring of the annular pad (14) is tightly attached to the first flange plate (4) and the second flange plate (6).
5. The petrochemical instrument mounting structure according to claim 4, wherein: and a second annular groove (15) is formed in each of the first flange plate (4) and the second flange plate (6), a second annular ring (16) is arranged on the annular pad (14), and the second annular ring (16) is sleeved in the second annular groove (15).
CN202022144582.4U 2020-09-25 2020-09-25 Petrochemical instrument mounting structure Active CN213361925U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022144582.4U CN213361925U (en) 2020-09-25 2020-09-25 Petrochemical instrument mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022144582.4U CN213361925U (en) 2020-09-25 2020-09-25 Petrochemical instrument mounting structure

Publications (1)

Publication Number Publication Date
CN213361925U true CN213361925U (en) 2021-06-04

Family

ID=76155929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022144582.4U Active CN213361925U (en) 2020-09-25 2020-09-25 Petrochemical instrument mounting structure

Country Status (1)

Country Link
CN (1) CN213361925U (en)

Similar Documents

Publication Publication Date Title
CN203309102U (en) Oil sleeve external-pressure collapse test sealing device
CN213361925U (en) Petrochemical instrument mounting structure
CN201198744Y (en) Packing apparatus capable of rapidly changing faucet
CN201827066U (en) Connecting structure of drilling pump cylinder liner
CN202091290U (en) Novel hydraulic oil cylinder device
CN210830897U (en) Outer flange plate capable of being installed quickly
CN209432341U (en) A kind of fluid survey pressure pressure ga(u)ge damper
CN115711285A (en) Input shaft sealing device of reduction gearbox
CN211347204U (en) Novel mounting structure of water treatment facilities manometer
CN209592943U (en) A kind of novel cable via seal cover
CN108317885B (en) Sealing connection structure of heat exchange tube and tube plate
CN201177043Y (en) Elevated plain oil pumping machine reduction box input shaft sealer
CN205261071U (en) Flange structure
CN202927330U (en) Quick coupling used for plate radiator gas / oil rapid filling
CN221034442U (en) Pipeline connecting device of offshore wind turbine generator
CN215660663U (en) Punching tool for processing aramid oil-resistant rubber gasket
CN202442009U (en) Mounting structure for signal wires on cases
CN217898727U (en) End cover sealing device of large-scale speed reducer
CN219082519U (en) Pipeline flange connector
CN202631022U (en) Mounting sleeve device
CN211175393U (en) Electric regulating valve
CN220749165U (en) Two-position five-way electromagnetic valve
CN219140129U (en) Self-sealing rotary compensator
CN221075406U (en) Chemical strain unification is in valve box of eight
CN219866494U (en) Quick dismounting device for end cover of regulating valve

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Heshun (Liaoning) Information Technology Co.,Ltd.

Assignor: Shenyang Hangke Intelligent System Co.,Ltd.

Contract record no.: X2023980043239

Denomination of utility model: A Petrochemical Instrument Installation Structure

Granted publication date: 20210604

License type: Common License

Record date: 20231012

EE01 Entry into force of recordation of patent licensing contract