Publication number
CN213143789U
CN213143789U CN202020898015.5U CN202020898015U CN213143789U CN 213143789 U CN213143789 U CN 213143789U CN 202020898015 U CN202020898015 U CN 202020898015U CN 213143789 U CN213143789 U CN 213143789U
Authority
CN
China
Prior art keywords
scaffold
water
base
main body
main part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020898015.5U
Other languages
Chinese (zh)
Inventor
董文涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Tenglu Heavy Industry Technology Co Ltd
Original Assignee
Xuzhou Tenglu Heavy Industry Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Tenglu Heavy Industry Technology Co Ltd filed Critical Xuzhou Tenglu Heavy Industry Technology Co Ltd
Priority to CN202020898015.5U priority Critical patent/CN213143789U/en
Application granted granted Critical
Publication of CN213143789U publication Critical patent/CN213143789U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Non-Portable Lighting Devices Or Systems Thereof (AREA)

Abstract

A steel structure scaffold comprises a scaffold main body (1), a base (3) and a top plate (2), the top plate (2) is clamped at the top of the scaffold main body (1), the base (3) is fixedly connected at the bottom of the scaffold main body (1), the upper surfaces of two ends of the top plate (2) are connected with crystal gypsum lamps (9), a water tank (4) is arranged at the joint of the base (3) at one side and the scaffold main body (1), the upper surface of the water tank (4) is connected with a water pump (6), the water pump (6) is connected with a water pipe (7) which is movably connected with the scaffold main body (1) in a surrounding way, a water spray nozzle (8) is connected on the water delivery pipe (7), a storage battery (5) is connected on the upper surface of the base (3) at one side of the water tank (4), the scaffold is characterized in that a climbing frame (10) is connected to the side edge of the scaffold main body (1), and a first inclined rod (11) and a second inclined rod (12) which are connected in a cross mode are connected inside the scaffold main body (1).

Description

Steel structure scaffold
Technical Field
The utility model relates to a scaffold technical field, in particular to steel construction scaffold.
Background
The scaffold is a temporary building tool which is erected for workers to operate and solve vertical and horizontal transportation on a construction site, is mainly used for outer walls, interior decoration or places where the floor height is high and cannot be directly constructed, is mainly used for maintenance of safety nets of construction personnel to live up and down or peripheral safety nets, high-altitude installation components and the like, is usually made of bamboo, wood, steel pipes or synthetic materials and the like, but the existing scaffold basically takes a steel structure as a main part, but in daily arduous building work, the working environment is severe when the building is built, a large amount of dust, noise and the like can be generated, the work of the constructors is influenced, the mood is influenced, and the working efficiency is further reduced.
SUMMERY OF THE UTILITY MODEL
The utility model mainly aims to provide a steel structure scaffold to overcome the defects in the prior art;
in order to solve the technical problem, the utility model provides a following technical scheme:
a steel structure scaffold comprises a scaffold main body, a base and a top plate, wherein the top plate is clamped at the top of the scaffold main body, the base is fixedly connected to the bottom of the scaffold main body, crystal gypsum lamps are connected to the upper surfaces of two ends of the top plate, a water tank is installed at the joint of the base and the scaffold main body, the upper surface of the water tank is connected to a water pump, the water pump is connected to a water pipe which is movably connected to the scaffold main body in a surrounding mode, a water mist spray nozzle is connected to the water pipe, a storage battery is connected to the base where the water tank is located, a climbing frame is connected to the side edge of the scaffold main body, a first inclined rod and a second inclined rod which;
optionally, the top plate is in a metal mesh shape, so that the top plate is light in weight and convenient to carry and mount;
optionally, the crystal gypsum lamps are two in number and electrically connected to the storage battery, the crystal gypsum lamps can emit natural negative ions, so that the content of the positive and negative ions in the air can be effectively balanced, the negative ions can improve the emotion and the environmental mental stress and fatigue, and the crystal gypsum lamps are greatly helpful for the emotion of workers during construction to improve the working efficiency;
optionally, the water pump is electrically connected to the storage battery;
optionally, the number of the water mist nozzles is multiple, so that water mist purification and dust reduction can be performed on the surrounding environment during construction, and a cool and refreshing effect is achieved;
optionally, the base is provided with four screw holes, which can be used for splicing scaffolds, so that the scaffolds are more stable;
optionally, the water pipe is a rubber hose, and the water pipe can be movably connected to the scaffold main body after the scaffold is installed;
optionally, the number of the climbing frames is four, and two climbing frames are arranged on each side of the scaffold main body, so that workers can climb the scaffold;
has the advantages that: the utility model discloses increased water smoke dust device on original scaffold structure's basis and can improve operational environment and throw light on and can improve the crystal gypsum lamp of workman's mood, can improve mood, the mental tension fatigue of environment, help greatly in order to improve work efficiency to workman's mood when the construction.
Drawings
FIG. 1 is a schematic structural view of the present invention;
the scaffold comprises a scaffold body 1, a top plate 2, a base 3, a water tank 4, a storage battery 5, a water pump 6, a water delivery pipe 7, a water mist spray head 8, a crystal gypsum lamp 9, a climbing frame 10, a first inclined rod 11, a second inclined rod 12 and a screw hole 13.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases by those skilled in the art.
As shown in fig. 1, the device comprises a scaffold main body, a base and a top plate, wherein the top plate is clamped at the top of the scaffold main body, the base is fixedly connected to the bottom of the scaffold main body, crystal gypsum lamps are connected to the upper surfaces of two ends of the top plate, a water tank is installed at the joint of the base and the scaffold main body, the upper surface of the water tank is connected to a water pump, the water pump is connected to a water pipe which is movably connected to the scaffold main body in a surrounding manner, a water mist spray nozzle is connected to the water pipe, a storage battery is connected to the base where the water tank is located, a climbing frame is connected to the side edge of the scaffold main body, a first inclined rod and a second; the top plate is in a metal mesh shape, so that the weight is light, and the carrying and the installation are convenient; the crystal gypsum lamps are electrically connected with the storage battery, can emit natural negative ions, can effectively balance the content of positive and negative ions in the air, can improve emotion and relieve mental stress and fatigue of the environment, and greatly helps workers to improve working efficiency during construction; the water pump is electrically connected with the storage battery; the water mist nozzles are provided with a plurality of water mist nozzles, so that water mist purification and dust fall can be carried out on the surrounding environment during construction, and a cool and refreshing effect is achieved; the base is provided with four screw holes which can be used for splicing scaffolds, so that the scaffolds are more stable; the water pipe is a rubber hose, and can be movably connected to the scaffold main body after the scaffold is installed; the climbing frame is totally four, and there are two on every side of scaffold frame main part to the workman scrambles.
The working principle is as follows: when in use, the top plate 2 and the scaffold main body 1 are spliced, then the inclined rods 11 and 12 are connected with the scaffold main body 1 in a cross way to reinforce the scaffold main body, then the water pipe 7 is arranged on the scaffold main body 1 and the top plate 2 to wait for water supply and carry out water mist dust fall through the water mist spray head 8, the storage battery 5 can be opened for power supply after the assembly is finished, at the moment, the water pump 6 absorbs water from the inside of the water tank 4 through the guide pipe and conveys the water to the water conveying pipe 7, and then the water is sprayed out from the water mist spray head 8 to reduce dust and improve the quality of the working environment, meanwhile, the crystal gypsum lamp 9 can also be lighted up to emit joyful light and natural negative ions to improve the emotion and the mental stress and fatigue of the environment, the worker is greatly helped in the mood during the construction to improve the working efficiency, and then the worker can ascend the scaffold through the climbing frame 10 for work.

Claims (8)

1. The utility model provides a steel construction scaffold, includes scaffold main part (1), base (3) and roof (2), roof (2) joint in scaffold main part (1) top, base (3) fixed connection in scaffold main part (1) bottom, its characterized in that: roof (2) both ends upper surface is connected with crystal gypsum lamp (9), water tank (4) are installed with the junction of scaffold frame main part (1) in base (3), water tank (4) upper surface connection is in water pump (6), water pump (6) are connected in raceway (7) around swing joint in scaffold frame main part (1), be connected with water smoke shower nozzle (8) on raceway (7), be connected with battery (5) on base (3) at water tank (4) place, scaffold frame main part (1) side is connected with climbing frame (10), scaffold frame main part (1) internal connection has cross connection's down tube one (11) and down tube two (12), screw (13) have been seted up to base (3) inside.
2. A steel structural scaffold according to claim 1 wherein: the top plate (2) is in a metal net shape.
3. A steel structural scaffold according to claim 1 wherein: the crystal gypsum lamps (9) are arranged in two, and the crystal gypsum lamps (9) are electrically connected to the storage battery (5).
4. A steel structural scaffold according to claim 1 wherein: the water pump (6) is electrically connected with the storage battery (5).
5. A steel structural scaffold according to claim 1 wherein: the water mist spray heads (8) are provided with a plurality of water mist spray heads.
6. A steel structural scaffold according to claim 1 wherein: the base (3) is provided with four screw holes (13).
7. A steel structural scaffold according to claim 1 wherein: the water delivery pipe (7) is a rubber hose.
8. A steel structural scaffold according to claim 1 wherein: the number of the climbing frames (10) is four, and two climbing frames are arranged on each side of the scaffold main body (1).
CN202020898015.5U 2020-05-26 2020-05-26 Steel structure scaffold Expired - Fee Related CN213143789U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020898015.5U CN213143789U (en) 2020-05-26 2020-05-26 Steel structure scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020898015.5U CN213143789U (en) 2020-05-26 2020-05-26 Steel structure scaffold

Publications (1)

Publication Number Publication Date
CN213143789U true CN213143789U (en) 2021-05-07

Family

ID=75725265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020898015.5U Expired - Fee Related CN213143789U (en) 2020-05-26 2020-05-26 Steel structure scaffold

Country Status (1)

Country Link
CN (1) CN213143789U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116164260A (en) * 2023-01-18 2023-05-26 江苏鑫昇腾科技发展股份有限公司 Lighting system for night construction of attached lifting scaffold

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116164260A (en) * 2023-01-18 2023-05-26 江苏鑫昇腾科技发展股份有限公司 Lighting system for night construction of attached lifting scaffold
CN116164260B (en) * 2023-01-18 2024-03-29 江苏鑫昇腾科技发展股份有限公司 Lighting system for night construction of attached lifting scaffold

Similar Documents

Publication Publication Date Title
CN213143789U (en) Steel structure scaffold
CN212970861U (en) Greening curtain wall structure for building
CN216156780U (en) A liftable viewing platform for chinese style wayside pavilion corridor frame
CN216662305U (en) Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform
CN204876519U (en) Building interior decoration frame of ascending a height
CN205063284U (en) Watering curing means is decorated to building outer wall
CN216740998U (en) Fence for building construction
CN209893260U (en) High-pole lamp convenient to height-adjusting
CN113896124A (en) Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform, installation process and climbing method thereof
CN215802721U (en) Steel construction factory building with daylighting structure
CN209620551U (en) A kind of multi-functional mounting platform of high voltage power cable
CN108442805B (en) Safety fence for maintaining low-pressure cylinder of steam turbine of nuclear power station
CN215027165U (en) Desulfurizing tower for environmental protection atmosphere treatment
CN215594817U (en) Concrete pouring workstation is built in room
CN215760283U (en) Portable scaffold for building installation
CN219864434U (en) Novel safety guard rail
CN213626615U (en) Building engineering safety protection net
CN210685313U (en) Safe convenient house steel connection structure
CN216641343U (en) Make things convenient for integral type scaffold frame of block
CN221277183U (en) Tank boarding ladder for marine LNG liquid tank
CN219260750U (en) Hanging basket for bridge side construction
CN219139267U (en) C-shaped tower assembled foundation splicing device
CN217247722U (en) Industrial tail gas purifying tower
CN210122701U (en) Water spray dust device for constructional engineering
CN215138089U (en) Dust exhausting fan for construction engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210507