CN213142996U - High mountain gorge area side slope exploration open cut tunnel arrangement structure - Google Patents

High mountain gorge area side slope exploration open cut tunnel arrangement structure Download PDF

Info

Publication number
CN213142996U
CN213142996U CN201821581006.2U CN201821581006U CN213142996U CN 213142996 U CN213142996 U CN 213142996U CN 201821581006 U CN201821581006 U CN 201821581006U CN 213142996 U CN213142996 U CN 213142996U
Authority
CN
China
Prior art keywords
exploration
river
hole
tunnel
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821581006.2U
Other languages
Chinese (zh)
Inventor
杨静熙
肖华波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201821581006.2U priority Critical patent/CN213142996U/en
Application granted granted Critical
Publication of CN213142996U publication Critical patent/CN213142996U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model discloses a mountain gorge area slope exploration open cut tunnel arrangement structure belongs to geological exploration technical field for in solving current exploration open cut tunnel arrangement structure, to the open cut tunnel of different layers needs the time-sharing period construction in order to avoid the potential safety hazard during its excavation construction, still have the construction cycle length simultaneously, environmental pollution is big, the degree of difficulty is high and construction cost scheduling problem. The utility model discloses an adopt the arrangement structure of the horizontal river open cut and the following river open cut that intercross and communicate in each layer of exploration open cut, and set up a slag notch in each layer of exploration open cut, stagger the setting of the slag notch of each layer of exploration open cut in the incline direction along the side slope simultaneously, can avoid the mutual influence of slagging tap when each layer of exploration open cut is under construction, can realize to be under construction to the multilayer exploration open cut simultaneously, improved the efficiency of construction, shortened the construction period and still avoided the potential safety hazard simultaneously; in addition, the number of slag outlets can be reduced, the environmental pollution is reduced, and the construction cost and the construction difficulty are reduced.

Description

High mountain gorge area side slope exploration open cut tunnel arrangement structure
Technical Field
The utility model relates to a geological exploration technical field especially relates to a mountain gorge area slope exploration open cut tunnel arrangement structure and construction method thereof.
Background
In order to generate electricity by utilizing the fall of river water energy, hydropower stations are mostly built in high mountain canyon regions. The influence of deep cutting weathering, unloading and the like of the river valley causes complex geological conditions of the dam area. In order to find out the geological conditions of the side slopes of the dam area, drilling or excavating a flat hole on the corresponding side slope is usually needed for geological exploration; and usually requires the exploration to be carried out by implementing a plurality of layers of flat holes or drill holes on the side slope according to the elevation, and the exploration flat holes generally comprise a cross river flat hole and a down river flat hole.
In the existing exploration flat tunnel excavation process, construction interference problems exist in the implementation of different layers of exploration flat tunnels on the upper layer and the lower layer, and each horizontal river flat tunnel in each layer of exploration flat tunnel is provided with a plurality of slag discharging points by taking an outlet of the horizontal river flat tunnel as a slag discharging hole, so that the slag discharging of each layer of exploration flat tunnel can directly influence the lower exploration points; therefore, the construction of the upper and lower exploration caves must be carried out in the same longitudinal direction at different time intervals at present, so that the potential safety hazard caused by the construction of the upper exploration cave to the construction of the lower exploration cave is avoided, and the problems of long construction period, low efficiency and the like are caused. In addition, as each horizontal river open cut construction in each layer of exploration open cut forms a slag discharging point, the slag discharging points are more, and the environmental pollution is great; the slag body distributed all over the side slope has poor stability, and forms potential safety hazard for later-period lower exploration personnel; in addition, before construction, the ground surface road is required to be constructed to each hole position to reach the open cut for slag transportation, so that the construction workload of the ground surface road is greatly increased, and the construction cost and the construction difficulty are increased.
SUMMERY OF THE UTILITY MODEL
The utility model provides a technical problem be: the existing exploration open cut tunnel arrangement structure needs time-phased construction for different layers of exploration open cuts during excavation construction so as to avoid potential safety hazards, and meanwhile, the problems of long construction period, high environmental pollution, high difficulty, high construction cost and the like exist.
The utility model provides a technical scheme that its technical problem adopted is: the arrangement structure of the side slope exploration flat holes in the high mountain valley region comprises at least one exploration flat hole layer arranged in a side slope, each exploration flat hole layer comprises a down-the-river flat hole and a cross-river flat hole, and the down-the-river flat holes in the same exploration flat hole layer are communicated with all the cross-river flat holes in the same exploration flat hole layer; a slag hole is arranged in each layer of exploration flat hole, and the slag holes corresponding to the exploration flat holes of each layer are staggered along the inclination direction of the side slope.
Further, the method comprises the following steps: each exploration flat hole comprises a down-the-river flat hole and a plurality of cross-river flat holes.
Further, the method comprises the following steps: the trend of the down-the-river flat tunnel is consistent with the trend of gullies at the bottom of the side slope or rivers, and the trend of the cross-river flat tunnel is vertical to the trend of the down-the-river flat tunnel; one end of the horizontal river flat tunnel penetrates out of or is close to the surface of the side slope, and the other end of the horizontal river flat tunnel penetrates into the side slope.
Further, the method comprises the following steps: the slag hole is formed after one of the horizontal river flat holes in the exploration flat hole of the corresponding layer penetrates out of the surface of the side slope.
Further, the method comprises the following steps: the slag hole is formed after one end of a down-the-river adit in the exploration adit of the corresponding layer penetrates out of the surface of the side slope.
Further, the method comprises the following steps: an auxiliary hole is arranged in any layer of exploration flat hole, one end of the auxiliary hole is communicated with the down-the-river flat hole in the exploration flat hole of the corresponding layer, the other end of the auxiliary hole penetrates out of the surface of the side slope, and a slag hole of the exploration flat hole of the layer is a hole formed after one end of the corresponding auxiliary hole penetrates out of the surface of the side slope.
Additionally, the utility model also provides a mountain gorge area side slope exploration open cut tunnel construction method, it adopts the above-mentioned the mountain gorge area side slope exploration open cut tunnel arrangement structure, include following step:
step one, selecting a slag hole: through field investigation, a slag hole is respectively selected for each layer of exploration adit, and the slag holes of each layer of exploration adit are ensured to be staggered along the inclination direction of the side slope;
and step two, constructing a down-river flat tunnel: excavating construction is carried out towards the inside of the side slope from a slag hole determined by each layer of exploration flat tunnel, and after the excavation construction reaches the position of the river-following flat tunnel of the exploration flat tunnel of the corresponding layer, the excavation construction of the river-following flat tunnel is carried out;
thirdly, constructing the horizontal river flat tunnel: when the excavating construction of the down-the-river open cut is carried out to the position of the intersection of the down-the-river open cut and the corresponding cross-river open cut, the excavating construction of the cross-river open cut at the position is carried out;
and (4) deslagging the slag soil generated in the excavation construction process in the second step and the third step from the slag hole conveyed to the exploration hole of the corresponding layer of exploration hole in the corresponding layer of exploration hole.
Further, the method comprises the following steps: in the third step, in the exploration flat tunnel on the same layer, after the construction of the down-the-river flat tunnel is finished, the construction of the cross-river flat tunnel is carried out.
Further, the method comprises the following steps: and in the second step, the construction of exploration flat holes on different layers is carried out simultaneously.
The utility model has the advantages that: the utility model discloses an adopt the arrangement structure of the horizontal river open cut and the following river open cut that intercrossing communicates in every layer of exploration open cut, and set up a slag notch in every layer of exploration open cut, stagger the setting in the incline direction along the side slope with the slag notch of each layer of exploration open cut simultaneously, can avoid the mutual influence of slagging tap when each layer of exploration open cut is under construction like this on the one hand, can realize to the multilayer exploration open cut to be under construction simultaneously, improved the efficiency of construction, shortened the construction period and still avoided the potential safety hazard simultaneously; in addition, because each layer of exploration adit can be only provided with one slag hole, the quantity of the slag holes can be greatly reduced, the environmental pollution is reduced, the potential safety hazard is reduced, the workload of constructing ground surface roads is reduced, and the construction cost and the construction difficulty are reduced. In addition, because power station exploration itself need arrange multilayer cross river open cut, find out its geological conditions along with the exploration of river open cut, adopt arrangement structure and construction method, through rational layout, reasonable arrangement construction method, can realize simultaneously and be under construction to each layer exploration open cut, under the condition that the engineering volume does not increase, can greatly shorten construction period, improve the efficiency of construction.
Drawings
FIG. 1 is a schematic side-on-axis view of a slope surface;
FIG. 2 is a front view of a side slope;
FIG. 3 is a cross-sectional view of section A-A of FIG. 2;
FIG. 4, FIG. 5, and FIG. 6 are different exploration hole configurations corresponding to the cross-sectional view of section B-B of FIG. 3, respectively.
Labeled as: the device comprises a down-the-river cave 1, a cross-river cave 2, a slag hole 3, an auxiliary cave 4, a terrain line 5 and a river channel 6.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and the following detailed description.
As shown in fig. 1 to 6, the arrangement structure of the horizontal hole for side slope exploration in the alpine valley region of the present invention comprises at least one layer of exploration horizontal hole arranged in the side slope, each layer of exploration horizontal hole comprises a river-following horizontal hole 1 and a cross river horizontal hole 2, and the river-following horizontal hole 1 in the same layer of exploration horizontal hole is communicated with all the cross river horizontal holes 2 in the same layer; a slag hole 3 is arranged in each layer of exploration flat tunnel, and the slag holes 3 corresponding to each layer of exploration flat tunnel are staggered along the inclination direction of the side slope.
In the utility model, because the river-following flat tunnel 1 and the cross river flat tunnel 2 are in a cross communication relationship in the same exploration flat tunnel, as shown in the attached drawing; therefore, a plurality of cross-river flat holes 2 can be sequentially communicated through the down-river flat hole 1 in the same layer of exploration flat hole, and further, the excavated hole slag can be transported in the down-river flat hole 1 and the corresponding cross-river flat hole 2, so that the excavated hole slag of each hole in the same layer of exploration flat hole can be transported and collected to the same position of the slag hole 3 and then discharged; therefore, the condition that each horizontal river open cut 2 is respectively used as a slag hole on each layer of exploration open cut is avoided; the number of slag outlets on the side slope can be reduced, and the environmental pollution, potential safety hazards and the like are reduced. In addition, theoretically, only one slag hole 3 is arranged in each layer of exploration flat hole, and the slag discharge requirement of all hole slag in the layer of exploration flat hole can be met.
In addition, without loss of generality, referring to the attached drawings, the river-following horizontal tunnel 1 in the present invention means that the direction of the tunnel is approximately consistent with the direction of gullies at the bottom of the side slope or rivers, i.e. along the direction of the river course or along the direction of the gullies; the following called river-following direction is consistent with the trend of the river-following flat tunnel 1; the direction of the transverse river flat tunnel 2 is approximately vertical to the direction of the transverse river flat tunnel 1, one end of the transverse river flat tunnel 2 penetrates out of or approaches to the surface of the side slope, and the other end of the transverse river flat tunnel 2 penetrates into the side slope, namely the direction of the transverse river flat tunnel 2 is approximately the direction of penetrating into the side slope from the surface of the side slope; the following direction of the cross river is consistent with the direction of the cross river flat tunnel 2. Certainly, both the cross river cave 2 and the down river cave 1 are approximately positioned at the same horizontal elevation position and are mutually crossed and communicated; thus, the corresponding horizontal river open caves 2 can be communicated through the down river open caves 1, and the insides of the horizontal river open caves can be used as channels for transporting the cave slag.
In addition, according to the actual engineering requirement, when the length of the down-river adit 1 is longer, for example, reaches about 700m, one end of the corresponding cross-river adit 2 can be arranged to penetrate out from the surface of the side slope, so that the ventilation effect of the whole exploration adit can be ensured by means of the penetrating-out openings of the cross-river adit 2. Of course, when the length of the down-the-river bunghole 1 is short, for example, below 200m, one end of the corresponding cross-river bunghole 2 can be theoretically disposed close to the surface of the slope without being torn through.
Without loss of generality, the utility model discloses in every layer of exploration flat hole to the concrete quantity that sets up of following the river flat hole 1 and the horizontal river flat hole 2 all do not have the restriction, can set up according to actual exploration needs. Typically, at least one down-the-river bunghole 1 and a plurality of cross-river bungholes 2 may be provided, as shown with reference to fig. 4, in an arrangement in which one down-the-river bunghole 1 and three cross-river bungholes 2 are provided. When a plurality of the cross river tunnels 2 are arranged, the distance between two adjacent cross river tunnels 2 can be set according to the actual exploration requirement, and can be generally set to be about 50 m-200 m.
The function of the horizontal river open cut 2 in the utility model is mainly used for exploring the geological condition of the slope in the direction of the horizontal river; similarly, the utility model discloses in the following river open cut 1 then be in the side slope certain depth position set up one along the side slope in the same direction as the open cut of river direction to the geological conditions in the same direction as the river direction of the inside certain depth position department of side slope is surveyed in the realization. Therefore, the utility model discloses a set up simultaneously in the same direction as river open cut 1 and horizontal open cut 2, except that the aforesaid can be to the hole sediment in the same layer exploration open cut transport collect the back from the row sediment of same slag notch 3, still can further realize in the same direction as the geological prospecting on the equidirectional not such as river direction and the horizontal river direction in the side slope, and then improve the exploration effect.
More specifically, the utility model discloses in set up the setting of staggering along the incline direction of side slope of the slag notch 3 that each layer exploration adit corresponds, refer to and show in figure 1 or figure 2. Namely, when a plurality of layers of exploration flat holes are arranged, the slag hole openings of different layers of exploration flat holes are staggered in the inclination direction of the side slope, so that potential safety hazards caused by slag discharge of the upper layer of exploration flat hole on slag discharge of the lower exploration flat hole and other constructions are avoided; therefore, the construction of exploration flat holes on different layers can be realized simultaneously, and the construction period can be greatly shortened.
More specifically, for each layer of exploration adit, the corresponding tapping holes 3 can adopt various arrangements as follows: one of the cross river tunnels 2 in the layer can be directly adopted to penetrate out of the opening of the side slope surface, as shown in the attached figure 4; or the down-the-river cave 1 in the layer can also be adopted to penetrate out of the opening of the side slope surface, as shown in the attached figure 5; or when all the cross-river open caves 2 in any layer of exploration open caves and the cave mouths of the down-river open caves 1 are inconvenient to construct earth surface roads to reach or excavation construction is inconvenient, an auxiliary cave 4 can be additionally arranged in the layer of exploration open caves, and after the auxiliary cave 4 is communicated with the down-river open caves 1, the auxiliary cave 4 penetrates out of the cave mouths of the side slope surfaces to serve as a slag discharging cave mouth 3 so as to facilitate slag discharging and construction, as shown in the attached figure 6. Of course, without loss of generality, the various slag hole 3 setting modes can be set according to actual construction environment conditions, and the slag hole 3 is set under the condition that earth surface roads are conveniently built or other convenient construction is considered as far as possible.
Additionally, mountain canyon region side slope exploration open cut tunnel construction method, adopt above-mentioned the mountain canyon region side slope exploration open cut tunnel arrangement structure to specifically include following step:
step one, selecting a slag hole 3: through field investigation, a slag hole 3 is respectively selected for each layer of exploration adit, and the slag holes 3 of each layer of exploration adit are ensured to be staggered along the inclination direction of the side slope;
and step two, constructing a down-river flat tunnel: excavating construction is carried out towards the inside of the side slope from a slag hole 3 determined by each layer of exploration flat tunnel, and after the excavation construction reaches the position 1 of the river-following flat tunnel of the corresponding layer of exploration flat tunnel, the excavation construction of the river-following flat tunnel is carried out;
thirdly, constructing the horizontal river flat tunnel: when the excavation construction of the down-the-river open cut 1 is carried out to the position of the intersection with the corresponding cross-river open cut 2, the excavation construction of the cross-river open cut 2 at the position is carried out;
and (4) deslagging the slag soil generated in the excavation construction process in the second step and the third step from the slag hole 3 conveyed to the exploration hole in the corresponding layer in the exploration hole.
After the construction site is investigated in the step one, selecting corresponding slag hole openings 3 for each layer of exploration adit at positions convenient for constructing a ground surface road or excavating construction according to actual conditions, and ensuring that the slag hole openings 3 corresponding to each layer of exploration adit are arranged in a staggered manner along the inclined direction of the side slope; and then carrying out subsequent exploration flat tunnel excavation construction. Of course, when the arrangement position of the exploration open cut tunnel is designed, the exploration open cut tunnel is corresponding to the slope rock mass needing to be explored in geological conditions, for example, the down-the-river open cut tunnel 1 is approximately arranged near the foundation plane of a hydropower station dam needing to be built so as to be used for exploring the geological conditions of the corresponding foundation rock mass; meanwhile, the device is correspondingly arranged on each horizontal river flat tunnel 2 communicated with the down-the-river flat tunnel 1.
After the positions of the slag holes 3 of the exploration flat holes on each layer are determined, excavation construction can be carried out on the exploration flat holes on each layer from the slag holes 3. Specifically, for each layer of exploration flat tunnel, the slag hole 3 is firstly excavated into the side slope to the position of the river-following flat tunnel 1, then the river-following flat tunnel 1 is excavated, and the excavation work of the corresponding river-following flat tunnel 2 can be carried out after the river-following flat tunnel 1 is excavated to the position communicated with the corresponding river-following flat tunnel 2. And in the excavation process of the exploration flat tunnel on the same layer, all the generated tunnel slag is firstly transported to the corresponding slag outlet 3 in the tunnel slag outlet for slag discharge. More specifically, the excavation sequence of each layer of exploration open cut is different according to the different arrangement modes of the slag hole openings 3; referring to the arrangement shown in fig. 4 to 6, the excavation sequence can be performed along the direction of the arrows shown in fig. 4 to 6 for different selected positions of the slag hole 3, and the corresponding conveying direction of the hole slag inside the hole slag is opposite to the direction of the arrows in the drawings. For example, taking the example shown in fig. 4, the slag hole 3 is excavated into the side slope from the position, when the slag hole is excavated to the position connected with the down-the-river adit 1, the slag hole can be continuously excavated towards both ends along the direction of the down-the-river adit 1, when the slag hole is excavated to the position connected with a certain cross-river adit 2 along the direction of the down-the-river adit 1, the cross-river adit 2 is excavated, and in order to ensure that the ventilation effect of the whole-layer exploration adit is good, one end of the cross-river adit 2 can be directly penetrated from the surface of the side slope to form the hole, thereby facilitating ventilation.
Additionally, because the utility model discloses in set up the slag notch 3 of each layer exploration concora crush into the setting of staggering of the incline direction along the side slope, can avoid the influence of different layers exploration concora crush excavation construction like this, consequently in the above-mentioned step two of construction method, can carry out the construction of different layers exploration concora crush simultaneously. The hole slag of each layer of exploration flat hole is transported out from different positions in the inclination direction of the side slope, so that the influence of the slag discharge of the upper layer of exploration flat hole on the slag discharge of the lower layer of exploration flat hole and other constructions is avoided, the construction efficiency can be further improved, and the construction period is shortened.
More specifically, in the third step of the construction method, if the down-the-river adit 1 is short, the ventilation effect of the whole exploration adit can be ensured, so that theoretically, the down-the-river adit 2 can be excavated and constructed in the same layer of exploration adit 1 after the construction of the down-the-river adit 1 is completed; or the excavation construction of the horizontal river flat tunnel 2 and the further excavation construction of the horizontal river flat tunnel 1 can be simultaneously carried out after the horizontal river flat tunnel 1 is excavated to the position communicated with the corresponding horizontal river flat tunnel 2 along the direction.

Claims (6)

1. Mountain canyon region side slope exploration open cut tunnel arrangement structure, its characterized in that: the horizontal tunnel comprises at least one layer of exploration horizontal tunnel arranged in a side slope, each layer of exploration horizontal tunnel comprises a down-the-river horizontal tunnel (1) and a cross-river horizontal tunnel (2), and the down-the-river horizontal tunnel (1) in the same layer of exploration horizontal tunnel is communicated with all the cross-river horizontal tunnels (2) in the same layer; a slag hole (3) is arranged in each layer of exploration flat tunnel, and the slag holes (3) corresponding to each layer of exploration flat tunnel are staggered along the inclination direction of the side slope.
2. The arrangement structure of the horizontal hole for slope exploration in the high mountain canyon region as claimed in claim 1, wherein: each exploration flat hole comprises a down-the-river flat hole (1) and a plurality of cross-river flat holes (2).
3. The arrangement structure of the horizontal hole for slope exploration in the high mountain canyon region as claimed in claim 1 or 2, wherein: the trend of the down-the-river open tunnel (1) is consistent with the trend of gullies or rivers at the bottom of the side slope, and the trend of the cross-river open tunnel (2) is vertical to the trend of the down-the-river open tunnel (1); one end of the horizontal river flat tunnel (2) penetrates out of or approaches to the surface of the side slope, and the other end of the horizontal river flat tunnel (2) penetrates into the side slope.
4. The arrangement structure of the horizontal hole for slope exploration in the high mountain canyon region as claimed in claim 3, wherein: the slag hole (3) is formed after one of the horizontal river open tunnels (2) in the exploration open tunnels of the corresponding layer penetrates out of the surface of the side slope.
5. The arrangement structure of the horizontal hole for slope exploration in the high mountain canyon region as claimed in claim 3, wherein: the slag hole (3) is formed after one end of the down-the-river open tunnel (1) in the exploration open tunnel of the corresponding layer penetrates out of the surface of the side slope.
6. The arrangement structure of the horizontal hole for slope exploration in the high mountain canyon region as claimed in claim 3, wherein: an auxiliary hole (4) is arranged in any layer of exploration flat hole, one end of the auxiliary hole (4) is communicated with the river-following flat hole (1) in the exploration flat hole of the corresponding layer, the other end of the auxiliary hole (4) penetrates out of the surface of the side slope, and a slag hole (3) of the exploration flat hole of the layer is a hole formed after one end of the corresponding auxiliary hole (4) penetrates out of the surface of the side slope.
CN201821581006.2U 2018-09-27 2018-09-27 High mountain gorge area side slope exploration open cut tunnel arrangement structure Active CN213142996U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821581006.2U CN213142996U (en) 2018-09-27 2018-09-27 High mountain gorge area side slope exploration open cut tunnel arrangement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821581006.2U CN213142996U (en) 2018-09-27 2018-09-27 High mountain gorge area side slope exploration open cut tunnel arrangement structure

Publications (1)

Publication Number Publication Date
CN213142996U true CN213142996U (en) 2021-05-07

Family

ID=75707580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821581006.2U Active CN213142996U (en) 2018-09-27 2018-09-27 High mountain gorge area side slope exploration open cut tunnel arrangement structure

Country Status (1)

Country Link
CN (1) CN213142996U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056671A (en) * 2018-09-27 2018-12-21 中国电建集团成都勘测设计研究院有限公司 High-mountain gorge areas side slope explores adit arragement construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056671A (en) * 2018-09-27 2018-12-21 中国电建集团成都勘测设计研究院有限公司 High-mountain gorge areas side slope explores adit arragement construction
CN109056671B (en) * 2018-09-27 2023-11-21 中国电建集团成都勘测设计研究院有限公司 High mountain gorge valley area side slope exploration open hole arrangement structure

Similar Documents

Publication Publication Date Title
CN107869349A (en) A kind of mechanized mining method of gently inclined medium thick orebody
CN106223958A (en) The slant middle thick orebody subregion rock drilling stage ore deposit afterwards filling that falls works in coordination with mining codes
CN101509377B (en) High-dipping ore block house column mining method
CN1052525C (en) Open-air high-step mining method
CN106869936A (en) It is a kind of to be suitable to the surface mining new method of steep slope topography
CN110578468B (en) Engineering geology exploration method adopting horizontal directional drilling
AU2018378009B2 (en) Mine field layout method suitable for fluidized mining of coal resources
CA3050034C (en) Automatic coal mining machine and fluidized coal mining method
CN103470263A (en) New-level development method for open-pit metal mine
CN115879333A (en) Method for arranging geological exploration drill holes of linear directional drill
CN105527452A (en) Isotope-labeled method for measuring pressure bearing water quantity of water-intercepted bottom plate
CN213142996U (en) High mountain gorge area side slope exploration open cut tunnel arrangement structure
CN210774240U (en) Multilayer underground water level monitoring structure for soft structural surface in rock stratum
CN109056671B (en) High mountain gorge valley area side slope exploration open hole arrangement structure
CN110644993B (en) Z-shaped strip working face mining method
US3348482A (en) Excavating apparatus and method for excavating materials
CN106703809A (en) Method for forming cover layer through induced falling of open-pit-to-underground multi-branched orebody
CN106245621A (en) A kind of electric osmose inverted well construction method
CN111364994B (en) Fully-mechanized mining-to-filling continuous propulsion collaborative mining method
CN205858367U (en) The push plate device of tunnel excavation machine
CN112796760A (en) Strip mine non-stripping mining method, device and system using side slope coal mining machine
CN212927864U (en) Slag discharging system of heading machine
CN214091883U (en) Improved three-mountain-climbing advanced shield structure for mining area
CN110159271B (en) Arch-shaped ground exploration open-hole tunneling method based on small TBM (tunnel boring machine)
CN104131574A (en) Step water lowering method of phreatic water fully-penetrating well inclined shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant