CN213115837U - Temporary fence for municipal road construction - Google Patents
Temporary fence for municipal road construction Download PDFInfo
- Publication number
- CN213115837U CN213115837U CN202020769318.7U CN202020769318U CN213115837U CN 213115837 U CN213115837 U CN 213115837U CN 202020769318 U CN202020769318 U CN 202020769318U CN 213115837 U CN213115837 U CN 213115837U
- Authority
- CN
- China
- Prior art keywords
- baffle
- rod
- temporary fence
- road construction
- fixing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model belongs to the technical field of auxiliary equipment for construction, in particular to a temporary fence for municipal road construction, aiming at the problem that the prior metal plate used as the temporary fence is inconvenient to disassemble and assemble and has relatively poor fixing effect, the scheme is proposed, which comprises three bases, a first baffle, a second baffle and a third baffle are respectively arranged at the top of the three bases, a first transverse rod, a second transverse rod and a third transverse rod are respectively arranged at the side surfaces of the first baffle, the second baffle and the third baffle, one end of the second transverse rod and the first transverse rod are jointly and rotatably provided with the same first connecting rod, the other end of the second transverse rod and the third transverse rod are jointly and rotatably provided with the same second connecting rod, the whole temporary fence is convenient to disassemble and assemble through the matching of structures such as the first connecting rod, and the matching of the limiting rod and the telescopic rod can ensure that the temporary fence has better fixing effect, and the whole using process needs less operation and is convenient to use.
Description
Technical Field
The utility model relates to an auxiliary assembly technical field is used in the construction, especially relates to a temporary fence is used in town road construction.
Background
When the road need be maintained and be under construction, often can use interim rail, through setting up interim rail, can remind the vehicle of coming and going in time to dodge, can separate construction site, constructor and road simultaneously to do not influence the construction.
Current interim rail is ordinary promptly for ordinary metal sheet usually, and the metal sheet needs arrange as required earlier, and reuse iron wire etc. is fixed the metal sheet afterwards, and this kind of fixed mode makes the fixed effect of metal sheet relatively poor, takes place to collapse easily and slope, and need twist off earlier the iron wire again when demolising and just can demolish the metal sheet, and consequently whole process complex operation and fixed effect are not good, consequently just need a neotype interim rail to solve this problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the inconvenient dismouting that carries out of the metal sheet that exists as interim rail among the prior art, and fixed effect relatively poor shortcoming, and the interim rail is used in town road construction that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a temporary fence for municipal road construction comprises three bases, wherein the tops of the three bases are respectively and fixedly provided with a first baffle, a second baffle and a third baffle, the side faces of the first baffle, the side faces of the second baffle and the side faces of the third baffle are respectively and fixedly provided with a first cross rod, a second cross rod and a third cross rod, one end of the second cross rod and the first cross rod are jointly and rotatably provided with the same first connecting rod, the other end of the second cross rod and the third cross rod are jointly and rotatably provided with the same second connecting rod, namely the first cross rod, the second cross rod and the third cross rod are sequentially connected, under the action of the first connecting rod and the second connecting rod, the first cross rod, the second cross rod and the third cross rod can rotate in two directions, namely the first baffle, the second baffle and the third baffle can be mutually unfolded, and the first baffle, the second baffle and the third baffle are respectively provided with a reflective coating.
Preferably, one side of the first baffle, which is far away from the first cross rod, is fixedly provided with two fixing plates, the two fixing plates are fixedly provided with the same first fixing rod, the first fixing rod is rotatably provided with a rotating block, and the two fixing plates are close to one end, which is far away from the second baffle, of the first baffle.
Preferably, a first sliding groove is formed in the rotating block, a second fixing rod is fixedly mounted in the first sliding groove, a limiting rod is rotatably mounted on the second fixing rod, namely the rotating block can rotate on the first fixing rod in the horizontal direction, and the limiting rod can rotate on the second fixing rod in the vertical direction.
Preferably, a through hole is formed in the limiting rod, the second fixing rod is rotatably installed in the through hole, a plurality of second sliding grooves are formed in the limiting rod, and the size of each second sliding groove is slightly larger than the width of the telescopic rod.
Preferably, one side fixed mounting who keeps away from the third horizontal pole of third baffle has the fixed block, and the fixed block is located the one end of keeping away from the second baffle of third baffle, rotates on the fixed block and installs the telescopic link, and the telescopic link cooperatees with the gag lever post, and the telescopic link can rotate in vertical direction, and can extend, and the telescopic link can be put into in the second spout.
The utility model discloses in, a temporary fence is used in town road construction, for making the dismouting of temporary fence more convenient, set up first connecting rod, second connecting rod isotructure, with first baffle, second baffle, third baffle interconnect, and the three can the rotation each other to according to the area size that the adjustment of construction area enclosed, whole temporary fence can accomplish the dismouting through launching each other and withdrawing.
The utility model discloses in, in order to make interim rail installation firm, the difficult slope collapse, set up telescopic link and gag lever post, telescopic link and gag lever post all can move about, work as the telescopic link card and advance the second spout on the gag lever post, then gag lever post and telescopic link block each other, first baffle and third baffle are also fixed thereupon simultaneously, whole interim rail is fixed promptly.
The utility model discloses in, through the cooperation of first connecting rod isotructure for the dismouting of being convenient for of whole interim rail, the cooperation of gag lever post and telescopic link makes interim rail can have better fixed effect simultaneously, and the operation that whole use needs is less, convenient to use.
Drawings
Fig. 1 is a schematic perspective view of a temporary fence for municipal road construction according to the present invention;
FIG. 2 is a schematic perspective view of a second baffle of the temporary fence for municipal road construction;
fig. 3 is the utility model provides a spatial structure schematic diagram of gag lever post isotructure in temporary fence is used in town road construction.
In the figure: the light-reflecting type LED lamp comprises a base 1, a first baffle 2, a second baffle 3, a third baffle 4, a first cross rod 5, a second cross rod 6, a third cross rod 7, a first connecting rod 8, a second connecting rod 9, a light-reflecting coating 10, a fixing plate 11, a first fixing rod 12, a rotating block 13, a first sliding groove 14, a second fixing rod 15, a limiting rod 16, a second sliding groove 17, a fixing block 18 and a telescopic rod 19.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Example one
Referring to fig. 1-3, a temporary fence for town road construction comprises three bases 1, wherein the tops of the three bases 1 are respectively fixedly provided with a first baffle 2, a second baffle 3 and a third baffle 4, the sides of the first baffle 2, the second baffle 3 and the third baffle 4 are respectively fixedly provided with a first cross bar 5, a second cross bar 6 and a third cross bar 7, one end of the second cross bar 6 and the first cross bar 5 are jointly and rotatably provided with a same first connecting rod 8, the other end of the second cross bar 6 and the third cross bar 7 are jointly and rotatably provided with a same second connecting rod 9, namely the first cross bar 5, the second cross bar 6 and the third cross bar 7 are sequentially connected, and under the action of the first connecting rod 8 and the second connecting rod 9, the first cross bar 5, the second cross bar 6 and the third cross bar 7 can rotate together, namely the first baffle 2, the second baffle 3 and the third baffle 4 can be mutually unfolded, only need expand first baffle 2, second baffle 3, third baffle 4 angle as required each other and can accomplish the installation as required during the use, also can withdraw the three each other and fold when demolising, all be equipped with reflective coating 10 on first baffle 2, second baffle 3, the third baffle 4, reflective coating 10 can play better warning effect to the vehicle of coming and going.
The utility model discloses in, one side fixed mounting who keeps away from first horizontal pole 5 of first baffle 2 has two fixed plates 11, and common fixed mounting has same first dead lever 12 on two fixed plates 11, rotates on the first dead lever 12 and installs turning block 13, and two fixed plates 11 are located the one end of keeping away from second baffle 3 of first baffle 2, are located the edge of first baffle 2 promptly.
The utility model discloses in, first spout 14 has been seted up on the turning block 13, fixed mounting has second dead lever 15 in the first spout 14, rotates on the second dead lever 15 and installs gag lever post 16, and turning block 13 can rotate with the horizontal direction on first dead lever 12 promptly, and gag lever post 16 can rotate with vertical direction on second dead lever 15, therefore gag lever post 16 for first baffle 2, both can the horizontal rotation, can vertical rotation again, the convenient adjustment of position.
The utility model discloses in, seted up the through-hole on the gag lever post 16, second dead lever 15 rotates and installs in the through-hole, has seted up several second spout 17 on the gag lever post 16, and second spout 17's size slightly is greater than the width of telescopic link 19.
The utility model discloses in, one side fixed mounting who keeps away from third horizontal pole 7 of third baffle 4 has fixed block 18, fixed block 18 is located the one end of keeping away from second baffle 3 of third baffle 4, it installs telescopic link 19 to rotate on the fixed block 18, telescopic link 19 cooperatees with gag lever post 16, fixed block 18 promptly and telescopic link 19 are located the edge of third baffle 4, thereby when making telescopic link 19 be connected with gag lever post 16, be located the edge of whole interim rail, can not obstruct the construction operation in the interim rail, telescopic link 19 can rotate in vertical direction, and can extend, telescopic link 19 can be put into in second spout 17.
Example two
Referring to fig. 1-3, a temporary fence for town road construction comprises three bases 1, a first baffle 2, a second baffle 3 and a third baffle 4 are welded on the top of each base 1, a first cross bar 5, a second cross bar 6 and a third cross bar 7 are welded on the side surfaces of each baffle 2, 3 and 4, one end of each cross bar 6 and the first cross bar 5 are rotatably provided with the same first connecting rod 8, the other end of each cross bar 6 and the third cross bar 7 are rotatably provided with the same second connecting rod 9, namely, the first cross bar 5, the second cross bar 6 and the third cross bar 7 are sequentially connected, and under the action of the first connecting rod 8 and the second connecting rod 9, the first cross bar 5, the second cross bar 6 and the third cross bar 7 can rotate by two, namely, the first baffle 2, the second baffle 3 and the third baffle 4 can be unfolded, only need expand first baffle 2, second baffle 3, third baffle 4 angle as required each other and can accomplish the installation as required during the use, also can withdraw the three each other and fold when demolising, all be equipped with reflective coating 10 on first baffle 2, second baffle 3, the third baffle 4, reflective coating 10 can play better warning effect to the vehicle of coming and going.
The utility model discloses in, the welding of one side of keeping away from first horizontal pole 5 of first baffle 2 has two fixed plates 11, and common welding has same first dead lever 12 on two fixed plates 11, rotates on the first dead lever 12 and installs turning block 13, and two fixed plates 11 are located the one end of keeping away from second baffle 3 of first baffle 2, are located the edge of first baffle 2 promptly.
The utility model discloses in, first spout 14 has been seted up on the turning block 13, the second dead lever 15 has been welded in the first spout 14, rotate on the second dead lever 15 and install gag lever post 16, turning block 13 can rotate with the horizontal direction on first dead lever 12 promptly, and gag lever post 16 can rotate with vertical direction on second dead lever 15, therefore gag lever post 16 for first baffle 2, both can the horizontal rotation, can vertical rotation again, the convenient adjustment of position.
The utility model discloses in, seted up the through-hole on the gag lever post 16, second dead lever 15 rotates and installs in the through-hole, has seted up several second spout 17 on the gag lever post 16, and second spout 17's size slightly is greater than the width of telescopic link 19.
In the utility model, a fixed block 18 is welded on one side of the third baffle 4 far from the third cross bar 7, the fixed block 18 is positioned at one end of the third baffle 4 far from the second baffle 3, a telescopic rod 19 is rotatably mounted on the fixed block 18, the telescopic rod 19 is matched with the limiting rod 16, namely, the fixed block 18 and the telescopic rod 19 are positioned at the edge of the third baffle 4, so that when the telescopic rod 19 is connected with the limiting rod 16, the fixed block is positioned at the edge of the whole temporary fence, the construction operation in the temporary fence can not be obstructed, the telescopic rod 19 can be rotated in the vertical direction and can be extended, the limiting rod 16 can be rotated to keep the mutually perpendicular state with the telescopic rod 19 as far as possible, then the telescopic rod 19 can be put into the second chute 17, and when the telescopic rod 19 is clamped into the second chute 17, because the telescopic rod 19 can only be rotated in the vertical direction, therefore, the telescopic rod 19 fixes the, while the first 2 and third 4 baffle plates are also fixed.
In the utility model, when in construction, the first baffle 2, the second baffle 3 and the third baffle 4 are mutually unfolded at a proper angle according to requirements, the base 1 makes the first baffle 2, the second baffle 3 and the third baffle 4 not easy to topple, then the limiting rod 16 is rotated, the limiting rod 16 is placed on the ground, then the limiting rod 16 is horizontally rotated to make the limiting rod 16 approach to be vertical to the telescopic rod 19, then the telescopic rod 19 is put down, the telescopic rod 19 is extended according to requirements, the extended telescopic rod 19 is put into the second chute 17, because the telescopic rod 19 can only rotate in the vertical direction, the telescopic rod 19 is clamped in the second chute 17, the limiting rod 16 and the telescopic rod 19 are mutually fixed, therefore, the first baffle 2 and the third baffle 4 are mutually fixed, the second baffle 3 clamped in the middle is fixed along with the first baffle, at this moment, the fixing effect of the whole temporary fence is better, and the temporary fence is not easy to incline and fall, and when the temporary fence needs to be dismantled, the steps are executed in the reverse order.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (5)
1. The utility model provides a temporary fence is used in town road construction, includes three base (1), and the top of three base (1) is fixed mounting respectively has first baffle (2), second baffle (3), third baffle (4), its characterized in that, the side of first baffle (2), second baffle (3), third baffle (4) is fixed mounting respectively has first horizontal pole (5), second horizontal pole (6), third horizontal pole (7), rotate jointly on the one end of second horizontal pole (6) and first horizontal pole (5) and install same first connecting rod (8), rotate jointly on the other end of second horizontal pole (6) and third horizontal pole (7) and install same second connecting rod (9), all be equipped with reflective coating (10) on first baffle (2), second baffle (3), third baffle (4).
2. The temporary fence for the municipal road construction according to claim 1, wherein two fixing plates (11) are fixedly mounted on one side of the first baffle (2) far away from the first cross rod (5), the two fixing plates (11) are fixedly mounted with a same first fixing rod (12), and the first fixing rod (12) is rotatably mounted with a rotating block (13).
3. The temporary fence for the municipal road construction according to claim 2, wherein the rotating block (13) is provided with a first chute (14), a second fixing rod (15) is fixedly installed in the first chute (14), and a limiting rod (16) is rotatably installed on the second fixing rod (15).
4. The temporary fence for the municipal road construction according to claim 3, wherein the limiting rod (16) is provided with a through hole, the second fixing rod (15) is rotatably mounted in the through hole, and the limiting rod (16) is provided with a plurality of second sliding grooves (17).
5. The temporary fence for the municipal road construction according to claim 1, wherein a fixing block (18) is fixedly mounted on one side of the third baffle (4) far away from the third cross rod (7), a telescopic rod (19) is rotatably mounted on the fixing block (18), and the telescopic rod (19) is matched with the limiting rod (16).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020769318.7U CN213115837U (en) | 2020-05-11 | 2020-05-11 | Temporary fence for municipal road construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020769318.7U CN213115837U (en) | 2020-05-11 | 2020-05-11 | Temporary fence for municipal road construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213115837U true CN213115837U (en) | 2021-05-04 |
Family
ID=75643389
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020769318.7U Expired - Fee Related CN213115837U (en) | 2020-05-11 | 2020-05-11 | Temporary fence for municipal road construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213115837U (en) |
-
2020
- 2020-05-11 CN CN202020769318.7U patent/CN213115837U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208363800U (en) | A kind of construction guard fender | |
CN213115837U (en) | Temporary fence for municipal road construction | |
CN212153070U (en) | Cross-road special-shaped steel structure overbridge | |
CN101654904B (en) | Installation method of angle sound barrier acoustic boards | |
CN208632965U (en) | A kind of superelevation steel pipe support adjustable-angle formula cable wind system | |
CN214463221U (en) | Municipal administration building rail | |
CN211341971U (en) | Protection canopy for building engineering | |
CN210195457U (en) | Safety protective guard is used in civil engineering | |
CN211079988U (en) | Indicating guideboard | |
CN210499945U (en) | Interim mounting fixture convenient to sun shade overhauls | |
CN221167452U (en) | Bridge bent cap movable support filler stone safety protection platform | |
CN210462929U (en) | Foldable street lamp built-in fitting | |
CN208294175U (en) | Pitching type three-dimensional parking equipment | |
CN214423261U (en) | Municipal works are with interim fence of just adorning | |
CN218581324U (en) | Protective fence for construction of constructional engineering | |
CN117211190A (en) | Bridge bent cap movable support filler stone safety protection platform | |
CN220868039U (en) | Equipment for rapidly arranging signboards on anti-collision wall | |
CN220540976U (en) | Lighting equipment | |
CN221861123U (en) | Angle adjusting device suitable for traffic signal lamp | |
CN114922506B (en) | Construction auxiliary assembly of power transmission and transformation engineering | |
CN212958014U (en) | Fender is enclosed to municipal administration turning cooperation type | |
CN214116358U (en) | Warning sign is used in highway construction | |
CN220889790U (en) | Building engineering security fence | |
CN220150077U (en) | Road seepage prevention structure | |
CN216474500U (en) | Combined bridge guardrail |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210504 |