CN213115482U - Template supporting system for shear walls on two sides of deformation joint - Google Patents

Template supporting system for shear walls on two sides of deformation joint Download PDF

Info

Publication number
CN213115482U
CN213115482U CN202021809260.0U CN202021809260U CN213115482U CN 213115482 U CN213115482 U CN 213115482U CN 202021809260 U CN202021809260 U CN 202021809260U CN 213115482 U CN213115482 U CN 213115482U
Authority
CN
China
Prior art keywords
bag
templates
sides
bags
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021809260.0U
Other languages
Chinese (zh)
Inventor
黄小龙
吕长利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN202021809260.0U priority Critical patent/CN213115482U/en
Application granted granted Critical
Publication of CN213115482U publication Critical patent/CN213115482U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a template support system for shear walls on two sides of a deformation joint, which comprises two outer templates positioned on the outer sides of two shear walls and two inner templates positioned on the inner sides of two shear walls, wherein at least two vertical inflatable elastic bags are arranged between the two inner templates along the length direction of the two inner templates; the bag extends vertically along the height direction of the inner side template and is arranged at the same height with the inner side template; the two outer side templates are reinforced by penetrating a plurality of opposite pull rod, and the adjacent bags are arranged at intervals to be staggered with the opposite pull rod. The utility model provides a shear force wall inner form board prop up and establish the problem of inefficiency, have the advantage that makes things convenient for the later stage to demolish, repeatedly usable has practiced thrift construction cycle greatly.

Description

Template supporting system for shear walls on two sides of deformation joint
Technical Field
The utility model relates to a formwork support technical field, concretely relates to formwork support system for movement joint both sides shear force wall.
Background
For the narrow space of the building concrete structure, such as the deformation joint in the double shear wall, because the space of the deformation joint is narrow, some template supporting pieces are required to be used for supporting when the shear wall is constructed, and therefore the width of the deformation joint is ensured. However, for the traditional formwork support piece, the batten or the foam material is mainly used for being clamped between the two inner side formworks, and the problem is that after concrete pouring of the shear wall is completed, self stress in the concrete curing process can generate expansion action on the side formwork, so that the side formwork is easy to expand, concrete overflows out of the side formwork and finally flows into a deformation joint. And under the two-way extrusion effect of both sides shear force wall, traditional flitch or extrusion molding cystosepiment are pressed from both sides tightly and are difficult for taking out, and foam or flitch occupy the space of movement joint, can influence the service function of follow-up movement joint.
Although, also there are some detachable strutting arrangement to place between two shear force walls among the prior art, provide the supporting role for the inboard template of shear force wall, follow-up dismantlement used repeatedly that also can realize strutting arrangement like this, chinese patent that publication number is CN106088581A discloses an adjustable template structure that building wall structure seam was pour and is used, solves the narrow and small template that causes in template supporting space and struts the difficulty and template and strut the technical problem that size precision is low, and technical scheme is: and an adjusting device is arranged between the two symmetrically arranged templates, and two ends of the adjusting device are respectively hinged with the two templates. The adjusting device comprises: the adjusting screw rod is a screw rod with reverse threads at two ends, the pair of mobile control plates are in threaded connection with two ends of the adjusting screw rod respectively, two ends of each mobile control plate are in hinged connection with the two supporting plates respectively, and the other ends of the two supporting plates are in hinged connection with the two templates respectively.
Although the adjusting device has a simple structure, the distance between the two templates is convenient and accurate to adjust, the two templates are mutually supported without other auxiliary supports, and the supporting and the dismounting are convenient. However, the wall height and the wall length of the shear wall are two to three meters long, and the width of the deformation joint is only about 200mm, so that the operation space is limited in the narrow space, workers cannot uniformly place the adjusting devices between the inner side forms of the two shear walls, and can only install and place the adjusting devices at the left side, the right side, the upper end and the lower end of the inner side form plates of the two shear walls.
SUMMERY OF THE UTILITY MODEL
To the not enough of above-mentioned prior art, the utility model aims to solve the technical problem that: the utility model provides a template braced system for movement joint both sides shear force wall has solved the problem that the shear force wall inside form board established inefficiency, has the advantage that makes things convenient for the later stage to demolish, and repeatedly usable has practiced thrift construction cycle greatly.
In order to solve the technical problem, the utility model discloses a following technical scheme:
a template supporting system for shear walls on two sides of a deformation joint comprises two outer side templates positioned on the outer sides of the two shear walls and two inner side templates positioned on the inner sides of the two shear walls, wherein at least two vertical inflatable elastic bags are arranged between the two inner side templates along the length direction of the two inner side templates; the bag extends vertically along the height direction of the inner side template and is arranged at the same height with the inner side template; the two outer side templates are reinforced by penetrating a plurality of opposite pull rod, and the adjacent bags are arranged at intervals to be staggered with the opposite pull rod.
In the concrete implementation of the utility model, firstly, the steel bars of the shear walls on the two sides of the bottom layer are bound, then the inner side and the outer side of the shear walls on the two sides of the deformation joint are erected, a plurality of wire drawing rods are transversely penetrated to limit and fix the two outer side templates, and the space between the two inner side templates is the designed width of the deformation joint; then put into the deformation joint of two inboard templates from top to bottom a plurality of bags in proper order, because be the shear force wall of bottom, the bottom of bag can directly fall on the structural plane, when the bag was in the deformation joint of middle floor, accessible adds at the bag top and establishes rings and wear to establish the bracing piece and set up on the template of both sides and provide the supporting role for the bag, a plurality of bags are placed side by side at interval and stagger with the diagonal draw pole, then open air charging system, air charging system can be car pump or air compressor machine etc. aerify to the pressure port of a plurality of bags, let the bag slightly extrude inboard template and make inboard template take place slight deformation, because the shear force wall is after concreting, the concrete extrusion stress in the shear force wall can extrude the bag and make the bag produce slight deformation, consequently aerify the deformation that is used for buffering the bag to the bag in sufficient. After the bag is filled to a saturated state, when the air pressure in the bag can resist the extrusion force of the inner side template of the shear wall to the bag and the deformation can be controlled within an error range, the air filling is stopped and the pressurizing opening is closed. The support of the two inner side templates is completed through the bag, and the contact part of the outer side wall of the bag and the two inner side templates is tightly attached to provide enough function for the inner side templates of the shear wall. Then carrying out concrete pouring on the shear walls on the two sides, curing and forming, observing the deformation of the bag in the concrete pouring and curing process of the shear walls, and ensuring that the smaller outer diameter of the bag in a compressed state is the designed seam width of a deformation seam through real-time inflation or deflation; and after the concrete curing of the shear wall is finished and the dismantling condition is met, the plurality of bags are deflated, then the bags are separated from the two inner side templates, and then the plurality of bags are lifted upwards to the position between the inner side templates of the shear walls on the two sides of the next layer of deformation joint to prepare for the inner side template support of the next layer of shear wall.
It should be noted that the split-lead screw in the scheme is a split bolt used in a conventional formwork support, a steel pipe and a batten are additionally arranged between the split bolt and the outer formwork, the construction mode is the same as that of the conventional construction mode, and the two outer formworks can be reinforced through the split bolt. The water bag can be supported in an inflation mode, water can be injected into the water bag to form the water bag, and the water pressure in the water bag is enough to bear the extrusion deformation of the two inner side templates of the shear walls on the two sides of the deformation joint.
The utility model discloses in, the bag can adopt high strength rubber materials to make, and the bag fills the deflection after the saturated condition little, through the cylindricality and with inboard template height bag, can effectively support the whole perpendicular face of two inboard templates of movement joint both sides shear force wall, replaced traditional flitch or cystosepiment to use, the phenomenon that takes place to rise the mould or explode the mould when avoiding the side form to pour, and the bag after the gassing can demolish fast, does not occupy the space of movement joint, has guaranteed the normal use function of movement joint. More importantly, this bag sets up along the vertical extension of the inboard template of shear force wall to stagger with the split bar pole of outside template, when carrying out the shear force wall formwork of next floor movement joint both sides, only need with the bag along the vertical direction of movement joint upwards hoist and mount alright, the dismantlement and the installation that need not relapse, it is faster than traditional construction method speed, repeatedly usable has practiced thrift construction cycle greatly.
The bag is made of rubber tire materials and is in an annular cylindrical shape, a steel keel vertically penetrates through the center of the bag along the height direction of the bag, the axis of the steel keel is overlapped with the axis of the bag, and the outer diameter of the steel keel is matched with the inner diameter of the inflated bag; the bottom end of the steel keel is provided with a supporting part for placing the bag, and the bag is placed on the supporting part.
Therefore, the bag is made of rubber tire material, the strength of the bag is high, the air pressure in the bag can resist the extrusion force of the inner template to the bag without damage, the deformation allowance of the bag after being filled to a saturated state is small, and the extrusion deformation amount of the bag by the inner template is in a controlled error range. Cylindrical pouches are more resistant to deformation than rectangular parallelepiped pouches. Because the bag mainly bears the extrusion force of the concrete in the shear wall to the two inner side templates, the gravity of the concrete and the internal extrusion stress generated by expansion in the curing process are large, in order to ensure the anti-extrusion capacity of the bag, the steel keel is penetrated in the bag, the axis of the steel keel is coincided with the axis of the bag, the anti-extrusion capacity of the bag is enhanced and the deformation of the bag is reduced by utilizing the steel keel, the bag is similar to the action of a hub in an automobile tire, and therefore the bag can be better supported effectively for the two inner side templates of the shear wall. The supporting part is formed outwards through the bottom end of the steel keel, so that the bag is directly placed on the supporting part of the steel keel, and the vertical supporting effect is provided for the bag.
Preferably, the steel keels are steel pipes, the adjacent bags are connected into a whole through a horizontal connecting rod, the top ends of the steel keels extend upwards and extend out of the bags to form connecting parts, and the left ends and the right ends of the connecting rods are fixedly connected with the connecting parts on the steel keels of the adjacent bags respectively.
Like this, the top of steel joist is formed with connecting portion, then connects through the connecting rod between each adjacent bag and form wholly, has not only improved the wholeness between each bag, makes each bag be in on same vertical plane all the time, when the shear force wall formwork of next floor movement joint both sides is carried out to needs moreover, has had the existence of connecting rod, can be directly with these each bag together along the direction of movement joint hoist upwards alright, reduced the number of times of hoist and mount.
As optimization, the connecting rod is a telescopic rod with adjustable length so as to adjust the distance between the adjacent bags; the telescopic rod comprises an inner tube and an outer tube, the inner tube is arranged in the outer tube in a penetrating mode and is in sliding fit with the outer tube, and two opposite ends of the inner tube and the outer tube are fixedly connected with the connecting parts on the steel keels of the adjacent bags respectively; the telescopic rod is characterized in that a plurality of locking holes are formed in the inner pipe at intervals along the length direction, a locking rod is arranged on the outer pipe in a penetrating mode, and the locking rod is arranged on the corresponding locking holes of the inner pipe in a penetrating mode to lock the length of the telescopic rod.
Like this, because the opposite wire rod that wears to establish between the outside template of shear force wall does not have exact fixed position, consequently probably need adjust the interval between two adjacent bags and stagger between the opposite wire rod, consequently the length through the connecting rod is adjustable, can be used for satisfying and stagger and set up with the position to the wire rod, it is adjustable simultaneously through the length of connecting rod, can support the adjustment that corresponds bag adaptability to the position department that the inboard template is weak, for example handing-over position department of controlling adjacent template in the inboard template is weak position department.
Preferably, the connecting part of the steel keel is welded with a hanging ring.
Like this, connect through the connecting rod and form wholly between with a plurality of bags, then utilize hoisting equipment hoist and mount rings can directly carry out hoist and mount in step to a plurality of bags, simplified the hoist and mount number of times. And when the bag was in between the movement joint of middle floor, the accessible wore through establishing horizontal bracing piece on rings, and the bracing piece both ends are taken on the template of both sides and are provided the supporting role for the bag.
To sum up, the beneficial effects of the utility model reside in that: through the cylindricality in this scheme and with the equal altitude bag of inboard template, can effectively support the whole perpendicular face of two inboard templates of movement joint both sides shear force wall, replaced traditional flitch or cystosepiment to use, take place to rise the mould or explode the phenomenon of mould when avoiding the side form to pour, and bag after the gassing can demolish fast, does not occupy the space of movement joint, has guaranteed the normal use function of movement joint. More importantly, this bag sets up along the vertical extension of the inboard template of shear force wall to stagger with the split bar pole of outside template, when carrying out the shear force wall formwork of next floor movement joint both sides, only need with the bag along the vertical direction of movement joint upwards hoist and mount alright, the dismantlement and the installation that need not relapse, it is faster than traditional construction method speed, repeatedly usable has practiced thrift construction cycle greatly.
Drawings
In order to make the objects, technical solutions and advantages of the present invention clearer, the present invention will be described in further detail with reference to the accompanying drawings, in which:
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is an overall schematic view of the middle bag and the connecting rod of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Reference numerals in the drawings of the specification include: the shear wall comprises a shear wall 1, a deformation joint 2, an inner side template 3, an outer side template 4, a bag 5, a steel keel 6, a connecting rod 7, a hanging ring 8, a split wire rod 9 and a bearing part 10.
In the present embodiment, as shown in fig. 1 and 2, fig. 1 is a top view of two shear walls, and includes two outer side formworks 4 located outside the two shear walls 1 and two inner side formworks 3 located inside the two shear walls 1, at least two vertical inflatable elastic bladders 5 are arranged between the two inner side formworks 3 along a length direction of the two inner side formworks, a pressure port of the bladder 5 is communicated with an inflation device, and the inflated bladders 5 are columnar to provide a supporting function for the two inner side formworks 3; the bag 5 vertically extends along the height direction of the inner side template 3 and is arranged at the same height with the inner side template 3; the two outer side templates are reinforced by penetrating a plurality of opposite tension rod 9, and the adjacent bags 5 are arranged at intervals to be staggered with the opposite tension rod 9.
In the concrete implementation of the utility model, firstly, the steel bars of the shear walls 1 at the two sides of the bottom layer are bound, then the inner side and the outer side of the shear walls at the two sides of the deformation joint 2 are erected, a plurality of counter-pull rods 9 are transversely penetrated to limit and fix the two outer side templates 4, and the distance between the two inner side templates 3 is the designed width of the deformation joint 2; then a plurality of bags 5 are sequentially placed between the deformation joints 2 of the two inner side templates 3 from top to bottom, the bottoms of the bags 5 can directly fall on the structural surface due to the shear wall at the bottom layer, when the bags 5 are positioned between the deformation joints 2 of the middle floors, the supporting function can be provided for the bag 5 by adding the hanging ring 8 on the top of the bag 5 and arranging the supporting rod to be lapped on the tops of the templates at two sides in a penetrating way, a plurality of bags 5 are arranged side by side at intervals and staggered with the opposite pull rod 9, then, the inflating device, which can be an automobile inflating pump or an air compressor, is opened to inflate the pressurizing ports of the plurality of bags 5, so that the bags slightly press the inner side template and slightly deform the inner side template, because the compression stress of the concrete in the shear wall 1 will compress the bladder 5 and slightly deform the bladder 5 after the shear wall 1 is poured with concrete, the bladder 5 is inflated sufficiently to cushion the deformation of the bladder 5. After the bag 5 is filled to a saturated state, when the air pressure in the bag 5 can resist the extrusion force of the template 3 on the inner side of the shear wall 1 to the bag 5 and can control the deformation amount within an error range, the air filling is stopped and the pressurizing port is closed. The two inner templates 3 are supported by the pocket 5, and the contact part of the outer side wall of the pocket 5 and the two inner templates 3 is tightly attached to provide enough function for the inner templates 3 of the shear wall 1. Then carrying out concrete pouring on the shear walls 1 on the two sides, curing and forming, observing the deformation of the bag 5 in the concrete pouring and curing process of the shear walls, and ensuring that the smaller outer diameter of the bag in a compressed state is the designed seam width of a deformation joint by real-time inflation or deflation; and (3) finishing the concrete curing of the shear wall 1, deflating the plurality of bags 5 after the dismantling condition is reached, then separating the bags 5 from the two inner side templates 3, and then lifting the plurality of bags 5 upwards to a position between the inner side templates 3 of the shear wall 1 at two sides of the next layer of deformation joint 2 to prepare for supporting the inner side template 3 of the next layer of shear wall 1. It should be noted that the split-lead screw 9 in the present scheme is a split bolt used in a conventional formwork support, a steel pipe and a batten are further padded between the split bolt and the outer formwork 4, the construction method is the same as that of the conventional construction method, and the two outer formworks are reinforced by the split bolt. The water bag can be supported in an inflation mode, water can be injected into the water bag to form the water bag, and the water pressure in the water bag is enough to bear the extrusion deformation of the two inner side templates of the shear walls on the two sides of the deformation joint.
The utility model discloses in, bag 5 can adopt high strength rubber material to make, and bag 5 fills the deflection after the saturated condition little, through cylindricality and with bag 5 such as inboard template 3 height, can effectively support the whole vertical plane of two inboard templates 3 of 2 both sides shear force walls 1 of movement joint, traditional flitch or cystosepiment have been replaced and have been used, the phenomenon that takes place to rise the mould or explode the mould when avoiding the side form to pour, and bag 5 after the gassing can demolish fast, do not occupy the space of movement joint 2, the normal use function of movement joint 2 has been guaranteed. More importantly, this bag 5 sets up along the vertical extension of the inboard template 3 of shear force wall 1 to stagger with the split bar pole of outside template 4, when carrying out the shear force wall 1 formwork of next floor movement joint 2 both sides, only need with bag 5 along the vertical direction of movement joint 2 upwards hoist and mount alright, need not repeated dismantlement and installation, it is faster than traditional construction method speed, repeatedly usable, practiced thrift construction cycle greatly.
In a specific embodiment, the bag 5 is made of rubber tire material and is in a circular cylindrical shape, a steel keel 6 vertically penetrates through the center position of the bag 5 along the height direction of the bag, the axis of the steel keel 6 is overlapped with the axis of the bag 5, and the outer diameter of the steel keel is matched with the inner diameter of the inflated bag; the bottom end of the steel keel 6 is provided with a supporting part 10 for placing the bag 5, and the bag 5 is placed on the supporting part 10.
Thus, the bladder 5 is made of rubber tire material, the strength of the bladder 5 is high, the air pressure in the bladder 5 can resist the extrusion force of the inner template 3 to the bladder 5 without damage, the deformation allowance of the bladder 5 after being filled to the saturated state is small, and the extrusion deformation amount of the bladder 5 by the inner template 3 is within the controlled error range. The cylindrical pouch 5 has a stronger resistance to deformation than the rectangular parallelepiped pouch 5. Because the bag 5 mainly bears the extrusion force of the concrete in the shear wall 1 to the two inner side templates 3, the gravity of the concrete and the internal extrusion stress generated by expansion in the curing process are large, in order to ensure the anti-extrusion capability of the bag 5, the steel keel 6 is arranged in the bag 5 in a penetrating way, the axis of the steel keel 6 is coincided with the axis of the bag 5, the anti-extrusion capability of the bag 5 is enhanced by the steel keel 6, the deformation of the bag 5 is reduced, the bag is similar to the effect of a hub in an automobile tire, and therefore the bag 5 can be ensured to better effectively support the two inner side templates 3 of the shear wall 1. The support 10 is formed outwardly from the bottom end of the steel keel 6 so that the bladder 5 rests directly on the support 10 of the steel keel 6 to provide vertical support for the bladder 5.
In a specific embodiment, the steel keels 6 are steel pipes, the adjacent bags 5 are connected into a whole through a horizontal connecting rod 7, the top ends of the steel keels 6 extend upwards and extend out of the bags 5 to form connecting parts, and the left end and the right end of each connecting rod 7 are fixedly connected with the connecting parts on the steel keels 6 of the adjacent bags 5.
Like this, steel joist 6's top is formed with connecting portion, then connects through connecting rod 7 between each adjacent bag 5 and form wholly, has not only improved the wholeness between each bag 5, makes each bag 5 be in on same vertical plane all the time, when the shear force wall 1 formwork of next floor movement joint 2 both sides is carried out to needs moreover, has had the existence of connecting rod 7, can be directly with these each bag 5 together along the direction of movement joint 2 hoist upwards alright, reduced the number of times of hoist and mount.
In a specific embodiment, the connecting rod 7 is a telescopic rod with adjustable length so as to adjust the distance between the adjacent bags 5; the telescopic rod comprises an inner tube and an outer tube, the inner tube is arranged in the outer tube in a penetrating mode and is in sliding fit with the outer tube, and two opposite ends of the inner tube and the outer tube are fixedly connected with the connecting parts on the steel keels 6 of the adjacent bags 5 respectively; the telescopic rod is characterized in that a plurality of locking holes are formed in the inner pipe at intervals along the length direction, a locking rod is arranged on the outer pipe in a penetrating mode, and the locking rod is arranged on the corresponding locking holes of the inner pipe in a penetrating mode to lock the length of the telescopic rod.
Like this, because the opposite wire rod that wears to establish between the outside template 4 of shear force wall 1 does not have exact fixed position, consequently probably need adjust the interval between two adjacent bags 5 come with stagger between the opposite wire rod, consequently the length through connecting rod 7 is adjustable, can be used for satisfying with stagger and set up to the position of opposite wire rod 9, simultaneously through the length of connecting rod 7 is adjustable, can support the position department that corresponds the adjustment of 5 adaptability of bag to the inboard template 3 is weak, for example handing-over position department of controlling adjacent template in the inboard template 3 is weak position department.
In the specific implementation process, a hanging ring 8 is further welded on the connecting part of the steel keel 6.
Like this, connect through connecting rod 7 and form wholly between with a plurality of bags 5, then utilize hoisting equipment hoist and mount rings 8 can directly carry out hoist and mount in step to a plurality of bags 5, simplified the hoist and mount number of times. Because the weight of the bag and the steel keel is relatively light, the hoisting equipment can be a common electric hoist in building construction. And when the bag 5 is in the movement joint 2 of middle floor, the horizontal bracing piece is worn to establish on rings 8 to the accessible, and the bracing piece both ends are taken on the template of both sides and are provided the supporting role for bag 5.
Finally, it is noted that the above-mentioned embodiments illustrate rather than limit the invention, and that, while the invention has been described with reference to preferred embodiments thereof, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (5)

1. The utility model provides a template braced system for movement joint both sides shear force wall, includes two outside templates that are located two shear force wall outsides and two inboard templates of two shear force wall inboards, its characterized in that: at least two vertical inflatable elastic bags are arranged between the two inner side templates along the length direction of the inner side templates, the pressurizing ports of the bags are communicated with an inflating device, and the inflated bags are columnar and provide a supporting effect for the two inner side templates; the bag extends vertically along the height direction of the inner side template and is arranged at the same height with the inner side template; the two outer side templates are reinforced by penetrating a plurality of opposite pull rod, and the adjacent bags are arranged at intervals to be staggered with the opposite pull rod.
2. The formwork support system for shear walls on two sides of a deformation joint according to claim 1, wherein: the bag is made of rubber tire materials and is in an annular cylindrical shape, a steel keel vertically penetrates through the center of the bag along the height direction of the bag, the axis of the steel keel is overlapped with the axis of the bag, and the outer diameter of the steel keel is matched with the inner diameter of the inflated bag; the bottom end of the steel keel is provided with a supporting part for placing the bag, and the bag is placed on the supporting part.
3. The formwork support system for shear walls on two sides of a deformation joint according to claim 2, wherein: the steel keel is a steel pipe, adjacent bags are connected into a whole through a horizontal connecting rod, the top end of the steel keel extends upwards and extends out of the bags to form a connecting part, and the left end and the right end of the connecting rod are fixedly connected with the connecting part on the steel keel of the adjacent bag respectively.
4. The formwork support system for shear walls on two sides of a deformation joint as claimed in claim 3, wherein: the connecting rod is a telescopic rod with adjustable length so as to adjust the distance between the adjacent bags; the telescopic rod comprises an inner tube and an outer tube, the inner tube is arranged in the outer tube in a penetrating mode and is in sliding fit with the outer tube, and two opposite ends of the inner tube and the outer tube are fixedly connected with the connecting parts on the steel keels of the adjacent bags respectively; the telescopic rod is characterized in that a plurality of locking holes are formed in the inner pipe at intervals along the length direction, a locking rod is arranged on the outer pipe in a penetrating mode, and the locking rod is arranged on the corresponding locking holes of the inner pipe in a penetrating mode to lock the length of the telescopic rod.
5. The formwork support system for shear walls on two sides of a deformation joint as claimed in claim 3, wherein: and a lifting ring is welded on the connecting part of the steel keel.
CN202021809260.0U 2020-08-26 2020-08-26 Template supporting system for shear walls on two sides of deformation joint Active CN213115482U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021809260.0U CN213115482U (en) 2020-08-26 2020-08-26 Template supporting system for shear walls on two sides of deformation joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021809260.0U CN213115482U (en) 2020-08-26 2020-08-26 Template supporting system for shear walls on two sides of deformation joint

Publications (1)

Publication Number Publication Date
CN213115482U true CN213115482U (en) 2021-05-04

Family

ID=75656363

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021809260.0U Active CN213115482U (en) 2020-08-26 2020-08-26 Template supporting system for shear walls on two sides of deformation joint

Country Status (1)

Country Link
CN (1) CN213115482U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115110765A (en) * 2022-06-27 2022-09-27 中国化学工程第四建设有限公司 Construction method and device for shear wall at deformation joint

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115110765A (en) * 2022-06-27 2022-09-27 中国化学工程第四建设有限公司 Construction method and device for shear wall at deformation joint
CN115110765B (en) * 2022-06-27 2024-06-21 中国化学工程第四建设有限公司 Construction method and device for shear wall at deformation joint

Similar Documents

Publication Publication Date Title
CN106863552B (en) Integral forming die for cement prefabricated member by direct extrusion vibration method and processing method thereof
CN111946055B (en) Construction method of shear walls on two sides of deformation joint
CN107419746B (en) Movable formwork system and construction method thereof
CN213115482U (en) Template supporting system for shear walls on two sides of deformation joint
CN204728724U (en) A kind of discharge mechanism for large-span steel
CN113216195A (en) Air bag type steel reinforcement framework construction system and construction method thereof
CN210458925U (en) Temporary support for bridge structural system conversion
CN215564505U (en) Device convenient to different intensity grade concrete are separated to beam column node
CN112092164A (en) Expansion mandrel for horizontal processing of electroceramic blank
CN115110765B (en) Construction method and device for shear wall at deformation joint
CN107471427A (en) A kind of construction method of prefabricated assembled cassette ceiling
CN207211196U (en) A kind of mobile formwork system
CN217998915U (en) On-spot erection equipment of concrete dado template
CN216109709U (en) Pneumatic compression type independent column variable-temperature fastening structure
CN211993468U (en) Special forming die of prefabricated bridge beam slab
CN202012083U (en) Inclined-plane movable end of steel support
CN210343360U (en) Air bag template for tunnel blind ditch construction
CN212582664U (en) Tubular pile crack reinforcing structure
CN208052212U (en) Pre-stress rail plate production mould
CN116044073B (en) Prestressed concrete composite floor slab and preparation process thereof
CN113802569A (en) Steel sleeve node for connecting inner support-enclosure structure of steel pipe
CN219101364U (en) Full-circle lining trolley
CN221160811U (en) Concrete placement compaction device
CN219637708U (en) Concrete column building detection device
CN216238601U (en) Simple bottom-containing steel pouring jacket template device for bridge engineering