CN213063600U CN202021901467.0U CN202021901467U CN213063600U CN 213063600 U CN213063600 U CN 213063600U CN 202021901467 U CN202021901467 U CN 202021901467U CN 213063600 U CN213063600 U CN 213063600U
Authority
CN
China
Prior art keywords
fagging
supporting plate
concrete
coal mine
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021901467.0U
Other languages
Chinese (zh)
Inventor
许晓峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021901467.0U priority Critical patent/CN213063600U/en
Application granted granted Critical
Publication of CN213063600U publication Critical patent/CN213063600U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a colliery tunnel tunnelling auxiliary support device, including first fagging and second fagging, the relative one end swing joint of first fagging and second fagging, the other end of first fagging and second fagging all is equipped with the connecting piece, the bottom surface of first fagging and second fagging just is close to connecting piece department and is equipped with hydraulic pressure vaulting pole subassembly. The utility model discloses in, after accomplishing the tunnel excavation, can accomplish preliminary supporting through first fagging and second fagging under the effect of hydraulic pressure vaulting pole subassembly, guarantee artifical support personnel's safety work, later can be connected grouting equipment and grout mouth, grout operation, the concrete can spill over through the overflow hole, be full of the clearance between first fagging and second fagging and the tunnel roof, and after the concrete solidifies, make concrete and tunnel constitute integratively, first fagging and second fagging have not only improved the structural strength of concrete simultaneously with the concrete combined action, improve supporting construction's adult intensity.

Description

Auxiliary supporting device for coal mine roadway excavation
Technical Field
The utility model relates to a supporting device field specifically is a colliery tunnelling auxiliary supporting device.
Background
In the coal mining process, a roadway needs to be developed, the roadway serves a whole mine, however, no matter which roadway is used, the roadway needs to be supported in the actual tunneling process, the existing roadway tunneling is generally performed by a tunneling machine, the supporting is performed manually, and due to the fact that the structure of a supporting device is complex, the construction period of manual supporting is long, and the supporting structure cannot be well attached to the roadway.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a colliery tunnel tunnelling auxiliary supporting device to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a colliery tunnel tunnelling auxiliary supporting device, includes first fagging and second fagging, the relative one end swing joint of first fagging and second fagging, the other end of first fagging and second fagging all is equipped with the connecting piece, the bottom surface of first fagging and second fagging just is close to connecting piece department and is equipped with hydraulic pressure vaulting pole subassembly, first fagging and second fagging are hollow structure, and the top surface of first fagging and second fagging corresponds hollow structure department and evenly is equipped with a plurality of overflow hole, the bottom surface of first fagging and second fagging just is close to swing joint department and is equipped with the grout mouth.
Furthermore, the middle parts of the bottom surfaces of the first supporting plate and the second supporting plate are connected through a push rod, and a hydraulic cylinder is arranged on the push rod.
Furthermore, the top surfaces of the first supporting plate and the second supporting plate are provided with sealing strips close to the connecting piece.
Further, first fagging and second fagging are convex structure, and first fagging and second fagging are the steel material.
Furthermore, the hydraulic support rod assembly comprises a rod body and a jack, and the rod body is located at the top end of the jack.
Further, the first supporting plate and the second supporting plate are connected through fixing pins.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses in, after accomplishing the tunnel excavation, can accomplish preliminary supporting through first fagging and second fagging under the effect of hydraulic pressure vaulting pole subassembly, guarantee artifical support personnel's safety work, later can be connected grouting equipment and grout mouth, grout operation, the concrete can spill over through the overflow hole, be full of the clearance between first fagging and second fagging and the tunnel roof, and after the concrete solidifies, make concrete and tunnel constitute integratively, first fagging and second fagging have not only improved the structural strength of concrete simultaneously with the concrete combined action, improve supporting construction's adult intensity.
Drawings
FIG. 1 is a schematic structural view of an auxiliary supporting device for coal mine roadway excavation;
FIG. 2 is a top view of an auxiliary support device for coal mine roadway excavation;
fig. 3 is a partially enlarged view of a portion a in fig. 1.
In the figure: 1. a first supporting plate; 2. a second supporting plate; 3. a connecting member; 4. a hydraulic strut assembly; 41. a rod body; 42. a jack; 5. an overflow aperture; 6. grouting ports; 7. a top rod; 8. a hydraulic cylinder; 9. a sealing strip; 10. and fixing the pin.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution:
the utility model provides a colliery tunnel tunnelling auxiliary support device, including first fagging 1 and second fagging 2, the relative one end swing joint of first fagging 1 and second fagging 2, the other end of first fagging 1 and second fagging 2 all is equipped with connecting piece 3, the bottom surface of first fagging 1 and second fagging 2 just is close to connecting piece 3 department and is equipped with hydraulic pressure vaulting pole subassembly 4, first fagging 1 and second fagging 2 are hollow structure, and the top surface of first fagging 1 and second fagging 2 corresponds hollow structure department and evenly is equipped with a plurality of overflow hole 5, the bottom surface of first fagging 1 and second fagging 2 just is close to swing joint department and is equipped with grout mouth 6.
In this scheme, after accomplishing the tunnel excavation, can accomplish preliminary supporting through first fagging 1 and second fagging 2 under hydraulic pressure vaulting pole subassembly 4's effect, guarantee artifical support personnel's safety work, later can be connected grouting equipment and grout mouth 6, grout the operation, the concrete can spill over through overflow hole 5, it is full of the clearance between first fagging 1 and second fagging 2 and the tunnel roof, and after the concrete solidifies, make concrete and tunnel constitute integratively, first fagging 1 and second fagging 2 have not only improved the structural strength of concrete simultaneously with the concrete combined action, improve supporting construction's adult intensity.
Wherein, connect through ejector pin 7 between the bottom surface middle part of first fagging 1 and second fagging 2, and be equipped with pneumatic cylinder 8 on the ejector pin 7, through the cooperation of pneumatic cylinder 8 with ejector pin 7 for closely laminate between the roof in first fagging 1 and second fagging 2 and tunnel.
The top surface of first fagging 1 and second fagging 2 just is close to 3 departments of connecting piece and is equipped with sealing strip 9, and sealing strip 9 can adopt to have elastic rubber material for can prevent the concrete when sealing strip 9 can laminate with the tunnel wall and spill over.
First fagging 1 and second fagging 2 are convex structure, and first fagging 1 and second fagging 2 are steel, constitute that domes have stronger bearing capacity, and the resistance to compression effect is better, and steel plays similar steel reinforcement frame's effect.
Hydraulic pressure vaulting pole subassembly 4 includes the body of rod 41 and jack 42, and the body of rod 41 is located jack 42's top, through jack 42 with the body of rod 41, first fagging 1 and the jack-up of second fagging 2 for the top surface and the roof laminating of first fagging 1 and second fagging 2.
First fagging 1 and second fagging 2 are connected through fixed pin 10 round pin, and connection structure is simple, and first fagging 1 and second fagging 2 can open and shut through fixed pin 10, and the installation and the transportation of first fagging 1 and second fagging 2 of being convenient for also reduce the setting of middle support post for tunnel inner space is bigger more succinct.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a colliery tunnel tunnelling auxiliary support device, includes first fagging (1) and second fagging (2), its characterized in that: first fagging (1) and the relative one end swing joint of second fagging (2), the other end of first fagging (1) and second fagging (2) all is equipped with connecting piece (3), the bottom surface of first fagging (1) and second fagging (2) just is close to connecting piece (3) department and is equipped with hydraulic pressure vaulting pole subassembly (4), first fagging (1) and second fagging (2) are hollow structure, and the top surface of first fagging (1) and second fagging (2) corresponds hollow structure department and evenly is equipped with a plurality of overflow hole (5), the bottom surface of first fagging (1) and second fagging (2) just is close to the swing joint department and is equipped with grout mouth (6).
2. The auxiliary support device for coal mine roadway excavation according to claim 1, characterized in that: the middle parts of the bottom surfaces of the first supporting plate (1) and the second supporting plate (2) are connected through a push rod (7), and a hydraulic cylinder (8) is arranged on the push rod (7).
3. The auxiliary support device for coal mine roadway excavation according to claim 2, characterized in that: and sealing strips (9) are arranged on the top surfaces of the first supporting plate (1) and the second supporting plate (2) and close to the connecting piece (3).
4. The auxiliary support device for coal mine roadway excavation according to claim 3, characterized in that: the first supporting plate (1) and the second supporting plate (2) are of circular arc structures, and the first supporting plate (1) and the second supporting plate (2) are made of steel.
5. The auxiliary support device for coal mine roadway excavation according to claim 1, characterized in that: the hydraulic support rod assembly (4) comprises a rod body (41) and a jack (42), wherein the rod body (41) is located at the top end of the jack (42).
6. The auxiliary support device for coal mine roadway excavation according to claim 1, characterized in that: the first supporting plate (1) and the second supporting plate (2) are connected through a fixing pin (10) in a pin joint mode.
CN202021901467.0U 2020-09-03 2020-09-03 Auxiliary supporting device for coal mine roadway excavation Expired - Fee Related CN213063600U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021901467.0U CN213063600U (en) 2020-09-03 2020-09-03 Auxiliary supporting device for coal mine roadway excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021901467.0U CN213063600U (en) 2020-09-03 2020-09-03 Auxiliary supporting device for coal mine roadway excavation

Publications (1)

Publication Number Publication Date
CN213063600U true CN213063600U (en) 2021-04-27

Family

ID=75557974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021901467.0U Expired - Fee Related CN213063600U (en) 2020-09-03 2020-09-03 Auxiliary supporting device for coal mine roadway excavation

Country Status (1)

Country Link
CN (1) CN213063600U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914901A (en) * 2021-11-11 2022-01-11 中国铁建大桥工程局集团有限公司 Tunnel supporting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914901A (en) * 2021-11-11 2022-01-11 中国铁建大桥工程局集团有限公司 Tunnel supporting structure
CN113914901B (en) * 2021-11-11 2024-04-09 中国铁建大桥工程局集团有限公司 Tunnel supporting structure

Similar Documents

Publication Publication Date Title
CN209510325U (en) A kind of drill+blast tunnel structure using prefabrication and assembly construction inverted arch
CN213063600U (en) Auxiliary supporting device for coal mine roadway excavation
CN104947714A (en) End sealing door structure for immersed tube tunnel
CN101570973B (en) Internal-bonded water-proof technique for externally-bonded waterstop
CN204738309U (en) Immersed tube tunnel is with holding structure of sealing up a door
CN217841695U (en) Bridge tunnel reinforcing apparatus
CN211646295U (en) Hydraulic tunnel carbon cloth reinforced structure
CN214462562U (en) Beam reinforcing and mold hanging device
CN211873355U (en) Steel structure beam column
CN110130957B (en) Mine underground pneumatic anchor rod charging device
CN211080251U (en) Structure for replacing support by utilizing structural bottom plate when diaphragm wall is used for separating enclosure
CN212614746U (en) Roadway safety support mechanism
CN211038098U (en) Road and bridge beam pile reinforcing device
CN113026678B (en) But take automatic tensioning function's reuse colliery underground reservoir dam body
CN2908784Y (en) Automatic unloading support device for expansion soft rock tunnel
CN215145910U (en) Hydraulic engineering gate overhauls uses reinforced structure
CN220433910U (en) Reinforcing structure for steel structure joint
CN217536733U (en) Town road bridge crack reinforced structure
CN213953351U (en) Prefabricated windowsill of assembly type structure
CN216741612U (en) Filling mining device based on fully mechanized mining support
CN209742239U (en) ridge assembly of assembled building roof
CN219364573U (en) Underground diaphragm wall steel reinforcement cage structure
CN217400917U (en) Polymer composite plug plate lower die
CN213508033U (en) Public road bridge roof beam expansion joint device
CN211849264U (en) Metal flood control gate for urban flood control

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210427

Termination date: 20210903