CN213025275U - Engineering progress display device for building engineering management - Google Patents

Engineering progress display device for building engineering management Download PDF

Info

Publication number
CN213025275U
CN213025275U CN202021794958.XU CN202021794958U CN213025275U CN 213025275 U CN213025275 U CN 213025275U CN 202021794958 U CN202021794958 U CN 202021794958U CN 213025275 U CN213025275 U CN 213025275U
Authority
CN
China
Prior art keywords
fixed
display device
bottom plate
show board
progress display
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021794958.XU
Other languages
Chinese (zh)
Inventor
曹松平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021794958.XU priority Critical patent/CN213025275U/en
Application granted granted Critical
Publication of CN213025275U publication Critical patent/CN213025275U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Devices For Indicating Variable Information By Combining Individual Elements (AREA)

Abstract

The utility model discloses an engineering progress display device for building engineering management, which comprises a bottom plate, wherein a bracket is fixed on the edge of the upper surface of the bottom plate, a first display plate is fixed at the top end of the bracket, an installation block is fixed on the side surface of the first display plate, a rotating column is arranged on the inner side of the installation block, a second display plate is fixed on one side wall of the rotating column, a fixed block is arranged at the top end of the second display plate, and a limiting rod is arranged on the inner side of the fixed block in a sliding manner; through being provided with installation piece, rotation post, second show board, gag lever post, spacing ring piece and spring, be convenient for avoid inconvenient to show board area adjustment, lead to show board area too big or undersize, influence the result of use, through being provided with storage sand jar, seal baffle and spliced pole, be convenient for avoid inconvenient to bottom plate weight adjustment, under the great environment of wind-force, the show board takes place to incline and emptys.

Description

Engineering progress display device for building engineering management
Technical Field
The utility model belongs to the technical field of the engineering progress show, concretely relates to engineering progress display device for building engineering management.
Background
The building engineering refers to an engineering entity formed by the construction of various building buildings and auxiliary facilities thereof and the installation activities of lines, pipelines and equipment matched with the building buildings, so that workers can better know the progress degree of the engineering for the convenience of management, and the progress of the engineering is generally shown by a display board.
The engineering progress display device for the building engineering management is in the use, and the show area of show board is generally when fixed, and when show board area is less, it is inconvenient to the show of more show content, when show board area is great, will cause the outside space that occupies great, and the not convenient to use person adjusts the show area according to the in service behavior, and in strong wind weather, the inconvenient adjustment of bottom plate weight probably causes the show board to incline and empty, for this we propose an engineering progress display device for the building engineering management.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an engineering progress display device for building engineering management, in order to solve and to propose current engineering progress display device for building engineering management in the above-mentioned background art in the use, the show area of show board is generally when fixed, when show board area is less, show inconvenience to more show content, when show board area is great, the exterior space that will cause to occupy is great, the person of not being convenient for adjusts the show area according to the in service behavior, in addition at strong wind weather, the inconvenient adjustment of bottom plate weight, probably cause the crooked problem of empting of show board.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an engineering progress display device for building engineering management, includes the bottom plate, bottom plate upper surface edge is fixed with the support, the support top is fixed with first show board, first show board side surface is fixed with the installation piece, the installation piece inboard is provided with rotates the post, it is fixed with second show board to rotate a post lateral wall, second show board top is provided with the fixed block, the inboard slip of fixed block is provided with the gag lever post, gag lever post outside cover is equipped with the spring, installation piece top is provided with the spacing ring piece, the gag lever post cooperates through the spacing ring piece with the installation piece and is connected, bottom plate upper surface middle part is provided with counter weight mechanism.
Preferably, the counter weight mechanism is including storing up husky jar, seal baffle and spliced pole, it is fixed in the bottom plate upper surface to store up husky jar, store up husky jar upper end and seted up exit, it is fixed with the spliced pole to store up husky jar upper surface edge, the spliced pole outside is rotated the cover and is equipped with seal baffle.
Preferably, the sealing baffle is of a plate-shaped structure, and sealing rubber is arranged on the lower surface of the sealing baffle.
Preferably, the second display board is provided with two positions, and the two positions are symmetrically distributed along the center of the long edge of the first display board.
Preferably, a handle rod is fixed on the surface of one end of the limiting rod, and anti-skid grains are arranged on the outer side of the handle rod.
Preferably, the limiting rods are four, and the end parts of the limiting rods are provided with chamfers.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) through being provided with installation piece, rotation post, second show board, gag lever post, spacing ring piece and spring, be convenient for avoid inconvenient to show board area adjustment, lead to the show board area too big or undersize, influence the bandwagon effect, device convenient operation has improved the practicality.
(2) Through being provided with sand storage tank, seal baffle and spliced pole, be convenient for avoid inconvenient to bottom plate weight adjustment, under the great environment of wind-force, the show board takes place to incline and emptys, is convenient for improve the stability that the device placed.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic cross-sectional view at a in fig. 1 according to the present invention;
fig. 3 is a schematic cross-sectional view of the utility model at B in fig. 1;
in the figure: 1. a base plate; 2. a sand storage tank; 3. a first display board; 4. mounting blocks; 5. a second display board; 6. a support; 7. a limiting rod; 8. a fixed block; 9. a spring; 10. rotating the column; 11. sealing the baffle; 12. connecting columns; 13. a handle rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: an engineering progress display device for building engineering management comprises a bottom plate 1, a support 6 is fixed on the edge of the upper surface of the bottom plate 1, a first display plate 3 is fixed at the top end of the support 6, an installation block 4 is fixed on the side surface of the first display plate 3, a rotating column 10 is arranged on the inner side of the installation block 4, and is convenient for rotating and folding a second display plate 5, a second display plate 5 is fixed on one side wall of the rotating column 10, and is convenient for better display area, a fixed block 8 is arranged at the top end of the second display plate 5, a limiting rod 7 is arranged on the inner side of the fixed block 8 in a sliding manner, and is convenient for limiting the rotation between the second display plate 5 and the first display plate 3, a spring 9 is sleeved on the outer side of the limiting rod 7, and is convenient for pushing the limiting rod 7 to the inner side of the limiting ring block, a limiting ring block is arranged at the top end of the installation block 4, the limiting rod 7 is, the middle part of the upper surface of the bottom plate 1 is provided with a counterweight mechanism.
In this embodiment, preferably, counter weight mechanism is including storing up husky jar 2, seal baffle 11 and spliced pole 12, stores up husky jar 2 and is fixed in 1 upper surface of bottom plate, stores up husky jar 2 upper end and has seted up exit, stores up husky jar 2 upper surface edge and is fixed with spliced pole 12, and the spliced pole 12 outside is rotated the cover and is equipped with seal baffle 11, is convenient for adjust 1 counter weight of bottom plate, improves anti strong wind effect.
In this embodiment, preferably, the sealing baffle 11 is a plate-shaped structure, and sealing rubber is arranged on the lower surface of the sealing baffle 11, so that the upper inlet and the outlet of the sand storage tank 2 can be better sealed.
In this embodiment, preferably, the second display board 5 is provided with two positions, and the two second display boards 5 are symmetrically distributed along the center of the long side of the first display board 3, so as to facilitate a better display area.
In this embodiment, preferably, a handle rod 13 is fixed on the surface of one end of the limiting rod 7, and anti-slip threads are arranged on the outer side of the handle rod 13, so that the position of the limiting rod 7 can be better adjusted.
In this embodiment, preferably, four limiting rods 7 are provided to better limit the movement of the second display board 5, and the end portions of the limiting rods 7 are provided with chamfers.
The utility model discloses a theory of operation and use flow: when in use, the management contents are conveniently displayed through the second display board 5 and the first display board 3, when the second display board 5 is not used, the limiting rod 7 can be pulled to withdraw from the inner side of the limiting ring block, at this time, the second display board 5 and the mounting block 4 can rotate through the rotating column 10, so that the second display board 5 can be conveniently rotated to the rear surface of the first display board 3 to be attached to the first display board, the external space occupied by the second display board 5 is reduced, a user can conveniently adjust the display space according to the actual situation, the operation is simple and convenient, the sand storage tank 2 is convenient to adjust the weight of the sand grains stored in the inner side of the sand storage tank 2 according to the wind power condition of the placing place, thereby facilitating to improve the weight of the bottom plate 1, reducing the blow-down of the first display plate 3 caused by strong wind, improving the stability of the device placement, the sealing baffle plate 11 is convenient to rotate and open and close, and sand grains stored in the inner side of the sand storage tank 2 are easy to dump.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a construction progress display device for building engineering management, includes bottom plate (1), bottom plate (1) upper surface edge is fixed with support (6), support (6) top is fixed with first show board (3), its characterized in that: first show board (3) side surface is fixed with installation piece (4), installation piece (4) inboard is provided with rotates post (10), it is fixed with second show board (5) to rotate post (10) a lateral wall, second show board (5) top is provided with fixed block (8), fixed block (8) inboard is slided and is provided with gag lever post (7), gag lever post (7) outside cover is equipped with spring (9), installation piece (4) top is provided with the spacing ring piece, gag lever post (7) and installation piece (4) cooperate through the spacing ring piece to be connected, bottom plate (1) upper surface middle part is provided with counter weight mechanism.
2. The project progress display device for building project management according to claim 1, characterized in that: the counter weight mechanism is including storing up husky jar (2), seal baffle (11) and spliced pole (12), it is fixed in bottom plate (1) upper surface to store up husky jar (2), store up husky jar (2) upper end and seted up exit, it is fixed with spliced pole (12) to store up husky jar (2) upper surface edge, spliced pole (12) outside is rotated the cover and is equipped with seal baffle (11).
3. The project progress display device for building project management according to claim 2, characterized in that: the sealing baffle (11) is of a plate-shaped structure, and sealing rubber is arranged on the lower surface of the sealing baffle (11).
4. The project progress display device for building project management according to claim 1, characterized in that: the second display board (5) is provided with two positions, and the two positions are symmetrically distributed on the second display board (5) along the long edge of the first display board (3).
5. The project progress display device for building project management according to claim 1, characterized in that: a handle rod (13) is fixed on the surface of one end of the limiting rod (7), and anti-skid lines are arranged on the outer side of the handle rod (13).
6. The project progress display device for building project management according to claim 1, characterized in that: the limiting rods (7) are four, and chamfers are arranged at the end parts of the limiting rods (7).
CN202021794958.XU 2020-08-25 2020-08-25 Engineering progress display device for building engineering management Active CN213025275U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021794958.XU CN213025275U (en) 2020-08-25 2020-08-25 Engineering progress display device for building engineering management

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021794958.XU CN213025275U (en) 2020-08-25 2020-08-25 Engineering progress display device for building engineering management

Publications (1)

Publication Number Publication Date
CN213025275U true CN213025275U (en) 2021-04-20

Family

ID=75470448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021794958.XU Active CN213025275U (en) 2020-08-25 2020-08-25 Engineering progress display device for building engineering management

Country Status (1)

Country Link
CN (1) CN213025275U (en)

Similar Documents

Publication Publication Date Title
CN213025275U (en) Engineering progress display device for building engineering management
CN211523095U (en) Reinforcement type enclosure assembly based on reservoir flood prevention
CN206636082U (en) A kind of aluminium alloy railing being easily installed
CN207794108U (en) A kind of anti-slope of highway landslide device
CN204137306U (en) Floating on water Sunshading articles
CN213220658U (en) Fire-fighting sandbox for electric fire fighting
CN211653955U (en) Earthwork collapse experience device
CN211057804U (en) Foundation pit supporting structure
CN212002637U (en) Electromechanical maintenance construction protection network of highway
CN212565281U (en) Large storage tank for liquid argon storage tank
CN209699055U (en) A kind of dust seal display equipment for ships and light boats hydraulic sterring engine maintenance training platform
CN207114107U (en) Portable negative pressure device for investigating water-tightness of structures
CN217970872U (en) Butyl daub storage container
CN206175965U (en) Suspension type digital panel meter
CN206229405U (en) A kind of chemistry experiment operating table apparatus
CN105735457B (en) A kind of fall arrest overflow-proof structure and inspection well construction and method
CN215760853U (en) Basic base with strengthened compression-resistant and wind-resistant structure for air film building
CN211608804U (en) Lecture board for meeting room
CN216034596U (en) Mining portable watering device
CN212396754U (en) Novel mesh ripple packs device
CN116608405B (en) Collecting equipment for electronic grade fluorine preparation
CN213038469U (en) Rainwater intelligent control device
CN204979902U (en) Opening device for be used for vertical tank top flange apron
CN215206644U (en) Be used for environmental protection equipment installation fixing device
CN219933638U (en) Hydraulic engineering foundation detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant